<?xml version='1.0' encoding='utf-8'?>
<baltimore-city-law heading="Article 7 – Natural Resources">
  <container prefix="Division" num="I" heading="Floodplain Management">
    <container prefix="Subtitle" num="1" heading="Definitions; General Provisions">
      <section prefix="§" num="1-1" heading="Definitions – In general.">
        <text>In this Division I, the following terms have the meanings indicated.</text>
        <annotation type="History">Ord. 14-208</annotation>
      </section>
      <section prefix="§" num="1-2" heading="Definitions – “Accessory structure” to “Floodplain District”.">
        <para num="(a)" heading="Accessory structure.">“Accessory structure” means a detached structure:<para num="(1)">that is usable solely for parking vehicles or limited storage;</para>
          <para num="(2)">that is on the same parcel of property as the principal structure;</para>
          <para num="(3)">that is no larger than 300 square feet and 1 story; and</para>
          <para num="(4)">the use of which is incidental to the use of the principal structure.</para>
        </para>
        <para num="(b)" heading="Actual start of construction.">&lt;em&gt;See &lt;/em&gt;“new construction”.</para>
        <para num="(c)" heading="ASCE 24.">“ASCE 24” means the most current of ASCE/SEI 24, “Flood Resistant Design and Construction” (American Society of Civil Engineers).</para>
        <para num="(d)" heading="Base flood.">“Base flood” means a flood that has a 1% chance of being equaled or exceeded in any given year.</para>
        <para num="(e)" heading="Base-flood elevation.">
          <para num="(1)" heading="In general.">“Base-flood elevation” means the elevation of surface water resulting from a flood that has a 1%  chance of equaling or exceeding that level in any given year.</para>
          <para num="(2)" heading="Areas of shallow flooding.">In areas of shallow flooding, “base-flood elevation” means the highest natural elevation of the ground surface, prior to construction, that is adjacent to the proposed foundation of a structure; plus:<para num="(i)">the depth number specified in feet on the Flood Insurance Rate Map; or</para>
            <para num="(ii)">if the depth number is not specified, 4 feet.</para>
          </para>
        </para>
        <para num="(f)" heading="Basement.">“Basement” means any area of the building, including any sunken room or sunken portion of a room, having its floor below ground level on all sides.</para>
        <para num="(g)" heading="Coastal A Zone.">“Coastal A Zone” means an area within a special flood hazard area, landward of a coastal high hazard area (V Zone) or landward of a shoreline without a mapped coastal high hazard area, in which the principal source(s) of flooding are astronomical tides and storm surges, and in which, during base flood conditions, the potential exists for breaking waves with heights greater than or equal to 1.5 feet.  The inland limit of the Coastal A Zone may be delineated on FIRMs as the Limit of Moderate Wave Action (LiWMA).</para>
        <para num="(h)" heading="Design flood.">“Design flood”, as used in ASCE 24, is the greater of the following two flood events:<para num="(1)">area within a floodplain subject to a 1%  or greater chance of flooding in any year as identified on the Flood Insurance Rate Map as a Special Flood Hazard Area; or</para>
          <para num="(2)">area designated as a flood hazard area on a community’s flood hazard map or otherwise legally designated.</para>
        </para>
        <para num="(i)" heading="Design-flood elevation.">“Design-flood elevation”, as used in ASCE 24 for application to the City, means the elevation of the design flood, including wave height, relative to the datum specified on the flood hazard map.</para>
        <para num="(j)" heading="Development.">
          <para num="(1)" heading="In general.">“Development” means:<para num="(i)">any man-made change to improved or unimproved real estate; or</para>
            <para num="(ii)">the subdivision of land.</para>
          </para>
          <para num="(2)" heading="Inclusions.">“Development” includes any construction, reconstruction, modification, extension, or expansion of structures, placement of fill or concrete, construction of new or replacement infrastructure, temporary development, placement of manufactured homes or buildings, dumping, mining, dredging, grading, paving, drilling operations, storage of equipment, vehicles, materials, or products, land excavation, land clearing, land improvement, land fill operation, or any combination of these.</para>
        </para>
        <para num="(k)" heading="Dry floodproofing.">&lt;em&gt;See &lt;/em&gt;“floodproofing”.</para>
        <para num="(l)" heading="Elevation Certificate.">
          <para num="(1)" heading="In general.">“Elevation Certificate” means a certification, in the form and containing the information required by the Federal Emergency Management Agency, of the elevations of a structure and its improvements.</para>
          <para num="(2)" heading="By whom and how prepared.">An Elevation Certificate may only be prepared and certified by a licensed land surveyor or professional engineer, using Mean Sea Level as established by the North American Vertical Datum of 1988 (“NAVD”).</para>
        </para>
        <para num="(m)" heading="Fair market value.">
          <para num="(1)" heading="In general.">“Fair market value” means the price at which the improvement portion of the property will change hands between a willing buyer and a willing seller, neither of which is under compulsion to buy or sell and both of which have reasonable knowledge of relevant facts.</para>
          <para num="(2)" heading="By whom determined.">For purpose of this Division I, the fair market value of a structure is determined by:<para num="(i)">a licensed real estate appraiser; or</para>
            <para num="(ii)">the most recent, fully phased-in assessed value of the structure, as determined by the Maryland Department of Assessments and Taxation.</para>
          </para>
        </para>
        <para num="(n)" heading="FEMA.">“FEMA” means the Federal Emergency Management Agency.</para>
        <para num="(o)" heading="FIRM.">&lt;em&gt;See&lt;/em&gt; “Flood Insurance Rate Map”.</para>
        <para num="(p)" heading="FIS.">&lt;em&gt;See &lt;/em&gt;“Flood Insurance Study”.</para>
        <para num="(q)" heading="Flood.">“Flood” means a general and temporary condition of partial or complete inundation of normally dry land areas from:<para num="(1)">the overflow of inland or tidal waters; or</para>
          <para num="(2)">the unusual and rapid accumulation or runoff of surface waters from any source.
&lt;em&gt;See also&lt;/em&gt; “base flood” and “design flood”.</para>
        </para>
        <para num="(r)" heading="Flood elevation.">&lt;em&gt;See &lt;/em&gt;“base-flood elevation”, “design-flood elevation”, and “flood-protection elevation”.</para>
        <para num="(s)" heading="Flood hazard area.">&lt;em&gt;See&lt;/em&gt; “Regulated Flood Hazard Area” and “Special Flood Hazard Area”.</para>
        <para num="(t)" heading="Flood Insurance Rate Map (FIRM).">“Flood Insurance Rate Map” or “FIRM” means an official map on which the Federal Emergency Management Agency has delineated special flood hazard areas to indicate the magnitude and nature of flood hazards, to designate applicable flood zones, and to delineate floodways, if applicable.  FIRMs that have been prepared in digital format or converted to digital format are referred to as Digital FIRMs (DFIRM).</para>
        <para num="(u)" heading="Flood Insurance Study (FIS).">“Flood Insurance Study” or “FIS” means the official report in which the Federal Emergency Management Agency has provided flood profiles, floodway information, and water surface elevations.</para>
        <para num="(v)" heading="Flood-protection elevation.">“Flood-protection elevation” is:<para num="(1)">the base flood elevation plus 2 feet of freeboard in the non-tidal floodplain; and</para>
          <para num="(2)">the modeled elevation of the 0.2% chance of flood plus 2 feet of freeboard in the tidal floodplain as listed on the Flood Insurance Study (Table 4).</para>
        </para>
        <para num="(w)" heading="Floodplain.">“Floodplain” means any land area and watercourse susceptible to partial or complete inundation by water from any source, including::<para num="(1)">a relatively flat or low land area adjoining a river, stream, or watercourse that is subject to partial or complete inundation;</para>
          <para num="(2)">an area subject to the unusual and rapid accumulation or runoff of surface waters from any source; or</para>
          <para num="(3)">an area subject to tidal surge or extreme tides.</para>
        </para>
        <para num="(x)" heading="Floodplain District.">“Floodplain District” means the District, and its constituent subdistricts, established under Subtitle 2 {“Floodplain District”} of &lt;cite data-path="|7"&gt;this article&lt;/cite&gt;.</para>
        <annotation type="Prior Codifications">City Code, 1976/83, art. 7, §3</annotation>
        <annotation type="Prior Codifications">2000, art. 7 §1-1(part)</annotation>
        <annotation type="History">Ord. 88-188</annotation>
        <annotation type="History">Ord. 92-134</annotation>
        <annotation type="History">Ord. 11-516</annotation>
        <annotation type="History">Ord. 14-208</annotation>
        <annotation type="History">Ord. 21-020</annotation>
      </section>
      <section prefix="§" num="1-3" heading="Definitions – “Floodproofing” to “Wet floodproofing”.">
        <para num="(a)" heading="Floodproofing.">
          <para num="(1)" heading="In general.">“Floodproofing” means any combination of structural and nonstructural additions, changes, or adjustments to buildings or structures that reduce or eliminate flood damage to real estate or improved real property, water and sanitary facilities, &lt;em&gt;{and} &lt;/em&gt;structures and their contents, such that the buildings or structures are watertight with walls substantially impermeable to the passage of water and with structural components having the capability of resisting hydrostatic and hydrodynamic loads and effects of buoyancy.</para>
          <para num="(2)" heading="Methods of floodproofing.">For purposes of this Division I, the two methods of floodproofing are as follows:<para num="(i)">“Dry floodproofing”, which is a combination of measures that results in a structure, including the attendant utilities and equipment, being watertight with all elements substantially impermeable and with structural components having the capacity to resist flood loads, as specified in ASCE 24; and</para>
            <para num="(ii)">“Wet floodproofing”, which is the floodproofing method that, as specified in the following FEMA Technical Bulletins and on ASCE 24, relies on flood-damage-resistant materials and construction techniques in areas of a structure that are below the flood-protection elevation required by this standard by intentionally allowing those areas to flood :<para num="(A)">FEMA Technical Bulletin 2 {“Flood Damage-Resistant Material Requirements for Buildings Located in Special Flood Hazard Areas in accordance with the National Flood Insurance Program”}; and</para>
              <para num="(B)">FEMA Technical Bulletin 7 {“Wet Floodproofing Requirements for Structures Located in Special Flood Hazard Areas in accordance with the National Flood Insurance Program”}.</para>
            </para>
          </para>
        </para>
        <para num="(b)" heading="Floodproofing Certificate.">
          <para num="(1)" heading="In general.">“Floodproofing Certificate” means the FEMA Form 086-0-34 that is to be completed, signed and sealed by a licensed professional engineer or licensed architect to certify that the design of floodproofing and proposed methods of construction are in accordance with the applicable requirements of &lt;cite data-path="|7|§3-14"&gt;§ 3-14 of this article&lt;/cite&gt;.</para>
          <para num="(2)" heading="By whom prepared.">A floodproofing certificate may only be prepared and certified by a licensed professional engineer or professional architect.</para>
        </para>
        <para num="(c)" heading="Flood Resilience Area.">“Flood Resilience Area” means the area described in &lt;cite data-path="|7|§2-2|(g)"&gt;§ 2-2(g) {“Subdistricts: Flood Resilience Area”} of this article&lt;/cite&gt;, and that:<para num="(1)">appears on the Flood Insurance Rate Map as Shaded Zone X; and</para>
          <para num="(2)">includes all areas subject to the 0.2% annual chance flood.</para>
        </para>
        <para num="(d)" heading="Floodway.">
          <para num="(1)" heading="In general.">“Floodway” means the channel of a river or other watercourse and the adjacent land areas that must be reserved to pass the base-flood discharge so that the cumulative increase in the water surface elevation of the base-flood discharge is no more than a designated height.  When shown on a FIRM, the floodway is referred to as the “designated floodway.”</para>
          <para num="(2)" heading="Considered high-velocity-flow area.">An area shown on a FIRM as a “designated floodway” is considered an area with “high velocity flow”, as that term is used in ASCE 24, § 1.2 {“Definitions”}.</para>
        </para>
        <para num="(e)" heading="Freeboard.">
          <para num="(1)" heading="In general.">“Freeboard” is a factor of safety expressed in feet above the:<para num="(i)">height of the 0.2% annual chance of flood in the tidal floodplain; or</para>
            <para num="(ii)">base flood elevation in the non-tidal floodplain.</para>
          </para>
          <para num="(2)" heading="In Baltimore.">The freeboard in Baltimore City is 2 feet.</para>
        </para>
        <para num="(f)" heading="Functionally dependent use.">
          <para num="(1)" heading="In general.">“Functionally dependent use” means, except as otherwise provided in this subsection, any of the following uses that cannot perform their intended purposes unless located or carried out in close proximity to water:<para num="(i)">docking facilities that are necessary for the loading and unloading of cargo or passengers; and</para>
            <para num="(ii)">ship building and ship repair facilities.</para>
          </para>
          <para num="(2)" heading="Exclusions.">“Functionally dependent use” does not include long-term storage or related manufacturing facilities.</para>
        </para>
        <para num="(g)" heading="Historic structure.">“Historic structure” means a structure that is:<para num="(1)">individually listed in the National Register of Historic Places or certified or preliminarily determined by the Secretary of the Interior as meeting the requirements for individual listing in the Register;</para>
          <para num="(2)">individually listed in the Maryland Register of Historic Properties;</para>
          <para num="(3)">individually listed in the Baltimore City Landmark List; or</para>
          <para num="(4)">certified or preliminarily determined by the Secretary of the Interior as contributing to the historic significance of an historic district registered with the Secretary.</para>
        </para>
        <para num="(h)" heading="Limit of Moderate Wave Action (LiMWA).">“Limit of Moderate Wave Action (LiMWA)” means the inland limit of the area affected by waves greater than 1.5 feet during the base flood.  Base flood conditions between the VE Zone and the LiMWA will be similar to, but less severe than, those in the VE Zone.</para>
        <para num="(i)" heading="Limited storage.">“Limited storage” means storage that is incidental to the primary use of the principal structure and consists of low-damage items that cannot be conveniently stored above the flood-protection elevation.</para>
        <para num="(j)" heading="Lowest floor.">
          <para num="(1)" heading="In general.">“Lowest floor” means, except as otherwise provided in this subsection:<para num="(i)">the lowest floor of the lowest enclosed area (including basement) of a building or structure; the floor of an enclosure below the lowest floor is not the lowest floor provided the enclosure is constructed in accordance with these regulations; and</para>
            <para num="(ii)">the lowest floor of a manufactured home is the bottom of the lowest horizontal supporting member (longitudinal chassis frame beam).</para>
          </para>
          <para num="(2)" heading="Exclusions.">“Lowest floor” does not include any unfinished or flood-resistant enclosure that is usable solely for parking vehicles, building access, or limited storage, as long as the enclosure is not built so as to render the structure in violation of the applicable non-elevation design requirements of the Federal Emergency Management Agency, National Flood Insurance Program.</para>
        </para>
        <para num="(k)" heading="Manufactured home or building.">
          <para num="(1)" heading="In general.">“Manufactured home or building” means a structure, transportable in 1 or more sections, that is built on a permanent chassis and is designed for use with or without a permanent foundation when connected to the required utilities.</para>
          <para num="(2)" heading="Inclusions.">For floodplain management purposes,“manufactured home or building” includes any park trailer, travel trailer, and other similar vehicle placed on a site for more than 180 consecutive days.</para>
        </para>
        <para num="(l)" heading="Mixed-use structure.">Any structure that is used or intended for use for a mixture of nonresidential and residential uses in the same structure.</para>
        <para num="(m)" heading="New construction.">Structures include additions and improvements and the placement of manufactured homes, for which the start of construction commenced on or after March 15, 1978, the initial effective date of the City of Baltimore Flood Insurance Rate Map, including any subsequent improvements, alterations, modifications, and additions to such structures.<para num="(1)" heading="Exclusions.">“New construction” does not include any structure for which the building permit was issued before March 15, 1978, and the actual start of construction was within 180 days of the permit date.</para>
          <para num="(2)" heading="“Actual start of construction”.">As used in paragraph (1) of this subsection, “actual start of construction” means either:<para num="(i)">the first placement of permanent construction of a structure on a site, such as the pouring of slab or footings, the installation of piles, the construction of columns, or any work beyond the stage of excavation; or</para>
            <para num="(ii)">the placement of a manufactured home on a foundation.</para>
          </para>
          <para num="(3)" heading="“Permanent construction”.">As used in paragraph (2) of this subsection, “permanent construction” does not include:<para num="(i)">land preparation, such as clearing, grading, and filling;</para>
            <para num="(ii)">the installation of streets and walkways;</para>
            <para num="(iii)">excavation for basements, footings, piers, or foundations;</para>
            <para num="(iv)">the erection of temporary forms; or</para>
            <para num="(v)">the installation on the property of accessory structures.</para>
          </para>
        </para>
        <para num="(n)" heading="Nonconforming structure.">“Nonconforming structure” means any lawfully existing structure that does not comply with the applicable floodplain regulations of the subdistrict in which it is located.</para>
        <para num="(o)" heading="Nonresidential structure.">“Nonresidential structure” includes the nonresidential portion of a mixed-use structure.</para>
        <para num="(p)" heading="Planning Department.">“Planning Department” means the Baltimore City Department of Planning.</para>
        <para num="(q)" heading="Planning Director.">“Planning Director” means the Director of the Baltimore City Department of Planning or the Director’s designee.</para>
        <para num="(r)" heading="Regulated Flood Hazard Area.">“Regulated Flood Hazard Area” means:<para num="(1)">any Flood Resilience Area; and</para>
          <para num="(2)">any Special Flood Hazard Area.</para>
        </para>
        <para num="(s)" heading="Residential structure.">“Residential structure” includes the residential portion of a mixed-use structure.</para>
        <para num="(t)" heading="Special Flood Hazard Area.">
          <para num="(1)" heading="In general.">“Special Flood Hazard Area” means the land in a floodplain subject to a 1% or greater chance of flooding in any given year.</para>
          <para num="(2)" heading="By whom and how designated.">Special Flood Hazard Areas are designated by the Federal Emergency Management Agency in the Flood Insurance Study and on the Flood Insurance Rate Map as Zones A, AE, AH, AO, A1-30, and A99, and ZonesV1-30 and VE.</para>
        </para>
        <para num="(u)" heading="Structure.">
          <para num="(1)" heading="In general.">“Structure” means any building or other structure, specifically, a walled and roofed building.</para>
          <para num="(2)" heading="Inclusions.">“Structure” includes a gas or liquid storage tank that is principally above ground, as well as a manufactured home.</para>
        </para>
        <para num="(v)" heading="Subdivision.">
          <para num="(1)" heading="In general.">“Subdivision” means the division or redivision by any means of a lot, tract, or parcel of land into 2 or more lots, tracts, parcels, or other divisions of land.</para>
          <para num="(2)" heading="Inclusions.">“Subdivision” includes a change in existing lot lines for the purpose, whether immediate or future, of lease, transfer of ownership, building, or lot development.</para>
        </para>
        <para num="(w)" heading="Substantial damage.">
          <para num="(1)" heading="In general.">“Substantial damage” means damage of any origin sustained by a structure where the cost of restoring the structure to its before-damaged condition would equal or exceed 50% of the market value of the structure before the damage occurred.</para>
          <para num="(2)" heading="Calculation of costs.">
            <para num="(i)">The calculation of these costs must comply with FEMA P-758 {“Substantial Improvement / Substantial Damage Desk Reference”}.</para>
            <para num="(ii)">&lt;em&gt;See also &lt;/em&gt;§ 1-2(x){“Definitions: Substantial improvement”} of this subtitle.</para>
          </para>
        </para>
        <para num="(x)" heading="Substantial improvement.">
          <para num="(1)" heading="In general.">
            <para num="(i)">“Substantial improvement” means, except as otherwise provided in this subsection, any combination of repairs, reconstruction, rehabilitation, additions, or other improvements to a structure made during the 6-year period immediately preceding a permit application, the aggregate cost of which, together with the cost of the work proposed by the latest permit application, equals or exceeds 50% of the fair market value of the structure before the improvement is started.</para>
            <para num="(ii)">The calculation of these costs must comply with FEMA P-758 {“Substantial Improvement / Substantial Damage Desk Reference”}.</para>
            <para num="(iii)">For purposes of this definition, “substantial improvement” is considered to occur when the first alteration of any wall, ceiling, floor, or other structural part of the structure commences, whether or not that alteration affects the external dimensions of the structure.</para>
          </para>
          <para num="(2)" heading="Inclusions.">“Substantial improvement” includes improvements to a structure that has been substantially damaged, regardless of the actual repair work done.</para>
          <para num="(3)" heading="Exclusions.">“Substantial improvement” does not include either:<para num="(i)">an improvement of a structure that is required by a condemnation or violation notice, order, or citation to secure safe living conditions in compliance with State or City health, sanitary, or safety code specifications; or</para>
            <para num="(ii)">an alteration of an historic structure if the alteration will preclude the structure’s continued designation as an historic structure as approved by the Executive Director of the Historic and Architectural Preservation.</para>
          </para>
        </para>
        <para num="(y)" heading="Water &amp; Science Administration.">“Water &amp;amp; Science Administration” means the Water &amp;amp; Science Administration of the Maryland Department of the Environment.</para>
        <para num="(z)" heading="Wetland.">“Wetland” means any land that is:<para num="(1)">considered a “private wetland”  or a “State wetland” under Title 9 {”Wetlands and Riparian Rights”} of the State Natural Resources Article; or</para>
          <para num="(2)">defined as a “wetland” by the U.S. Fish and Wildlife Service Identification and Classification Procedures.</para>
        </para>
        <para num="(aa)" heading="Wet floodproofing.">&lt;em&gt;See &lt;/em&gt;“floodproofing”.</para>
        <annotation type="Prior Codifications">City Code, 1976/83, art. 7, §3</annotation>
        <annotation type="Prior Codifications">2000, art. 7 §1-1(part)</annotation>
        <annotation type="History">Ord. 88-188</annotation>
        <annotation type="History">Ord. 92-134</annotation>
        <annotation type="History">Ord. 11-516</annotation>
        <annotation type="History">Ord. 14-208</annotation>
        <annotation type="History">Ord. 14-283</annotation>
        <annotation type="History">Ord. 16-503</annotation>
        <annotation type="History">Ord. 21-020</annotation>
      </section>
      <section prefix="§" num="1-4" reserved="true" />
