  <section prefix="Regulation" num=".01" heading="Adoption, Applicability and Scope of Regulations.">
    <para num="A.">These rules and regulations are promulgated by the Baltimore City Department of Transportation (“DOT”) pursuant to &lt;cite data-doc="City of Baltimore, Md., Code" data-path="|26"&gt;City Code Article 26&lt;/cite&gt;, Subtitle 15.</para>
    <para num="B.">These rules and regulations are in addition to all applicable laws found in &lt;cite data-doc="City of Baltimore, Md., Code" data-path="|26"&gt;Baltimore City Code Article 26&lt;/cite&gt;, other applicable sections of Baltimore City Code, and Maryland State Code.</para>
    <para num="C.">Scope of Regulations.<para num="(1)">These rules and procedures are intended to ensure proper excavation of the public way;</para>
      <para num="(2)">These rules and procedures are intended to ensure complete restoration of the public way to match preexisting conditions; and</para>
      <para num="(3)">These rules and procedures are intended to ensure the proper use of the public way while work is ongoing.</para>
    </para>
  </section>
  <section prefix="Regulation" num=".02" heading="Definitions.">
    <para num="A.">In &lt;cite data-path="14.03.01"&gt;this chapter&lt;/cite&gt;, the following terms have the meanings indicated.</para>
    <para num="B.">Terms Defined.<para num="(1)">"ADA" means the federal Americans with Disabilities Act.</para>
      <para num="(2)">Bicycle Facility.<para num="(a)">"Bicycle facility" means infrastructure to accommodate or encourage bicycling.</para>
        <para num="(b)">"Bicycle facility" includes a:<para num="(i)">Bike lane;</para>
          <para num="(ii)">Bike parking facility;</para>
          <para num="(iii)">Storage facility; or</para>
          <para num="(iv)">Shared roadway specifically designated for bicycle use.</para>
        </para>
      </para>
      <para num="(3)">"Blanket permit" means an authorization that allows a person to undertake an action related to a street cut in the right-of-way without first applying for a street-cut permit for that location.</para>
      <para num="(4)">"Book of Standards" means the Baltimore City Department of Transportation Book of Standards, which is incorporated by reference into &lt;cite data-path="14"&gt;this title&lt;/cite&gt;.</para>
      <para num="(5)">"Crosswalk" means a pedestrian crossing delineated by:<para num="(a)">A pavement marking; or</para>
        <para num="(b)">Signage.</para>
      </para>
      <para num="(6)">"Decorative surface" means a non-functional, ADA-compliant element installed to aesthetically enhance or otherwise embellish a right-of-way.</para>
      <para num="(7)">"Demarcation materials" means a warning surface treatment applied to an affected roadway, including a:<para num="(a)">Flex post;</para>
        <para num="(b)">Monolithic curb; or</para>
        <para num="(c)">Vertical barrier.</para>
      </para>
      <para num="(8)">"Department" means the Baltimore City Department of Transportation.</para>
      <para num="(9)">"Directional boring" means a trenchless method of installing underground conduit and facilities with minimal impact along a prescribed underground path.</para>
      <para num="(10)">"Director" means the Director of Transportation or the Director's designee.</para>
      <para num="(11)">"Duration" means the time during which an activity required by a street cut occurs.</para>
      <para num="(12)">"Emergency" means a situation that arises as the result of an unforeseen event in which excavation is needed to abate imminent potential danger to life, health, or property.</para>
      <para num="(13)">"Excavation" has the meaning stated in &lt;cite data-doc="City of Baltimore, Md., Code" data-path="|26|§15-1|(d)"&gt;City Code Article 26, §15-1(d)&lt;/cite&gt;.</para>
      <para num="(14)">Facility.<para num="(a)">"Facility" means utility infrastructure used for the provision of services.</para>
        <para num="(b)">"Facility" includes infrastructure for the transportation of:<para num="(i)">Water;</para>
          <para num="(ii)">Energy; and</para>
          <para num="(iii)">Telecommunications.</para>
        </para>
      </para>
      <para num="(15)">"Landscaped area" means an outdoor space improved with living vegetation or synthetic material designed to be visually appealing.</para>
      <para num="(16)">"Pavement marking" means a device or material that is used on a road to demarcate lanes and conduct traffic.</para>
      <para num="(17)">"Pavement type" means a reference to the material from which a road is constructed, including:<para num="(a)">Flexible material;</para>
        <para num="(b)">Rigid material; or</para>
        <para num="(c)">Composite material.</para>
      </para>
      <para num="(18)">"Performance security" means a:<para num="(a)">A performance bond;</para>
        <para num="(b)">An irrevocable letter of credit;</para>
        <para num="(c)">A cash deposit; or</para>
        <para num="(d)">A combination of the items noted in &lt;cite data-path="14.03.01.02|B.|(18)|(a)"&gt;§B(18)(a)&lt;/cite&gt;&lt;cite data-path="14.03.01.02|B.|(18)|(c)"&gt;-(c)&lt;/cite&gt; of &lt;cite data-path="14.03.01.02"&gt;this Regulation&lt;/cite&gt;.</para>
      </para>
      <para num="(19)">Person.<para num="(a)">"Person" has the meaning stated in &lt;cite data-doc="City of Baltimore, Md., Code" data-path="|general|§1-107"&gt;City Code General Provisions Article, §1-107&lt;/cite&gt;.</para>
        <para num="(b)">"Person" includes a government entity that performs work on the right-of-way.</para>
      </para>
      <para num="(20)">"Primary street" means an arterial road as defined by the Department.</para>
      <para num="(21)">"PROWAG" means the Federal Public Rights-of-Way Accessibility Guidelines.</para>
      <para num="(22)">Right-of-Way (ROW).<para num="(a)">"Right-of-way" means an area intended to facilitate the movement of pedestrians that falls within the boundary lines of a public:<para num="(i)">Street, including a curb;</para>
          <para num="(ii)">Alley;</para>
          <para num="(iii)">Sidewalk;</para>
          <para num="(iv)">Footway; or</para>
          <para num="(v)">Property otherwise owned or controlled by the City of Baltimore.</para>
        </para>
        <para num="(b)">"Right-of-way" includes a public way as it is referred to in &lt;cite data-doc="City of Baltimore, Md., Code" data-path="|31"&gt;Article 31 of the Baltimore City Code&lt;/cite&gt;.</para>
      </para>
      <para num="(23)">"Right-of-Way (ROW) permit" means a permit, including a street-cut permit, issued by the Department that allows temporary use of the public right-of-way to perform work related to facilities.</para>
      <para num="(24)">"Separate offense" means each day that a violation continues.</para>
      <para num="(25)">"Stop work order" means the issuance of an administrative order by the Department to cease work at an excavation site due to a violation of:<para num="(a)">The Baltimore City Code;</para>
        <para num="(b)">A regulation adopted under the Code of Baltimore Regulations Annotated; or</para>
        <para num="(c)">A condition of the permit until the violation is abated.</para>
      </para>
      <para num="(26)">"Street cut" means work which involves excavating a road.</para>
