<?xml version='1.0' encoding='utf-8'?>
<baltimore-city-law heading="Subtitle 15 – Street Cuts">
  <container prefix="Part" num="1" heading="Definitions; General Provisions">
    <section prefix="§" num="15-1" heading="Definitions.">
      <para num="(a)" heading="In general.">In this subtitle, the following terms have the meanings indicated.</para>
      <para num="(b)" heading="Department.">“Department” means the Department of Transportation.</para>
      <para num="(c)" heading="Director.">“Director” means the Director of Transportation or the Director’s designee.</para>
      <para num="(d)" heading="Excavation.">“Excavation” means any work for or in connection with the installation, improvement, maintenance, or repair of any facilities that:<para num="(1)">involves the displacement or removal of materials; and</para>
        <para num="(2)">is performed in or below the surface of a public way.</para>
      </para>
      <para num="(e)" heading="Facilities.">
        <para num="(1)">“Facilities” means any equipment or other property that is located or proposed to be located in a public way.</para>
        <para num="(2)">“Facilities” includes access holes, cables, cabinets, ducts, conduits, converters, drains, handholds, pipes, pipelines, splice boxes, surface location markers, tracks, tunnels, valves, vaults, wires, or other appurtenances or property.</para>
      </para>
      <para num="(f)" heading="Person.">
        <para num="(1)" heading="In general.">“Person” has the meaning stated in &lt;cite data-path="|general|1|1|1-107|(a)"&gt;§ 1-107(a) {“Person: In general”}&lt;/cite&gt; of the City Code’s &lt;cite data-path="|general"&gt;General Provisions Article&lt;/cite&gt;.</para>
        <para num="(2)" heading="Inclusion of governmental entities.">Notwithstanding &lt;cite data-path="|general|1|1|1-107|(b)"&gt;§ 1-107(b) {“Person: Exclusion”}&lt;/cite&gt; of the &lt;cite data-path="|general"&gt;General Provisions Article&lt;/cite&gt;, in this subtitle “person”also  includes a governmental entity or an instrumentality or unit of a governmental entity.</para>
      </para>
      <para num="(g)" heading="Public way.">“Public way” means the entire area within the boundary lines of any public street, alley, sidewalk, footway, or other right-of-way, whether acquired by purchase, grant, dedication, or otherwise.</para>
      <para num="(h)" heading="Street-cut permit.">“Street-cut permit” means any permit required by or issued under this subtitle.</para>
      <para num="(i)" heading="Utility.">“Utility” means any person that owns or operates facilities used to provide electrical, gas, steam, water, sewer, telecommunications, information, video, or other services to customers.</para>
      <annotation type="History">Ord. 06-245</annotation>
      <annotation type="History">Ord. 15-435</annotation>
      <annotation type="History">Ord. 22-125</annotation>
    </section>
    <section prefix="§" num="15-2" heading="Scope of subtitle.">
      <para num="(a)" heading="In general.">This subtitle applies to any excavation on or in a public way by or on behalf of any public or private utility or any other person.</para>
      <para num="(b)" heading="Subtitle supplemental.">
        <para num="(1)">The requirements of this subtitle are in addition to any other law, rule, regulation, or standard applicable to excavations, construction, maintenance, repair, or other work in a public way.</para>
        <para num="(2)">Other applicable requirements include:<para num="(i)">obtaining and complying with the terms of any required franchise, minor privilege permit, developer’s agreement, right of entry, or similar authority; and</para>
          <para num="(ii)">notifying the City’s One-Call System contractor for the marking of facilities, as required by the State Public Utility Companies Article, Title 12, Subtitle 1.</para>
        </para>
      </para>
      <para num="(c)" heading="No private rights granted.">
        <para num="(1)">The issuance of a street-cut permit does not give any person any property right in or to the use of a public way.</para>
        <para num="(2)">All permits issued and held under this subtitle are subject to the superior right of the City to control the use of public ways and to ensure the safe and orderly movement of traffic.</para>
      </para>
      <annotation type="History">Ord. 06-245</annotation>
    </section>
    <section prefix="§" num="15-3" reserved="true" />
    <section prefix="§" num="15-4" heading="Administration.">
      <text>The Department of Transportation is responsible for administering and enforcing this subtitle.</text>
      <annotation type="History">Ord. 06-245</annotation>
      <annotation type="History">Ord. 15-435</annotation>
    </section>
    <section prefix="§" num="15-5" heading="Rules and regulations.">
      <para num="(a)" heading="Authorized.">Subject to Title 4 {“Administrative Procedure Act – Regulations”} of the &lt;cite data-path="|general"&gt;City General Provisions Article&lt;/cite&gt;, the Department of Transportation shall adopt rules and regulations to carry out this subtitle.</para>