      <section prefix="§" num="1-5" heading="Rules of interpretation.">
        <para num="(a)" heading="In general.">In interpreting and applying this Division I, the following rules of interpretation apply:<para num="(i)">those contained in Subtitles 2 and 3 of the City Code’s &lt;cite data-path="|general"&gt;General Provisions Article&lt;/cite&gt;; and</para>
          <para num="(ii)">any additional rules contained in this section.</para>
        </para>
        <para num="(b)" heading="Conflicting provisions.">
          <para num="(1)" heading="Division sets minimum requirements.">In their interpretation and application, the provisions of this Division I must be taken to be the minimum requirements for the promotion of the public health, safety, and general welfare.</para>
          <para num="(2)" heading="Most restrictive provision governs.">If any condition imposed by a provision of this Division I is either more or less restrictive than a comparable condition imposed by any other provision of this Division or by any other law, rule, or regulation of any kind, the condition that is the more restrictive governs.</para>
        </para>
        <para num="(c)" heading="Liberal interpretation.">In their interpretation and application, the provisions of this Division I are to be:<para num="(1)">liberally construed in favor of proper flood hazard management and Baltimore City; and</para>
          <para num="(2)">considered as neither repealing nor limiting any powers granted by State law.</para>
        </para>
        <annotation type="Prior Codifications">City Code, 1976/83, art. 7, §2</annotation>
        <annotation type="Prior Codifications">2000, art. 7, §1-3(a)</annotation>
        <annotation type="History">Ord. 88-188</annotation>
        <annotation type="History">Ord. 14-208</annotation>
        <annotation type="History">Ord. 22-125</annotation>
      </section>
      <section prefix="§" num="1-6" reserved="true" />
      <section prefix="§§" num="1-7 to 1-8" reserved="true" />
      <section prefix="§" num="1-9" heading="Findings, intent, and design.">
        <para num="(a)" heading="Findings.">
          <para num="(1)">Certain areas of Baltimore City are subject to periodic inundation that results in loss of life and property, risks to health and safety, disruption of commerce and governmental services, and extraordinary public expenditures for flood protection and relief.</para>
          <para num="(2)">Flood losses and associated losses are created by structures inappropriately located, inadequately elevated, or otherwise unprotected and vulnerable to floods or erosion or by development that increases flood or erosion damage to other lands or development.</para>
          <para num="(3)">The biological values of floodplains, particularly tidal and non-tidal wetlands, can be adversely affected by floodplain development.</para>
          <para num="(4)">Baltimore City has the responsibility under the Flood Hazard Management Act of 1976, Title 5, Subtitle 8 of the State Environment Article, to control floodplain development in order to protect persons and property from danger and destruction and to preserve the biological values and environmental quality of the watersheds or the portions of watersheds under its jurisdiction.</para>
          <para num="(5)">Baltimore City has the responsibility under the National Flood Insurance Act of 1968 and the Flood Disaster Protection Act of 1973 to adopt and enforce floodplain management regulations that, at a minimum, meet the requirements of 44 Code of Federal Regulations Parts 55-77 et seq., in order to participate in the National Flood Insurance Program and remain eligible for federally subsidized flood insurance, federal disaster relief, and Federal and State financial assistance.</para>
          <para num="(6)">Baltimore City contains densely developed tidal shorelines that are and will continue to be in high demand.  The science behind climate change acknowledges that sea-level rise and coastal flooding will impact current and future development along the shoreline.  Floodplain regulations are meant to protect people and property while making the City more resilient to the impacts from natural disasters and climate change.</para>
        </para>
        <para num="(b)" heading="Intent.">It is, therefore, the intent of the Mayor and City Council by this Division I:<para num="(1)">to protect human life and health;</para>
          <para num="(2)">to minimize public and private property damage;</para>
          <para num="(3)">to encourage the utilization of appropriate construction practices in order to prevent or minimize flood damage in the future;</para>
          <para num="(4)">to protect individuals from unwittingly buying lands and structures that are unsuited for intended purposes because of the flood hazards;</para>
          <para num="(5)">to protect water supply, sanitary sewage disposal, and natural drainage;</para>
          <para num="(6)">to reduce financial burdens imposed on the community, its governmental units, and its residents by preventing the unwise design and construction of development in areas subject to flooding;</para>
          <para num="(7)">to provide for public awareness of the flooding potential; and</para>
          <para num="(8)">to provide for the biological and environmental quality of the watersheds or the portions of watershed located in Baltimore City.</para>
        </para>
        <para num="(c)" heading="Design.">This Division I provides a unified comprehensive approach to floodplain management that addresses the requirements of the following Federal and State programs concerned with floodplain management:<para num="(1)">the National Flood Insurance Program and the President’s Executive Order 11988 of May 27, 1977, on floodplain management;</para>
          <para num="(2)">the State Waterway Construction Permit Program;</para>
          <para num="(3)">the State Wetlands Permit Program;</para>
          <para num="(4)">the U.S. Army Corps of Engineers’ Section 10 and Section 404 Permit Programs; and</para>
          <para num="(5)">the State Coastal Zone Management Program.</para>
        </para>
        <para num="(d)" heading="Warning and disclaimer of liability.">
          <para num="(1)" heading="Warning.">The degree of flood protection required by these regulations is considered reasonable for regulatory purposes and is based on scientific and engineering considerations.  Larger floods can and will occur, and flood heights may be increased by man-made or natural causes.  These regulations do not imply that land outside of the special flood hazard areas or uses that are permitted within those areas will be free from flooding or flood damage.</para>
          <para num="(2)" heading="Disclaimer of liability.">These regulations shall not create liability on the part of the City of Baltimore, any of its officers or employees, the Maryland Department of the Environment (MDE), or the Federal Emergency Management Agency (FEMA) for any flood damage that results from reliance on these regulations or any administrative decision lawfully made hereunder.</para>
        </para>
        <annotation type="Prior Codifications">City Code, 1976/83, art. 7, §2</annotation>
        <annotation type="Prior Codifications">2000, art. 7, §1-2</annotation>
        <annotation type="History">Ord. 88-188</annotation>
        <annotation type="History">Ord. 14-208</annotation>
        <annotation type="History">Ord. 21-020</annotation>
      </section>
      <section prefix="§" num="1-10" heading="Short title.">
        <text>This Division I may be cited as the “Baltimore City Floodplain Management Code”.</text>
        <annotation type="Prior Codifications">City Code, 1976/83, art. 7, §1</annotation>
        <annotation type="Prior Codifications">2000, art. 7, §1-4</annotation>
        <annotation type="History">Ord. 88-188</annotation>
        <annotation type="History">Ord. 14-208</annotation>
      </section>
    </container>
    <container prefix="Subtitle" num="2" heading="Floodplain District">
      <section prefix="§" num="2-1" heading="Establishment of district.">
        <para num="(a)" heading="City to establish.">The City must establish a Floodplain District and an official floodplain map to include all areas subject to inundation by floodwaters.</para>
        <para num="(b)" heading="Bases.">
          <para num="(1)">The bases of this delineation must be, at a minimum, the data contained in the most recent Flood Insurance Study for Baltimore City, and illustrated in the Flood Insurance Rate Map.  The Flood Insurance Rate Map illustrates both the most recently adopted Special Flood Hazard Areas and the Flood Resilience Area.</para>
          <para num="(2)">The base-flood elevation, as determined in the Flood Insurance Study, is graphically delineated on the official floodplain map.</para>
          <para num="(3)">Where field-surveyed topography or digital topography indicates that ground elevations are above the base-flood elevation in a Special Flood Hazard Area, then the area is considered in the Special Flood Hazard Area until FEMA issues a Letter of Map Change.</para>
          <para num="(4)">Where field-surveyed topography or digital topography indicates that ground elevations are below the closest applicable flood-protection elevation, even in areas not delineated on the FIRM as a Regulated Flood Hazard Area, the area is considered to be a Regulated Flood Hazard Area.</para>
        </para>
        <para num="(c)" heading="District as overlay to zoning.">The Floodplain District is an overlay on any zoning district, as provided in the Zoning Code of Baltimore City.</para>
        <annotation type="Prior Codifications">City Code, 1976/83, art. 7, §4(a)</annotation>
        <annotation type="Prior Codifications">2000, art. 7, §2-1</annotation>
        <annotation type="History">Ord. 88-188</annotation>
        <annotation type="History">Ord. 92-134</annotation>
        <annotation type="History">Ord. 99-547</annotation>
        <annotation type="History">Ord. 11-516</annotation>
        <annotation type="History">Ord. 14-208</annotation>
        <annotation type="History">Ord. 14-307</annotation>
        <annotation type="History">Ord. 21-020</annotation>
      </section>
      <section prefix="§" num="2-2" heading="Subdistricts.">
        <para num="(a)" heading="In general.">
          <para num="(1)">The Floodplain District comprises the subdistricts set forth in this section.</para>
          <para num="(2)">In all floodplain districts, the flood-protection elevation is calculated as follows:<para num="(i)">In the tidal floodplain areas, it is the height and geographic extent of the 0.2% annual chance flood in the tidal area plus freeboard.</para>
            <para num="(ii)">In the non-tidal floodplain areas, it is the extent of the 0.2% annual chance flood, and the height of the 1% annual chance flood plus freeboard.</para>
          </para>
        </para>
        <para num="(b)" heading="Floodway.">The Floodway is that part of the Floodplain District that is reserved to convey a base-flood discharge so that the cumulative increase in the water surface elevation of the base-flood discharge is no more than the height designated by FEMA in the Flood Insurance Study.</para>
        <para num="(c)" heading="Floodway Fringe.">
          <para num="(1)">The Floodway Fringe comprises those lands within the Floodplain District that:<para num="(i)">are subject to inundation by a base flood; and</para>
            <para num="(ii)">lie beyond the Floodway (where a floodway has been determined), or in areas where detailed study data, profiles, and base-flood elevations have been established.</para>
          </para>
          <para num="(2)">The Floodway Fringe appears on the Flood Insurance Rate Map as Zone AE.</para>
        </para>
        <para num="(d)" heading="Approximated Floodplain.">
          <para num="(1)">The Approximated Floodplain comprises those lands within the Floodplain District that:<para num="(i)">are subject to inundation by a base flood; and</para>
            <para num="(ii)">lie in:<para num="(A)">areas for which a detailed study has not been performed, but a base floodplain boundary has been approximated; or</para>
              <para num="(B)">areas that are subject to shallow flooding.</para>
            </para>
          </para>
          <para num="(2)">A base-flood elevation must be established after consideration of any flood elevation and floodway data available from Federal, State, or other sources.</para>
          <para num="(3)">The Approximated Floodplain appears on the Flood Insurance Rate Map as Zones A and AO.</para>
        </para>
        <para num="(e)" heading="Coastal Floodplain.">
          <para num="(1)">The Coastal Floodplain, also referred to as tidal floodplain, comprises those lands within the Floodplain District that:<para num="(i)">due to high tides, hurricanes, tropical storms, and steady onshore winds, are subject to coastal or tidal inundation by a base flood; and</para>
            <para num="(ii)">lie in areas where detailed study data are available.</para>
          </para>
          <para num="(2)">The Coastal Floodplain appears on the Flood Insurance Rate Map as Zones A and AE, and includes areas encompassed by transects delineated by FEMA in the Flood Insurance Study.  (In Zone AE, a designation on the FIRM indicating “Limit of Moderate Wave Action” refers to the landward limit of waves of 1.5 feet or more in height.)</para>
        </para>
        <para num="(f)" heading="Coastal High Hazard Area.">
          <para num="(1)">The Coastal High Hazard Area is the area within a special flood hazard area extending from offshore to the inland limit of a primary frontal dune along an open coast and any other area that is subject to high velocity wave action from storms or seismic sources. This area is designated on FIRMs as velocity zones V, VO, VE, or V1-30, and includes areas encompassed by transects delineated by FEMA in the Flood Insurance Study.</para>
          <para num="(2)">The Coastal High Hazard Area appears on the Flood Insurance Rate Map as Zones V and VE.</para>
        </para>
        <para num="(g)" heading="Flood Resilience Area.">&lt;em&gt;See &lt;/em&gt;&lt;cite data-path="|7|§1-3|(c)"&gt;§ 1-3(c) {“Definitions: Flood Resilience Area”} of this Division I&lt;/cite&gt;.</para>
        <annotation type="Prior Codifications">City Code, 1976/83, art. 7, §4(b)</annotation>
        <annotation type="Prior Codifications">2000, art. 7, §2-2</annotation>
        <annotation type="History">Ord. 88-188</annotation>
        <annotation type="History">Ord. 92-134</annotation>
        <annotation type="History">Ord. 11-516</annotation>
        <annotation type="History">Ord. 14-208</annotation>
        <annotation type="History">Ord. 14-283</annotation>
        <annotation type="History">Ord. 21-020</annotation>
      </section>
      <section prefix="§" num="2-3" heading="Official map.">
        <para num="(a)" heading="In general.">
          <para num="(1)">The official floodplain map is the most current Flood Insurance Rate Map, as prepared by the Federal Emergency Management Agency.</para>
          <para num="(2)">The official floodplain map:<para num="(i)">must be maintained by the Planning Department; and</para>
            <para num="(ii)">is incorporated by reference as part of this Division I.</para>
          </para>
        </para>
        <para num="(b)" heading="Bases.">The minimum bases for establishing Regulated Flood Hazard Areas and their respective flood elevations are as follows:<para num="(1)">the most recent revision of the Flood Insurance Study for the City of Baltimore, dated June 16, 2021;</para>
          <para num="(2)">the accompanying Flood Insurance Rate Map; and</para>
          <para num="(3)">all subsequent amendments and revisions to the FIRM.</para>
        </para>
        <annotation type="Prior Codifications">City Code, 1976/83, art. 7, §4(c)</annotation>
        <annotation type="Prior Codifications">2000, art. §2-3</annotation>
        <annotation type="History">Ord. 88-188</annotation>
        <annotation type="History">Ord. 92-134</annotation>
        <annotation type="History">Ord. 11-516</annotation>
        <annotation type="History">Ord. 14-208</annotation>
        <annotation type="History">Ord. 21-020</annotation>
      </section>
      <section prefix="§" num="2-4" heading="Flood elevations.">
        <para num="(a)" heading="Nontidal floodplain.">
          <para num="(1)">Regulated Flood Hazard Areas in the nontidal floodplain are designated on the FIRM as “Special Flood Hazard Areas”.</para>
          <para num="(2)">The flood elevations for these areas correspond to the base-flood elevations specified in the Flood Insurance Study.</para>
        </para>
        <para num="(b)" heading="Tidal floodplain.">
          <para num="(1)">Regulated Flood Hazard Areas in the tidal floodplain are designated on the FIRM as Zones AE, V, VE, and X.</para>
          <para num="(2)">The flood elevations for Zones V and VE are as shown in the Flood Insurance Study’s Table 4 {“Transect Data”}, under the column heading “Zone Designation and BFE”.</para>
          <para num="(3)">The flood elevations for Shaded Zone X (“areas of 0.2% annual chance flood”) and for Zones A and AE are those shown in the Flood Insurance Study’s Table 4 {“Transect Data”}, under the column heading “0.2% Annual Chance”.</para>
        </para>
        <para num="(c)" heading="Flood elevations not provided by FIRM or FIS.">To establish flood elevations for Regulated Flood Hazard Areas that do not have these elevations shown on the Flood Insurance Rate Map or in the Flood Insurance Study, the Floodplain Manager may:<para num="(1)">provide the best available data for flood elevations;</para>
          <para num="(2)">require the applicant to obtain available information from Federal, State, or other sources; or</para>
          <para num="(3)">require the applicant to establish Regulated Flood Hazard Areas and design-flood elevations as set forth in &lt;cite data-path="|7|§2-5"&gt;§ 2-5 {“Changes to District”} of this subtitle&lt;/cite&gt;.</para>
        </para>
        <annotation type="Prior Codifications">City Code, 1976/83, art. 7, §4(c)(part)</annotation>
        <annotation type="Prior Codifications">2000, art. 7, §2-3(a)(part)</annotation>
        <annotation type="History">Ord. 14-208</annotation>
        <annotation type="History">Ord. 21-020</annotation>
      </section>
      <section prefix="§" num="2-5" heading="Changes to District.">
        <para num="(a)" heading="When authorized.">The delineation of the Floodplain District and its subdistricts may be revised, amended, or modified by the City, in compliance with the requirements of the National Flood Insurance Program and the Maryland Department of the Environment, if:<para num="(1)">there are changes through natural or other causes to flood elevations and boundaries; or</para>
          <para num="(2)">changes are indicated by detailed hydrologic and hydraulic information and studies.</para>
        </para>
        <para num="(b)" heading="Notice of changes.">As soon as practicable, but not later than 6 months after changes become known, the Planning Department must notify the Federal Insurance Administrator of the changes by submitting technical and scientific data in accordance with 44 Code of Federal Regulations, Part 65.</para>
        <para num="(c)" heading="Required Federal and State approvals.">All changes are subject to the review and approval of the Federal Emergency Management Agency and the Maryland Department of the Environment.</para>
        <annotation type="Prior Codifications">City Code, 1976/83, art. 7, §4(d)</annotation>
        <annotation type="Prior Codifications">2000, art. 7, §2-4</annotation>
        <annotation type="History">Ord. 88-188</annotation>
        <annotation type="History">Ord. 11-516</annotation>
        <annotation type="History">Ord. 14-208</annotation>
      </section>
      <section prefix="§" num="2-6" heading="Unmapped streams.">
        <para num="(a)" heading="Minimum flood protection setback.">If development is proposed in the vicinity of an unmapped stream that has no delineated base floodplain, a minimum of a 25-foot flood protection setback from the stream’s bank may be used.</para>
        <para num="(b)" heading="State permits.">State permits may be required.  Applicants should request the State Water &amp;amp; Science Administration for a determination of whether its permit requirements apply.</para>
        <para num="(c)" heading="Variances.">Variances may be applied for under Subtitle 5 {“Floodplain Variances”} of this Division I.</para>
        <annotation type="Prior Codifications">City Code, 1976/83, art. 7, §4(f)</annotation>
        <annotation type="Prior Codifications">2000, art. 7, §2-6</annotation>
        <annotation type="History">Ord. 92-134</annotation>
        <annotation type="History">Ord. 11-516</annotation>
        <annotation type="History">Ord. 14-208</annotation>
        <annotation type="History">Ord. 21-020</annotation>
      </section>
      <section prefix="§" num="2-7" heading="Floodplain Manager.">
        <para num="(a)" heading="Duties of Planning Department.">The Planning Department is responsible to ensure compliance with the National Flood Insurance Program.</para>
        <para num="(b)" heading="Planning Director to appoint Manager.">The Planning Director is responsible for appointing staff to carry out the duties of the Floodplain Manager.</para>
        <para num="(c)" heading="Duties of Floodplain Manager.">The Floodplain Manager is responsible for:<para num="(1)">overseeing and implementing the City’s floodplain program;</para>
          <para num="(2)">responding to all requests and inquiries by the Administrator of the National Flood Insurance Program;</para>
          <para num="(3)">reviewing applications to determine whether the proposed uses and other activities will be reasonably safe from flooding;</para>
          <para num="(4)">reviewing elevation certificates and requiring incomplete or deficient certificates to be corrected; and</para>
          <para num="(5)">keeping all files required by the National Flood Insurance Program.</para>
        </para>
        <annotation type="Prior Codifications">City Code, 2000, art. 7 §2-7</annotation>
        <annotation type="History">Ord. 11-516</annotation>
        <annotation type="History">Ord. 14-208</annotation>
      </section>
    </container>
    <container prefix="Subtitle" num="3" heading="Development Regulations">
      <container prefix="Part" num="1" heading="Overview">
        <section prefix="§" num="3-1" heading="In general.">
          <para num="(a)" heading="New construction and substantial improvements.">
            <para num="(1)">In order to prevent excessive damage to structures, all new construction and substantial improvements to existing structures in the Floodplain District must comply with:<para num="(i)">the regulations and restrictions of this subtitle; and</para>
              <para num="(ii)">except as otherwise provided in this Division I, the design and construction standards of:<para num="(A)">ASCE 24 {“Flood Resistant Design and Construction”}; and</para>
                <para num="(B)">ASCE 7 {“Minimum Design Loads for Buildings and Other Structures”}, Chapter 5 {“Flood Loads”}.</para>
              </para>
            </para>
            <para num="(2)">Where flood elevation data are used, the applicant must provide to the Planning Department:<para num="(i)">floodproofing elevations for all new construction and all substantial improvements to an existing structure; and</para>
              <para num="(ii)">corresponding elevation certificates.</para>
            </para>
          </para>
          <para num="(b)" heading="Projects overlapping subdistricts or elevations.">If a proposed structure or substantial improvement is sited in 2 different subdistricts or in a subdistrict with 2 different flood elevations, the most restrictive regulation or higher flood elevation prevails.</para>
          <para num="(c)" heading="Classification of structures.">For the purpose of applying appropriate requirements, structures are classified according to ASCE 24, Table 1-1 {“Classification of Structures for flood Resistant Design and Construction”}.</para>
          <annotation type="Prior Codifications">City Code, 1976/83, art. 7, §5(intro)</annotation>
          <annotation type="Prior Codifications">2000, art. §3-1</annotation>
          <annotation type="History">Ord. 88-188</annotation>
          <annotation type="History">Ord. 11-516</annotation>
          <annotation type="History">Ord. 14-208</annotation>
          <annotation type="History">Ord. 21-020</annotation>
        </section>
      </container>
      <container prefix="Part" num="2" heading="Districtwide Regulations">
        <section prefix="§" num="3-2" heading="In general.">
          <text>In the entire Floodplain District, the following regulations and restrictions apply.</text>
          <annotation type="Prior Codifications">City Code, 1976/83, art. 7, §5(a)(intro)</annotation>
          <annotation type="Prior Codifications">2000, art. 7, §3-2</annotation>
          <annotation type="History">Ord. 88-188</annotation>
          <annotation type="History">Ord. 14-208</annotation>
        </section>
        <section prefix="§" num="3-3" heading="Conformance to programs, plans, and BFR Codes.">
          <para num="(a)" heading="Permit programs.">The approval of any development must conform with the requirements of the permit programs of:<para num="(1)">the State Water &amp;amp; Science Administration; and</para>
            <para num="(2)">all other applicable Federal, State, and City agencies.</para>
          </para>
          <para num="(b)">Building, Fire, and Related Codes.