      <para num="(27)">"Street-cuts permit" means a permit required by or issued under &lt;cite data-doc="City of Baltimore, Md., Code" data-path="|26|15"&gt;subtitle 15, of Article 26 of the Baltimore City Code&lt;/cite&gt;.</para>
      <para num="(28)">"Traffic Control Plan (TCP)" means an arrangement intended to preserve safe pedestrian and vehicular traffic to the greatest extent possible for the duration of work in a road.</para>
      <para num="(29)">"TMC" means the Department's Transportation Management Center.</para>
      <para num="(30)">"Traffic control channelization device" means a device used to:<para num="(a)">Warn roadway users of conditions created by work activities in or near the road; and</para>
        <para num="(b)">Guide roadway users for the duration of the work.</para>
      </para>
      <para num="(31)">"Unsafe condition" means an unsatisfactory physical condition existing at a street cut location that has the potential to result in injury, death, or property damage if not corrected.</para>
      <para num="(32)">"Utility" means a person that owns or operates facilities used to provide a transmittable service to customers, including:<para num="(a)">Electrical service;</para>
        <para num="(b)">Gas service;</para>
        <para num="(c)">Water service;</para>
        <para num="(d)">Sewer service, including stormwater drainage; or</para>
        <para num="(e)">Telecommunication networks.</para>
      </para>
    </para>
  </section>
  <section prefix="Regulation" num=".03" heading="Exceptions to Street-cuts Permits.">
    <para num="A.">Unless the work qualifies as an emergency excavation under &lt;cite data-doc="City of Baltimore, Md., Code" data-path="|26"&gt;City Code Article 26&lt;/cite&gt;, §15-13, no person, including a City agency, may excavate in a Public Way without first obtaining a Street-cuts permit.</para>
    <para num="B.">Directional Drilling is not permitted within the City Right-of-Way<para num="(1)">for electrical utilities and facilities,</para>
      <para num="(2)">for other utilities and facilities, including sanitary and gas lines, without prior written approval from the Director.</para>
    </para>
  </section>
  <section prefix="Regulation" num=".04" heading="Applications for a Street-cuts Permit.">
    <para num="A.">An application for a Street-cuts Permit<para num="(1)">shall include the following information:<para num="(a)">applicant name and contact information;</para>
        <para num="(b)">contractor name and contact information;</para>
        <para num="(c)">work location and address;</para>
        <para num="(d)">description of proposed work;</para>
        <para num="(e)">information for the Street-cut including:<para num="(i)">requested start date and time;</para>
          <para num="(ii)">requested end date and time;</para>
          <para num="(iii)">street lane, bicycle facility or sidewalk closures;</para>
          <para num="(iv)">use of steel plates;</para>
          <para num="(v)">length, depth and width of any trench;</para>
          <para num="(vi)">work which will occur on weekends;</para>
          <para num="(vii)">work which will occur at night;</para>
          <para num="(viii)">a Traffic Control Plan (“TCP”), if required;</para>
          <para num="(ix)">estimated number of Street-cuts; and</para>
          <para num="(x)">drawing showing the location, type, size, and TCP.</para>
        </para>
      </para>
      <para num="(2)">shall provide evidence of Performance Security in an amount specified on the DOT website at transportation.baltimorecity.gov/<para num="(a)">A single Performance Security may be used for multiple permits by the same contractor as allowed by the Department.</para>
        <para num="(b)">Contractors who fail to maintain a minimum Performance Security, as determined by the Director, shall be prohibited from working in the Public Way, unless specifically authorized by the Director.</para>
      </para>
      <para num="(3)">shall provide a point of contact in case of emergency that includes:<para num="(a)">a name, email address, and phone number;</para>
        <para num="(b)">someone who is available on a 24-hour basis.</para>
      </para>
    </para>
    <para num="B.">An applicant shall be required to submit the following for a permit:<para num="(1)">Drawings or acceptable sketches which shall include or identify:<para num="(a)">the size and location of each Street-Cut;</para>
        <para num="(b)">pavement restoration details;</para>
        <para num="(c)">pavement type; and</para>
        <para num="(d)">work that impacts any traffic on one of the following roadway classes, as defined by Roadway Functional Classification map located at https://transportation.baltimorecity.gov:<para num="(i)">Collector,</para>
          <para num="(ii)">Minor Arterial,</para>
          <para num="(iii)">Other Principal Arterial,</para>
          <para num="(iv)">Freeway and Expressway, or</para>
          <para num="(v)">Interstate Principal Arterial.</para>
        </para>
        <para num="(e)">a final pavement marking plan consistent with the applicable requirements for pavement marking as set forth in the Book of Standards issued by the Department of Transportation and the Department of Public Works (“DPW”) (the “Green Book”), including:<para num="(i)">bicycle facilities;</para>
          <para num="(ii)">parking facilities;</para>
          <para num="(iii)">crosswalks; and</para>
          <para num="(iv)">other pedestrian pavement marking.</para>
        </para>
      </para>
      <para num="(2)">Within 5 days of application submission, an applicant shall submit a color photograph including:<para num="(a)">the current pavement condition of the right-of-way;</para>
        <para num="(b)">the date; and</para>
        <para num="(c)">a time stamp.</para>
      </para>
    </para>
    <para num="C.">An applicant is required to submit a Traffic Control Plan (“TCP”).<para num="(1)">Traffic Control Plans are required when any of the following conditions exist:<para num="(a)">sidewalk closure or detour;</para>
        <para num="(b)">bicycle facility closure or detour; or</para>
        <para num="(c)">roadway closure or detour on a roadway.</para>
      </para>
      <para num="(2)">All lanes in the roadway shall be treated as travel lanes, unless clearly marked as a parking lane by a solid white line.</para>
      <para num="(3)">A TCP shall include:<para num="(a)">a site plan covering 2 to 3 blocks in each direction from the construction site;</para>
        <para num="(b)">the installation and location of advanced warning signs which include:<para num="(i)">for any roadway lane closure, a minimum of the following three advanced warning signs installed at least 300 feet apart, unless a request to change the spacing is submitted for prior approval:<para num="(A)">Road Work Ahead,</para>
            <para num="(B)">Right/Left/Center Lane Closed Ahead, and</para>
            <para num="(C)">a transition sign for the lane being closed.</para>
          </para>
          <para num="(ii)">for a parking lane closure, no arrow board is required; however, the following three advanced warning signs shall be installed at least 300 feet apart:<para num="(A)">Road Work Ahead,</para>
            <para num="(B)">Curb Lane Closed Ahead, and</para>
            <para num="(C)">a transition sign for the lane being closed.</para>
          </para>
