<baltimore-city-law heading="Regulation .07 Pavement Repairs and Restoration.">
  <section prefix="Regulation" num=".07" heading="Pavement Repairs and Restoration.">
    <para num="A.">Regardless of cut type, repairs will be done in accordance with Baltimore City DOT Standards.<para num="(1)">The Book of Standards is located on DOT’s website at:
&lt;u&gt;https://transportation.baltimorecity.gov/transportation/bookofstandards&lt;/u&gt;.</para>
      <para num="(2)">The DOT Street Cuts Section has the authority to increase the requirements of pavement restoration beyond minimum standards shown in the standard details based on<para num="(a)">site conditions, and</para>
        <para num="(b)">Street-cuts permit application information.</para>
      </para>
    </para>
    <para num="B.">Applicants and contractors shall adhere to the Street-cuts policies contained in these regulations; however,<para num="(1)">the Director has the discretion to permit exceptions to this policy under special circumstances; and</para>
      <para num="(2)">such exceptions shall be approved by the Director in writing.</para>
    </para>
    <para num="C.">The following are additional requirements for pavement repairs:<para num="(1)">when a utility cut is within 5 feet of a new or preexisting cut, both cuts shall be encapsulated into a single patch<para num="(a)">by milling away the intervening existing surface to allow for a single surface patch when one cut is preexisting and one cut is new; or</para>
        <para num="(b)">by combining the cuts into a single full-depth patch when both cuts are new; and</para>
        <para num="(c)">combined patches are subject to applicable Baltimore City DOT Standards.</para>
      </para>
      <para num="(2)">During resurfacing, the longitudinal pavement joints shall be constructed within 6 inches of the lane lines and not within the travel lanes.</para>
      <para num="(3)">If more than 50 percent of an asphalt or asphalt overlaid (composite) roadway is disturbed during longitudinal or transverse trenching, the entire block shall be milled and resurfaced<para num="(a)">from curb to curb, or</para>
        <para num="(b)">to the median curb, if applicable.</para>
      </para>
      <para num="(4)">The entire intersection must be milled and resurfaced if<para num="(a)">an asphalt or asphalt overlaid (composite) intersection is trenched diagonally, or</para>
        <para num="(b)">more than 50 percent of the intersection is disturbed during longitudinal and/or transverse trenching.</para>
      </para>
      <para num="(5)">All utility cuts must be backfilled and compacted in accordance with<para num="(a)">Baltimore City Standards outlined in Article 32.01.10 of the City of Baltimore Department of Public Works Specifications for Materials, Highways, Bridges, Utilities, and Incidental Structures (the “Green Book’);</para>
        <para num="(b)">the standards are found at &lt;u&gt;https://generalservices.baltimorecity.gov/gs-majorprojects/greenbook&lt;/u&gt;.</para>
      </para>
      <para num="(6)">Suitable fill material must be placed in 6-inch lifts and tamped with a mechanical tamper; and<para num="(a)">material one foot below subgrade must be compacted to 92 percent,</para>
        <para num="(b)">material in the top one foot must be compacted to 97percent; and</para>
        <para num="(c)">compaction of all material must be per the Modified Proctor ASTM D1557 (“AASHTO T180”).<para num="(i)">In lieu of borrow, CR-6 or excavation fills, #57 stone may be used; and</para>
          <para num="(ii)">it must be placed in no greater than one-foot lifts and tamped with a mechanical tamper.</para>
        </para>
      </para>
      <para num="(7)">Crusher Run Aggregate (“CR-6”) or Graded Aggregate Base (“GAB”) must be used for the proposed roadway paving sub-base, and<para num="(a)">must meet the requirements of Article 32 11 23.10 of the Green Book; and</para>
        <para num="(b)">Recycled Concrete (“RC-6”) may not be used for the sub-base material.</para>
      </para>
      <para num="(8)">The Contractor must supply compaction testing results for<para num="(a)">any paving patch greater than 1,000 square feet in area, and</para>