The approval of any development must conform with all applicable requirements of the &lt;cite data-path="|building-codes"&gt;Baltimore City Building, Fire, and Related Codes Article&lt;/cite&gt;.</para>
          <para num="(c)" heading="Management plans.">Where flood control and watershed management plans exist, all development must be consistent with those plans.</para>
          <annotation type="Prior Codifications">City Code, 1976/83, art. 7, §5(a)(1), (2)</annotation>
          <annotation type="Prior Codifications">2000, art. 7, §3-3</annotation>
          <annotation type="History">Ord. 88-188</annotation>
          <annotation type="History">Ord. 11-516</annotation>
          <annotation type="History">Ord. 14-208</annotation>
          <annotation type="History">Ord. 21-020</annotation>
        </section>
        <section prefix="§" num="3-4" heading="Residential structures.">
          <para num="(a)" heading="Elevation.">
            <para num="(1)">Every new or substantially improved residential structure, including a manufactured home, must have its lowest floor elevated to at least the flood-protection elevation.</para>
            <para num="(2)">The elevation of the lowest floor and the lowest elevation of machinery serving the structure  must be certified on an elevation certificate after the lowest floor and machinery are in place.</para>
            <para num="(3)">Every new or substantially improved residential structure must meet the requirements of &lt;cite data-path="|7|§3-14"&gt;§ 3-14 {“Enclosures below lowest floor or flood-protection elevation”} of this subtitle&lt;/cite&gt;.</para>
          </para>
          <para num="(b)" heading="Placement.">Every proposed structure must be placed on the lot so as to avoid location in the floodplain as much as possible.</para>
          <para num="(c)" heading="Basements.">Basements are not permitted in new structures and substantial improvement of existing structures (including repair of substantial damage).</para>
          <para num="(d)" heading="Enclosures below flood-protection elevation.">Enclosures below the flood-protection elevation shall be:<para num="(1)">used solely for parking of vehicles, limited storage and building access;</para>
            <para num="(2)">constructed using flood damage-resistant materials; and</para>
            <para num="(3)">provided with flood openings that meet the criteria listed under &lt;cite data-path="|7|§1-3|(a)"&gt;§ 1-3(a) {“Definitions: Floodproofing”} of this Division I&lt;/cite&gt;.</para>
          </para>
          <para num="(e)" heading="Expansions in tidal and nontidal floodplains.">Any horizontal expansion that increases the footprint and that is less than substantial must also have the lowest floor elevated to at least the flood-protection elevation.</para>
          <annotation type="Prior Codifications">City Code, 1976/83, art. 7, §5(a)(3)</annotation>
          <annotation type="Prior Codifications">2000, art. 7, §3-4</annotation>
          <annotation type="History">Ord. 92-134</annotation>
          <annotation type="History">Ord. 11-516</annotation>
          <annotation type="History">Ord. 14-208</annotation>
          <annotation type="History">Ord. 21-020</annotation>
        </section>
        <section prefix="§" num="3-5" heading="Nonresidential or mixed use structures.">
          <para num="(a)" heading="In general.">
            <para num="(1)">Every new or substantially improved nonresidential structure must be either:<para num="(i)">elevated to at least the flood-protection elevation; or</para>
              <para num="(ii)">dry or wet floodproofed.</para>
            </para>
            <para num="(2)">Basements are prohibited for any new nonresidential structure in the tidal and nontidal floodplains.</para>
            <para num="(3)">Every new or substantially improved nonresidential structure must meet the requirements of &lt;cite data-path="|7|§3-14"&gt;§ 3-14 {“Enclosures below lowest floor or flood-protection elevation”} of this subtitle&lt;/cite&gt;.</para>
            <para num="(4)">The elevation of the lowest floor of the improvement must be certified on an elevation certificate after the lowest floor is in place.</para>
            <para num="(5)">In mixed-use structures, areas below the flood-protection elevation may not be used for residential use even if the area is floodproofed.</para>
          </para>
          <para num="(b)" heading="Floodproofing option.">
            <para num="(1)">Floodproofing designs for existing structures must ensure that areas below the flood- protection elevation are watertight with walls substantially impermeable to the passage of water and with structural components capable of resisting hydrostatic and hydrodynamic loads and effects of buoyancy, as described in &lt;cite data-path="|7|§1-3|(a)"&gt;§ 1-3(a) {“Definitions: Floodproofing”} of this Division I&lt;/cite&gt;.</para>
            <para num="(2)">If the floodproofing option is chosen, a floodproofing certificate must be completed by a licensed professional engineer or professional architect who has reviewed the design and specifications and certifies that the nonresidential structure will meet this standard.  A Use and Occupancy permit cannot be approved until the floodproofing certificate is submitted.</para>
          </para>
          <para num="(c)" heading="Expansions in tidal and nontidal floodplains.">In tidal and nontidal floodplains, any horizontal expansion that increases the footprint and that is less than substantial must also have the lowest floor elevated to at least the flood-protection elevation.</para>
          <annotation type="Prior Codifications">City Code, 1976/83, art. 7, §5(a)(3-a)</annotation>
          <annotation type="Prior Codifications">2000, art. 7, §3-5</annotation>
          <annotation type="History">Ord. 92-134</annotation>
          <annotation type="History">Ord. 11-516</annotation>
          <annotation type="History">Ord. 14-208</annotation>
          <annotation type="History">Ord. 21-020</annotation>
        </section>
        <section prefix="§" num="3-6" heading="Less than substantial improvement.">
          <para num="(a)" heading="In general.">If the construction, reconstruction, or modification of any structure constitutes less than a substantial improvement:<para num="(1)">the installation of any electric, plumbing, or mechanical systems must comply with &lt;cite data-path="|7|§3-10"&gt;§ 3-10 {“Electric, plumbing, and mechanical systems”} of this subtitle&lt;/cite&gt;; and</para>
            <para num="(2)">those parts of the improvement below the flood-protection elevation must:<para num="(i)">be floodproofed; and</para>
              <para num="(ii)">otherwise comply with the design and construction standards of ASCE 24.</para>
            </para>
          </para>
          <para num="(b)" heading="Exceptions.">
            <para num="(1)">Routine maintenance, repairs, and the in-kind replacement of mechanical, electrical, and plumbing systems are exempt from the requirements of this section.</para>
            <para num="(2)">For in-kind replacement, the systems must be elevated to the maximum extent possible to avoid or minimize flood damage.</para>
          </para>
          <annotation type="Prior Codifications">City Code, 1976/83, art. 7, §5(a)(4)</annotation>
          <annotation type="Prior Codifications">2000, art. 7, §3-6</annotation>
          <annotation type="History">Ord. 88-188</annotation>
          <annotation type="History">Ord. 11-516</annotation>
          <annotation type="History">Ord. 14-208</annotation>
        </section>
        <section prefix="§" num="3-7" heading="Impacts on habitat.">
          <text>All development must be undertaken in a manner that minimizes adverse impacts on aquatic and terrestrial habitat and their related flora and fauna.</text>
          <annotation type="Prior Codifications">City Code, 1976/83, art. 7, §5(a)(6)</annotation>
          <annotation type="Prior Codifications">2000, art. 7, §3-7</annotation>
          <annotation type="History">Ord. 88-188</annotation>
          <annotation type="History">Ord. 14-208</annotation>
        </section>
        <section prefix="§" num="3-8" heading="Design, anchoring, and materials.">
          <para num="(a)" heading="In general.">All construction and improvements must be:<para num="(1)">designed, constructed, connected, and anchored to prevent flotation, collapse, or lateral movement of the structure, in accordance with the standards for new construction and substantial improvements specified in ASCE 24, § 1.5.1 {“General”};</para>
            <para num="(2)">constructed and placed on the lot so as to offer the minimum obstruction to the flow and height of floodwaters;</para>
            <para num="(3)">constructed with material and utility equipment resistant to flood damage; and</para>
            <para num="(4)">constructed by methods and practices that minimize flood damage.</para>
          </para>
          <para num="(b)" heading="Materials below the flood-protection elevation.">Unless the structure is dry floodproofed to the flood-protection elevation, materials used below that elevation must be resistant to floodwater damage, as specified in:<para num="(1)">FEMA Technical Bulletin 2, “Flood Damage-Resistant Materials Requirements for Buildings Located in Special Flood Hazard Areas in accordance with the National Flood Insurance Program”; and</para>
            <para num="(2)">ASCE 24, § 5.0 {“Materials”}.</para>
          </para>
          <para num="(c)" heading="Tanks.">Tanks must be designed and installed as specified in ASCE 24, § 7.4.1 {“Tanks”}.</para>
          <para num="(d)" heading="Elevators.">For installation in any structure located in any floodplain subdistrict, elevators must be designed and installed:<para num="(1)">as specified in ASCE 24, § 7.5 {“Elevators”}; and</para>
            <para num="(2)">as specified in FEMA Technical Bulletin 4: Technical Bulletin 4, Elevators in Buildings Located in Special Flood Hazard Areas.</para>
          </para>
          <annotation type="Prior Codifications">City Code, 1976/83, art. 7, §5(a)(7)</annotation>
          <annotation type="Prior Codifications">2000, art. 7, §3-8</annotation>
          <annotation type="History">Ord. 88-188</annotation>
          <annotation type="History">Ord. 14-208</annotation>
          <annotation type="History">Ord. 21-020</annotation>
        </section>
        <section prefix="§" num="3-9" heading="Landscape design.">
          <para num="(a)" heading="Ground cover.">Adequate ground cover must be provided for soil stabilization within the Floodplain District.</para>
          <para num="(b)" heading="Land contours and plant material.">Land contours must be designed and plant material chosen to direct surface runoff away from structures and not increase surface runoff onto neighboring properties.</para>
          <annotation type="Prior Codifications">City Code, 1976/83, art. 7, §5(a)(8)</annotation>
          <annotation type="Prior Codifications">2000, art. 7, §3-9</annotation>
          <annotation type="History">Ord. 88-188</annotation>
          <annotation type="History">Ord. 14-208</annotation>
        </section>
        <section prefix="§" num="3-10" heading="Electric, plumbing, and mechanical systems.">
          <para num="(a)" heading="In general.">Except as otherwise provided in subsection (b) of this section, electric, plumbing, and mechanical systems and their attendant components and equipment, including heaters, furnaces, generators, heat pumps, air conditioners, distribution panels, toilets, showers, sinks, duct work, and other permanent electrical, plumbing, or mechanical installations, are only permitted at or above the flood-protection elevation.</para>
          <para num="(b)" heading="Exceptions.">
            <para num="(1)">Subsection (a) of this section does not apply to a system that is designed and installed, in accordance with ASCE 24, to prevent water from entering or accumulating within its components and to resist hydrostatic and hydrodynamic loads and stresses, including the effects of buoyancy, during the occurrence of flooding to the flood-protection elevation.</para>
            <para num="(2)">In addition, electrical wiring systems for 1- and 2-family dwellings must conform to the requirements of the Baltimore City &lt;cite data-path="|building-codes|X"&gt;Residential Code&lt;/cite&gt; for One- and Two-Family Dwellings, Part VIII {“Electrical”}, for wet locations.</para>
            <para num="(3)">Subsection (a) of this section does not apply to routine maintenance, repairs, and the in-kind replacement of mechanical, electrical and plumbing systems in less than substantial improvement projects.</para>
          </para>
          <annotation type="Prior Codifications">City Code, 1976/83, art. 7, §5(a)(9), (10)</annotation>
          <annotation type="Prior Codifications">2000, art. 7, §3-10</annotation>
          <annotation type="History">Ord. 88-188</annotation>
          <annotation type="History">Ord. 11-516</annotation>
          <annotation type="History">Ord. 14-208</annotation>
          <annotation type="History">Ord. 21-020</annotation>
        </section>
        <section prefix="§" num="3-11" heading="Storage.">
          <text>Materials and products that are buoyant, flammable, or explosive, or that in times of flooding could be injurious to human, animal, or plant life may not be stored below the flood-protection elevation.</text>
          <annotation type="Prior Codifications">City Code, 1976/83, art. 7, §5(a)(11)</annotation>
          <annotation type="Prior Codifications">2000, art. 7, §3-11</annotation>
          <annotation type="History">Ord. 88-188</annotation>
          <annotation type="History">Ord. 11-516</annotation>
          <annotation type="History">Ord. 14-208</annotation>
          <annotation type="History">Ord. 21-020</annotation>
        </section>
        <section prefix="§" num="3-12" heading="Fill.">
          <para num="(a)" heading="In general.">
            <para num="(1)">In the Coastal High Hazard Area:<para num="(i)">fill is prohibited for structural support; but</para>
              <para num="(ii)">placement of nonstructural fill is allowed to the extent provided in this section and in ASCE 24, § 4.5.4 {“Use of Fill”}.</para>
            </para>
            <para num="(2)">In the Coastal Floodplain:<para num="(i)">fill material must meet the requirements of this section; and</para>
              <para num="(ii)">structural fill must comply with all applicable provisions of ASCE 24.</para>
            </para>
          </para>
          <para num="(b)" heading="Maximum fill amount.">The placement of more than 600 cubic yards of fill per acre in the floodplain is prohibited except by variance.</para>
          <para num="(c)" heading="Required alternate consideration.">
            <para num="(1)">Elevating a structure by other methods must be considered unless 600 cubic yards or less of fill are required.</para>
            <para num="(2)">An applicant must demonstrate that:<para num="(i)">fill is the only alternative to raising the structure to at least the flood- protection elevation; and</para>
              <para num="(ii)">the amount of fill used will not affect the flood storage capacity or increase flooding onto neighboring properties.</para>
            </para>
          </para>
          <para num="(d)" heading="Affect on adjacent properties.">Fill may be used only to the extent to which it does not adversely affect adjacent properties.</para>
          <para num="(e)" heading="Materials.">
            <para num="(1)">Fill may consist of soil or rock materials only.</para>
            <para num="(2)">Landfills, dumps, and sanitary soil fills are not permitted.</para>
          </para>
          <para num="(f)" heading="Compacting standards.">Fill material must be compacted in accordance with the standard proctor test method issued by the American Society for Testing and Materials (ASTM Standard D-698) to provide the necessary stability and resistance to erosion, scouring, or settling.</para>
          <para num="(g)" heading="Slopes.">Fill slopes may be no steeper than 1 vertical to 2 horizontal, unless substantiating data justifying steeper slopes are submitted to and approved by the Department of Public Works.</para>
          <para num="(h)" heading="Hydrologic and hydraulic analyses.">
            <para num="(1)">If structures on adjacent properties are known or determined to be subject to flooding under current conditions, the Floodplain Manager may require submission of hydrologic and hydraulic analyses to adequately demonstrate the effects of the proposed fill.</para>
            <para num="(2)">A hydrologic and hydraulic analysis requirement does not apply to projects located in the Coastal Floodplain or tidal portion of the Flood Resilience Area.</para>
          </para>
          <annotation type="Prior Codifications">City Code, 1976/83, art. 7, §5(a)(12)</annotation>
          <annotation type="Prior Codifications">2000, art. 7, §3-12</annotation>
          <annotation type="History">Ord. 88-188</annotation>
          <annotation type="History">Ord. 92-134</annotation>
          <annotation type="History">Ord. 14-208</annotation>
          <annotation type="History">Ord. 21-020</annotation>
        </section>
        <section prefix="§" num="3-13" heading="Accessory structures.">
          <para num="(a)" heading="In general.">Accessory structures shall be limited to no more than 300 square feet in total floor area.</para>
          <para num="(b)" heading="Requirements.">Accessory structures:<para num="(1)">shall comply with the elevation requirements and other requirements of &lt;cite data-path="|7|§3-14"&gt;§ 3-14 {“Enclosures below the first floor or flood-protection elevation”} of this subtitle&lt;/cite&gt;; or</para>
            <para num="(2)">shall:<para num="(i)">be useable only for parking of vehicles or limited storage;</para>
              <para num="(ii)">be constructed with flood damage-resistant materials below the flood-protection elevation;</para>
              <para num="(iii)">be constructed and placed to offer the minimum resistance to the flow of   floodwaters;</para>
              <para num="(iv)">be anchored to prevent flotation;</para>
              <para num="(v)">have electrical service and mechanical equipment elevated to or above the flood-protection elevation; and</para>
              <para num="(vi)">have flood openings that meet the criteria described in &lt;cite data-path="|7|§1-3|(a)"&gt;§ 1-3(a) {“Definitions: Floodproofing”} of this Division I&lt;/cite&gt;.</para>
            </para>
          </para>
          <annotation type="Prior Codifications">City Code, 1976/83, art. 7, §5(a)(14)</annotation>
          <annotation type="Prior Codifications">2000, art. 7, §3-13</annotation>
          <annotation type="History">Ord. 88-188</annotation>
          <annotation type="History">Ord. 92-134</annotation>
          <annotation type="History">Ord. 11-516</annotation>
          <annotation type="History">Ord. 14-208</annotation>
          <annotation type="History">Ord. 21-020</annotation>
        </section>
        <section prefix="§" num="3-14" heading="Enclosures below lowest floor or flood-protection elevation.">
          <para num="(a)" heading="In general.">New construction and substantial improvements of fully enclosed areas below the lowest floor or below the flood-protection elevation:<para num="(1)">are limited to floodproofed areas usable solely for parking vehicles, limited storage, and building access, as specified in §§ 1-3(a) {“Definitions: Floodproofing”}, § 3-4 {“Residential structures”}, and 3-5 {“Non-residential and mixed-used structures”} of this Division I; or</para>
            <para num="(2)">must be designed to meet or exceed the minimum criteria described in &lt;cite data-path="|7|§1-3|(a)"&gt;§ 1-3(a) {“Definitions: Floodproofing”} of this Division I&lt;/cite&gt; for dry floodproofing and wet floodproofing.</para>
          </para>
          <para num="(b)" heading="State regulations.">The State may have different, more stringent requirements set forth in &lt;cite data-doc="Code of Maryland Regulations" data-path="|26.17.03"&gt;COMAR 26.17.03&lt;/cite&gt; {“Construction on Nontidal Waters and Floodplains”}.</para>
          <annotation type="Prior Codifications">City Code, 1976/83, art. 7, §5(a)(14)</annotation>
          <annotation type="Prior Codifications">2000, art. 7, §3-14</annotation>
          <annotation type="History">Ord. 88-188</annotation>
          <annotation type="History">Ord. 92-134</annotation>
          <annotation type="History">Ord. 04-672</annotation>
          <annotation type="History">Ord. 11-516</annotation>
          <annotation type="History">Ord. 14-208</annotation>
          <annotation type="History">Ord. 21-020</annotation>
        </section>
        <section prefix="§" num="3-15" heading="Watercourses.">
          <para num="(a)" heading="In general.">
            <para num="(1)">For any proposed development that involves alteration of a watercourse, unless waived by MDE, the applicant shall develop hydrologic and hydraulic engineering analyses and technical data reflecting such changes, and submit such technical data to the Floodplain Administrator and to FEMA.  The analyses shall be prepared by a licensed professional engineer in a format required by MDE and by FEMA for a Conditional Letter of Map Revision and a Letter of Map Revision upon completion of the project.</para>
            <para num="(2)">Submittal requirements and fees shall be the responsibility of the applicant.</para>
          </para>
          <para num="(b)" heading="Submission requirements.">Alteration of a watercourse may be permitted only upon submission, by the applicant, of the following:<para num="(1)">a description of the extent to which the watercourse will be altered or relocated;</para>
            <para num="(2)">a certification by a licensed professional engineer that the flood-carrying capacity of the watercourse will not be diminished;</para>
            <para num="(3)">evidence that adjacent communities, the U.S. Army Corps of Engineers, and MDE have been notified of the proposal, and evidence that the notifications have been submitted to FEMA; and</para>
            <para num="(4)">evidence that the applicant shall be responsible for providing the necessary maintenance for the altered or relocated portion of the watercourse so that the flood carrying capacity will not be diminished.</para>
          </para>
          <para num="(c)" heading="Agreement with City.">
            <para num="(1)">The Floodplain Administrator may require the applicant to enter into an agreement with the Mayor and City Council specifying the maintenance responsibilities.</para>
            <para num="(2)">If an agreement is required, the permit shall be conditioned to require that the agreement be recorded on the deed of the property which shall be binding on future owners.</para>
          </para>
          <annotation type="Prior Codifications">City Code, 1976/83, art. 7, §5(a)(15-a)</annotation>
          <annotation type="Prior Codifications">2000, art. 7, §3-15</annotation>
          <annotation type="History">Ord. 92-134</annotation>
          <annotation type="History">Ord. 11-516</annotation>
          <annotation type="History">Ord. 14-208</annotation>
          <annotation type="History">Ord.  21-020</annotation>
        </section>
        <section prefix="§" num="3-16" heading="Flood protection setback.">
          <para num="(a)" heading="Watercourse with floodplain.">
            <para num="(1)">A minimum 25-foot flood protection setback must be maintained from the edge of the banks of any watercourse delineated on the floodplain map or FIRM as having a floodplain.</para>
            <para num="(2)">To prevent erosion, natural vegetation must be maintained in this area.</para>
            <para num="(3)">Where natural vegetation does not exist along the water course and conditions for replanting are suitable, high priority must be given to planting trees in the setback area to stabilize banks and to enhance aquatic resources.</para>
          </para>
          <para num="(b)" heading="Stream with no floodplain.">
            <para num="(1)">A minimum 25-foot flood-protection setback must be maintained from the top of the bank of any stream that has no designated floodplain.</para>
            <para num="(2)">Natural vegetation must be maintained and, if needed, trees planted.</para>
          </para>
          <annotation type="Prior Codifications">City Code, 1976/83, art. 7, §5(a)(15-b)</annotation>
          <annotation type="Prior Codifications">2000, art. 7, §3-16</annotation>
          <annotation type="History">Ord. 92-134</annotation>
          <annotation type="History">Ord. 14-208</annotation>
          <annotation type="History">Ord. 21-020</annotation>
        </section>
        <section prefix="§" num="3-17" heading="Utilities and facilities.">
          <para num="(a)" heading="In general.">In the entire Floodplain District, the design, placement, and construction of all public and private utilities and facilities must meet:<para num="(1)">the requirements of this section; and</para>
            <para num="(2)">all applicable requirements of ASCE 24.</para>
          </para>
          <para num="(b)" heading="Design and floodproofing.">
            <para num="(1)">New or replacement water supply systems, on-site disposal systems, or sanitary sewage systems must be designed and floodproofed:<para num="(i)">to eliminate or minimize infiltration of floodwaters into the systems and discharges from the systems into floodwaters; and</para>
              <para num="(ii)">to avoid impairment during flooding and minimize flood damage.</para>
            </para>
            <para num="(2)">All gas, electrical, and other facility and utility systems must be located, constructed, and floodproofed to eliminate or minimize flood damage.</para>
          </para>
          <para num="(c)" heading="Sewage systems.">
            <para num="(1)">All pipes connected to sewage systems must be sealed to prevent leakage.</para>
            <para num="(2)">Cesspools and seepage pits are prohibited.</para>
            <para num="(3)">Septic tanks are permitted if they are securely anchored to resist buoyant forces during inundation.</para>
          </para>
          <para num="(d)" heading="New storm drainage facilities.">All new storm drainage facilities within or leading to or from the Floodplain District must be adequately designed, floodproofed, and installed to:<para num="(1)">eliminate or minimize property damage resulting from the floodwaters of a base flood; and</para>
            <para num="(2)">minimize adverse environmental impacts of their installation and use.</para>
          </para>
          <annotation type="Prior Codifications">City Code, 1976/83, art. 7, §5(a)(16)</annotation>
          <annotation type="Prior Codifications">2000, art. 7, §3-17</annotation>
          <annotation type="History">Ord. 88-188</annotation>
          <annotation type="History">Ord. 92-134</annotation>
          <annotation type="History">Ord. 11-516</annotation>
          <annotation type="History">Ord. 14-208</annotation>
        </section>
        <section prefix="§" num="3-18" heading="Nontidal AE Zones without designated floodways.">
          <text>New development is not permitted within a nontidal AE Zone that is without a designated floodway, unless it is demonstrated that the cumulative effect of all past and projected development will not increase the base-flood elevation by more than 1 foot.</text>
          <annotation type="Prior Codifications">City Code, 2000, art. 7, §3-19</annotation>
          <annotation type="History">Ord. 11-516</annotation>
          <annotation type="History">Ord. 14-208</annotation>
        </section>
        <section prefix="§" num="3-19" heading="Recreational vehicles.">
          <para num="(a)" heading="“Recreational vehicle” defined.">In this section, “recreational vehicle” means a vehicle that is:<para num="(1)">built on a single chassis;</para>
            <para num="(2)">400 square feet or less when measured at the largest horizontal projection;</para>
            <para num="(3)">designed to be self-propelled or to be permanently towable by a light duty truck; and</para>
            <para num="(4)">designed primarily not for use as a permanent dwelling, but as temporary living quarters for recreational, camping, travel, or seasonal use.</para>
          </para>
          <para num="(b)" heading="Treatment of recreational vehicles.">All recreational vehicles in the Floodplain District must be:<para num="(1)">elevated and anchored as required by applicable State and Federal laws; or</para>
            <para num="(2)">fully licensed and highway ready.</para>
          </para>
          <annotation type="Prior Codifications">City Code, 2000, art. 7, §3-20</annotation>
          <annotation type="History">Ord. 11-516</annotation>
          <annotation type="History">Ord. 14-208</annotation>
        </section>
        <section prefix="§" num="3-20" heading="Temporary structures or storage.">
          <para num="(a)" heading="“Temporary structure” defined.">In this section, “temporary structure” a structure erected, installed, and used for a period not to exceed 180 days.</para>