          <para num="(iii)">for the closure of multiple roadway lanes<para num="(A)">an arrow board is required for each lane being closed, and</para>
            <para num="(B)">the placement of advanced warning signs as required by the Manual on Uniform Traffic Control Devices (“MUTCD”).</para>
          </para>
        </para>
        <para num="(c)">a flagging operation and multiple lane closure for utility cuts and work areas that extend more than 10 feet from the curb lane;</para>
        <para num="(d)">when a flagging operation is provided for by the applicant or required by the Department:<para num="(i)">all directions of travel must be controlled by a flagger;</para>
          <para num="(ii)">it must be noted on your application when working at a signalized intersection; and</para>
          <para num="(iii)">advanced warning signage must include Flagman Ahead signs;</para>
        </para>
        <para num="(e)">road closure detours shall<para num="(i)">be clearly signed to direct traffic around the road closure and reestablish travel back to the road after the closure;</para>
          <para num="(ii)">include the following advanced warning signs:<para num="(A)">Road Closed Ahead,</para>
            <para num="(B)">Detour ahead, and</para>
            <para num="(C)">Road Closed;</para>
          </para>
          <para num="(iii)">include a physical barrier at the actual road closure for all directions of travel;</para>
        </para>
        <para num="(f)">roadway classification;</para>
        <para num="(g)">a note to contact TMC each work morning prior to start of work and each afternoon at end of work;</para>
        <para num="(h)">all affected bicycle and pedestrian facilities and the traffic control for each;</para>
        <para num="(i)">traffic control channelization devices to be used;</para>
        <para num="(j)">location of all steel plates in the area affected;</para>
        <para num="(k)">information as to any pedestrian detours which shall:<para num="(i)">maintain a minimum 4 foot ADA accessible path for pedestrians when work is conducted on a sidewalk:<para num="(A)">the ADA accessible pathway may be located in a parking lane, and</para>
            <para num="(B)">shall have an appropriate physical barrier between vehicles and pedestrians;</para>
          </para>
          <para num="(ii)">if a sidewalk is to be closed, the closure must be at the nearest intersection crosswalk with signs directing pedestrians across the street, and<para num="(A)">the sidewalk on the opposite side of the street must be ADA accessible, and</para>
            <para num="(B)">must include a ramp and 4-foot pedestrian pathway;</para>
          </para>
        </para>
        <para num="(l)">information as to any bicycle facility detours which shall provide for or adhere to the following:<para num="(i)">lane and road closures include lane transitions for bicyclists, and</para>
          <para num="(ii)">if the bicycle lane cannot be maintained, an explanation of why it cannot be maintained and an alternate route for the bicyclist; and</para>
          <para num="(iii)">if a bicyclist must use the sidewalk as an alternate route, warning signage must include:<para num="(A)">Bike Lane Closure, and</para>
            <para num="(B)">Dismount and Walk Bicycle on Sidewalk;</para>
          </para>
        </para>
        <para num="(m)">any other TCP control needed for unique locations or work;</para>
        <para num="(n)">for Emergency work performed under a blanket permit, a trained and certified emergency traffic manager shall be on-site at all times until the contractor has provided the Department with a TCP which is approved.</para>
      </para>
      <para num="(4)">The following conditions, if not immediately corrected, constitute a violation of the Street-cuts permit and may result in a fine or issuance of a Stop work order:<para num="(a)">failure to obtain an approved TCP when required to do so,</para>
        <para num="(b)">failure to maintain at the work site a copy of the approved TCP for inspection, or</para>
        <para num="(c)">failure to adhere to the conditions of the TCP.</para>
      </para>
      <para num="(5)">No equipment, materials, or other construction matter is permitted to be staged or stored, in bicycle facilities, on sidewalks, or within other non-motorized travel facilities unless the contractor obtains<para num="(a)">prior written approval, and</para>
        <para num="(b)">any additional required permits.</para>
      </para>
    </para>
    <para num="D.">Applications for a Street-cuts permit are<para num="(1)">processed through the DOT Right-of-Way Permits Section which is located at 401 East Fayette Street, Lower Level, Baltimore, Maryland 21202;</para>
      <para num="(2)">on the DOT website under Quick Forms; and</para>
      <para num="(3)">submitted by email with all required information to &lt;u&gt;row.permit.documents@baltimorecity.gov&lt;/u&gt;.</para>
    </para>
    <para num="E.">The applicant listed on a Temporary Use Right-of-Way Permit<para num="(1)">is responsible for all work performed under the permit, including but not limited to any subcontractor; and</para>
      <para num="(2)">will receive any notice from the Department concerning the work.</para>
    </para>
  </section>
  <section prefix="Regulation" num=".05" heading="Issuance of a Street-cuts Permit.">
    <para num="A.">A Street-cuts permit shall be issued upon<para num="(1)">the provision of the required information,</para>
      <para num="(2)">receipt by DOT of the required permit fees,</para>
      <para num="(3)">payment of the required Performance Security, and</para>
      <para num="(4)">correction of outstanding or unresolved deficiencies with existing permits.</para>
    </para>
    <para num="B.">It is the contractor’s responsibility to<para num="(1)">schedule the work, and</para>
      <para num="(2)">notify DOT of completion of the work<para num="(a)">with sufficient time for the work to be inspected and approved prior to the expiration of the permit; and</para>
        <para num="(b)">sufficient time constitutes notice to DOT a minimum of 48 hours prior to the expiration date of the permit.</para>
      </para>
    </para>
    <para num="C.">Notice to DOT of an Emergency Excavation shall be made by<para num="(1)">calling the Street-cuts Section, at 410-396-2889, between the hours of 7 am and 4:30 pm Monday-Friday;</para>
      <para num="(2)">calling the TMC, at 443-984-2189, 24 hours a day; or</para>
      <para num="(3)">email to &lt;u&gt;streetcuts@baltimorecity.gov&lt;/u&gt;, 24 hours a day.</para>
    </para>
    <para num="D.">A Blanket Permit shall be issued to a utility provider or the Department of Public Works (“DPW”) for Emergency Excavations only.<para num="(1)">A Utility provider with a Blanket Permit shall complete a permit application within<para num="(a)">18 hours of beginning the emergency excavation, or</para>
        <para num="(b)">the next business day.</para>
      </para>
      <para num="(2)">Emergency Excavations shall be inspected by DOT Street-cuts Section prior to backfilling of the excavation.<para num="(a)">The utility provider shall notify DOT Street-cuts Section that the excavation is ready for inspection.</para>
        <para num="(b)">Notice shall be made as set forth in &lt;cite data-path="14.03.01.05|C."&gt;Regulation .05.C&lt;/cite&gt;.</para>
      </para>
    </para>