        <para num="(b)">any trench longer than 100 feet.</para>
      </para>
      <para num="(9)">A permittee must submit to the Department, at streetcuts@baltimorecity.gov, within 24 hours of the compaction:<para num="(a)">a copy of the compaction test results;</para>
        <para num="(b)">relevant location;</para>
        <para num="(c)">work date(s), and</para>
        <para num="(d)">designated permit number</para>
      </para>
    </para>
    <para num="D.">Final pavement restorations must include:<para num="(1)">removal of temporary backfill;</para>
      <para num="(2)">properly squaring off all Street-cuts to the bottom of the sub-base;</para>
      <para num="(3)">proper permanent backfills and compaction as specified in &lt;cite data-path="14.03.01.07|C.|(5)"&gt;Regulation .07.C(5)&lt;/cite&gt;;</para>
      <para num="(4)">permanent street restoration as specified in<para num="(a)">these Street-cuts regulations;</para>
        <para num="(b)">the City of Baltimore DOT Standards; and</para>
        <para num="(c)">the DPW Green Book;</para>
      </para>
      <para num="(5)">the patch must be installed so that it will remain flush with the surrounding pavement for 1 year after the work has been completed, inspected, and approved.</para>
    </para>
    <para num="E.">For utility upgrades and repairs that are performed in advance of a scheduled DOT contract, DOT may, at its sole discretion, allow the permit holder to provide temporary pavement repairs<para num="(1)">based upon the timing of the work in relation to the DOT contract schedule and the extent of the proposed trench excavations necessary for the utility work;</para>
      <para num="(2)">the type of temporary repair to be allowed will be decided by the Department on a case-by-case basis; and</para>
      <para num="(3)">the temporary pavement trench repair must conform to the current backfill procedures.</para>
    </para>
    <para num="F.">If the permittee uses steel plates to secure the public way during construction, they shall conform to:<para num="(1)">the Green Book; and</para>
      <para num="(2)">Baltimore City DOT Book of Standards.</para>
    </para>
    <para num="G.">Crosswalks.
In executing a street cut that disturbs a crosswalk, a person shall ensure that:<para num="(1)">The crosswalk is restored in accordance with the "Continental Crosswalk" style standards outlined in the Book of Standards;</para>
      <para num="(2)">Notwithstanding the provisions of &lt;cite data-path="14.03.01.07|G.|(1)"&gt;§G(1) of this regulation&lt;/cite&gt;, the crosswalk is restored with a decorative surface that:<para num="(a)">Matches the characteristics of a preexisting decorative surface; and</para>
        <para num="(b)">Is in accordance with standards provided by the Department when applicable;</para>
      </para>
      <para num="(3)">Each portion of a disturbed crosswalk is restored, including a portion of a disturbed crosswalk that is:<para num="(a)">Faded;</para>
        <para num="(b)">Missing; or</para>
        <para num="(c)">Otherwise noncompliant with an expected standard.</para>
      </para>
      <para num="(4)">The crosswalk is restored from curb to curb, unless the undisturbed portion of the crosswalk is:<para num="(a)">Compliant with the Book of Standards; and</para>
        <para num="(b)">In good condition, meaning it is:<para num="(i)">In new or like-new condition;</para>
          <para num="(ii)">Free of fading;</para>
          <para num="(iii)">Free of peeling; and</para>
          <para num="(iv)">Not otherwise defective in a way that reduces its visibility;</para>
        </para>
      </para>
      <para num="(5)">Notwithstanding the provisions of &lt;cite data-path="14.03.01.07|G.|(4)"&gt;§G(4) of this regulation&lt;/cite&gt;, the crosswalk is restored from curb to curb when trenching is done lengthwise through the crosswalk; and</para>
      <para num="(6)">When required by the Department to resurface an intersection in its entirety, each abutting crosswalk is restored as required by &lt;cite data-path="14.03.01.07|G.|(4)"&gt;§G(4) of this regulation&lt;/cite&gt;.</para>
    </para>
  </section>