          <para num="(b)" heading="Application for permit.">In addition to the requirements of &lt;cite data-path="|7|§4-2"&gt;§ 4-2 {“Development Permits: Applications”} of this Division I&lt;/cite&gt;, an application for the placement or erection of a temporary structure or for the temporary storage of any goods, materials, or equipment must specify the duration of the temporary use.</para>
          <para num="(c)" heading="Structures.">The temporary structure:<para num="(1)">must be designed and constructed to prevent flotation, collapse, or lateral movement resulting from hydrodynamic loads and hydrostatic loads during conditions of a base flood;</para>
            <para num="(2)">must have electric service installed in compliance with the Baltimore City &lt;cite data-path="|building-codes|III"&gt;electric code&lt;/cite&gt;;</para>
            <para num="(3)">must comply with all other requirements of the applicable State and City permit authorities; and</para>
            <para num="(4)">if in a Floodway, all necessary Federal and State permits must be obtained.</para>
          </para>
          <para num="(d)" heading="Storage.">Storage in a temporary structure may not include any hazardous materials.</para>
          <annotation type="History">Ord. 14-208</annotation>
          <annotation type="History">Ord. 21-020</annotation>
        </section>
        <section prefix="§" num="3-21" heading="Letter of Map Change.">
          <para num="(a)" heading="Scope of section.">This section applies to any property owner requesting mapping changes.</para>
          <para num="(b)" heading="Letter of Map Change.">A Letter of Map Change is an official FEMA determination, by letter, that amends or revises an effective Flood Insurance Rate Map or Flood Insurance Study.</para>
          <para num="(c)" heading="Letter of Map Amendment (LOMA).">A Letter of Map Amendment is an amendment based on technical data showing that a property was incorrectly included in a designated special flood hazard area.  A LOMA amends the current effective Flood Insurance Rate Map and establishes that a specific property or structure is not located in a special flood hazard area.</para>
          <para num="(d)" heading="Letter of Map Revision (LOMR).">A Letter of Map Revision is a revision based on technical data that may show changes to flood zones, flood elevations, floodplain and floodway delineations, and planimetric features.  A Letter of Map Revision Based on Fill (LOMR-F), is a determination that a structure or parcel of land has been elevated by fill above the base flood elevation and is, therefore, no longer exposed to flooding associated with the base flood. In order to qualify for this determination, the fill must have been permitted and placed in accordance with the community’s floodplain management regulations.</para>
          <para num="(e)" heading="Conditional Letter of Map Revision (CLOMR).">A Conditional Letter of Map Revision is a formal review and comment as to whether a proposed flood protection project or other project comply with the minimum NFIP requirements for such projects with respect to delineation of special flood hazard areas.  A Conditional Letter of Map Revision Based on Fill (CLOMR-F) is a determination that a parcel of land or proposed structure that will be elevated by fill would not be inundated by the base flood if fill is placed on the parcel as proposed or the structure is built as proposed.  A CLOMR does not revise the effective Flood Insurance Rate Map or Flood Insurance Study; on submission and approval of certified as-built documentation, a Letter of Map Revision may be issued by FEMA, to revise the effective FIRM.</para>
          <para num="(f)" heading="Issuance of permits.">If a proposed development is contingent upon a map change, no permits will be issued for the development until the Letter of Map Revision (LOMR) has been issued by FEMA.  The proposed development must be compliant with all pertinent requirements of Division I of &lt;cite data-path="|7"&gt;Article 7&lt;/cite&gt;.</para>
          <annotation type="History">Ord. 21-020</annotation>
        </section>
        <section prefix="§" num="3-22" reserved="true" />
      </container>
      <container prefix="Part" num="3" heading="Floodway Regulations">
        <section prefix="§" num="3-23" heading="In general.">
          <text>In the Floodway, the following regulations and restrictions apply.</text>
          <annotation type="Prior Codifications">City Code, 1976/83, art. 7, §5(b)(intro)</annotation>
          <annotation type="Prior Codifications">2000, art. 7, §3-21</annotation>
          <annotation type="History">Ord. 88-188</annotation>
          <annotation type="History">Ord. 14-208</annotation>
        </section>
        <section prefix="§" num="3-24" heading="New private principal structures prohibited.">
          <text>New construction of private principal structures, whether residential, commercial, or industrial, is prohibited.</text>
          <annotation type="Prior Codifications">City Code, 1976/83, art. 7, §5(b)(1)</annotation>
          <annotation type="Prior Codifications">2000, art. 7, §3-22</annotation>
          <annotation type="History">Ord. 88-188</annotation>
          <annotation type="History">Ord. 92-134</annotation>
          <annotation type="History">Ord. 14-208</annotation>
          <annotation type="History">Ord. 14-307</annotation>
        </section>
        <section prefix="§" num="3-25" heading="All development requires offset.">
          <text>Public infrastructure and environmental projects taking place on public land that aim to improve drainage and water quality are permitted in the floodway if:</text>
          <para num="(1)">the development complies with all otherwise applicable requirements of this Division I;</para>
          <para num="(2)">the effect of that development on flood heights is fully offset by accompanying stream modification; and</para>
          <para num="(3)">the development is approved by all appropriate local authorities, the State Water &amp;amp; Science Administration, and the U.S. Army Corps of Engineers.</para>
          <annotation type="Prior Codifications">City Code, 1976/83, art. 7, §5(b)(2)</annotation>
          <annotation type="Prior Codifications">2000, art. 7, §3-23</annotation>
          <annotation type="History">Ord. 88-188</annotation>
          <annotation type="History">Ord. 92-134</annotation>
          <annotation type="History">Ord. 11-516</annotation>
          <annotation type="History">Ord. 14-208</annotation>
          <annotation type="History">Ord. 21-020</annotation>
        </section>
        <section prefix="§" num="3-26" heading="Engineering report.">
          <para num="(a)" heading="Report required.">Any proposal to offset the effect of development in the Floodway by construction of stream modifications must be documented by an engineering report, prepared by a licensed professional engineer, that fully evaluates the effects of the construction and is submitted with the application for a building permit.</para>
          <para num="(b)" heading="Basis.">As the basis of analysis, the report must use the base flood and floodway data prepared by the Federal Emergency Management Agency.</para>
          <annotation type="Prior Codifications">City Code, 1976/83, art. 7, §5(b)(3)(1st and 2nd sens.)</annotation>
          <annotation type="Prior Codifications">2000, art. 7, §3-24</annotation>
          <annotation type="History">Ord. 88-188</annotation>
          <annotation type="History">Ord. 11-516</annotation>
          <annotation type="History">Ord. 14-208</annotation>
        </section>
        <section prefix="§" num="3-27" heading="Map revision.">
          <text>Any development in the floodway that proposes to increase the water surface elevation or change the delineation of the floodway requires a Conditional Letter of Map Revision and a Letter of Map Revision as described in &lt;cite data-path="|7|§3-21"&gt;§ 3-21 {“Letter of map change”} of this subtitle&lt;/cite&gt;.</text>
          <annotation type="Prior Codifications">City Code, 1976/83, art. 7, §5(b)(3)(2nd par.)</annotation>
          <annotation type="Prior Codifications">2000, art. 7, §3-26</annotation>
          <annotation type="History">Ord. 88-188</annotation>
          <annotation type="History">Ord. 92-134</annotation>
          <annotation type="History">Ord. 11-516</annotation>
          <annotation type="History">Ord. 14-208</annotation>
          <annotation type="History">Ord. 21-020</annotation>
        </section>
        <section prefix="§" num="3-28" heading="Alternative analysis.">
          <para num="(a)" heading="Required for permit.">Before a permit may be issued for any allowed development in the Floodway, the applicant must prepare and submit to the Planning Department an alternative analysis in accordance with this section.</para>
          <para num="(b)" heading="Scope of analysis.">The alternative analysis must demonstrate that:<para num="(1)">no reasonable alternative exists outside of the Floodway;</para>
            <para num="(2)">the encroachment in the Floodway is the minimum necessary;</para>
            <para num="(3)">the development will withstand a base flood without significant damage; and</para>
            <para num="(4)">on the basis of hydrologic and hydraulic analyses, prepared by a licensed professional engineer in accordance with the requirements of the Federal Emergency Management Agency and the Maryland Department of the Environment, the development:<para num="(i)">will not result in any increase in the base-flood elevation; and</para>
              <para num="(ii)">will neither increase downstream or upstream flooding or erosion nor significantly contribute to debris.</para>
            </para>
          </para>
          <annotation type="Prior Codifications">City Code, 1976/83, art. 7, §5(b)(3)(3rd par.) and (3-a)</annotation>
          <annotation type="Prior Codifications">2000, art. 7, §3-27</annotation>
          <annotation type="History">Ord. 88-188</annotation>
          <annotation type="History">Ord. 92-134</annotation>
          <annotation type="History">Ord. 11-516</annotation>
          <annotation type="History">Ord. 14-208</annotation>
        </section>
        <section prefix="§" num="3-29" heading="Changes to existing structures.">
          <para num="(a)" heading="Substantial improvements.">
            <para num="(1)">An existing structure in the Floodway may be substantially improved only:<para num="(i)">by variance;</para>
              <para num="(ii)">if the structure can be brought into conformance with this Division I without increasing its existing footprint; and</para>
              <para num="(iii)">if all residential uses of the structure are provided egress outside of the base flood.</para>
            </para>
            <para num="(2)">Substantial improvement of a nonconforming structure, regardless of location, may only be undertaken in compliance with this Division I and any other applicable law.</para>
          </para>
          <para num="(b)" heading="Substantial damage or proposed replacement.">
            <para num="(1)">In the event of substantial damage or proposed replacement, the applicant must submit an alternative analysis to determine if the structure can be relocated to a less hazardous site.</para>
            <para num="(2)">Where replacement structures cannot be relocated, they must be limited to the footprint of the previous structure.</para>
            <para num="(3)">Any replacement structure must meet all applicable requirements of this Division I.</para>
          </para>
          <para num="(c)" heading="Elevation or floodproofing.">The modification, alteration, repair, reconstruction, or improvement of any nonconforming structure amounting to less than a substantial improvement must be elevated or floodproofed to the greatest extent possible.</para>
          <para num="(d)" heading="Nuisance to be eliminated.">Uses or their adjuncts that are or become nuisances may not be permitted to continue.</para>
          <annotation type="Prior Codifications">City Code, 1976/83, art. 7, §5(b)(4)</annotation>
          <annotation type="Prior Codifications">2000, art. 7, §3-28</annotation>
          <annotation type="History">Ord. 88-188</annotation>
          <annotation type="History">Ord. 92-134</annotation>
          <annotation type="History">Ord. 14-208</annotation>
          <annotation type="Editor's Notes">This section, along with the rest of this Division I, was amended by Ordinance 14-208.  Initially, however, the specific changes to this section were inadvertently omitted from the section’s codification here.  The following text has since been corrected to incorporate all changes made by Ord.  14-208.</annotation>
        </section>
        <section prefix="§" num="3-30" heading="Prohibited structures.">
          <para num="(a)" heading="Manufactured homes or buildings.">The placement of any manufactured homes or buildings is prohibited.</para>
          <para num="(b)" heading="Fences, enclosures, etc.">The following may not be placed or caused to be placed in the Floodway:<para num="(1)">fences, except 2-rail or single-cable fences; and</para>
            <para num="(2)">any enclosures or materials (including fill) that:<para num="(i)">might impede, retard, or change the direction of the flow of water;</para>
              <para num="(ii)">will catch or collect debris carried by water; or</para>
              <para num="(iii)">is placed where the natural flow of stream or floodwaters would carry enclosures or materials downstream to the damage or detriment of public or private property in or adjacent to the floodplain.</para>
            </para>
          </para>
          <annotation type="Prior Codifications">City Code, 1976/83, art. 7, §5(b)(5), (6)</annotation>
          <annotation type="Prior Codifications">2000, art. 7, §3-29</annotation>
          <annotation type="History">Ord. 88-188</annotation>
          <annotation type="History">Ord. 14-208</annotation>
        </section>
        <section prefix="§§" num="3-31 to 3-32" reserved="true" />
      </container>
      <container prefix="Part" num="4" heading="Other Subdistrict Regulations">
        <section prefix="§" num="3-33" heading="Approximated Floodplain.">
          <para num="(a)" heading="In general.">In the Approximated Floodplain (Zones A and AO), the following additional regulations apply.</para>
          <para num="(b)" heading="Use of available data.">In the enforcement of this Division I, the Planning Department must obtain, review, and reasonably use any base-flood elevation and floodway data available from Federal, State, or other sources, such as the U.S. Army Corps of Engineers, the Soil Conservation Service, the State Water &amp;amp; Science Administration, or any regional planning organization.</para>
          <para num="(c)" heading="When data unavailable.">When the base-flood elevation is not known, the Planning Department, in consultation with the State Water &amp;amp; Science Administration, must evaluate each site and establish an approximate base-flood elevation.</para>
          <annotation type="Prior Codifications">City Code, 1976/83, art. 7, §5(c)</annotation>
          <annotation type="Prior Codifications">2000, art. 7, §3-31</annotation>
          <annotation type="History">Ord. 88-188</annotation>
          <annotation type="History">Ord. 11-516</annotation>
          <annotation type="History">Ord. 14-208</annotation>
          <annotation type="History">Ord. 21-020</annotation>
        </section>
        <section prefix="§" num="3-34" heading="Coastal Floodplain and Flood Resilience Area.">
          <text>In the Coastal Floodplain and the Flood Resilience Area, the regulations specified in ASCE 24, § 4.0 {“Coastal High Hazard Areas and Coastal A Zones”} apply.</text>
          <annotation type="Prior Codifications">City Code, 1976/83, art. 7, §5(d)</annotation>
          <annotation type="Prior Codifications">2000, art. 7, §3-32</annotation>
          <annotation type="History">Ord. 88-188</annotation>
          <annotation type="History">Ord. 14-208</annotation>
        </section>
        <section prefix="§" num="3-35" heading="Coastal High Hazard Area.">
          <para num="(a)" heading="In general.">In the Coastal High Hazard Area (Zones V and VE):<para num="(1)">the regulations of this section apply; and</para>
            <para num="(2)">except as otherwise provided in this Division I, the regulations specified in ASCE 24, § 4.0 {“Coastal High Hazard Areas and Coastal a Zones”} also apply.</para>
          </para>
          <para num="(b)" heading="Land below base flood level.">No land below the level of the base flood may be developed unless the new construction or substantial improvement:<para num="(1)">is located landward of the reach of mean high tide;</para>
            <para num="(2)">is elevated on adequately anchored pilings or columns to resist flotation, collapse, and lateral movement due to the effects of base-flood wind and water loads acting simultaneously on all building components, and the bottom of the lowest horizontal structural members of the lowest floor (excluding the pilings or columns) is elevated to at least the flood-protection elevation;</para>
            <para num="(3)">has been certified by a licensed professional engineer or professional architect that it is securely anchored to adequately anchored pilings or columns so as to withstand velocity waters and hurricane wave wash and that it will meet the requirements of item (2) of this subsection;</para>
            <para num="(4)">has no basement and has the space below the lowest floor free of obstructions (which space may not be used for human habitation, but may be used solely for parking, building access, or limited storage) and is constructed with breakaway walls, as that term is defined in ASCE 24, § 1.2 {“Definitions”}; and</para>
            <para num="(5)">does not utilize fill for structural support of structures.</para>
          </para>
          <para num="(c)" heading="Required showings.">No new development in the Coastal High Hazard Area may be permitted unless the applicant demonstrates that:<para num="(1)">the encroachment into the Coastal High Hazard Area is the minimum necessary;</para>
            <para num="(2)">the development will withstand, without damage, the wind and water loads attendant a base flood; and</para>
            <para num="(3)">the development will not create an additional hazard to existing structures.</para>
          </para>
          <para num="(d)" heading="Existing structures.">An existing nonconforming structure located on land below the level of the base flood may not be expanded, vertically, horizontally, or otherwise, unless:<para num="(1)">the foundation system is certified by a licensed professional engineer or professional architect as capable of supporting the existing structure and the proposed improvements during a base flood; and</para>
            <para num="(2)">all construction is in full compliance with this and all other applicable laws.</para>
          </para>
          <para num="(e)" heading="Manufactured homes or buildings.">The placement of manufactured homes or buildings is strictly prohibited.</para>
          <para num="(f)" heading="Record management.">For all new construction and every substantially improved structure in the Coastal High Hazard Area, the developer must submit and the Floodplain Manager must maintain on file an elevation certificate that certifies the elevation of the bottom of the lowest horizontal structural member of the lowest floor.</para>
          <para num="(g)" heading="Recreational vehicles.">
            <para num="(1)">In this subsection, “recreational vehicle” has the meaning stated in &lt;cite data-path="|7|§3-19"&gt;§ 3-19 {“Recreational vehicles”} of this subtitle&lt;/cite&gt;.</para>
            <para num="(2)">In the Coastal High Hazard Area, recreational vehicles are prohibited.</para>
          </para>
          <annotation type="Prior Codifications">City Code, 1976/83, art. 7, §5(e)</annotation>
          <annotation type="Prior Codifications">2000, art. 7, §3-33</annotation>
          <annotation type="History">Ord. 88-188</annotation>
          <annotation type="History">Ord. 92-134</annotation>
          <annotation type="History">Ord. 11-516</annotation>
          <annotation type="History">Ord. 14-208</annotation>
          <annotation type="History">Ord. 14-283</annotation>
        </section>
      </container>
    </container>
    <container prefix="Subtitle" num="4" heading="Development Permits">
      <section prefix="§" num="4-1" heading="Permit required.">
        <text>A Building permit issued by the Building Official under the Baltimore City &lt;cite data-path="|building-codes|II"&gt;Building Code&lt;/cite&gt;:</text>
        <para num="(1)">is required for all development in the Floodplain District; and</para>
        <para num="(2)">may be granted only after necessary permits from the State Water &amp;amp; Science Administration and all other applicable Federal, State, and City agencies have been obtained and verified by the Planning Department.</para>
        <annotation type="Prior Codifications">City Code, 1976/83, art. 7, §6(intro)</annotation>
        <annotation type="Prior Codifications">2000, art. 7, §4-1</annotation>
        <annotation type="History">Ord. 88-188</annotation>
        <annotation type="History">Ord. 11-516</annotation>
        <annotation type="History">Ord. 14-208</annotation>
        <annotation type="History">Ord. 21-020</annotation>
      </section>
      <section prefix="§" num="4-2" heading="Applications.">
        <para num="(a)" heading="From and to whom submitted.">The application for the permit must be submitted by the owner or authorized agent of the owner to the Building Official.</para>
        <para num="(b)" heading="Required information.">The application must contain, in addition to the information otherwise required by the Building Official for a building permit, the following information:<para num="(1)">the name and address of the applicant;</para>
          <para num="(2)">the name and address of the owner of land on which development is proposed;</para>
          <para num="(3)">the name and address of the contractor;</para>
          <para num="(4)">the site location;</para>
          <para num="(5)">a plan of the site showing the size and location of the proposed development, as well as any existing structures;</para>
          <para num="(6)">plans, drawn to scale, that show the location, dimensions, and NAVD elevation of the site in relation to:<para num="(i)">the stream channel or shoreline, as the case may be; and</para>
            <para num="(ii)">the Floodplain District delineation;</para>
          </para>
          <para num="(7)">a summary description of the proposed work and estimated cost; and</para>
          <para num="(8)">copies of all necessary permits from the State Water &amp;amp; Science Administration and all other applicable Federal, State, and City agencies.</para>
        </para>
        <para num="(c)" heading="Conditional information.">
          <para num="(1)">Depending on the type of development or structure involved, the Floodplain Manager may require:<para num="(i)">that an elevation certificate for the proposed development be submitted with the application; and</para>
            <para num="(ii)">that the following information be shown on plans submitted with the application:<para num="(A)">the size of each proposed structure and the position on the lot where it is to be constructed;</para>
              <para num="(B)">the elevations of the proposed final grading and lowest floor and the existing ground and base-flood elevation, as certified by a licensed land surveyor or professional engineer; and</para>
              <para num="(C)">the method of elevating the proposed structure, including details of proposed fills, pile structures, retaining walls, foundations, erosion protection measures, and the like.</para>
            </para>
          </para>
          <para num="(2)">These plans must be prepared by a licensed professional engineer or professional architect.</para>
        </para>
        <para num="(d)" heading="Appraisals for existing structures.">If substantial improvement to an existing structure is proposed, an appraisal must be submitted by a professional real estate appraiser of the fair market value of the existing structure, less land value.</para>
        <annotation type="Prior Codifications">City Code, 1976/83, art. 7, §6(a)</annotation>
        <annotation type="Prior Codifications">2000, art. 7, §4-2</annotation>
        <annotation type="History">Ord. 88-188</annotation>
        <annotation type="History">Ord. 11-516</annotation>
        <annotation type="History">Ord. 14-208</annotation>
        <annotation type="History">Ord. 14-307</annotation>
        <annotation type="History">Ord. 21-020</annotation>
      </section>
      <section prefix="§" num="4-3" heading="Plans for subdivisions or new development.">
        <para num="(a)" heading="Plan drawing required.">
          <para num="(1)">Every proposal for the subdivision of land or for new development must include a plan that shows the location of all existing and proposed public and private utilities, facilities, drainage structure, and road access.</para>
          <para num="(2)">If the base-flood elevation has been determined by the Flood Insurance Study or other reliable source, as provided in &lt;cite data-path="|7|§2-3"&gt;§ 2-3 {“Official map”} of this Division I&lt;/cite&gt;, that flood elevation must be delineated on the plan.</para>
          <para num="(3)">If the proposal involves more than 5 lots or more than 5 acres and the base-flood elevation has not been determined for the land area, the developer must determine the base-flood elevation and delineate that flood elevation on the plan.  If hydrologic and hydraulic engineering analyses are submitted, they must be certified in accordance with the requirements of the Maryland Department of the Environment and the Federal Emergency Management Agency.</para>
        </para>
        <para num="(b)" heading="Certification and review.">All plans must be certified by a licensed professional engineer or professional architect and reviewed by the Department of General Services to assure that:<para num="(1)">all proposals are consistent with the need to minimize flood damage;</para>
          <para num="(2)">all necessary permits have been received from the State Water &amp;amp; Science Administration and appropriate Federal agencies;</para>
          <para num="(3)">all public and private utilities and facilities (including sewer, water, telephone, electric, gas, etc.) are located, constructed, and floodproofed to minimize or eliminate flood damage;</para>
          <para num="(4)">adequate drainage is provided to reduce exposure to flood hazards;</para>
          <para num="(5)">during a base flood, at least 1 access point provides safe vehicular access to and egress from the subdivision or new development; and</para>
          <para num="(6)">adequate measures have been taken to minimize adverse environmental impacts of the proposed development.</para>
        </para>
        <annotation type="Prior Codifications">City Code, 1976/83, art. 7, §6(b)</annotation>
        <annotation type="Prior Codifications">2000, art. 7, §4-3</annotation>
        <annotation type="History">Ord. 88-188</annotation>
        <annotation type="History">Ord. 11-516</annotation>
        <annotation type="History">Ord. 14-208</annotation>
        <annotation type="History">Ord. 21-020</annotation>
      </section>
      <section prefix="§" num="4-4" heading="Conformance to codes required.">
        <text>A permit may be granted only after it has been determined that the proposed work will be in conformance with the requirements of this and all other applicable laws.</text>
        <annotation type="Prior Codifications">City Code, 1976/83, art. 7, §6(c)</annotation>
        <annotation type="Prior Codifications">2000, art. 7, §4-4</annotation>
        <annotation type="History">Ord. 88-188</annotation>
        <annotation type="History">Ord. 14-208</annotation>
      </section>
      <section prefix="§" num="4-5" heading="Alteration of watercourse.">
        <para num="(a)" heading="Notices required.">
          <para num="(1)">When the proposed development includes the relocation or alteration of a watercourse, evidence must be presented as part of the permit application that all adjacent communities and the State Water &amp;amp; Science Administration have been notified by certified mail and have approved of the proposed alteration or relocation.</para>
          <para num="(2)">Copies of these notifications must then be forwarded to the Federal Emergency Management Agency, Federal Insurance Administration.</para>
        </para>
        <para num="(b)" heading="Assurances of flood-carrying capacity.">In addition, the developer must assure the City, in writing, that the flood-carrying capacity within the altered or relocated portion of the watercourse in question will be preserved.</para>
        <annotation type="Prior Codifications">City Code, 1976/83, art. 7, §6(d)</annotation>
        <annotation type="Prior Codifications">2000, art. 7, §4-5</annotation>
