§ 10-3 By whom work to be done.
Current through 2026-07-17. Source: City of Balt., Md., Ord. 26-129. Published by the Baltimore City Department of Legislative Reference.
Balt., Md., Code art. 26, § 10-3 (2026)
§ 10-3 By whom work to be done.LinkCopy Citation
(a)Director.
If no appeal is taken from the Director’s decision or if, after appeal, the Director’s decision is affirmed by the Board of Municipal and Zoning Appeals, the Director must then have the footway properly improved, graded, paved, repaved, or repaired.
(b)Owner.
The owner of the property may privately improve, grade, pave, repave, or repair the footway either:
(1)
within 45 days after the notice described under §10-1(b) is provided to the owner; or
(2)
if an appeal is taken, within 15 days after the decision of the Board of Municipal and Zoning Appeals
History: Rev. Ords. 1858-013
History: Ord. 12-102
History: Ord. 21-573
History: Ord. 22-711
History: Ord. 48-319
History: Ord. 76-139
History: Ord. 00-010
History:
History: