<?xml version='1.0' encoding='utf-8'?>
<baltimore-city-law heading="§ 5-3 Schedule of compliance.">
  <section prefix="§" num="5-3" heading="Schedule of compliance.">
    <para num="(a)" heading="When required.">If pretreatment or operation and maintenance changes will be required for an industrial user to comply with any provisions of &lt;cite data-path="|25"&gt;this article&lt;/cite&gt; or any state or federal pretreatment standard or requirement, the City may require the industrial user to submit for approval a schedule specifying the shortest time frame for the industry to achieve compliance.</para>
    <para num="(b)" heading="Tenor of schedule.">
      <para num="(1)">Such schedule may not extend the compliance date beyond applicable federal deadlines.</para>
      <para num="(2)">This schedule will contain increments of progress in the form of dates for the commencement and completion of major events, leading to the construction and operation of the additional pretreatment to bring the industrial user into compliance.</para>
    </para>
    <annotation type="Prior Codifications">City Code, 1976/83, art. 25, §7(d)(1)(2nd - 4th sens.)</annotation>
    <annotation type="History">Ord. 91-775</annotation>
  </section>