    <para num="E.">A Street-cut permit fee shall be assessed in accordance with a fee schedule, established by the Director and approved by the Board of Estimates (“BOE”).<para num="(1)">Street-cut permit fees are in addition to the Temporary Use of the Right-of-Way Permit fee.</para>
      <para num="(2)">Current Street-cut permit fees are posted on the DOT website at    transportation.baltimore.gov/quick-forms.</para>
      <para num="(3)">Additional fees may be assessed as provided in these regulations and allowed by law.</para>
    </para>
  </section>
  <section prefix="Regulation" num=".06" heading="Performance Schedule and Standards.">
    <para num="A.">Any person doing excavation work shall:<para num="(1)">always maintain the Street-cut permit on site, and</para>
      <para num="(2)">exhibit the permit when requested to do so by the Department.</para>
    </para>
    <para num="B.">If an excavation is interrupted by an agency of Baltimore City, the permittee shall<para num="(1)">notify DOT Street-cuts Section immediately, and provide the following information:<para num="(a)">permit number,</para>
        <para num="(b)">location of excavation,</para>
        <para num="(c)">City agency involved in the interruption,</para>
        <para num="(d)">City agency contact person,</para>
        <para num="(e)">City agency work order number,</para>
        <para num="(f)">expected length of the interruption, and</para>
        <para num="(g)">procedures taken to secure the site.</para>
      </para>
      <para num="(2)">Upon verification of an interruption caused by an agency of Baltimore City, the Street-cuts Section shall notify the permittee of<para num="(a)">additional time allowed under the permit to account for the interruption, and</para>
        <para num="(b)">any additional requirements pertaining to the permit.</para>
      </para>
    </para>
    <para num="C.">Prior to being given permission to disturb existing bicycle facilities, an applicant for a Street-cut permit shall provide proof that no alternative to such action is available.       D.   When restoring an open Street-cut a permittee must:<para num="(1)">comply with all conditions and requirements of the permit;</para>
      <para num="(2)">conform with current rules, regulations, and standards of Baltimore City; and</para>
      <para num="(3)">ensure restoration matches preexisting conditions.</para>
    </para>
    <para num="D.">Prior to beginning work in any roadway, the permittee shall<para num="(1)">meet with the Traffic Division to review and develop a pavement marking plan for the affected roadway; and</para>
      <para num="(2)">where the affected roadway has bicycle facilities, meet with the Traffic Division and the Bicycle Planning Section to review and develop<para num="(a)">a pavement marking plan, and</para>
        <para num="(b)">demarcation materials.</para>
      </para>
    </para>
    <para num="E.">When an Order to Remove or Relocate a Pole is issued by the Department it shall:<para num="(1)">be in writing and signed by the Director or the Director’s designee; and contain the following:<para num="(a)">name of the permit holder,</para>
        <para num="(b)">facts that support issuing a pole removal or relocation order, and</para>
        <para num="(c)">the location of the pole.</para>
      </para>
      <para num="(2)">The Order shall be served by:<para num="(a)">delivery to any employee, agent, contractor, or sub-contractor of the permit holder on site;</para>
        <para num="(b)">mailing or emailing a copy of the order to the address on file for the permit holder; or</para>
        <para num="(c)">sending a facsimile to the permit holder to the fax number on file for the permit holder.</para>
      </para>
      <para num="(3)">The location of the pole shall not create non-compliance with the ADA.</para>
    </para>
  </section>
  <section prefix="Regulation" num=".07" heading="Pavement Repairs and Restoration.">
    <para num="A.">Regardless of cut type, repairs will be done in accordance with Baltimore City DOT Standards.<para num="(1)">The Book of Standards is located on DOT’s website at:
&lt;u&gt;https://transportation.baltimorecity.gov/transportation/bookofstandards&lt;/u&gt;.</para>
      <para num="(2)">The DOT Street Cuts Section has the authority to increase the requirements of pavement restoration beyond minimum standards shown in the standard details based on<para num="(a)">site conditions, and</para>
        <para num="(b)">Street-cuts permit application information.</para>
      </para>
    </para>
    <para num="B.">Applicants and contractors shall adhere to the Street-cuts policies contained in these regulations; however,<para num="(1)">the Director has the discretion to permit exceptions to this policy under special circumstances; and</para>
      <para num="(2)">such exceptions shall be approved by the Director in writing.</para>
    </para>
    <para num="C.">The following are additional requirements for pavement repairs:<para num="(1)">when a utility cut is within 5 feet of a new or preexisting cut, both cuts shall be encapsulated into a single patch<para num="(a)">by milling away the intervening existing surface to allow for a single surface patch when one cut is preexisting and one cut is new; or</para>
        <para num="(b)">by combining the cuts into a single full-depth patch when both cuts are new; and</para>
        <para num="(c)">combined patches are subject to applicable Baltimore City DOT Standards.</para>
      </para>
      <para num="(2)">During resurfacing, the longitudinal pavement joints shall be constructed within 6 inches of the lane lines and not within the travel lanes.</para>
      <para num="(3)">If more than 50 percent of an asphalt or asphalt overlaid (composite) roadway is disturbed during longitudinal or transverse trenching, the entire block shall be milled and resurfaced<para num="(a)">from curb to curb, or</para>
        <para num="(b)">to the median curb, if applicable.</para>
      </para>
      <para num="(4)">The entire intersection must be milled and resurfaced if<para num="(a)">an asphalt or asphalt overlaid (composite) intersection is trenched diagonally, or</para>
        <para num="(b)">more than 50 percent of the intersection is disturbed during longitudinal and/or transverse trenching.</para>
      </para>
      <para num="(5)">All utility cuts must be backfilled and compacted in accordance with<para num="(a)">Baltimore City Standards outlined in Article 32.01.10 of the City of Baltimore Department of Public Works Specifications for Materials, Highways, Bridges, Utilities, and Incidental Structures (the “Green Book’);</para>
        <para num="(b)">the standards are found at &lt;u&gt;https://generalservices.baltimorecity.gov/gs-majorprojects/greenbook&lt;/u&gt;.</para>
      </para>
      <para num="(6)">Suitable fill material must be placed in 6-inch lifts and tamped with a mechanical tamper; and<para num="(a)">material one foot below subgrade must be compacted to 92 percent,</para>
        <para num="(b)">material in the top one foot must be compacted to 97percent; and</para>
        <para num="(c)">compaction of all material must be per the Modified Proctor ASTM D1557 (“AASHTO T180”).<para num="(i)">In lieu of borrow, CR-6 or excavation fills, #57 stone may be used; and</para>
          <para num="(ii)">it must be placed in no greater than one-foot lifts and tamped with a mechanical tamper.</para>