        <annotation type="History">Ord. 88-188</annotation>
        <annotation type="History">Ord. 11-516</annotation>
        <annotation type="History">Ord. 14-208</annotation>
        <annotation type="History">Ord. 21-020</annotation>
      </section>
      <section prefix="§" num="4-6" heading="Changes to application, permit, etc.">
        <text>After the issuance of a building permit by the Building Official, no changes of any kind may be made to the application, permit, or any of the plans, specifications, or other documents submitted with the application without the written consent or approval of the Building Official.</text>
        <annotation type="Prior Codifications">City Code, 1976/83, art. 7, §6(e)</annotation>
        <annotation type="Prior Codifications">2000, art. 7, §4-6</annotation>
        <annotation type="History">Ord. 88-188</annotation>
        <annotation type="History">Ord. 14-208</annotation>
      </section>
      <section prefix="§" num="4-7" heading="Inspections; permit revocation.">
        <para num="(a)" heading="Inspections by City and State.">
          <para num="(1)">During the construction period, the Building Official must inspect the premises to determine that the work is progressing in compliance with the permit and with all applicable laws.</para>
          <para num="(2)">The premises are also subject to inspection by the State Water &amp;amp; Science Administration.</para>
        </para>
        <para num="(b)" heading="Revocation of permit.">If the Building Official determines that the work is not in compliance with the permit and all applicable laws or that there has been a false statement or misrepresentation by the applicant, the Building Official, on instruction from the Planning Department, may revoke the permit and report that fact to the State Water &amp;amp; Science Administration.</para>
        <annotation type="Prior Codifications">City Code, 1976/83, art. 7, §6(f)</annotation>
        <annotation type="Prior Codifications">2000, art. 7, §4-7</annotation>
        <annotation type="History">Ord. 88-188</annotation>
        <annotation type="History">Ord. 11-516</annotation>
        <annotation type="History">Ord. 14-208</annotation>
        <annotation type="History">Ord. 21-020</annotation>
      </section>
      <section prefix="§" num="4-8" heading="Requisites for occupancy permit.">
        <para num="(a)" heading="Elevation Certificate.">An occupancy permit issued by the Building Official:<para num="(1)">is required for all new construction and substantial improvements in the Floodplain District; and</para>
          <para num="(2)">may not be issued until the Building Official has been provided with an elevation certificate that certifies the “as-built” elevations of the new construction or substantial improvements.</para>
        </para>
        <para num="(b)" heading="Dry Floodproofing Certificate.">When applicable, a dry floodproofing certificate is also required prior to the approval of the occupancy permit.</para>
        <annotation type="Prior Codifications">City Code, 1976/83, art. 7, §6(g)</annotation>
        <annotation type="Prior Codifications">2000, art. 7, §4-8</annotation>
        <annotation type="History">Ord. 88-188</annotation>
        <annotation type="History">Ord. 11-516</annotation>
        <annotation type="History">Ord. 14-208</annotation>
        <annotation type="History">Ord. 21-020</annotation>
      </section>
      <section prefix="§" num="4-9" heading="Record of permit actions.">
        <para num="(a)" heading="Required.">A record of all permit actions in the Floodplain District, including all permits from applicable Federal, State, and City agencies, must be maintained by the Planning Department and must be made available on the request of the Federal Emergency Management Agency or the State Water &amp;amp; Science Administration during periodic assessments of Baltimore City’s participation in the National Flood Insurance Program.</para>
        <para num="(b)" heading="Contents.">This record must include, at a minimum:<para num="(1)">the date the permit was issued;</para>
          <para num="(2)">the “as-built” lowest floor elevation of all new construction or substantial improvement;</para>
          <para num="(3)">a copy of all other elevation certificates submitted under this Division I;</para>
          <para num="(4)">the issuance date of any occupancy permit; and</para>
          <para num="(5)">any map amendments issued by the Federal Emergency Management Agency.</para>
        </para>
        <annotation type="Prior Codifications">City Code, 1976/83, art. 7, §6(h)</annotation>
        <annotation type="Prior Codifications">2000, art. 7, §4-9</annotation>
        <annotation type="History">Ord. 88-188</annotation>
        <annotation type="History">Ord. 11-516</annotation>
        <annotation type="History">Ord. 14-208</annotation>
        <annotation type="History">Ord. 21-020</annotation>
      </section>
    </container>
    <container prefix="Subtitle" num="5" heading="Floodplain Variances">
      <section prefix="§" num="5-1" heading="In general.">
        <text>Applications for variances may be considered by the Planning Department, after a review by the City agencies responsible for stormwater management and erosion control, for the following:</text>
        <para num="(1)">functionally dependent uses;</para>
        <para num="(2)">all necessary City utilities in the Floodway or the Coastal High Hazard Area; and</para>
        <para num="(3)">substantial improvements to an existing structure in the Floodway.</para>
        <annotation type="Prior Codifications">City Code, 1976/83, art. 7, §7(a)</annotation>
        <annotation type="Prior Codifications">2000, art. 7, §5-1</annotation>
        <annotation type="History">Ord. 88-188</annotation>
        <annotation type="History">Ord. 92-134</annotation>
        <annotation type="History">Ord. 14-208</annotation>
        <annotation type="History">Ord. 21-020</annotation>
      </section>
      <section prefix="§" num="5-2" heading="Prohibited variances.">
        <text>A variance may not be granted for:</text>
        <para num="(1)">the placement of fill in the Floodway or the Coastal High Hazard Area unless approved by appropriate Federal and State agencies;</para>
        <para num="(2)">new construction of any principal structure in the Floodway or the Coastal High Hazard Area; or</para>
        <para num="(3)">manufactured homes or buildings within the Floodway and Coastal High Hazard Area.</para>
        <annotation type="Prior Codifications">City Code, 1976/83, art. 7, §7(b)</annotation>
        <annotation type="Prior Codifications">2000, art. 7, §5-2</annotation>
        <annotation type="History">Ord. 88-188</annotation>
        <annotation type="History">Ord. 14-208</annotation>
      </section>
      <section prefix="§" num="5-3" heading="Considerations; Findings of fact.">
        <para num="(a)" heading="Request for MDE comments.">The Floodplain Manager must:<para num="(1)">request the NFIP State Coordinator, Maryland Department of the Environment, to comment on variance applications; and</para>
          <para num="(2)">submit those comments, when received, to the Director of the Planning Department.</para>
        </para>
        <para num="(b)" heading="Factors to consider.">In considering a variance application, the Planning Department must consider and make findings of fact on all evaluations, relevant factors, and requirements specified in this Division I, including:.<para num="(1)">the danger that materials may be swept onto other lands to the injury of others;</para>
          <para num="(2)">the danger to life and property due to flooding or erosion damage;</para>
          <para num="(3)">the susceptibility of the proposed development and its contents to flood damage and the effect of that damage on the individual owner;</para>
          <para num="(4)">the importance of the services to the community provided by the proposed development;</para>
          <para num="(5)">the availability of alternative locations for the proposed use that are not subject to or are subject to less flooding or erosion damage;</para>
          <para num="(6)">the need of a waterfront location for the proposed use and whether the proposed use is a functionally dependent use;</para>
          <para num="(7)">the compatibility of the proposed use with existing and anticipated development;</para>
          <para num="(8)">the relationship of the proposed use to the comprehensive plan for that area;</para>
          <para num="(9)">the safety of access to the property in times of flood for passenger vehicles and emergency vehicles;</para>
          <para num="(10)">expected heights, velocity, duration, rate of rise, and sediment transport of floodwaters and the effects of wave action, if applicable, expected at the site;</para>
          <para num="(11)">the costs of providing government services during and after flood conditions,   including maintenance and repair of public utilities and facilities, such as streets, bridges, and sewer, gas, electrical, and water systems;</para>
          <para num="(12)">the comments provided by NFIP State Coordinator; and</para>
          <para num="(13)">the intent of environmental projects taking place on public land, including associated benefits and co-benefits.</para>
        </para>
        <annotation type="History">Ord. 14-208</annotation>
        <annotation type="History">Ord. 21-020</annotation>
      </section>
      <section prefix="§" num="5-4" heading="Limitations on granting variances.">
        <text>The Planning Department may make an affirmative decision on a variance request only on:</text>
        <para num="(1)">a showing of good and sufficient cause;</para>
        <para num="(2)">a determination that failure to grant the variance would result in exceptional hardship due to the physical characteristics of the property (for which determination, increased cost or inconvenience of meeting the requirements of this Division I does not constitute an “exceptional hardship”);</para>
        <para num="(3)">a determination that the granting of a variance for development within a designated floodway, or within a Special Flood Hazard Area with base-flood elevations but no designated floodway, will not result in increased flood heights beyond that which is allowed by this Division I;</para>
        <para num="(4)">a determination that the granting of a variance will not result in additional threats to public safety, extraordinary public expense, nuisances, fraud or victimization of the public, or conflict with existing local laws;</para>
        <para num="(5)">a determination that the structure or other development is protected by methods to minimize flood damage; and</para>
        <para num="(6)">a determination that the variance is the minimum necessary to afford relief, considering the flood hazard.</para>
        <annotation type="Prior Codifications">City Code, 1976/83, art. 7, §7(c)</annotation>
        <annotation type="Prior Codifications">2000, art. 7, §5-3</annotation>
        <annotation type="History">Ord. 88-188</annotation>
        <annotation type="History">Ord. 11-516</annotation>
        <annotation type="History">Ord. 14-208</annotation>
      </section>
      <section prefix="§" num="5-5" heading="Applications.">
        <para num="(a)" heading="In general.">The application for a variance must be submitted to the Planning Department and, to the greatest extent possible, must comply with the provisions of this Division I.</para>
        <para num="(b)" heading="Notices to applicant.">
          <para num="(1)">The Planning Department must notify the applicant, in writing:<para num="(i)">of the increased premium rates for flood insurance; and</para>
            <para num="(ii)">that construction below the level of the base flood increases risks to life and property.</para>
          </para>
          <para num="(2)">This notification must be maintained as part of the record required in &lt;cite data-path="|7|§5-7"&gt;§ 5-7 {“Record of variance actions”} of this subtitle&lt;/cite&gt;.</para>
        </para>
        <annotation type="Prior Codifications">City Code, 1976/83, art. 7, §7(e), (f)</annotation>
        <annotation type="Prior Codifications">2000, art. 7, §5-5</annotation>
        <annotation type="History">Ord. 88-188</annotation>
        <annotation type="History">Ord. 11-516</annotation>
        <annotation type="History">Ord. 14-208</annotation>
      </section>
      <section prefix="§" num="5-6" heading="Agreement not to convert accessary structures.">
        <text>The owner of any accessory structure for which a variance is granted must sign an agreement that the structure will never be converted to any use other than for parking vehicles or limited storage, and the deed restriction must be recorded with the Land Records.</text>
        <annotation type="Prior Codifications">City Code, 1976/83, art. 7, §7(g)</annotation>
        <annotation type="Prior Codifications">2000, art. 7, §5-6</annotation>
        <annotation type="History">Ord. 88-188</annotation>
        <annotation type="History">Ord. 14-208</annotation>
        <annotation type="History">Ord. 21-020</annotation>
      </section>
      <section prefix="§" num="5-7" heading="Record of variance actions.">
        <text>A record of all variance actions, including the justification for their issuance, must be:</text>
        <para num="(1)">maintained by the Planning Department;</para>
        <para num="(2)">included in the bi-annual report submitted to the Federal Insurance Administrator; and</para>
        <para num="(3)">available on request to the Federal Emergency Management Agency or its authorized agent during periodic assessments of Baltimore City’s participation in the National Flood Insurance Program.</para>
        <annotation type="Prior Codifications">City Code, 1976/83, art. 7, §7(h)</annotation>
        <annotation type="Prior Codifications">2000, art. 7, §5-7</annotation>
        <annotation type="History">Ord. 88-188</annotation>
        <annotation type="History">Ord. 14-208</annotation>
      </section>
      <section prefix="§" num="5-8" reserved="true" />
      <section prefix="§" num="5-9" heading="Notice on deed.">
        <text>Notice of the flood hazard and the variance action must be placed on the deed that conveys title to land on which construction has occurred under this subtitle.</text>
        <annotation type="Prior Codifications">City Code, 1976/83, art. 7, §7(j)</annotation>
        <annotation type="Prior Codifications">2000, art. 7, §5-9</annotation>
        <annotation type="History">Ord. 88-188</annotation>
        <annotation type="History">Ord. 92-134</annotation>
        <annotation type="History">Ord. 14-208</annotation>
      </section>
    </container>
    <container prefix="Subtitle" num="6" heading="Administration">
      <section prefix="§" num="6-1" heading="Municipal non-liability.">
        <text>The granting of a permit or approval is not a representation, guarantee, or warranty of any kind and does not create or impose any liability on the City, its officials, employees, or agents.</text>
        <annotation type="Prior Codifications">City Code, 1976/83, art. 7, §9</annotation>
        <annotation type="Prior Codifications">2000, art. 7, §6-1</annotation>
        <annotation type="History">Ord. 88-188</annotation>
        <annotation type="History">Ord. 14-208</annotation>
      </section>
      <section prefix="§" num="6-2" heading="Administrative fees.">
        <para num="(a)" heading="City may impose.">The City may impose additional application fees commensurate with those costs incurred in the processing, review, and evaluation of permit applications for development in Floodplain District.</para>
        <para num="(b)" heading="Costs included.">The costs covered by the fees may include:<para num="(1)">consultant fees for certification of as-built condition of structures;</para>
          <para num="(2)">Floodplain District and subdistrict delineations;</para>
          <para num="(3)">environmental impact characterizations;</para>
          <para num="(4)">staff assignments; and</para>
          <para num="(5)">other related costs.</para>
        </para>
        <annotation type="Prior Codifications">City Code, 1976/83, art. 7, §10</annotation>
        <annotation type="Prior Codifications">2000, art. 7, §6-2</annotation>
        <annotation type="History">Ord. 88-188</annotation>
        <annotation type="History">Ord. 14-208</annotation>
      </section>
    </container>
    <container prefix="Subtitle" num="7" heading="Enforcement">
      <section prefix="§" num="7-1" heading="Compliance required.">
        <para num="(a)" heading="In general.">No structure or other development may be located, erected, constructed, reconstructed, improved, repaired, extended, converted, enlarged, or altered except in full compliance with this Division I and all other applicable Federal, State, and City laws, rules, and regulations.</para>
        <para num="(b)" heading="Noncompliance presumed without documentation.">A structure or other development without the required design certifications, elevation certificates, or other evidence of compliance is presumed to be noncompliant with and in violation of this Division I until the required documentation is provided.</para>
        <para num="(c)" heading="Noncompliant structures as public nuisance.">Any structure or other development that is located, erected, constructed, reconstructed, improved, repaired, extended, converted, enlarged, or altered in violation of this Division I or of any other applicable Federal, State, and City law, rule, or regulation is declared to be a public nuisance and abatable as such.</para>
        <annotation type="Prior Codifications">City Code, 1976/83, art. 7, §8 (3rd par.)</annotation>
        <annotation type="Prior Codifications">2000, art. 7, §7-1</annotation>
        <annotation type="History">Ord. 88-188</annotation>
        <annotation type="History">Ord. 11-516</annotation>
        <annotation type="History">Ord. 14-208</annotation>
        <annotation type="History">Ord. 14-307</annotation>
      </section>
      <section prefix="§" num="7-2" reserved="true" />
      <section prefix="§" num="7-3" heading="Violation notice; Stop work order.">
        <para num="(a)" heading="In general.">If the Floodplain Manager finds that any development or person has failed to comply with or otherwise has violated any provision of this Division I, any provision of a rule or regulation adopted under this Division I, or any term or condition of a permit issued under this Division I, the Floodplain Manager may issue a violation notice and, for ongoing activities, a stop work order to:<para num="(1)">the person responsible for the violation or that person’s authorized agent;</para>
          <para num="(2)">the developer or owner of the development or that person’s authorized agent; and</para>
          <para num="(3)">on-site personnel.</para>
        </para>
        <para num="(b)" heading="Service.">The violation notice must be served:<para num="(1)">in person;</para>
          <para num="(2)">by certified or registered mail; or</para>
          <para num="(3)">if the identity or whereabouts of the person responsible, developer, or owner is unknown, by posting a copy of the notice in a conspicuous place in or on the property.</para>
        </para>
        <para num="(c)" heading="Contents.">The violation notice must:<para num="(1)">describe the nature of the violation;</para>
          <para num="(2)">describe the remedial action needed to correct the violation; and</para>
          <para num="(3)">specify a reasonable period of time within which to complete the remedial action.</para>
        </para>
        <annotation type="History">Ord. 14-208</annotation>
      </section>
      <section prefix="§" num="7-4" heading="Enforcement of notice or order.">
        <para num="(a)" heading="In general.">If a violation is not promptly discontinued or abated, or if the violation notice or order is not complied with promptly, the Floodplain Manager may institute or cause to be instituted any appropriate legal proceeding.</para>
        <para num="(b)" heading="Types of proceedings.">Enforcement proceedings may include:<para num="(1)">injunctive or other equity proceedings;</para>
          <para num="(2)">criminal prosecution, including a prosecution initiated by a prepayable criminal citation under City Code &lt;cite data-path="|19|§71-2"&gt;Article 19, § 71-2 {“Prepayable criminal citations”}&lt;/cite&gt;; and</para>
          <para num="(3)">administrative proceedings, including one initiated by a prepayable environmental citation under City Code &lt;cite data-path="|1|§40-14"&gt;Article 1, § 40-14 {“Violations to which subtitle applies”}&lt;/cite&gt;.</para>
        </para>
        <para num="(c)" heading="Remedies not exclusive.">In pursuing a violation, the Floodplain Manager may use any 1 or more available remedies or enforcement actions.  The initiation of any 1 remedy or enforcement action does not preclude pursuing any other remedy or enforcement action authorized by law.  Neither damages, irreparable injury, nor the lack of an adequate remedy at law is a prerequisite to enforcement in equity.</para>
        <annotation type="History">Ord. 14-208</annotation>
      </section>
    </container>
    <container prefix="Subtitle" num="8" heading="Administrative and Judicial Review">
      <section prefix="§" num="8-1" heading="Administrative review – In general.">
        <para num="(a)" heading="Right of appeal.">Any person aggrieved by the action of the Floodplain Manager or other official charged with the enforcement of this Division I, whether as the result of the disapproval of an application, the issuance of a violation notice, an alleged failure to properly enforce this Division I, or otherwise:<para num="(1)">may appeal the action to the Planning Director; and</para>
          <para num="(2)">on timely request, is entitled to a hearing on that appeal.</para>
        </para>
        <para num="(b)" heading="When and how taken.">The appeal must:<para num="(1)">be in writing;</para>
          <para num="(2)">state clearly the grounds on which the appeal is based;</para>
          <para num="(3)">if the person aggrieved desires a hearing on the appeal, contain an express statement to that effect; and</para>
          <para num="(4)">be filed with the Director within 10 days of the action in dispute.</para>
        </para>
        <annotation type="History">Ord. 14-208</annotation>
        <annotation type="History">Ord. 14-307</annotation>
      </section>
      <section prefix="§" num="8-2" heading="Administrative review – Delegation of hearing authority.">
        <para num="(a)" heading="In general.">Hearings may be conducted by:<para num="(1)">the Planning Director; or</para>
          <para num="(2)">a hearing officer designated by the Planning Director.</para>
        </para>
        <para num="(b)" heading="Scope of delegation.">The Director may delegate to a hearing officer the authority to issue:<para num="(1)">proposed or final findings of fact;</para>
          <para num="(2)">proposed or final conclusions of law;</para>
          <para num="(3)">proposed or final findings of fact and conclusions of law;</para>
          <para num="(4)">proposed or final orders; or</para>
          <para num="(5)">the final administrative decision of the Department.</para>
        </para>
        <annotation type="History">Ord. 14-208</annotation>
      </section>
      <section prefix="§" num="8-3" heading="Administrative review – Conduct of hearing.">
        <para num="(a)" heading="Notice.">
          <para num="(1)">The Planning Director must provide all parties reasonable written notice of the hearing.</para>
          <para num="(2)">The notice must state:<para num="(i)">the date, time, place, and nature of the hearing;</para>
            <para num="(ii)">the right of a party to be represented, at the party’s own expense, by an attorney or, if permitted by law, other representative;</para>
            <para num="(iii)">the right of a party to call witnesses and submit documents or other evidence   under &lt;cite data-path="|7|§8-4"&gt;§ 8-4 {“Administrative review – Evidence”} of this subtitle&lt;/cite&gt;; and</para>
            <para num="(iv)">that failure to appear for the scheduled hearing may result in an adverse action   against the party.</para>
          </para>
        </para>
        <para num="(b)" heading="Hearings to be open and informal.">Except as otherwise provided by law or by rule or regulation of the Planning Director, all hearings must be:<para num="(1)">open to the public; and</para>
          <para num="(2)">conducted in an orderly but informal manner.</para>
        </para>
        <annotation type="History">Ord. 14-208</annotation>
      </section>
      <section prefix="§" num="8-4" heading="Administrative review – Evidence.">
        <para num="(a)" heading="In general.">Except as otherwise provided by this section or by rule or regulation of the Planning Director, formal rules of evidence and trial procedures do not apply.</para>
        <para num="(b)" heading="Right to submit.">On a genuine issue of fact, a party is entitled to:<para num="(1)">call witnesses;</para>
          <para num="(2)">offer evidence, including rebuttal evidence;</para>
          <para num="(3)">cross-examine any witness that another party or the Planning Director calls; and</para>
          <para num="(4)">present summation and argument.</para>
        </para>
        <para num="(c)" heading="Scope.">The Planning Director or hearing officer:<para num="(1)">may admit probative evidence that reasonable and prudent individuals commonly accept in the conduct of their affairs and give probative effect to that evidence;</para>
          <para num="(2)">may not exclude evidence solely on the basis that it is hearsay;</para>
          <para num="(3)">must give effect to a privilege recognized by law;</para>
          <para num="(4)">may receive documentary evidence in the form of copies or excerpts or through incorporation by reference;</para>
          <para num="(5)">may take official notice of a fact that is judicially noticeable or that is general, technical, or scientific and within the specialized knowledge of the Planning Department; and</para>
          <para num="(6)">may exclude evidence that is:<para num="(i)">incompetent;</para>
            <para num="(ii)">irrelevant;</para>
            <para num="(iii)">immaterial; or</para>
            <para num="(iv)">unduly repetitious.</para>
          </para>
        </para>
        <annotation type="History">Ord. 14-208</annotation>
      </section>
      <section prefix="§" num="8-5" heading="Administrative review – Final decision.">
        <para num="(a)" heading="Form and contents.">A final decision must:<para num="(1)">be in writing; and</para>
          <para num="(2)">contain separate statements of:<para num="(i)">the findings of fact;</para>
            <para num="(ii)">the conclusions of law; and</para>
            <para num="(iii)">the decision or order.</para>
          </para>
        </para>
        <para num="(b)" heading="Distribution.">A copy of the final decision must be mailed or delivered to each party or that party’s attorney of record.</para>
        <annotation type="History">Ord. 14-208</annotation>
        <annotation type="History">Ord. 14-307</annotation>
      </section>
      <section prefix="§" num="8-6" heading="Administrative appeals.">
        <para num="(a)" heading="Appeal to Commission.">An applicant who is aggrieved by the final site plan decision of the Director of Planning may appeal that decision to the Planning Commission.</para>
        <para num="(b)" heading="When filed.">Appeals must be filed within 30 days of the Planning Director’s final decision, as specified in &lt;cite data-path="|7|§8-5"&gt;§ 8-5 {“Administrative review- Final decisions”} of this subtitle&lt;/cite&gt;.</para>
        <para num="(c)" heading="Hearing.">The Planning Commission must review the Director’s decision at a public hearing held within 45 days of receiving the appeal.</para>
        <annotation type="History">Ord.  21-020</annotation>
      </section>
      <section prefix="§" num="8-7" heading="Judicial and appellate review.">
        <para num="(a)" heading="Judicial review.">A party aggrieved by a final decision of the Planning Department under this subtitle may seek judicial review of that decision by petition to the Circuit Court for Baltimore City in accordance with the Maryland Rules of Procedure.</para>
        <para num="(b)" heading="Appellate review.">A party to the judicial review may appeal the court’s final judgment to the Court of Special Appeals in accordance with the Maryland Rules of Procedure.</para>
        <annotation type="History">Ord. 14-208</annotation>
        <annotation type="History">Ord. 19-332</annotation>
      </section>
    </container>
    <container prefix="Subtitle" num="9" heading="Penalties">
      <section prefix="§" num="9-1" heading="In general.">
        <para num="(a)" heading="In general.">Any person who violates or fails to comply with any provision of this Division I, any provision of a rule or regulation adopted under this Division I, or any term or condition of a permit issued under this Division I is guilty of a misdemeanor and, on conviction, is subject to a fine of not more than $500 for each violation.</para>