      <para num="(b)" heading="Inclusions.">These rules and regulations shall incorporate standards set by the Department to govern:<para num="(1)">backfilling, repaving, and repair specifications;</para>
        <para num="(2)">traffic control;</para>
        <para num="(3)">work hours;</para>
        <para num="(4)">lighting, fencing, and covering of work areas; and</para>
        <para num="(5)">incidental related matters.</para>
      </para>
      <para num="(c)" heading="Stop-work orders.">These rules and regulations may include procedures for the issuance, service, and enforcement of administrative orders to stop work being done in violation of this subtitle, a rule or regulation adopted under this subtitle, or a condition imposed on a permit issued under this subtitle.</para>
      <annotation type="History">Ord. 06-245</annotation>
      <annotation type="History">Ord. 15-435</annotation>
      <annotation type="History">Text Conformed 02/23/21</annotation>
      <annotation type="Editor's Notes">By authority of Ordinance 20-431, Section 5, the Director of Legislative Reference, in consultation with the Law Department, has conformed this section to refer expressly to and reflect the requirements of the recently-enacted Administrative Procedure Act that, effective January 15, 2021, governs the proposal, adoption, and publication of administrative rules and regulations.</annotation>
    </section>
    <section prefix="§§" num="15-6 to 15-10" reserved="true" />
  </container>
  <container prefix="Part" num="2" heading="Permit Requirements">
    <section prefix="§" num="15-11" heading="In general.">
      <text>No person may excavate on or in a public way unless:</text>
      <para num="(1)">the person first obtains from the Department a street-cut permit for that excavation; or</para>
      <para num="(2)">the work is emergency excavation performed in accordance with &lt;cite data-path="|26|§15-13"&gt;§ 15-13 {“Emergency excavation”} of this subtitle&lt;/cite&gt;.</para>
      <annotation type="History">Ord. 06-245</annotation>
    </section>
    <section prefix="§" num="15-12" heading="Street-cut permit.">
      <para num="(a)" heading="Application.">Each application for a street-cut permit must be in the form and contain the information that the Director requires.</para>
      <para num="(b)" heading="Approval of permit; conditions.">If an application is approved, the Director may:<para num="(1)">impose conditions on the permit as necessary or appropriate to preserve and maintain the health, safety, welfare, and convenience of the public; and</para>
        <para num="(2)">issue the permit on receipt of:<para num="(i)">the permit fees imposed under &lt;cite data-path="|26|§15-14"&gt;§ 15-14 {“Fees”} of this subtitle&lt;/cite&gt;; and</para>
          <para num="(ii)">the performance security required under &lt;cite data-path="|26|§15-31"&gt;§ 15-31 {“Performance security”} of this subtitle&lt;/cite&gt;.</para>
        </para>
      </para>
      <para num="(c)" heading="Denial of permit.">
        <para num="(1)">The Director may deny an application if the applicant:<para num="(i)">within the preceding 2 years, has done excavation work without a street-cut permit or otherwise in violation of any applicable laws, rules, or regulations;</para>
          <para num="(ii)">has not satisfactorily completed all repairs required under a previously issued street-cut permit; or</para>
          <para num="(iii)">remains indebted to the City for:<para num="(A)">expenses previously incurred under this subtitle by the City; or</para>
            <para num="(B)">fines previously imposed under this subtitle by the City.</para>
          </para>
        </para>
        <para num="(2)">If an application is denied, the Director must notify the applicant, by written, electronic, or facsimile communication, of:<para num="(i)">the reasons for the denial; and</para>
          <para num="(ii)">how to obtain administrative review of the denial.</para>
        </para>
      </para>
      <para num="(d)" heading="Term.">Each street-cut permit shall specify:<para num="(1)">a start date on which work is first authorized to begin; and</para>
        <para num="(2)">an end date by which all work, inspections, and approvals must be completed.</para>
      </para>
      <para num="(e)" heading="Expiration.">Unless extended by the Department, a street-cut permit expires if the work to be done under the permit:<para num="(1)">has not begun within 30 calendar days of the start date;</para>
        <para num="(2)">is not pursued diligently; or</para>
        <para num="(3)">is not completed by the end date.</para>
      </para>
      <para num="(f)" heading="Nontransferability.">A street-cut permit is not transferable.</para>
      <annotation type="History">Ord. 06-245</annotation>
    </section>
    <section prefix="§" num="15-13" heading="Emergency excavation.">