        </para>
      </para>
      <para num="(7)">Crusher Run Aggregate (“CR-6”) or Graded Aggregate Base (“GAB”) must be used for the proposed roadway paving sub-base, and<para num="(a)">must meet the requirements of Article 32 11 23.10 of the Green Book; and</para>
        <para num="(b)">Recycled Concrete (“RC-6”) may not be used for the sub-base material.</para>
      </para>
      <para num="(8)">The Contractor must supply compaction testing results for<para num="(a)">any paving patch greater than 1,000 square feet in area, and</para>
        <para num="(b)">any trench longer than 100 feet.</para>
      </para>
      <para num="(9)">A permittee must submit to the Department, at streetcuts@baltimorecity.gov, within 24 hours of the compaction:<para num="(a)">a copy of the compaction test results;</para>
        <para num="(b)">relevant location;</para>
        <para num="(c)">work date(s), and</para>
        <para num="(d)">designated permit number</para>
      </para>
    </para>
    <para num="D.">Final pavement restorations must include:<para num="(1)">removal of temporary backfill;</para>
      <para num="(2)">properly squaring off all Street-cuts to the bottom of the sub-base;</para>
      <para num="(3)">proper permanent backfills and compaction as specified in &lt;cite data-path="14.03.01.07|C.|(5)"&gt;Regulation .07.C(5)&lt;/cite&gt;;</para>
      <para num="(4)">permanent street restoration as specified in<para num="(a)">these Street-cuts regulations;</para>
        <para num="(b)">the City of Baltimore DOT Standards; and</para>
        <para num="(c)">the DPW Green Book;</para>
      </para>
      <para num="(5)">the patch must be installed so that it will remain flush with the surrounding pavement for 1 year after the work has been completed, inspected, and approved.</para>
    </para>
    <para num="E.">For utility upgrades and repairs that are performed in advance of a scheduled DOT contract, DOT may, at its sole discretion, allow the permit holder to provide temporary pavement repairs<para num="(1)">based upon the timing of the work in relation to the DOT contract schedule and the extent of the proposed trench excavations necessary for the utility work;</para>
      <para num="(2)">the type of temporary repair to be allowed will be decided by the Department on a case-by-case basis; and</para>
      <para num="(3)">the temporary pavement trench repair must conform to the current backfill procedures.</para>
    </para>
    <para num="F.">If the permittee uses steel plates to secure the public way during construction, they shall conform to:<para num="(1)">the Green Book; and</para>
      <para num="(2)">Baltimore City DOT Book of Standards.</para>
    </para>
    <para num="G.">Crosswalks.
In executing a street cut that disturbs a crosswalk, a person shall ensure that:<para num="(1)">The crosswalk is restored in accordance with the "Continental Crosswalk" style standards outlined in the Book of Standards;</para>
      <para num="(2)">Notwithstanding the provisions of &lt;cite data-path="14.03.01.07|G.|(1)"&gt;§G(1) of this regulation&lt;/cite&gt;, the crosswalk is restored with a decorative surface that:<para num="(a)">Matches the characteristics of a preexisting decorative surface; and</para>
        <para num="(b)">Is in accordance with standards provided by the Department when applicable;</para>
      </para>
      <para num="(3)">Each portion of a disturbed crosswalk is restored, including a portion of a disturbed crosswalk that is:<para num="(a)">Faded;</para>
        <para num="(b)">Missing; or</para>
        <para num="(c)">Otherwise noncompliant with an expected standard.</para>
      </para>
      <para num="(4)">The crosswalk is restored from curb to curb, unless the undisturbed portion of the crosswalk is:<para num="(a)">Compliant with the Book of Standards; and</para>
        <para num="(b)">In good condition, meaning it is:<para num="(i)">In new or like-new condition;</para>
          <para num="(ii)">Free of fading;</para>
          <para num="(iii)">Free of peeling; and</para>
          <para num="(iv)">Not otherwise defective in a way that reduces its visibility;</para>
        </para>
      </para>
      <para num="(5)">Notwithstanding the provisions of &lt;cite data-path="14.03.01.07|G.|(4)"&gt;§G(4) of this regulation&lt;/cite&gt;, the crosswalk is restored from curb to curb when trenching is done lengthwise through the crosswalk; and</para>
      <para num="(6)">When required by the Department to resurface an intersection in its entirety, each abutting crosswalk is restored as required by &lt;cite data-path="14.03.01.07|G.|(4)"&gt;§G(4) of this regulation&lt;/cite&gt;.</para>
    </para>
  </section>
  <section prefix="Regulation" num=".08" heading="Work by Utilities in Advance of a Scheduled DOT Contract.">
    <para num="A.">If a public or private utility owns a facility, or is planning to perform work, in a right-of- way that is scheduled to be repaved by the Department of Transportation, the utility shall:<para num="(1)">notify the Department of any planned utility work scheduled for the current fiscal year or the next 2 fiscal years within the limits of the Department’s scheduled repaving work;</para>
      <para num="(2)">coordinate such utility work with the Department;</para>
      <para num="(3)">investigate, test, repair and upgrade the utility’s existing facilities so that future maintenance or replacement will not be required for a minimum of 5 years after the right-of-way is repaved; and</para>
      <para num="(4)">immediately notify the Department of any emergency work that takes place in a rightof-way scheduled by the Department to be repaved during the current calendar year.</para>
    </para>
    <para num="B.">When DOT submits plans for its proposed work to all utilities several times during the design process, each utility shall consider and inform the Department of all the improvements it will need to make based on:<para num="(1)">uploads from DOT which will include scheduled roadways and repaving limits to the utility coordination platforms/software;</para>
      <para num="(2)">communication about scheduled roadways at the monthly utility coordination meetings held at DOT; and</para>
      <para num="(3)">any other communications between the Department and utility providers regarding scheduled roadway repaving locations.</para>
    </para>
    <para num="C.">When properly advised by a utility pursuant to &lt;cite data-path="14.03.01.08|B."&gt;Regulation .08.B&lt;/cite&gt;, DOT will consider delaying the advertisement, or altering the contract, to allow utility work to be completed first.</para>
  </section>
  <section prefix="Regulation" num=".09" heading="Violations and Fines.">
    <para num="A.">The following fineable offenses are for work being performed in a Public Way:

        &lt;table&gt;
          &lt;thead&gt;
            &lt;tr&gt;
              &lt;th&gt;Violation&lt;/th&gt;
              &lt;th&gt;Occurrence&lt;/th&gt;
            &lt;/tr&gt;
          &lt;/thead&gt;
          &lt;tbody&gt;
            &lt;tr&gt;
              &lt;td&gt;Failure to obtain a Street Cuts permit prior to beginning work or, in an emergency where permit cannot be obtained ahead of work, within 18 hours of an emergency street-cut (Absence of a permit at jobsite)&lt;/td&gt;
              &lt;td&gt;Daily&lt;/td&gt;