        <annotation type="Prior Codifications">City Code, 1976/83, art. 7, §8 (part)</annotation>
        <annotation type="Prior Codifications">2000, art. 7, §7-5(a)</annotation>
        <annotation type="History">Ord. 88-188</annotation>
        <annotation type="History">Ord. 11-516</annotation>
        <annotation type="History">Ord. 14-208</annotation>
      </section>
      <section prefix="§" num="9-2" heading="Department of Housing and Community Development to enforce.">
        <text>This Division I may be enforced by the Department of Housing and Community Development in the manner provided in § 104 {“Duties and powers of Building Official”} of the Baltimore City &lt;cite data-path="|building-codes|II"&gt;Building Code&lt;/cite&gt;.</text>
        <annotation type="History">Ord. 21-020</annotation>
      </section>
      <section prefix="§" num="9-3" heading="Each day a separate offense.">
        <para num="(a)" heading="In general.">Every day that a violation continues is a separate offense.</para>
        <para num="(b)" heading="Prima facie proof of continuation.">Proof that a violation exists on any date that follows the issuance of a violation notice constitutes prima facie evidence that the violation has continued throughout the intervening period of time.</para>
        <annotation type="Prior Codifications">City Code, 1976/83, art. 7, §8 (part)</annotation>
        <annotation type="Prior Codifications">2000, art. 7, §7-5(b)</annotation>
        <annotation type="History">Ord. 88-188</annotation>
        <annotation type="History">Ord. 11-516</annotation>
        <annotation type="History">Ord. 14-208</annotation>
        <annotation type="History">Ord. 21-020</annotation>
      </section>
      <section prefix="§" num="9-4" heading="Penalty not a substitute for remediation.">
        <para num="(a)" heading="In general.">The imposition of a fine or penalty for a violation or noncompliance does not excuse the violation or noncompliance nor permit it to continue.</para>
        <para num="(b)" heading="Remediation still required.">All offenders are required to correct or remedy the violation or noncompliance within a reasonable time.</para>
        <para num="(c)" heading="Penalty not substitute for correcting noncompliance.">
          <para num="(1)">The imposition of a fine or penalty for a violation or noncompliance does not excuse the violation or noncompliance nor permit it to continue.</para>
          <para num="(2)">All offenders are required to correct or remedy the violation or noncompliance within a reasonable time.</para>
        </para>
        <annotation type="Prior Codifications">City Code, 1976/83, art. 7, §8 (part)</annotation>
        <annotation type="Prior Codifications">2000, art. 7, §7-5(c)</annotation>
        <annotation type="History">Ord. 88-188</annotation>
        <annotation type="History">Ord. 11-516</annotation>
        <annotation type="History">Ord. 14-208</annotation>
        <annotation type="History">Ord. 21-020</annotation>
      </section>
    </container>
    <container prefix="Subtitles" num="10 to 20" />
  </container>
  <container prefix="Division" num="II" heading="Stormwater Management">
    <container prefix="Subtitle" num="21" heading="Definitions; General Provisions">
      <section prefix="§" num="21-1" heading="Definitions.">
        <para num="(a)" heading="In general.">In this Division II, the following terms have the meaning indicated.</para>
        <para num="(b)" heading="Adverse impact.">“Adverse impact” means any effect on waters or wetlands, including their quality, quantity, surface area, species composition, aesthetics, or usefulness for human or natural uses, that:<para num="(1)">is deleterious; and</para>
          <para num="(2)">either:<para num="(i)">is or potentially can be harmful or injurious to human health, welfare, or safety, to property, or to biological productivity, diversity, or stability; or</para>
            <para num="(ii)">unreasonably interferes with the enjoyment of life or property, including outdoor recreation.</para>
          </para>
        </para>
        <para num="(b-1)" heading="Approval.">
          <para num="(1)" heading="In general.">“Approval” means a documented action by the Department following a comprehensive review to determine and acknowledge that submitted materials demonstrate compliance with the requirements of a specified stage in a project’s process.</para>
          <para num="(2)" heading="Exclusions.">“Approval” does not include an acknowledgment by the Department that material has been received for review.</para>
        </para>
        <para num="(c)" heading="Best management practice .">“Best management practice” means a structural or nonstructural practice designed to store temporarily or treat stormwater runoff in order to mitigate flooding, reduce pollution, and provide other amenities.</para>
        <para num="(d)" heading="Channel protection storage volume.">“Channel protection storage volume” means the volume, calculated in accordance with the State’s Design Manual, used to design structural management practices to control stream channel erosion.</para>
        <para num="(e)" heading="Department.">“Department” means the Baltimore City Department of Public Works.</para>
        <para num="(e-1)" heading="Design Guidelines, City.">“Design Guidelines, City” means the 2010 Baltimore City Stormwater Design Guidelines, and all subsequent additions, revisions, and amendments to it, as adopted by the Department and approved by the State Water Management Administration.</para>
        <para num="(f)" heading="Design Manual.">“Design Manual, State” means the 2000 Maryland Stormwater Design Manual and all subsequent additions, revisions, and amendments to it.</para>
        <para num="(g)" heading="Develop.">“Develop” means to change the runoff characteristics of a parcel of land in conjunction with residential, commercial, industrial, or institutional construction or alteration.</para>
        <para num="(h)" heading="Disturb.">
          <para num="(1)">“Disturb” means to:<para num="(i)">clear or remove trees and brush from land;</para>
            <para num="(ii)">grade, stockpile, remove, excavate, scarify, or fill soil;</para>
            <para num="(iii)">grub or remove stumps; or</para>
            <para num="(iv)">strip or remove vegetative surface cover.</para>
          </para>
          <para num="(2)">“Disturb” does not include:<para num="(i)">mowing of grass;</para>
            <para num="(ii)">trimming of trees; or</para>
            <para num="(iii)">other maintenance activities that do not create unvegetated ground.</para>
          </para>
        </para>
        <para num="(i)" heading="Drainage area.">“Drainage area” means an area, measured in a horizontal plane, that:<para num="(1)">contributes runoff to a single point; and</para>
          <para num="(2)">is enclosed by a ridge line.</para>
        </para>
        <para num="(i-1)" heading="Environmental site design.">“Environmental site design” means using small-scale stormwater management practices, nonstructural techniques, and better site planning that, in accordance with methods specified in the State’s Design Manual, are used to mimic natural hydrologic runoff characteristics and minimize the impact of land development on water resources.</para>
        <para num="(j)" heading="Extreme flood volume.">“Extreme flood volume” means the storage volume required to control infrequent, large storm events in which overbank flows reach or exceed the boundaries of the 100- year floodplain.</para>
        <para num="(j-1)" heading="Impervious area.">“Impervious area” means any surface that does not allow stormwater to infiltrate into the soil surface.</para>
        <para num="(k)" />
        <para num="(l)" heading="Infiltration.">“Infiltration” means the passage or movement of water into the soil surface.</para>
        <para num="(l-1)" heading="Maximum extent practicable.">“Maximum extent practicable” means stormwater management systems designed so that:<para num="(1)">all reasonable opportunities for using environmental site design planning techniques and treatment practices are exhausted; and</para>
          <para num="(2)">a structural best management practice is implemented only where absolutely necessary.</para>
        </para>
        <para num="(m)" heading="Off-site ... management.">“Off-site ... management” means the design and construction of a facility necessary to control stormwater from more than one development.</para>
        <para num="(n)" heading="On-site ... management.">“On-site ... management” means the design and construction of systems necessary to control stormwater within one development.</para>
        <para num="(o)" heading="Overbank flood protection volume.">“Overbank flood protection volume” means the volume, calculated in accordance with the State’s Design Manual, controlled by structural practices to prevent an increase in the frequency of out of bank flooding generated by development.</para>
        <para num="(p)" heading="Person.">
          <para num="(1)" heading="In general.">“Person” has the meaning stated in &lt;cite data-path="|general|1|1|1-107|(a)"&gt;§ 1-107(a) {“Person: In general”}&lt;/cite&gt; of the City Code’s &lt;cite data-path="|general"&gt;General Provisions Article&lt;/cite&gt;.</para>
          <para num="(2)" heading="Qualified inclusion of governmental entities.">Notwithstanding &lt;cite data-path="|general|1|1|1-107|(b)"&gt;§ 1-107(b) {“Person: Exclusion”}&lt;/cite&gt; of the &lt;cite data-path="|general"&gt;General Provisions Article&lt;/cite&gt;, in this Division II “person” also includes, except as used in &lt;cite data-path="|general|28|1|28-13"&gt;§ 28-13{“Criminal penalties”}&lt;/cite&gt;, a governmental entity or an instrumentality or unit of a governmental entity.</para>
        </para>
        <para num="(p-1)" heading="Planning techniques.">“Planning techniques” means a combination of strategies employed early in project design to reduce the impact from development and to incorporate natural features into a stormwater management plan.</para>
        <para num="(q)" heading="Qualitative Control.">&lt;em&gt;See &lt;/em&gt;“Stormwater management – Qualitative control”.</para>
        <para num="(r)" heading="Quantitative Control.">&lt;em&gt;See &lt;/em&gt;“Stormwater management – Quantitative control”.</para>
        <para num="(s)" heading="Recharge volume.">“Recharge volume” means that portion of the water quality volume, calculated in accordance with the State’s Design Manual, used to maintain groundwater recharge rates at development sites.</para>
        <para num="(t)" heading="Redevelopment.">“Redevelopment” means any construction, alteration, or improvement that:<para num="(1)">disturbs more than 5,000 square feet of land;</para>
          <para num="(2)">is performed on a site where:<para num="(i)">the existing land use is commercial, industrial, institutional, or multi-family residential; and</para>
            <para num="(ii)">the existing impervious area of the site is more than 40% of the total area of the site.</para>
          </para>
        </para>
        <para num="(t-1)" heading="Retrofitting.">“Retrofitting” means the implementation of environmental site design practices, the construction of a structural best management practice, or the modification of an existing structural best management practice in a previously developed area to improve water quality over current conditions.</para>
        <para num="(u)" heading="Sediment.">“Sediment” means soils or other surficial materials that are the product of erosion and are transported or deposited by the action of wind, water, ice, gravity, or artificial means.</para>
        <para num="(v)" heading="Site.">“Site” means any tract, lot, parcel of land, or area of construction, or combination of tracts, lots, parcels of land, or areas of construction that are:<para num="(1)">in one ownership; or</para>
          <para num="(2)">in diverse ownership, but where:<para num="(i)">development is to be performed as part of a unit, subdivision, or project; and</para>
            <para num="(ii)">either:<para num="A.">the tracts, lots, or parcels of land are contiguous; or</para>
              <para num="B.">the development is a cooperative public-private undertaking.</para>
            </para>
          </para>
        </para>
        <para num="(w)" heading="Stabilization.">“Stabilization” means the prevention of soil movement by any of various vegetative or structural means.</para>
        <para num="(w-1)" heading="Stormwater.">“Stormwater” means water that originates from a precipitation event.</para>
        <para num="(w-2)" heading="Stormwater management system.">“Stormwater management system” means a system of natural areas, environmental site design practices, stormwater management practices, and any structure through which stormwater flows, infiltrates, or discharges from a site.</para>
        <para num="(x)" heading="Stormwater management – Qualitative control.">
          <para num="(1)" heading="In general.">“Stormwater management” means, for qualitative control, a system of vegetative, structural, and nonstructural practices, natural areas, environmental site design practices, stormwater management measures, and any other structure that reduces or eliminates pollutants that might otherwise be carried by surface runoff.</para>
          <para num="(2)" heading="Inclusions.">“Stormwater management” includes, for qualitative control, design parameters for:<para num="(i)">water quality volume; and</para>
            <para num="(ii)">recharge volume.</para>
          </para>
        </para>
        <para num="(y)" heading="Stormwater management – Quantitative control.">
          <para num="(1)" heading="In general.">“Stormwater management” means, for quantitative control, a system of vegetative, structural, and nonstructural practices, natural areas, environmental site design practices, stormwater management measures, and any other structure that controls the increased volume and rate of surface runoff caused by man-made changes to the land.</para>
          <para num="(2)" heading="Inclusions.">“Stormwater management” includes, for quantitative controls, design parameters for:<para num="(i)">channel protection storage volume;</para>
            <para num="(ii)">overbank flood protection volume; and</para>
            <para num="(iii)">extreme flood volume.</para>
          </para>
        </para>
        <para num="(z)" />
        <para num="(aa)" heading="Watershed.">“Watershed” means the total drainage area contributing runoff to a single point.</para>
        <para num="(bb)" heading="Water quality volume.">“Water quality volume” means the volume needed, calculated in accordance with the State’s Design Manual, to capture and treat the runoff from 90% of the average annual rainfall at a development site.</para>
        <para num="(cc)" heading="Wetlands.">“Wetlands” means an area that has saturated soils or periodic high groundwater levels and vegetation adapted to wet conditions and periodic flooding.</para>
        <annotation type="History">Ord. 02-367</annotation>
        <annotation type="History">Ord. 04-672</annotation>
        <annotation type="History">Ord. 10-277</annotation>
        <annotation type="History">Ord. 13- 095</annotation>
        <annotation type="History">Ord. 22-125</annotation>
      </section>
      <section prefix="§" num="21-2" heading="Rules of interpretation.">
        <para num="(a)" heading="In general.">In interpreting and applying this Division II, the following rules of interpretation apply:<para num="(i)">those contained in Subtitles 2 and 3 of the City Code’s &lt;cite data-path="|general"&gt;General Provisions Article&lt;/cite&gt;; and</para>
          <para num="(ii)">any additional rules contained in this section.</para>
        </para>
        <para num="(b)" heading="Conflicting provisions.">
          <para num="(1)" heading="Division sets minimum requirements.">In their interpretation and application, the provisions of this Division II must be taken to be the minimum requirements for the promotion of the public health, safety, and general welfare.</para>
          <para num="(2)" heading="Most restrictive provision governs.">If any condition imposed by a provision of this Division II is either more or less restrictive than a comparable condition imposed by any other provision of this Division or by any other law, rule, or regulation of any kind, the condition that is the more restrictive governs.</para>
        </para>
        <annotation type="History">Ord. 02-367</annotation>
        <annotation type="History">Ord. 22-125</annotation>
      </section>
      <section prefix="§" num="21-3" heading="Incorporation by reference.">
        <para num="(a)" heading="In general.">For purposes of this Division II, the following documents are incorporated by reference:<para num="(1)">the State’s Design Manual, which serves as the official City guide for stormwater management principles, methods, and practices;</para>
          <para num="(2)">the USDA Natural Resources Conservation Service Maryland Conservation Practice Standard Pond Code 378 (January 2000); and</para>
          <para num="(3)">the City’s Design Guidelines, which serve to supplement the State’s Design Manual as it relates to stormwater management principles, methods, and practices in the City.</para>
        </para>
        <para num="(b)" heading="Defined terms.">
          <para num="(1)">Terms used in the State’s Design Manual have the meanings ascribed to them in the Design Manual or otherwise by the State Water Management Administration.</para>
          <para num="(2)">These terms include, among others:<para num="(i)">“Agricultural land management practices”.</para>
            <para num="(ii)">“Aquifer”.</para>
            <para num="(iii)">“Detention structure”.</para>
            <para num="(iv)">“Direct discharge”.</para>
            <para num="(v)">“Extended detention”.</para>
            <para num="(vi)">“Grade”.</para>
          </para>
        </para>
        <annotation type="History">Ord. 02-367</annotation>
        <annotation type="History">Ord. 10-277</annotation>
      </section>
      <section prefix="§" num="21-4" heading="Purpose, goal, etc.">
        <para num="(a)" heading="Purpose.">The purpose of this Division II is to:<para num="(1)">protect, maintain, and enhance the public health, safety, and general welfare through the management of stormwater;</para>
          <para num="(2)">protect public and private property from damage;</para>
          <para num="(3)">reduce the adverse effects of development;</para>
          <para num="(4)">reduce stream channel erosion, pollution, siltation, and sedimentation;</para>
          <para num="(5)">reduce local flooding;</para>
          <para num="(6)">restore, enhance, and maintain the chemical, physical, and biological integrity
of streams; and</para>
          <para num="(7)">maintain after development, as nearly as possible, pre-development runoff characteristics.</para>
        </para>
        <para num="(b)" heading="Goal.">The goal of this Division II is to manage stormwater by:<para num="(1)">using environmental site design to the maximum extent practicable; and</para>
          <para num="(2)">using structural best management practices and alternative practices only when necessary.</para>
        </para>
        <para num="(c)" heading="Authority.">This Division II is adopted under the authority of State Environment Article, Title 4, Subtitle 2.</para>
        <para num="(d)" heading="Application.">This Division II applies to all new and redevelopment projects that have not received final approval for erosion and sediment control and stormwater management plans by May 4, 2010.</para>
        <annotation type="History">Ord. 02-367</annotation>
        <annotation type="History">Ord. 10-277</annotation>
      </section>
      <section prefix="§" num="21-5" heading="Administration.">
        <para num="(a)" heading="In general.">The Baltimore City Department of Public Works is responsible for administering and enforcing this Division II.</para>
        <para num="(b)" heading="Rules and regulations.">Subject to Title 4 {“Administrative Procedure Act – Regulations”} of the &lt;cite data-path="|general"&gt;City General Provisions Article&lt;/cite&gt;, the Department may adopt rules and regulations to carry out this Division II.</para>
        <annotation type="History">Ord. 02-367</annotation>
        <annotation type="History">Text Conformed 02/16/21</annotation>
        <annotation type="Editor's Notes">By authority of Ordinance 20-431, Section 5, the Director of Legislative Reference, in consultation with the Law Department, has conformed the text of this subsection to refer to and reflect the requirements of the recently-enacted Administrative Procedure Act that, effective January 15, 2021, governs the proposal, adoption, and publication of administrative rules and regulations.</annotation>
      </section>
      <section prefix="§" num="21-6" heading="Scope.">
        <para num="(a)" heading="In general.">Except as specified in subsection (b) of this section, this Division II applies to all development within the corporate limits of Baltimore City.</para>
        <para num="(b)" heading="Exemptions.">The following activities are exempt from this Division II:<para num="(1)">agricultural land management practices that employ methods and procedures to further crop and livestock production and conservation to conserve related soil and water resources;</para>
          <para num="(2)">a single-family detached dwelling if:<para num="(i)">the activity does not disturb more than 2,500 square feet of land area; and</para>
            <para num="(ii)">the tract, lot, or parcel has not previously been the subject of an exemption under this item (2);</para>
          </para>
          <para num="(3)">construction, grading, or development (other than for single-family dwellings) if:<para num="(i)">the activity does not disturb more than 5,000 square feet of land; and</para>
            <para num="(ii)">the tract, lot, or parcel has not previously been the subject of an exemption under this item (3);</para>
          </para>
          <para num="(4)">a single-family dwelling that disturbs more than 2,500 square feet of land area but less than 5,000 square feet of land area, subject to the payment of a “small-project” fee established under &lt;cite data-path="|7|§25-2"&gt;§ 25-2 {“Fees”} of this Division II&lt;/cite&gt;; and</para>
          <para num="(5)">development that the State Water Management Administration determines will be regulated under specific state laws that provide for managing stormwater runoff.</para>
        </para>
        <annotation type="History">Ord. 02-367</annotation>
        <annotation type="History">Ord. 10-277</annotation>
      </section>
    </container>
    <container prefix="Subtitle" num="22" heading="Stormwater Management Plans">
      <section prefix="§" num="22-1" heading="Phased plans required.">
        <text>Except as otherwise expressly provided in this Division II, no person may develop any land unless:</text>
        <para num="(1)">the project is a single-lot residential construction that establishes stormwater management measures in accordance with a standard stormwater management plan prepared in accordance with the City’s Design Guidelines and approved by the Department; or</para>
        <para num="(2)">the person:<para num="(i)">establishes stormwater management measures that control or manage runoff
from the development; and</para>
          <para num="(ii)">incorporates those measures into phased stormwater management plans approved by the Department.</para>
        </para>
        <annotation type="History">Ord. 02-367</annotation>
        <annotation type="History">Ord. 10-277</annotation>
      </section>
      <section prefix="§" num="22-2" heading="Design and construction.">
        <text>These stormwater management measures must:</text>
        <para num="(1)">meet the requirements of the State’s Design Manual, this Division II, and the City’s Design Guidelines; and</para>
        <para num="(2)">be constructed according to:<para num="(i)">an approved plan for new development; or</para>
          <para num="(ii)">the policies stated in &lt;cite data-path="|7|§23-7"&gt;§ 23-7 of this Division II&lt;/cite&gt; for redevelopment.</para>
        </para>
        <annotation type="History">Ord. 02-367</annotation>
        <annotation type="History">Ord. 10-277</annotation>
      </section>
      <section prefix="§" num="22-3" heading="Minimum control requirements.">
        <para num="(a)" heading="In general.">The minimum control requirements for these management measures are as provided in this section and the State’s Design Manual.</para>
        <para num="(b)" heading="Volume sizing criteria.">
          <para num="(1)">The criteria in the State’s Design Manual for environmental site design to the maximum extent practicable and the use of environmental site design planning techniques and treatment practices must be exhausted before any structural best management practice or alternative practice is implemented.</para>
          <para num="(2)">Stormwater management plans for development projects subject to this Division II must be designed using environmental site design sizing criteria, recharge volume, water quality volume, and channel protection storage volume criteria according to the State’s Design Manual. The maximum-extent-practicable standard is met when channel stability is maintained, predevelopment groundwater recharge is replicated, nonpoint source pollution is minimized, and structural stormwater management practices or alternative practices are used only if determined to be absolutely necessary.</para>
        </para>
        <para num="(c)" heading="10-year frequency storm event.">Runoff from the 10-year frequency storm event must be controlled in accordance with the State’s Design Manual if the Department determines that additional stormwater management is necessary because historical flooding problems exist and downstream floodplain development and conveyance system design cannot be controlled.</para>
        <para num="(d)" heading="Additional control requirements.">The Department may require more than the minimum control requirements of the State’s Design Manual if:<para num="(1)">hydrologic or topographic conditions warrant; or</para>
          <para num="(2)">flooding, stream channel erosion, or water quality problems exist downstream from a proposed project.</para>
        </para>
        <para num="(e)" heading="Alternative minimum controls.">With the approval of the State Water Management Administration, the Department may adopt alternative minimum control requirements that will:<para num="(1)">implement environmental site design to the maximum extent practicable; and</para>
          <para num="(2)">control flood damages, accelerated stream erosion, water quality, and sedimentation.</para>
        </para>
        <para num="(f)" heading="Consistency with FHMA plans.">Where applicable, stormwater management and development plans must be consistent with watershed management plans and flood management plans approved by the State Water Management Administration under the Flood Hazard Management Act of 1976.</para>
        <annotation type="History">Ord. 02-367</annotation>
        <annotation type="History">Ord. 10-277</annotation>
      </section>
      <section prefix="§" num="22-4" heading="Environmental site design; Structural practices.">
        <para num="(a)" heading="In general.">
          <para num="(1)">In designing stormwater management measures, the following must be used, either alone or in combination:<para num="(i)">environmental site design techniques and practices; and</para>
            <para num="(ii)">structural practices.</para>
          </para>
          <para num="(2)">The applicant must demonstrate that environmental site design has been implemented to the maximum extent practicable before the use of a structural best management practice or alternative practice may be considered in developing the stormwater management plan.</para>
          <para num="(3)">Stormwater management measures, their selection, basic design criteria, methodologies, and construction specifications:<para num="(i)">must comply with the State’s Design Manual and the City’s Design Guidelines; and</para>
            <para num="(ii)">are subject to approval of the Department and the State Water Management Administration.</para>
          </para>
          <para num="(4)">Environmental site design techniques and practices and structural stormwater management measures used to satisfy the minimum control requirements of &lt;cite data-path="|7|§22-3"&gt;§ 22-3 of this subtitle&lt;/cite&gt;:<para num="(i)">must have easements, as described in &lt;cite data-path="|7|§25-1|(b)|(1)"&gt;§ 25-1(b)(1) of this Division II&lt;/cite&gt;, recorded in the land records of Baltimore City;</para>
            <para num="(ii)">must have a recorded inspection and maintenance agreement, as described in &lt;cite data-path="|7|§27-3"&gt;§ 27-3 of this Division II&lt;/cite&gt;; and</para>