      <para num="(a)" heading="When authorized.">A person may conduct an emergency excavation without first obtaining a street-cut permit only if:<para num="(1)">the excavation is needed, as a result of an unforeseen event, to prevent or abate a potential danger to life, health, or property;</para>
        <para num="(2)">before undertaking the excavation:<para num="(i)">the person notifies the Director of the emergency; and</para>
          <para num="(ii)">the Director authorizes the person to proceed with the excavation; and</para>
        </para>
        <para num="(3)">the person obtains a street-cut permit for the excavation:<para num="(i)">within 18 hours after beginning the excavation; or</para>
          <para num="(ii)">if the Department’s offices are closed, on the next day that its offices are open.</para>
        </para>
      </para>
      <para num="(b)" heading="Limitations.">Under no circumstances may an emergency excavation be closed before:<para num="(1)">a street-cut permit is issued; and</para>
        <para num="(2)">the work is inspected and approved by the Department.</para>
      </para>
      <annotation type="History">Ord. 06-245</annotation>
    </section>
    <section prefix="§" num="15-14" heading="Fees.">
      <para num="(a)" heading="In general.">Fees for street-cut permits shall be assessed in accordance with a fee schedule established by the Director, with the approval of the Board of Estimates.</para>
      <para num="(b)" heading="Differentials.">The fee schedule may set differential rates based on:<para num="(1)">size of excavation;</para>
        <para num="(2)">portion of public way affected;</para>
        <para num="(3)">extent of damage to the public way;</para>
        <para num="(4)">recency and nature of any previous repaving or repair; and</para>
        <para num="(5)">any other relevant factor.</para>
      </para>
      <annotation type="History">Ord. 06-245</annotation>
    </section>
    <section prefix="§§" num="15-15 to 15-20" reserved="true" />
  </container>
  <container prefix="Part" num="3" heading="Performance Schedules and Standards">
    <section prefix="§" num="15-21" heading="Scope.">
      <text>The requirements of this Part 3 are in addition to any requirements or standards imposed by the Department in its rules and regulations or as a condition of a street-cut permit.</text>
      <annotation type="History">Ord. 06-245</annotation>
    </section>
    <section prefix="§" num="15-22" heading="Display of permit.">
      <text>Any person doing excavation work must:</text>
      <para num="(1)">maintain the appropriate street-cut permit on site at all times; and</para>
      <para num="(2)">exhibit the permit when requested by the Department.</para>
      <annotation type="History">Ord. 06-245</annotation>
    </section>
    <section prefix="§" num="15-23" heading="Work schedule.">
      <para num="(a)" heading="Start.">No person may begin work under a street-cut permit until:<para num="(1)">in the case of an emergency excavation performed in accordance with &lt;cite data-path="|26|§15-13"&gt;§ 15-13 {“Emergency excavation”} of this subtitle&lt;/cite&gt;, the person notifies the Department and obtains permission to begin work; and</para>
        <para num="(2)">in all other cases, the start date specified in the permit.</para>
      </para>
      <para num="(b)" heading="Diligent pursuit.">The permittee must diligently pursue the work until its completion.</para>
      <para num="(c)" heading="Completion.">All work to be done under a street-cut permit must be completed, inspected, and approved before the end date specified in the permit.</para>
      <annotation type="History">Ord. 06-245</annotation>
    </section>
    <section prefix="§" num="15-24" heading="Securing public way.">
      <text>At the end of each workday, the permittee must secure the public way:</text>
      <para num="(1)">with temporary fill or paving;</para>
      <para num="(2)">by trench plating; or</para>
      <para num="(3)">by other protective measures approved by the Department.</para>
      <annotation type="History">Ord. 06-245</annotation>
    </section>
    <section prefix="§" num="15-25" heading="Decorative or landscaped areas.">
      <para num="(a)" heading="Alternative considerations.">Before disturbing decorative surfaces, streetscapes, and landscaped areas, the applicant for a street-cut permit must provide proof that alternatives, such as rerouting, boring, jacking, or scooping, cannot be used.</para>
      <para num="(b)" heading="Restoration.">Restoration of these areas must:<para num="(1)">comply with all conditions and other requirements of the permit;</para>
        <para num="(2)">conform with all current rules, regulations, and standards; and</para>
        <para num="(3)">when completed, match preexisting conditions.</para>
      </para>
      <annotation type="History">Ord. 06-245</annotation>
    </section>
    <section prefix="§" num="15-26" heading="Locating or relocating poles.">