            &lt;/tr&gt;
            &lt;tr&gt;
              &lt;td&gt;Unsafe job site, TCP setup, or other unsafe condition&lt;/td&gt;
              &lt;td&gt;Daily&lt;/td&gt;
            &lt;/tr&gt;
            &lt;tr&gt;
              &lt;td&gt;Not reporting intended work forty-eight (48) hours prior and/or steel plate placement as required on permit&lt;/td&gt;
              &lt;td&gt;Daily&lt;/td&gt;
            &lt;/tr&gt;
            &lt;tr&gt;
              &lt;td&gt;Compaction testing not performed&lt;/td&gt;
              &lt;td&gt;Daily&lt;/td&gt;
            &lt;/tr&gt;
            &lt;tr&gt;
              &lt;td&gt;Non-compliant installation of steel plates&lt;/td&gt;
              &lt;td&gt;Daily&lt;/td&gt;
            &lt;/tr&gt;
            &lt;tr&gt;
              &lt;td&gt;Not clearing away construction debris&lt;/td&gt;
              &lt;td&gt;Daily&lt;/td&gt;
            &lt;/tr&gt;
            &lt;tr&gt;
              &lt;td&gt;Not providing for temporary patching or plating until full restoration is completed&lt;/td&gt;
              &lt;td&gt;Daily&lt;/td&gt;
            &lt;/tr&gt;
            &lt;tr&gt;
              &lt;td&gt;Patch not flush with the surrounding pavement&lt;/td&gt;
              &lt;td&gt;Daily&lt;/td&gt;
            &lt;/tr&gt;
            &lt;tr&gt;
              &lt;td&gt;Absence of identification markings (if faded, they must be refreshed daily)&lt;/td&gt;
              &lt;td&gt;Daily&lt;/td&gt;
            &lt;/tr&gt;
            &lt;tr&gt;
              &lt;td&gt;Blocked travel lanes before 9:00 AM or after 3:00 PM on weekdays without prior written DOT authorization&lt;/td&gt;
              &lt;td&gt;Daily&lt;/td&gt;
            &lt;/tr&gt;
            &lt;tr&gt;
              &lt;td&gt;Incorrect traffic control (TCP) setup and/or absence of the approved TCP in site&lt;/td&gt;
              &lt;td&gt;Daily&lt;/td&gt;
            &lt;/tr&gt;
            &lt;tr&gt;
              &lt;td&gt;Use of unapproved materials&lt;/td&gt;
              &lt;td&gt;Daily&lt;/td&gt;
            &lt;/tr&gt;
            &lt;tr&gt;
              &lt;td&gt;Failure to construct to Baltimore City standards&lt;/td&gt;
              &lt;td&gt;Daily&lt;/td&gt;
            &lt;/tr&gt;
            &lt;tr&gt;
              &lt;td&gt;Final striping not completed within 15 calendar days of permanent restoration&lt;/td&gt;
              &lt;td&gt;Daily&lt;/td&gt;
            &lt;/tr&gt;
            &lt;tr&gt;
              &lt;td&gt;Street Cuts not fully restored to be permanent within one hundred twenty (120) days from start of work in the public way&lt;/td&gt;
              &lt;td&gt;
                &lt;p&gt;Daily (beginning day 121 and each  day until permanent restoration is&lt;/p&gt;
                &lt;p&gt;complete)&lt;/p&gt;
              &lt;/td&gt;
            &lt;/tr&gt;
            &lt;tr&gt;
              &lt;td&gt;Steel plates extending beyond thirty (30) days in the public right-of-way without an approved extension&lt;/td&gt;
              &lt;td&gt;Daily (beginning day 31 and each day until steel plating is removed and replaced with temporary patching or until full and permanent restoration is complete)&lt;/td&gt;
            &lt;/tr&gt;
            &lt;tr&gt;
              &lt;td&gt;Permanent patch failure within the one-year warranty period if not corrected with thirty (30) days of notice&lt;/td&gt;
              &lt;td&gt;
                &lt;p&gt;Daily (beginning day 31 and each day&lt;/p&gt;
                &lt;p&gt;until permanent restoration is&lt;/p&gt;
                &lt;p&gt;complete)&lt;/p&gt;
              &lt;/td&gt;
            &lt;/tr&gt;
          &lt;/tbody&gt;
        &lt;/table&gt;
      </para>
    <para num="B.">A schedule of fines as previously approved by the BOE for the violations set forth in &lt;cite data-path="14.03.01.09|A."&gt;Regulation .09.A&lt;/cite&gt; are<para num="(1)">posted on the DOT website at transportation.baltimorecity.gov; and</para>
      <para num="(2)">subject to amendment by the Director with the approval of the Board of Estimates.</para>
    </para>
    <para num="C.">Unless specifically provided, fines may be imposed by DOT without provision of a Pre-Fine Notice.<para num="(1)">The Street-cuts Section is not required to issue a Pre-Fine Notice for any violation observed during inspection operations; and</para>
      <para num="(2)">DOT will not issue a Pre-Fine Notice for failure to complete permanent restoration within 120 days.</para>
    </para>
    <para num="D.">In the case of failure to complete full restoration of the Public Way within 120 days of the start of work;<para num="(1)">the total fine amount imposed will be equal to:<para num="(a)">the number of days past 120 days until the restoration is completed (b) times the daily fine amount per violation.</para>
      </para>
      <para num="(2)">The following time periods are not included in the calculation of the 120-day period within which full restoration must be completed:<para num="(a)">the winter season, which is defined generally as the period from November 15 to March 15, or</para>
        <para num="(b)">when paving plants are closed as determined by the Department.</para>
      </para>
      <para num="(3)">Any permit holder that is not able to complete full restoration within the 120-day period must<para num="(a)">make a written request for an extension to the Street-cuts Section prior to the expiration of the 120-day period, and</para>
        <para num="(b)">demonstrate good cause for the extension.</para>
      </para>
      <para num="(4)">The Street-cuts Section may then grant written extension for a reasonable time to the permit holder.</para>
      <para num="(5)">When no request for an extension of the 120-day period has been granted:<para num="(a)">Street-cuts not completed within the 120-day restoration period are required to apply for a new permit;</para>
        <para num="(b)">the new permit start date is the expiration date of the previous permit;</para>
        <para num="(c)">the new permit expiration date is the expected date that permanent restoration will be complete for the street cut; and</para>
        <para num="(d)">the permit fee owed to the City is for the entire timeframe.</para>
        <para num="(e)">these requirements are in addition to any fines imposed.</para>
      </para>
    </para>
    <para num="E.">Steel plates may not extend beyond 30 days in the public way unless<para num="(1)">an extension has been granted by the Department; and</para>
      <para num="(2)">the extension notification can be found at &lt;u&gt;https://transportation.baltimorecity.gov/quick-forms.&lt;/u&gt;</para>
    </para>
    <para num="F.">Permanent patch failure within the 1-year warranty period will be given a 30-day notice for repairs:<para num="(1)">a new permit is required for the repair;</para>
      <para num="(2)">beyond the 30-day notice period, a fine will be imposed until such time as the patch is repaired and approved; and</para>
      <para num="(3)">an additional 1-year warranty will take effect starting from the day of final approval of the repair.</para>
    </para>
    <para num="G.">The following unsafe conditions existing at a Street-cut may result in a fine:<para num="(1)">utility trench, permanent patch within the warranty phase, or utility cut where paving restoration is left:<para num="(a)">1 inch or more below existing grade, or</para>