            <para num="(iii)">may not be altered without the Department’s prior approval.</para>
          </para>
        </para>
        <para num="(b)" heading="Environmental site design planning techniques and practices.">
          <para num="(1)">The following planning techniques must be applied according to the State’s Design Manual to satisfy the applicable minimum control requirements of &lt;cite data-path="|7|§22-3"&gt;§ 22-3 of this subtitle&lt;/cite&gt;:<para num="(i)">preserving and protecting natural resources;</para>
            <para num="(ii)">conserving natural drainage patterns;</para>
            <para num="(iii)">minimizing impervious area;</para>
            <para num="(iv)">reducing runoff volume;</para>
            <para num="(v)">using environmental site design practices to maintain 100% of the annual predevelopment groundwater recharge volume;</para>
            <para num="(vi)">using green roofs, permeable pavement, reinforced turf, and other alternative surfaces;</para>
            <para num="(vii)">limiting soil disturbance, mass grading, and compaction;</para>
            <para num="(viii)">clustering development; and</para>
            <para num="(ix)">other practices approved by the Department.</para>
          </para>
          <para num="(2)">The following environmental site design treatment practices must be designed according to the State’s Design Manual and the City’s Design Guidelines to satisfy the applicable minimum control requirements established in &lt;cite data-path="|7|§22-3"&gt;§ 22-3 of this subtitle&lt;/cite&gt;:<para num="(i)">disconnection of rooftop runoff;</para>
            <para num="(ii)">disconnection of non-rooftop runoff;</para>
            <para num="(iii)">sheetflow to conservation areas;</para>
            <para num="(iv)">rainwater harvesting;</para>
            <para num="(v)">submerged gravel wetlands;</para>
            <para num="(vi)">landscape infiltration;</para>
            <para num="(vii)">infiltration berms;</para>
            <para num="(viii)">dry wells;</para>
            <para num="(ix)">micro-bioretention;</para>
            <para num="(x)">rain gardens;</para>
            <para num="(xi)">swales;</para>
            <para num="(xii)">enhanced filters; and</para>
            <para num="(xiii)">other practices approved by the Department.</para>
          </para>
          <para num="(3)">The use of environmental site design planning techniques and treatment practices may not conflict with existing State or local laws, ordinances, regulations, or policies.</para>
        </para>
        <para num="(c)" heading="Structural stormwater management measures.">
          <para num="(1)">The following structural stormwater management practices must be designed to satisfy the applicable minimum control requirements of &lt;cite data-path="|7|§22-3"&gt;§ 22-3 of this subtitle&lt;/cite&gt;.<para num="(i)">stormwater management ponds;</para>
            <para num="(ii)">stormwater management wetlands;</para>
            <para num="(iii)">stormwater management infiltration;</para>
            <para num="(iv)">stormwater management filtering systems;</para>
            <para num="(v)">stormwater management open channel systems; and</para>
            <para num="(vi)">other practices provided in the State’s Design Manual.</para>
          </para>
          <para num="(2)">In selecting structural practices, consideration must be given to the performance criteria specified in the State’s Design Manual for:<para num="(i)">general feasibility;</para>
            <para num="(ii)">conveyance;</para>
            <para num="(iii)">pretreatment;</para>
            <para num="(iv)">treatment and geometry;</para>
            <para num="(v)">environment and landscaping; and</para>
            <para num="(vi)">maintenance.</para>
          </para>
          <para num="(3)">Structural practices must accommodate the unique hydrologic or geologic regions of the site.</para>
        </para>
        <para num="(d)" heading="Alternative practices.">
          <para num="(1)">Alternative structural and nonstructural stormwater management practices may be used for new development water quality control if they:<para num="(i)">meet the performance criteria established in the State’s Design Manual; and</para>
            <para num="(ii)">are approved by the State Water Management Administration.</para>
          </para>
          <para num="(2)">Practices used for redevelopment projects must be approved by the Department.</para>
        </para>
        <para num="(e)" heading="Impact analysis.">
          <para num="(1)">For the purposes of modifying the minimum control requirements or design criteria, the applicant must submit to the Department an analysis of the impacts of stormwater flows downstream in the watershed.</para>
          <para num="(2)">The analysis must include the hydrologic and hydraulic calculations necessary to determine the impact of hydrograph timing modifications of the proposed development upon a dam, highway, structure, or natural point of restricted streamflow.</para>
          <para num="(3)">The point of investigation is to be established, with the Department’s concurrence, downstream of the first downstream tributary whose drainage area equals or exceeds the contributing area to the project or stormwater management facility.</para>
        </para>
        <annotation type="History">Ord. 02-367</annotation>
        <annotation type="History">Ord. 10-277</annotation>
      </section>
      <section prefix="§" num="22-5" heading="Contents of plan.">
        <para num="(a)" heading="In general.">
          <para num="(1)">For any proposed development, the applicant must submit phased stormwater management plans to the Department for review and approval.</para>
          <para num="(2)">At a minimum, plans must be submitted for the concept, site development, and final stormwater management construction phases of project design.</para>
          <para num="(3)">Each plan must:<para num="(i)">include the minimum content specified in &lt;cite data-path="|7|§22-3"&gt;§ 22-3 {“Minimum control requirements”} of this subtitle&lt;/cite&gt;; and</para>
            <para num="(ii)">meet the requirements of the State’s Design Manual, the City’s Design Guidelines, and &lt;cite data-path="|7|§22-4"&gt;§ 22-4 {“Environmental site design; Structural practices”} of this subtitle&lt;/cite&gt;.</para>
          </para>
        </para>
        <para num="(b)" heading="Concept plan.">
          <para num="(1)">The applicant must submit a concept plan that provides sufficient information for an initial assessment of the proposed project and whether stormwater management can be provided according to &lt;cite data-path="|7|§22-4"&gt;§ 22-4 {“Environmental site design; Structural practices”} of this subtitle&lt;/cite&gt; and the State’s Design Manual.</para>
          <para num="(2)">Plans submitted for concept approval must include the following, minimum information:<para num="(i)">a map that shows, at a scale specified by the Department:<para num="A.">site location;</para>
              <para num="B.">existing natural features;</para>
              <para num="C.">water and other sensitive resources;</para>
              <para num="D.">topography; and</para>
              <para num="E.">natural drainage patterns;</para>
            </para>
            <para num="(ii)">the anticipated location of all:<para num="A.">impervious areas;</para>
              <para num="B.">buildings;</para>
              <para num="C.">roadways;</para>
              <para num="D.">parking;</para>
              <para num="E.">sidewalks;</para>
              <para num="F.">utilities; and</para>
              <para num="G.">other site improvements;</para>
            </para>
            <para num="(iii)">the location of:<para num="A.">the proposed limit of disturbance;</para>
              <para num="B.">erodible soils;</para>
              <para num="C.">steep slopes; and</para>
              <para num="D.">areas to be protected during construction;</para>
            </para>
            <para num="(iv)">preliminary estimates of:<para num="A.">stormwater management requirements;</para>
              <para num="B.">the selection and location of environmental site design practices to be used; and</para>
              <para num="C.">the location of all points of discharge from the site;</para>
            </para>
            <para num="(v)">a narrative that supports the concept design and describes how environmental site design will be implemented to the maximum extent practicable; and</para>
            <para num="(vi)">any other information the Department requires.</para>
          </para>
        </para>
        <para num="(c)" heading="Site development plan.">
          <para num="(1)">After approval of the concept plan, the applicant must submit, unless exempted by the Department, at the Department’s discretion, site development plans that reflect comments received during the previous review phase.</para>
          <para num="(2)">Plans submitted for site development approval must be of sufficient detail to allow site development to be reviewed.</para>
          <para num="(3)">These plans must include the following, minimum information:<para num="(i)">all information provided during the concept plan review phase;</para>
            <para num="(ii)">final site layout, including:<para num="A.">exact impervious area locations and acreages;</para>
              <para num="B.">proposed topography;</para>
              <para num="C.">delineated drainage areas at all points of discharge from the site; and</para>
              <para num="D.">stormwater volume computations for environmental site design practices and quantity control structures;</para>
            </para>
            <para num="(iii)">a narrative that:<para num="A.">supports the site development design;</para>
              <para num="B.">describes how environmental site design will be used to meet the minimum control requirements; and</para>
              <para num="C.">justifies any proposed structural stormwater management or alternative practice measure; and</para>
            </para>
            <para num="(iv)">any other information the Department requires.</para>
          </para>
        </para>
        <para num="(d)" heading="Final stormwater management plans.">
          <para num="(1)">After site development approval, the applicant must submit final stormwater management plans that reflect the comments received during the previous review phase.</para>
          <para num="(2)">Stormwater management plans submitted for final approval must be in the form of construction drawings, in sufficient detail to allow all approvals and permits to be issued, and accompanied by a report that includes sufficient information to evaluate the effectiveness of the proposed runoff control design.</para>
        </para>
        <para num="(e)" heading="Waivers and variances.">The plan must be accompanied by an application for any waiver or variance sought under Subtitle 23 or Subtitle 24.</para>
        <annotation type="History">Ord. 02-367</annotation>
        <annotation type="History">Ord. 10-277</annotation>
        <annotation type="History">Ord. 13- 095</annotation>
      </section>
      <section prefix="§" num="22-6" heading="Report for final plan.">
        <text>The report submitted for final stormwater management plan approval must contain the following, minimum information:</text>
        <para num="(1)">a brief narrative description of the project;</para>
        <para num="(2)">geotechnical investigations, including soil maps, borings, site specific recommendations, and any additional information necessary to evaluate the final stormwater management design;</para>
        <para num="(3)">descriptions of all water courses, impoundments, and wetlands on or adjacent to the site or into which stormwater directly flows;</para>
        <para num="(4)">drainage area maps that show pre- development and post-development runoff flow path segmentation and land use;</para>
        <para num="(5)">hydrologic computations of the applicable environmental site design and unified sizing criteria, according to the State’s Design Manual, for all points of discharge from the site;</para>
        <para num="(6)">hydraulic computations for all environmental site design practices and structural stormwater management measures to be used;</para>
        <para num="(7)">structural computations;</para>
        <para num="(8)">volume sizing computations, according to the State’s Design Manual, that support the final stormwater management design; and</para>
        <para num="(9)">any other information that the Department requires.</para>
        <annotation type="History">Ord. 02-367</annotation>
        <annotation type="History">Ord. 10-277</annotation>
      </section>
      <section prefix="§" num="22-7" heading="Construction drawings for final plan.">
        <para num="(a)" heading="In general.">The construction drawings submitted for final stormwater management plan approval must include the following:<para num="(1)">a vicinity map;</para>
          <para num="(2)">a topography survey that shows existing and proposed contours, including the area necessary to determine downstream analysis for proposed stormwater management facilities;</para>
          <para num="(3)">any proposed improvements, including the location of buildings or other structures, impervious surfaces, storm drainage facilities, and all grading;</para>
          <para num="(4)">the location of existing and proposed structures and utilities;</para>
          <para num="(5)">any easements and rights-of-way;</para>
          <para num="(6)">the delineation, if applicable, of:<para num="(i)">the 100-year floodplain; and</para>
            <para num="(ii)">any on-site wetlands;</para>
          </para>
          <para num="(7)">structural and construction details, including representative cross sections, for all components of:<para num="(i)">the proposed drainage system or systems; and</para>
            <para num="(ii)">stormwater management facilities;</para>
          </para>
          <para num="(8)">all necessary construction specifications;</para>
          <para num="(9)">a sequence of construction;</para>
          <para num="(10)">data for:<para num="(i)">total site area;</para>
            <para num="(ii)">disturbed area;</para>
            <para num="(iii)">new impervious area; and</para>
            <para num="(iv)">total impervious area;</para>
          </para>
          <para num="(11)">a table that shows the environmental site design and unified sizing criteria volumes required by the State’s Design Manual;</para>
          <para num="(12)">a table of materials to be used for stormwater management facility planting;</para>
          <para num="(13)">all soil boring logs and locations;</para>
          <para num="(14)">a maintenance inspection and maintenance activity schedule;</para>
          <para num="(15)">a proposed construction and inspection schedule;</para>
          <para num="(16)">an as-built certification signature block, to be executed after the project is completed; and</para>
          <para num="(17)">any other information that the Department requires.</para>
        </para>
        <para num="(b)" heading="Certification of compliance.">The applicant must certify on the drawings that all grading, drainage, construction, and development will be done in strict accordance with the approved plan.</para>
        <annotation type="History">Ord. 02-367</annotation>
        <annotation type="History">Ord. 10-277</annotation>
      </section>
      <section prefix="§" num="22-8" heading="Preparation of plan.">
        <para num="(a)" heading="In general.">The design of all stormwater management plans must be prepared by a professional engineer, professional land surveyor, or landscape architect licensed in the State.</para>
        <para num="(b)" heading="Professional engineer only.">If stormwater best management practices require a dam safety permit from the Maryland Department of the Environment or small pond approval from the City, the plan must be prepared by a professional engineer licensed in the State.</para>
        <annotation type="History">Ord. 02-367</annotation>
        <annotation type="History">Ord. 10-277</annotation>
      </section>
      <section prefix="§" num="22-9" heading="Easements for runoff.">
        <para num="(a)" heading="Easement.">If a stormwater management plan involves directing some or all runoff from the site, the applicant is responsible for obtaining from adjacent property owners any needed easements or property interests for water flow.</para>
        <para num="(b)" heading="Plan creates no right.">Approval of a stormwater management plan does not create or affect any right to direct runoff onto adjacent property without that property owner’s permission.</para>
        <annotation type="History">Ord. 02-367</annotation>
        <annotation type="History">Ord. 10-277</annotation>
      </section>
      <section prefix="§" num="22-10" heading="Review and approval of plan.">
        <para num="(a)" heading="Review and comment.">
          <para num="(1)">The Department must perform a comprehensive review of the plans for each phase of site design to determine compliance with this Division II.</para>
          <para num="(2)">For each plan phase, coordinated comments will be provided that reflect input from all appropriate agencies, including Planning, Zoning, and Public Works.</para>
          <para num="(3)">At each phase of project design, comments from the Department and other appropriate agencies must be addressed by the applicant and approval received before subsequent submissions.</para>
        </para>
        <para num="(b)" heading="Conditions.">In approving a plan, the Department may impose any conditions that it considers necessary or appropriate to:<para num="(1)">ensure compliance with this Division II; and</para>
          <para num="(2)">preserve the public health and safety.</para>
        </para>
        <para num="(c)" heading="Notification.">After the Department has completed its comprehensive review for each phase of site design, the Department must notify the applicant of:<para num="(1)">the Department’s approval of the plan;</para>
          <para num="(2)">the Department’s disapproval of the plan, together with:<para num="(i)">the reasons for disapproval; and</para>
            <para num="(ii)">any modifications that the Department requires for approval; or</para>
          </para>
          <para num="(3)">if no decision has yet been made:<para num="(i)">the status of the review process; and</para>
            <para num="(ii)">the anticipated date of completion.</para>
          </para>
        </para>
        <para num="(d)" heading="Endorsement.">A stormwater management plan is not valid until the plan has been endorsed and dated by the Department.</para>
        <annotation type="History">Ord. 02-367</annotation>
        <annotation type="History">Ord. 10-277</annotation>
      </section>
    </container>
    <container prefix="Subtitle" num="23" heading="Waivers">
      <section prefix="§" num="23-1" heading="Quantitative control waiver.">
        <para num="(a)" heading="In general.">Except as provided for in &lt;cite data-path="|7|§23-5"&gt;§ 23-5 {“Phased development projects”} of this subtitle&lt;/cite&gt;, the Department may grant a waiver of quantitative control requirements, applied to the existing impervious cover on the site, for a project if:<para num="(1)">environmental site design has been implemented to the maximum extent practicable; and</para>
          <para num="(2)">1 or another of the following applies:<para num="(i)">the project is within an area for which a watershed management plan has been developed consistent with &lt;cite data-path="|7|§23-6"&gt;§ 23-6 of this subtitle&lt;/cite&gt;;</para>
            <para num="(ii)">the project has a direct, concentrated discharge of stormwater:<para num="A.">to tidal waters;</para>
              <para num="B.">to tidally influenced receiving wetlands; or</para>
              <para num="C.">to connected closed storm drainage systems of adequate capacity, as provided in subsection (b) of this section;</para>
            </para>
            <para num="(iii)">the project is an in-fill development to which all of the following apply:<para num="A.">the project is located in an area designated as a priority funding area under State Finance and Procurement Article Title 5, Subtitle 7B;</para>
              <para num="B.">the economic feasability of the project is tied to the planned density allowed under the City’s Zoning Code;</para>
              <para num="C.">implementation of stormwater management regulations adopted by the State in 2009 would result in a loss of planned density allowed under the City’s Zoning Code;</para>
              <para num="D.">the area is served by existing public water, sewer, and stormwater conveyances;</para>
              <para num="E.">the quantitative waiver is applied only to the impervious cover that previously existed on the site;</para>
              <para num="F.">environmental site design to the maximum extent practicable is used to meet the full water quality treatment requirements for the entire development; and</para>
              <para num="G.">environmental site design to the maximum extent practicable is used to provide full quantity control for all new impervious surfaces;</para>
            </para>
            <para num="(iv)">the applicant demonstrates through engineering analysis that unmanaged 10-year and 100-year storm events for the proposed development will not cause erosion, flooding, or an adverse impact on the receiving waters or downstream stormwater conveyance system; or</para>
            <para num="(v)">the Department determines that circumstances exist that prevent the reasonable implementation of quantity control practices.</para>
          </para>
        </para>
        <para num="(b)" heading="Closed drainage systems.">For purposes of subsection (a)(2)(ii)C of this section, hydrologic and hydraulic investigations must show that the receiving storm drainage system can accommodate anticipated storm water flows from the project site without downstream flooding or stream-bank erosion.</para>
        <annotation type="History">Ord. 02-367</annotation>
        <annotation type="History">Ord. 10-277</annotation>
      </section>
      <section prefix="§" num="23-2" heading="Qualitative control waiver.">
        <text>Except as provided for in &lt;cite data-path="|7|§23-5"&gt;§ 23-5 {“Phased development projects”} of this subtitle&lt;/cite&gt;, the Department may grant a waiver of qualitative control requirements for a project if:</text>
        <para num="(1)">the project will return the disturbed area to a predevelopment runoff condition, such as pipeline or conduit projects, certain landscaping projects, certain maintenance projects, and certain underground projects;</para>
        <para num="(2)">the project is an in-fill development project (that is, a development on vacant, bypassed, or underutilized land within an existing developed area) for which:<para num="(i)">environmental site design has been implemented to the maximum extent practicable; and</para>
          <para num="(ii)">it has been demonstrated that other best management practices are not feasible;</para>
        </para>
        <para num="(3)">the project is a redevelopment project for which the requirements of &lt;cite data-path="|7|§23-7"&gt;§ 23-7 of this subtitle&lt;/cite&gt; are satisfied; or</para>
        <para num="(4)">the Department determines that circumstances exist that prevent the reasonable implementation of environmental site design to the maximum extent practicable.</para>
        <annotation type="History">Ord. 02-367</annotation>
        <annotation type="History">Ord. 10-277</annotation>
      </section>
      <section prefix="§" num="23-3" heading="Conditions of waiver.">
        <para num="(a)" heading="Case-by-case.">A waiver may be granted only on a case-by-case basis, after considering the cumulative effects of the Department’s waiver policy.</para>
        <para num="(b)" heading="Impact.">A waiver may be granted only if it reasonably ensures that the development will not adversely impact stream quality.</para>
        <para num="(c)" heading="Fee in-lieu.">The Department may require a person who is granted a waiver to pay a fee in-lieu-of on-site management.</para>
        <annotation type="History">Ord. 02-367</annotation>
      </section>
      <section prefix="§" num="23-4" heading="Applications.">
        <para num="(a)" heading="In general.">The application for a waiver must:<para num="(1)">be in the form that the Department requires;</para>
          <para num="(2)">contain the descriptions, drawings, and other information needed to evaluate the proposed waiver;</para>
          <para num="(3)">contain any other information that the Department requires; and</para>
          <para num="(4)">be submitted to the Department with the applicant’s proposed stormwater management plan.</para>
        </para>
        <para num="(b)" heading="Separate applications for additions, etc.">A separate application is required for subsequent additions, extensions, or modifications to a development.</para>
        <annotation type="History">Ord. 02-367</annotation>
        <annotation type="History">Ord. 10-277</annotation>
      </section>
      <section prefix="§" num="23-4.1" heading="Public notices and comment.">
        <para num="(a)" heading="Website notice.">
          <para num="(1)">When an application for a waiver is submitted, the Department shall prepare and post on its website, available for download, a public notice of the application.</para>
          <para num="(2)">The public notice shall include:<para num="(i)">the applicant’s name and address;</para>
            <para num="(ii)">a description of the location and nature of the activity for which the application is made;</para>
            <para num="(iii)">the name, address, and telephone number of the office within the Department from which persons may obtain information about the application;</para>
            <para num="(iv)">a statement that any further notices about actions on the application will be posted on the Department’s website;</para>
            <para num="(v)">a description of how persons may submit information or comments about the application; and</para>
            <para num="(vi)">the date when the public comment period closes, not to exceed 30 days, and by which information or comments must be received by the Department.</para>
          </para>
        </para>
        <para num="(b)" heading="Mail and email notices.">The Department also shall mail or email public notices to:<para num="(1)">all contiguous property owners;</para>
          <para num="(2)">the City Councilmember in whose district the property is located; and</para>
          <para num="(3)">persons who have submitted information or comments about the application.</para>
        </para>
        <para num="(c)" heading="Comments.">Comments on an application must be submitted in writing to the Department before the close of the public comment period, as specified in the public notice.</para>
        <annotation type="History">Ord. 10-277</annotation>
      </section>
      <section prefix="§" num="23-5" heading="Phased development projects.">
        <text>The Department may grant a quantitative and qualitative control waiver for a phased development project if:</text>
        <para num="(1)">by May 4, 2010, a stormwater system has been constructed that is designed to meet:<para num="(i)">the regulatory requirements for stormwater adopted in 2000 by the Maryland Department of the Environment; and</para>
          <para num="(ii)">the requirements of this Division II, as in effect on July 27, 2002; or</para>
        </para>
        <para num="(2)">for future phases of a phased development project that are constructed after May 4, 2010:<para num="(i)">the regulatory requirements for stormwater adopted in 2009 by the Maryland Department of the Environment cannot be met; and</para>
          <para num="(ii)">the applicant demonstrates that all reasonable efforts were made to incorporate environmental site design into these phases of the development.</para>
        </para>
        <annotation type="History">Ord. 10-277</annotation>
      </section>
      <section prefix="§" num="23-6" heading="Watershed management plan.">
        <para num="(a)" heading="In general.">
          <para num="(1)">The Department may develop an overall watershed management plan for the purpose of implementing different policies for waivers and redevelopment.</para>
          <para num="(2)">If the Department establishes a watershed management plan for a specific watershed, the Department may develop quantitative control waivers and redevelopment provisions that differ from § 23-1(a)(2)(ii) through (v) and § 23-7.</para>
          <para num="(3)">
            <para num="(i)">If the Department establishes a watershed management plan for a specific watershed, then the Department may develop separate policies, reviewed and approved by the State Water Management Administration, for providing water quality control.</para>
            <para num="(ii)">These separate policies may include:<para num="A.">retrofitting;</para>