      <para num="(a)" heading="In general.">Before erecting or relocating any pole, the applicant for a street-cut permit must agree, for itself and its successors in interest, to the conditions specified in this section.</para>
      <para num="(b)" heading="Locating pole.">The pole may be placed only in the position that the Director specifies.</para>
      <para num="(c)" heading="Required removal or relation.">
        <para num="(1)">If, at any time, the Director orders the pole to be removed or relocated, the pole will be removed or relocated within 3 days of the order or, if longer, within the time specified in the order.</para>
        <para num="(2)">All costs of removing or relocating the pole, including the cost of all needed repairs to the public way, will be borne by the applicant or its successors in interest.</para>
      </para>
      <annotation type="History">Ord. 06-245</annotation>
    </section>
    <section prefix="§§" num="15-27 to 15-28" reserved="true" />
  </container>
  <container prefix="Part" num="4" heading="Warranty; Performance Security; Indemnification">
    <section prefix="§" num="15-29" heading="Scope.">
      <text>This Part 4 does not apply to excavation work performed by a governmental entity.</text>
      <annotation type="History">Ord. 06-245</annotation>
    </section>
    <section prefix="§" num="15-30" heading="Warranty; Correction of defects.">
      <para num="(a)" heading="1-year warranty.">By accepting a street-cut permit, the permitee warrants all work done under the permit against all defects in workmanship and materials for a period of 1 year after the work has been completed, inspected, and approved.</para>
      <para num="(b)" heading="Correction of defect.">On written notice from the Department of any defect in workmanship or materials during the warranty period, the permittee must make the necessary repairs within the period specified in the notice.</para>
      <para num="(c)" heading="Abatement by City.">
        <para num="(1)">If the permitte fails to correct the defects within the time specified in the notice, the City may make the repairs at the permittee’s expense.</para>
        <para num="(2)">The permittee:<para num="(i)">is responsible for all expenses incurred by the City, including any related administrative expenses; and</para>
          <para num="(ii)">shall pay those expenses to the City within 30 days following notice of the amount owed.</para>
        </para>
      </para>
      <para num="(d)" heading="Extension of warranty.">Any repair during the warranty period automatically extends the warranty period to run for 1 additional year beyond the original warranty period.</para>
      <annotation type="History">Ord. 06-245</annotation>
    </section>
    <section prefix="§" num="15-31" heading="Performance security.">
      <para num="(a)" heading="“Performance security” defined.">In this section, “performance security” means any one or a combination of:<para num="(1)">a performance bond;</para>
        <para num="(2)">an irrevocable letter of credit; or</para>
        <para num="(3)">a cash deposit.</para>
      </para>
      <para num="(b)" heading="Required.">No street-cut permit may be issued to any person unless that person submits performance security as required by this section.</para>
      <para num="(c)" heading="Form and tenor.">
        <para num="(1)">The performance security must be approved:<para num="(i)">as to form and legal sufficiency by the City Solicitor; and</para>
          <para num="(ii)">as to amount by the Director.</para>
        </para>
        <para num="(2)">The performance security must serve to save the City harmless from:<para num="(i)">any cost, liability, expense, claim, or suit for damages in any manner arising out of or resulting from the work done under the permit; and</para>
          <para num="(ii)">any loss or cost by reason of the restoring or failure to restore the public way to required conditions and standards.</para>
        </para>
      </para>
      <para num="(d)" heading="Multi-permit security.">
        <para num="(1)">The performance security may be made to cover all street-cut permits issued from time to time to any one person.</para>
        <para num="(2)">In that case, the Director may require from time to time that the amount of the security be increased to an amount sufficient in the Director’s judgment to protect the City, based on the volume of work undertaken by the person or the number of permits issued to the person.</para>
      </para>
      <para num="(e)" heading="Release of security.">The Department shall release the performance security, in whole or in part, after completion of the warranty period and the correction of any defects or violations identified during that period.</para>
      <annotation type="History">Ord. 06-245</annotation>
    </section>
    <section prefix="§" num="15-32" heading="Indemnification.">