        <para num="(b)">2 inches or more above existing grade;</para>
      </para>
      <para num="(2)">Utility trench, permanent patch within the warranty phase, or utility cut on roadways with bicycle facilities where paving restoration is left:<para num="(a)">¼ inch or more below existing grade, or</para>
        <para num="(b)">½ inch or more above existing grade;</para>
      </para>
      <para num="(3)">debris left onsite by a contractor for 24 hours or more;</para>
      <para num="(4)">wooden boards placed over utility cut;</para>
      <para num="(5)">fenced site where the fence has collapsed;</para>
      <para num="(6)">an exposed excavation left unattended;</para>
      <para num="(7)">blocking of a bicycle facility by equipment, debris, vehicles, signs or other obstruction;</para>
      <para num="(8)">blocking a pedestrian walkway, crosswalk, curb ramp or other facility by equipment, debris, vehicles, signs or other obstruction; and</para>
      <para num="(9)">any circumstance where the contractor has left work in a state considered to be a substantial threat to public safety.</para>
    </para>
  </section>
  <section prefix="Regulation" num=".10" heading="Stop Work Orders.">
    <para num="A.">The Director or the Director’s designee may issue a stop work order for work conducted on public right-of-way when it is determined that a violation of any of the following has occurred:<para num="(1)">State law or code;</para>
      <para num="(2)">City Code</para>
      <para num="(3)">DOT regulation; or</para>
      <para num="(4)">the requirements imposed by a permit issued for the project.</para>
    </para>
    <para num="B.">The Director or the Director’s designee may also issue a stop work order for any of the following:<para num="(1)">a project that endangers public health or safety; or</para>
      <para num="(2)">failing to abate a violation in a timely manner for which a notice was issued.</para>
    </para>
    <para num="C.">A stop work order shall<para num="(1)">be in writing;</para>
      <para num="(2)">signed by the Director or the Director’s designee; and</para>
      <para num="(3)">contain the following:<para num="(a)">name of the violator;</para>
        <para num="(b)">facts that support issuing a stop work order;</para>
        <para num="(c)">the location at which the violation occurred;</para>
        <para num="(d)">reference to the specific provision of law, regulation, or permit that has been violated; and</para>
        <para num="(e)">the remedial measures required for to abate the violation.</para>
      </para>
    </para>
    <para num="D.">The Department must serve a stop work order by<para num="(1)">delivering it to any employee, agent, contractor, or sub-contractor of the permit holder on site;</para>
      <para num="(2)">mailing or emailing a copy of the order to the address on file for the permit holder; or</para>
      <para num="(3)">sending a facsimile to the permit holder to the fax number on file for the permit holder.</para>
    </para>
    <para num="E.">A stop work order becomes effective as soon as it is served via one of the methods in Regulation 10.D., regardless of whether delivery is accepted.</para>
    <para num="F.">Upon the issuance of a stop work order the violator shall<para num="(1)">immediately cease all work as specified in the order and comply with all directives contained in the order to abate the violation, and</para>
      <para num="(2)">contact the Street-cuts Section to request on on-site inspection for correction of the violation<para num="(a)">by phone 410-396-5889 or</para>
        <para num="(b)">email &lt;u&gt;streetcuts@baltimorecity.gov&lt;/u&gt;.</para>
      </para>
    </para>
    <para num="G.">A stop work order remains in effect until the Department notifies the permit holder in writing of its termination or modification.</para>
    <para num="H.">Termination of the stop work order does not preclude separate enforcement action by the Department relating to the present or a subsequent violation.</para>
  </section>
  <section prefix="Regulation" num=".11" heading="Administrative Hearings.">
    <para num="A.">Any person aggrieved by a decision or action of the Department under &lt;cite data-doc="City of Baltimore, Md., Code" data-path="|26"&gt;City Code Article 26&lt;/cite&gt;, subtitle 15, may appeal the decision or action to the Director.</para>
    <para num="B.">A person shall be notified in writing of an appealable decision or action taken by the Department, and the notice shall<para num="(1)">be sent<para num="(a)">via first class mail, and</para>
        <para num="(b)">by email or facsimile, to the email address or facsimile number on record for the aggrieved person.</para>
      </para>
      <para num="(2)">Email notification is effective as of the date of transmission by the Department.</para>
    </para>
    <para num="C.">An appeal of a decision or action shall be filed by requesting a hearing<para num="(1)">within 10 days of the date of notification, or the date of receipt of the notice, whichever occurs first,</para>
      <para num="(2)">in writing and sent to the DOT Street-cuts Section by<para num="(a)">first class mail to: Baltimore City Department of Transportation, Street Cuts Section, 520 Fallsway, Baltimore, MD  21202; and</para>
        <para num="(b)">by email to &lt;u&gt;streetcuts@baltimorecity.gov&lt;/u&gt;.</para>
      </para>
      <para num="(3)">If no timely request for a hearing is filed, the aggrieved person shall be deemed to have waived the right to an administrative hearing.</para>
    </para>
    <para num="D.">The hearing shall be scheduled within a reasonable time after a request for a hearing is received, and<para num="(1)">DOT shall send a Hearing Notice to the aggrieved person by<para num="(a)">first class mail and</para>
        <para num="(b)">electronic mail requesting receipt confirmation;</para>
      </para>
      <para num="(2)">the Hearing Notice shall<para num="(a)">set the date, time and location of the hearing,</para>
        <para num="(b)">designate the Hearing Officer; and</para>
        <para num="(c)">describe the purpose and nature of the hearing</para>
        <para num="(d)">set forth any rules or procedures that may be required by the Hearing Officer.</para>
      </para>
    </para>
    <para num="E.">A Hearing Officer<para num="(1)">may be any individual member of the DOT designated as such by the Director of the DOT; but</para>
      <para num="(2)">shall not be the DOT employee who made the decision or took the action being appealed; and</para>
      <para num="(3)">shall have discretion to set reasonable limits for<para num="(a)">the time for the aggrieved party to present its case;</para>
        <para num="(b)">the time for the agency response;</para>
        <para num="(c)">the time for, and any limits on, cross examination; and (d) the time for closing arguments.</para>
      </para>
      <para num="(4)">may shorten or extend any time limits designated in these regulations<para num="(a)">at his discretion, and</para>
        <para num="(b)">for good cause shown.</para>
      </para>
    </para>
    <para num="F.">Not later than 5 days after the date of the Hearing Notice, the aggrieved party shall advise DOT in writing, via first class mail and electronic mail requesting receipt confirmation,<para num="(1)">if it will be represented by counsel and identify its counsel; or</para>