      <para num="(a)" heading="In general.">By accepting a street-cut permit, the permittee agrees, for and on behalf of itself and, if different, the owner and operator of the facilities, and their respective successors and assigns, to indemnify, defend, protect, and hold harmless the City, its officers, agents, and employees, from and against all claims, actions, costs, damages, demands, expenses, fines, injuries, judgments, liabilities, losses, penalties, suits, fees, and attorneys’ fees allegedly arising directly or indirectly from any act, omission, or negligence of the permitee, owner, or operator, their subcontractors, or the officers, agents, or employees of any of them relating to the permit or the activities authorized by the permit.</para>
      <para num="(b)" heading="Obligation to defend.">Each permittee, owner, and operator has an immediate and independent obligation to defend the City from any claims that actually or potentially fall within this indemnity obligation, even if the allegations are groundless, false, or fraudulent.</para>
      <para num="(c)" heading="Action by City.">The City has a cause of action for indemnity against each permittee, owner, and operator for any costs the City may incur with respect to the permit, except for claims resulting directly from the negligence or willful misconduct of the City.</para>
      <para num="(d)" heading="Indemnity survives permit, etc.">This indemnity obligation survives expiration of the permit and completion of the work authorized by it.</para>
      <annotation type="History">Ord. 06-245</annotation>
    </section>
    <section prefix="§§" num="15-33 to 15-35" reserved="true" />
  </container>
  <container prefix="Part" num="5" heading="Administrative and Judicial Review">
    <section prefix="§" num="15-36" heading="Administrative review.">
      <para num="(a)" heading="In general.">
        <para num="(1)">Any person aggrieved by a decision or action of the Department under this subtitle, whether as the result of the disapproval of an application, the issuance of a violation notice, an alleged failure to properly enforce this subtitle, or otherwise, may appeal that decision or action to the Director.</para>
        <para num="(2)">The appeal must:<para num="(i)">be in writing;</para>
          <para num="(ii)">be filed within 10 days of the decision or action in dispute; and</para>
          <para num="(iii)">clearly state the grounds on which the appeal is based.</para>
        </para>
      </para>
      <para num="(b)" heading="Procedures.">
        <para num="(1)">The Director shall adopt procedures for appeals and administrative hearings.</para>
        <para num="(2)">A copy of these procedures must be filed with the Department of Legislative Reference before they take effect.</para>
      </para>
      <annotation type="History">Ord. 06-245</annotation>
    </section>
    <section prefix="§" num="15-37" heading="Judicial review.">
      <text>A party aggrieved by a final decision of the Director under &lt;cite data-path="|26|§15-36"&gt;§ 15-36 {“Administrative review”} of this subtitle&lt;/cite&gt; may appeal that decision to the Circuit Court for Baltimore City in accordance with the Maryland Rules of Civil Procedure.</text>
      <annotation type="History">Ord. 06-245</annotation>
    </section>
    <section prefix="§§" num="15-38 to 15-40" reserved="true" />
  </container>
  <container prefix="Part" num="6" heading="Penalties">
    <section prefix="§" num="15-41" heading="Civil fines.">
      <para num="(a)" heading="In general.">The Director may impose civil fines for violations of:<para num="(1)">this subtitle.;</para>
        <para num="(2)">a rule or regulation adopted under this subtitle;</para>
        <para num="(3)">a condition imposed on a permit issued under this subtitle; or</para>
        <para num="(4)">a stop-work order issued under this subtitle.</para>
      </para>
      <para num="(b)" heading="Schedule of fines.">A schedule of fines, not to exceed $500 for any one offense, shall be established and may be amended from time to time by the Director with the approval of the Board of Estimates.</para>
      <annotation type="History">Ord. 06-245</annotation>
    </section>
    <section prefix="§" num="15-42" heading="Criminal penalties.">
      <text>Any person who violates any provision of this subtitle, of a rule or regulation adopted under this subtitle, of a condition imposed on a permit issued under this subtitle, or of a stop-work order issued under this subtitle is guilty of a misdemeanor and, on conviction, is subject to a fine of not more than $1,000, imprisonment for not more than 1 year, or both fine and imprisonment, for each offense.</text>
      <annotation type="History">Ord. 06-245</annotation>
    </section>
    <section prefix="§" num="15-43" heading="Each day a separate offense.">
      <text>Each day that a violation continues is a separate offense.</text>
      <annotation type="History">Ord. 06-245</annotation>
    </section>
  </container>
</baltimore-city-law>