      <para num="(2)">if the aggrieved party will not be represented by counsel, designate an individual to present the aggrieved party’s case at the hearing.</para>
    </para>
    <para num="G.">Formal evidence rules and trial procedures shall not apply, and the Hearing Officer<para num="(1)">may admit and give effect to evidence which possesses probative value commonly accepted by reasonable and prudent persons in the conduct of their affairs;</para>
      <para num="(2)">may exclude incompetent, irrelevant, immaterial, and unduly repetitious evidence;</para>
      <para num="(3)">may take judicial notice of general, technical, and scientific facts; and</para>
      <para num="(4)">shall give effect to the rules of privilege recognized by law.</para>
    </para>
    <para num="H.">All evidence, including records and documents, in the possession of DOT, the involved
City agency or the City of Baltimore which the Hearing Officer desires to utilize may<para num="(1)">be made a part of the record in the case, and</para>
      <para num="(2)">be received in the form of copies, excerpts, or by incorporation by reference.</para>
    </para>
    <para num="I.">The hearing shall<para num="(1)">proceed as follows:<para num="(a)">the Hearing Officer shall begin the hearing with a statement concerning the purpose of the hearing and the procedures that will be followed.</para>
        <para num="(b)">each party may present its case by narrative or by witnesses.</para>
        <para num="(c)">cross-examination of any witness shall be permitted; however, the parties will not be permitted to argue or engage in debate.  The Hearing Officer may reasonably limit or terminate cross examination at any time.</para>
        <para num="(d)">the Hearing Officer may question any witness or party at any time.</para>
        <para num="(e)">each party may present its final arguments and summarize its position.</para>
        <para num="(f)">each party shall have the right to make any additional statements before the hearing it terminated.</para>
        <para num="(g)">at the discretion of the Hearing officer, the hearing may be adjourned to another date, continued, and postponed.</para>
      </para>
      <para num="(2)">Notwithstanding the procedures in &lt;cite data-path="14.03.01.11|I."&gt;Regulation .11.I&lt;/cite&gt;., the Hearing officer may, in his discretion,<para num="(a)">decide the order and manner in which testimony and evidence is to be presented and</para>
        <para num="(b)">make changes to the hearing procedure.</para>
      </para>
    </para>
    <para num="J.">Following the hearing, the Hearing Officer shall<para num="(1)">make every attempt to render a decision within 30 days from the conclusion of the hearing,</para>
      <para num="(2)">base the decision on the facts and evidence introduced into the record,</para>
      <para num="(3)">prepare a decision of each hearing which contains the following information:<para num="(a)">date of the hearing,</para>
        <para num="(b)">name of the Hearing Officer;</para>
        <para num="(c)">name of the aggrieved party;</para>
        <para num="(d)">names, titles and affiliations of persons in attendance;</para>
        <para num="(e)">the purpose and nature of the hearing;</para>
        <para num="(f)">brief description of documents, testimony and data presented;</para>
        <para num="(g)">findings and conclusions of the Hearing Officer regarding the action or decision being appealed; and</para>
        <para num="(h)">the decision of the Hearing officer.</para>
      </para>
      <para num="(4)">send a copy of the decision to the aggrieved party, or his attorney of record; by<para num="(a)">first class mail, or</para>
        <para num="(b)">when provided, by email.</para>
      </para>
    </para>
    <para num="K.">Upon the direction of the Hearing Officer or the aggrieved party, a record of the proceedings may be made.<para num="(1)">The record is adequate if in the form of a tape recording.</para>
      <para num="(2)">The aggrieved party shall have access to the tape-recording during City business hours, and may have a transcript made at its expense.<para num="(a)">The City shall designate the transcriber, and</para>
        <para num="(b)">the cost of the transcript preparation shall be paid before the transcript is prepared.</para>
      </para>
    </para>
    <para num="L.">Within ten 10 days of DOT’s service of the final decision of the Hearing Officer, the aggrieved party may submit a written request for a review of the decision of the Hearing Officer,<para num="(1)">which shall be sent by<para num="(a)">first class mail to: Baltimore City Department of Transportation, Street Cuts Section, 520 Fallsway, Baltimore, MD  21202,  and</para>
        <para num="(b)">email to: streetcuts@baltimorecity.gov;</para>
      </para>
      <para num="(2)">if no written request for a review is filed within the time required by these rules, the aggrieved party will be deemed to have waived its rights to any further review of the decision of the Hearing Officer.</para>
    </para>
    <para num="M.">If a timely request for review is made, a Review Hearing Officer shall be appointed who<para num="(1)">may be an individual member of the DOT designated by the Director to serve as the Review Hearing Officer, but</para>
      <para num="(2)">shall not be<para num="(a)">the Hearing Officer or</para>
        <para num="(b)">the DOT employee who made the decision or took the action being appealed.</para>
      </para>
    </para>
    <para num="N.">The review shall proceed in the following order:<para num="(1)">prior to the review proceeding, any party may submit to the Review Hearing Officer and the other party, a brief containing a statement of facts and arguments;</para>
      <para num="(2)">the Review Hearing Officer shall begin the review hearing with a statement concerning the purpose of the review;</para>
      <para num="(3)">any party may present a brief articulation of its arguments and summarize its position;</para>
      <para num="(4)">any party may answer any questions posed by the Review Hearing Officer;</para>
      <para num="(5)">the Review Hearing Officer has the discretion to request additional testimony or evidence;</para>
      <para num="(6)">at the discretion of the Review Hearing Officer, the review hearing may be adjourned to another date, continued, or postponed.</para>
    </para>
    <para num="O.">Following the review proceeding, the Review Hearing Officer<para num="(1)">shall make every attempt to render a final decision of the review within 30 days;</para>
      <para num="(2)">may affirm, reverse, or modify the Hearing Officer’s decision;</para>
      <para num="(3)">shall consider the entire record;</para>
      <para num="(4)">shall make his decision in writing; and</para>
      <para num="(5)">shall send a copy of the decision to the aggrieved party.</para>
    </para>
    <para num="P.">The decision of the Review Hearing Officer shall constitute the final decision of the Director.</para>
    <para num="Q.">Under &lt;cite data-doc="City of Baltimore, Md., Code" data-path="|26"&gt;City Code Article 26&lt;/cite&gt;, §15-36, a party aggrieved by a final decision of the Director may appeal that decision to the Circuit Court for Baltimore City in accordance with the Maryland Rules of Civil Procedure.</para>