              <para num="B.">stream restoration;</para>
              <para num="C.">pollution trading;</para>
              <para num="D.">design criteria based on watershed management plans developed under &lt;cite data-path="|7|§23-6|(b)"&gt;§ 23-6(b) of this Division II&lt;/cite&gt;;</para>
              <para num="E.">payment of offset fees that are dedicated exclusively to provide for stormwater management within the same watershed as the proposed development; or</para>
              <para num="F.">other policies developed by the Department.</para>
            </para>
          </para>
        </para>
        <para num="(b)" heading="Requisites.">For this purpose, the watershed management plan must:<para num="(1)">include detailed hydrologic and hydraulic analyses to determine hydrograph timing;</para>
          <para num="(2)">include an evaluation of both quantity and quality management and of opportunities for environmental site design implementation;</para>
          <para num="(3)">include a cumulative impact assessment of current and proposed watershed development;</para>
          <para num="(4)">identify existing flooding conditions and receiving stream channel conditions;</para>
          <para num="(5)">be prepared at a reasonable scale;</para>
          <para num="(6)">specify where on-site or off-site quantitative and qualitative controls are to be implemented;</para>
          <para num="(7)">be consistent with the General Performance Standards for Stormwater Management in Maryland, found in Section 1.2 of the State’s Design Manual; and</para>
          <para num="(8)">be approved by the State Water Management Administration.</para>
        </para>
        <annotation type="History">Ord. 02-367</annotation>
        <annotation type="History">Ord. 10-277</annotation>
      </section>
      <section prefix="§" num="23-7" heading="Redevelopment.">
        <para num="(a)" heading="In general.">
          <para num="(1)">Stormwater management plans are required for all redevelopment, unless otherwise specified by watershed management plans developed under &lt;cite data-path="|7|§23-6|(b)"&gt;§ 23-6(b) of this subtitle&lt;/cite&gt;.</para>
          <para num="(2)">Stormwater management measures must be consistent with the State’s Design Manual.</para>
        </para>
        <para num="(b)" heading="Waived requirements.">Unless otherwise specified by the Department, a redevelopment project need not comply with requirements of the State’s Design Manual for:<para num="(1)">recharge volume;</para>
          <para num="(2)">channel protection storage volume;</para>
          <para num="(3)">overbank flood protection volume; and</para>
          <para num="(4)">extreme flood protection volume.</para>
        </para>
        <para num="(c)" heading="Applicable requirements – In general.">
          <para num="(1)">All redevelopment projects must, in accordance with the State’s Design Manual, reduce existing site impervious areas within the limits of disturbance by at least 50%.</para>
          <para num="(2)">If site conditions prevent the reduction of impervious area, then environmental site design practices must be implemented to the maximum extent practicable for at least 50% of the site’s existing impervious area within the limits of disturbance.</para>
          <para num="(3)">If a combination of impervious area reduction and stormwater practice implementation is used, the combined area must equal or exceed 50% of the site’s existing impervious area within the limits of disturbance.</para>
        </para>
        <para num="(d)" heading="Applicable requirements – Alternatives.">
          <para num="(1)">Alternative stormwater management measures may be used to meet the requirements of subsection (c) of this section if the applicant satisfactorily demonstrates to the Department that:<para num="(i)">impervious area reduction has been maximized; and</para>
            <para num="(ii)">environmental site design has been implemented to the maximum extent practicable.</para>
          </para>
          <para num="(2)">Alternative stormwater management measures include:<para num="(i)">an on-site structural best management practice;</para>
            <para num="(ii)">off-site implementation of structural best management practices to provide water quality treatment for an area equal to at least 50% of the existing impervious area within the limits of disturbance; and</para>
            <para num="(iii)">a combination of impervious area reduction, environmental site design implementation, and an on-site or off-site structural best management practice for an area equal to at least 50% of the existing site impervious area within the limits of disturbance.</para>
          </para>
        </para>
        <para num="(e)" heading="Separate policies.">
          <para num="(1)">The Department may develop separate policies for providing water quality treatment for redevelopment projects if the Department determines that the provisions of subsections (c) and (d) of this section have been implemented to the maximum extent practicable.</para>
          <para num="(2)">The Department’s criteria for separate policies are outlined in the City’s Design Guidelines.</para>
          <para num="(3)">Any separate redevelopment policy must be reviewed and approved by the State Water Management Administration.</para>
          <para num="(4)">These separate policies may include:<para num="(i)">a combination of impervious area reduction, environmental site design, and on-site and off-site structural best management practices;</para>
            <para num="(ii)">retrofitting to improve water quality over current conditions by:<para num="A.">construction of structural best management practices in a previously developed area; or</para>
              <para num="B.">modification of existing structural best management practices;</para>
            </para>
            <para num="(iii)">watershed or stream restoration;</para>
            <para num="(iv)">pollution trading;</para>
            <para num="(v)">design criteria based on watershed management plans developed under &lt;cite data-path="|7|§23-6|(b)"&gt;§ 23-6(b) of this subtitle&lt;/cite&gt;;</para>
            <para num="(vi)">payment of offset fees that are dedicated exclusively for stormwater management within the same watershed as the proposed development;</para>
            <para num="(vii)">a partial waiver of the treatment requirements if environmental site design is not practicable; or</para>
            <para num="(viii)">other practices approved by the Department.</para>
          </para>
          <para num="(5)">The Department will determine during the concept design phase which alternative measures may be made available. Prioritization of the alternative measures listed in paragraph (4) of this subsection must be considered after a determination by the Department that it is not practical to meet the 2009 regulatory requirements using environmental site design.</para>
          <para num="(6)">When determining which alternative measures may be authorized under paragraph (4) of this subsection for a project, the Department may consider whether:<para num="(i)">the redevelopment project is located in an area designated as:<para num="A.">a priority funding area under State Finance and Procurement Article Title 5, Subtitle 7B;</para>
              <para num="B.">a transit oriented development area under State Transportation Article Title 7, Subtitle 1; or</para>
              <para num="C.">a base realignment and closure revitalization and incentive zone under State Economic Development Article Title 5, Subtitle 13;</para>
            </para>
            <para num="(ii)">the redevelopment project is necessary to accommodate growth consistent with the City’s comprehensive plan for the area in which the project will be located; or</para>
            <para num="(iii)">bonding and financing have been secured based on an approval of a redevelopment plan approved by the Department.</para>
          </para>
        </para>
        <para num="(f)" heading="Applicable requirements – Increased impervious area.">For any net increase in impervious area resulting from the project, stormwater management must be addressed according to the new development requirements of the State’s Design Manual.</para>
        <annotation type="History">Ord. 02-367</annotation>
        <annotation type="History">Ord. 10-277</annotation>
      </section>
      <section prefix="§" num="23-8" heading="Administrative waiver.">
        <para num="(a)" heading="In general.">
          <para num="(1)">An administrative waiver is a decision by the Department to allow construction of a development project to be governed by the provisions of this Division II, as in effect on May 4, 2009.</para>
          <para num="(2)">An administrative waiver does not include quantitative or qualitative control waivers issued under § 23-1, § 23-2, or &lt;cite data-path="|7|§23-5"&gt;§ 23-5 of this Division II&lt;/cite&gt;.</para>
        </para>
        <para num="(b)" heading="Preliminary project approval.">
          <para num="(1)">An administrative waiver may be granted by the Department to a development project that, on or before May 4, 2010, has received preliminary project approval as part of a preliminary or planning review process.</para>
          <para num="(2)">At a minimum, a preliminary project approval includes:<para num="(i)">the number of planned dwelling units or lots;</para>
            <para num="(ii)">the proposed project density;</para>
            <para num="(iii)">the proposed size and location of all land uses for the project;</para>
            <para num="(iv)">a plan that identifies:<para num="A.">the proposed drainage patterns;</para>
              <para num="B.">the location of all points of discharge from the site; and</para>
              <para num="C.">the type, location, and size of all stormwater management measures based on site-specific stormwater management requirement computations; and</para>
            </para>
            <para num="(v)">any other information that the Department requires.</para>
          </para>
          <para num="(3)">An approval granted under this subsection does not require approval of an erosion and sediment control plan as a condition for the approval.</para>
        </para>
        <para num="(c)" heading="Expiration.">Except as provided by subsection (d) of this section, an administrative waiver granted under subsection (b) of this section expires on:<para num="(1)">May 4, 2013, if the development project does not have final erosion and sediment control and final stormwater management approval on or before that date; or</para>
          <para num="(2)">May 4, 2017, if the development project receives final erosion and sediment control and final stormwater management approval on or before May 4, 2013.</para>
        </para>
        <para num="(d)" heading="Extension.">
          <para num="(1)">Except as provided in paragraph (2) of this subsection, an administrative waiver may not be extended.</para>
          <para num="(2)">The Department may grant an extension for an administrative waiver only if, by May 4, 2010, a development project:<para num="(i)">has received a preliminary project approval as provided for in subsection (b) of this section; and</para>
            <para num="(ii)">was subject to:<para num="A.">a development rights and responsibilities agreement;</para>
              <para num="B.">a tax increment financing approval; or</para>
              <para num="C.">an annexation agreement.</para>
            </para>
          </para>
          <para num="(3)">When an agreement or approval identified in paragraph (2)(ii) of this subsection expires, any administrative waiver that was extended will expire.</para>
        </para>
        <para num="(e)" heading="Completion of construction.">Construction authorized by an administrative waiver granted under this section must be completed, with an occupancy permit issued under the &lt;cite data-path="|building-codes|II"&gt;Building Code&lt;/cite&gt; and a use permit issued under the Zoning Code, on or before either:<para num="(1)">May 4, 2017; or</para>
          <para num="(2)">the expiration date specified for any extension granted under subsection (d) of this section.</para>
        </para>
        <annotation type="History">Ord. 10-277</annotation>
      </section>
    </container>
    <container prefix="Subtitle" num="24" heading="Variances">
      <section prefix="§" num="24-1" heading="When authorized.">
        <text>The Department may grant a variance from any requirement of this Division II if, because of exceptional circumstances applicable to the site, strict adherence to that requirement will result in unnecessary hardship and not fulfill the intent of this Division II.</text>
        <annotation type="History">Ord. 02-367</annotation>
      </section>
      <section prefix="§" num="24-2" heading="Application for variance.">
        <text>The application for a variance must:</text>
        <para num="(1)">be in the form that the Department requires;</para>
        <para num="(2)">state the specific variance sought;</para>
        <para num="(3)">explain why the variance is needed;</para>
        <para num="(4)">contain any other information that the Department requires; and</para>
        <para num="(5)">be submitted to the Department with the applicant’s proposed stormwater management plan.</para>
        <annotation type="History">Ord. 02-367</annotation>
        <annotation type="History">Ord. 10-277</annotation>
      </section>
      <section prefix="§" num="24-2.1" heading="Public notices and comment.">
        <para num="(a)" heading="Website notice.">
          <para num="(1)">When an application for a variance is submitted, the Department shall prepare and post on its website, available for download, a public notice of the application.</para>
          <para num="(2)">The public notice shall include:<para num="(i)">the applicant’s name and address;</para>
            <para num="(ii)">a description of the location and nature of the activity for which the application is made;</para>
            <para num="(iii)">the name, address, and telephone number of the office within the Department from which persons may obtain information about the application;</para>
            <para num="(iv)">a statement that any further notices about actions on the application will be posted on the Department’s website;</para>
            <para num="(v)">a description of how persons may submit information or comments about the application; and</para>
            <para num="(vi)">the date when the public comment period closes, not to exceed 30 days, and by which information or comments must be received by the Department.</para>
          </para>
        </para>
        <para num="(b)" heading="Mail and email notices.">The Department also shall mail or email public notices to:<para num="(1)">all contiguous property owners;</para>
          <para num="(2)">the City Councilmember in whose district the property is located; and</para>
          <para num="(3)">persons who have submitted information or comments about the application.</para>
        </para>
        <para num="(c)" heading="Comments.">Comments on an application must be submitted in writing to the Department before the close of the public comment period, as specified in the public notice.</para>
        <annotation type="History">Ord. 10-277</annotation>
      </section>
      <section prefix="§" num="24-3" heading="Justification required.">
        <text>The Department may not grant a variance unless the applicant provides sufficient satisfactorily demonstrates that the implementation of environmental site design to the maximum extent practicable has been thoroughly investigated.</text>
        <annotation type="History">Ord. 02-367</annotation>
        <annotation type="History">Ord. 10-277</annotation>
      </section>
      <section prefix="§" num="24-4" heading="Offset fee.">
        <text>The Department may require a person who is granted a variance to pay an offset fee to the City.</text>
        <annotation type="History">Ord. 02-367</annotation>
      </section>
    </container>
    <container prefix="Subtitle" num="25" heading="Permits; Fees; Security">
      <section prefix="§" num="25-1" heading="Approved plan prerequisite to permits.">
        <para num="(a)" heading="Grading and building permits.">For any development that requires a stormwater management plan under this Division II, a grading or building permit may not be issued unless a final erosion and sediment control plan and a stormwater management plan has been approved by the Department.</para>
        <para num="(b)" heading="Building permits.">A building permit may not be issued without:<para num="(1)">recorded easements, as needed:<para num="(i)">for the environmental site design techniques and practices and structural stormwater management measures, as provided for in the approved stormwater management plan; and</para>
            <para num="(ii)">to provide adequate access for inspection and maintenance from a public right-of-way;</para>
          </para>
          <para num="(2)">a recorded stormwater management maintenance agreement, as described in &lt;cite data-path="|7|§27-3"&gt;§ 27-3 of this Division II&lt;/cite&gt;;</para>
          <para num="(3)">a performance bond; and</para>
          <para num="(4)">all necessary permissions from adjacent property owners.</para>
        </para>
        <annotation type="History">Ord. 02-367</annotation>
        <annotation type="History">Ord. 10-277</annotation>
      </section>
      <section prefix="§" num="25-2" heading="Fees.">
        <para num="(a)" heading="In general.">Non-refundable fees will be assessed and collected in advance by the Department for each phase of a development.</para>
        <para num="(b)" heading="Fee schedule.">
          <para num="(1)">The fees assessed under this Division II are in addition to the usual fees charged for grading or building permits.</para>
          <para num="(2)">Fees shall be assessed for plan reviews, waivers, offsets, stormwater approvals, administration and management of the approval process, inspections, “small-project” exemptions under &lt;cite data-path="|7|§21-6|(b)|(4)"&gt;§ 21-6(b)(4) of this Division II&lt;/cite&gt;, fees in lieu, and the like.</para>
          <para num="(3)">The amount of these fees shall be based on the relative complexity of a project, in accordance with a fee schedule established from time to time by the Board of Estimates.</para>
        </para>
        <annotation type="History">Ord. 02-367</annotation>
        <annotation type="History">Ord. 10-277</annotation>
      </section>
      <section prefix="§" num="25-3" heading="Performance security.">
        <para num="(a)" heading="Required.">For any development that requires a stormwater management plan under this Division II, a grading or building permit may not be issued until the applicant posts a surety or cash bond, or other means of security acceptable to the Department.</para>
        <para num="(b)" heading="Amount.">The amount of the security may not be less than the total estimated construction cost of the stormwater management facility.  This estimate must be prepared by the applicant and submitted with the plan.</para>
        <para num="(c)" heading="Tenor.">The security required by this section must provide for forfeiture on failure to:<para num="(1)">complete all work specified in the approved stormwater management plan;</para>
          <para num="(2)">comply with any provision of this Division II or of any other applicable law or regulation; or</para>
          <para num="(3)">comply with any applicable time limitations.</para>
        </para>
        <para num="(d)" heading="Release.">The security may not be released until:<para num="(1)">the Department conducts a final inspection of the completed work;</para>
          <para num="(2)">the applicant submits “as-built” plans to the Department, containing an executed as-built certification block; and</para>
          <para num="(3)">the Department verifies that the stormwater management facilities:<para num="(i)">have been completed; and</para>
            <para num="(ii)">comply with the approved plan and this Division II.</para>
          </para>
        </para>
        <annotation type="History">Ord. 02-367</annotation>
        <annotation type="History">Ord. 10-277</annotation>
      </section>
      <section prefix="§" num="25-4" heading="Permit suspension or revocation.">
        <text>After written notice to the permit holder, the Department may suspend or revoke any grading or building permit for any of the following reasons:</text>
        <para num="(1)">any violation of the conditions of the stormwater management plan approval;</para>
        <para num="(2)">any change in the site runoff characteristics on which a plan approval or waiver was granted;</para>
        <para num="(3)">construction not in accordance with the approved plan;</para>
        <para num="(4)">failure to comply with a correction notice or stop work order issued for the facility; or</para>
        <para num="(5)">a finding by the Department that an immediate danger exists in a downstream area.</para>
        <annotation type="History">Ord. 02-367</annotation>
        <annotation type="History">Ord. 10-277</annotation>
      </section>
    </container>
    <container prefix="Subtitle" num="26" heading="Inspections">
      <section prefix="§" num="26-1" heading="By whom conducted.">
        <text>All inspections under this Division II must be:</text>
        <para num="(1)">conducted by an authorized representative of the Department; or</para>
        <para num="(2)">certified by a professional engineer licensed in this State.</para>
        <annotation type="History">Ord. 02-367</annotation>
        <annotation type="History">Ord. 10-277</annotation>
      </section>
      <section prefix="§" num="26-2" heading="Notices by applicant.">
        <text>The applicant must notify the Department:</text>
        <para num="(1)">at least 48 hours before starting any work in conjunction with site development;</para>
        <para num="(2)">at least 48 hours before starting any work in conjunction with the stormwater management plan; and</para>
        <para num="(3)">on completion of the project.</para>
        <annotation type="History">Ord. 02-367</annotation>
        <annotation type="History">Ord. 10-277</annotation>
      </section>
      <section prefix="§" num="26-3" heading="Inspections during construction.">
        <para num="(a)" heading="In general.">At a minimum, regular inspections must be made and documented, at the stages of construction specified in this section, for each environmental site design planning technique and practice and each structural and nonstructural stormwater management practice.</para>
        <para num="(b)" heading="Ponds.">For ponds:<para num="(1)">On completion of excavation to sub-foundation and, when required, installation of structural supports or reinforcement for structures, including:<para num="(i)">core trenches for structural embankments;</para>
            <para num="(ii)">inlet and outlet structures, anti-seep collars or diaphragms, and watertight connectors on pipes; and</para>
            <para num="(iii)">trenches for enclosed storm drainage facilities;</para>
          </para>
          <para num="(2)">during placement of structural fill or concrete and installation of piping and catch basins;</para>
          <para num="(3)">during backfill of foundations and trenches;</para>
          <para num="(4)">during embankment construction; and</para>
          <para num="(5)">on completion of final grading and establishment of permanent stabilization.</para>
        </para>
        <para num="(c)" heading="Wetlands.">For wetlands:<para num="(1)">at the stages specified in subsection (b) of this section for pond construction;</para>
          <para num="(2)">during and after wetland reservoir area planting; and</para>
          <para num="(3)">during the second growing season to verify a vegetation survival rate of at least 50%.</para>
        </para>
        <para num="(d)" heading="Infiltration trenches.">For infiltration trenches:<para num="(1)">during excavation to subgrade;</para>
          <para num="(2)">during placement and backfill of underdrain systems and observation wells;</para>
          <para num="(3)">during placement of geotextiles and all filter media;</para>
          <para num="(4)">during construction of appurtenant conveyance systems, such as diversion structures, pre-filters and filters, inlets, outlets, and flow distribution structures; and</para>
          <para num="(5)">on completion of final grading and establishment of permanent stabilization.</para>
        </para>
        <para num="(e)" heading="Infiltration basins.">For infiltration basins:<para num="(1)">at the stages specified in subsection (b) of this section for pond construction; and</para>
          <para num="(2)">during placement and backfill of underdrain systems.</para>
        </para>
        <para num="(f)" heading="Filtering systems.">For filtering systems:<para num="(1)">during excavation to subgrade;</para>
          <para num="(2)">during placement and backfill of underdrain systems;</para>
          <para num="(3)">during placement of geotextiles and all filter media;</para>
          <para num="(4)">during construction of appurtenant conveyance systems, such as flow diversion structures, pre-filters and filters, inlets, outlets, orifices, and flow distribution structures; and</para>
          <para num="(5)">on completion of final grading and establishment of permanent stabilization.</para>
        </para>
        <para num="(g)" heading="Open channel systems.">For open channel systems:<para num="(1)">during excavation to subgrade;</para>
          <para num="(2)">during placement and backfill of underdrain systems for dry swales;</para>
          <para num="(3)">during installation of diaphragms, check dams, or weirs; and</para>
          <para num="(4)">on completion of final grading and establishment of permanent stabilization.</para>
        </para>
        <para num="(h)" heading="Environmental site design and nonstructural practices.">For environmental site design and nonstructural practices:<para num="(1)">on completion of final grading;</para>
          <para num="(2)">on establishment of permanent stabilization; and</para>
          <para num="(3)">before issuance of an occupancy permit under the &lt;cite data-path="|building-codes|II"&gt;Building Code&lt;/cite&gt; and a use permit under the Zoning Code.</para>
        </para>
        <annotation type="History">Ord. 02-367</annotation>
        <annotation type="History">Ord. 10-277</annotation>
      </section>
      <section prefix="§" num="26-4" heading="Inspection reports.">
        <para num="(a)" heading="Reports required.">Written reports must be made of all inspections conducted during construction.</para>
        <para num="(b)" heading="Scope.">Each inspection report must specify:<para num="(1)">the date and location of the inspection;</para>
          <para num="(2)">whether the construction complies with the approved stormwater management plan;</para>
          <para num="(3)">any variations from the approved construction specifications;</para>
          <para num="(4)">any violations found; and</para>
          <para num="(5)">any other information that the Department requires.</para>
        </para>
        <para num="(c)" heading="Notice to applicant.">The Department must provide the applicant with the results of each inspection report as soon as possible after the inspection.</para>
        <annotation type="History">Ord. 02-367</annotation>
        <annotation type="History">Ord. 10-277</annotation>
      </section>
      <section prefix="§" num="26-5" heading="Work stoppage pending inspection.">
        <text>At the completion of each construction stage for which an inspection is required, no further work may be done until the Department inspects and approves the work completed to date.</text>
        <annotation type="History">Ord. 02-367</annotation>
      </section>
      <section prefix="§" num="26-6" heading="Final inspection.">
        <text>A final inspection must be conducted after construction is completed.</text>
        <annotation type="History">Ord. 02-367</annotation>
      </section>
      <section prefix="§" num="26-7" heading="As-built certification.">
        <para num="(a)" heading="Required.">Once construction is complete, the applicant must submit to the Department an as-built plan certification by a professional engineer or professional land surveyor licensed in the State.</para>
        <para num="(b)" heading="Tenor.">The certification must certify that the completed stormwater management practices and conveyance systems comply with the specifications contained in the approved plan.</para>
        <para num="(c)" heading="Contents.">The certification must include:<para num="(1)">a set of drawings that compare the approved stormwater management plan with what has been constructed; and</para>
          <para num="(2)">any other information that the Department requires.</para>
        </para>
        <annotation type="History">Ord. 02-367</annotation>
        <annotation type="History">Ord. 10-277</annotation>
      </section>
      <section prefix="§" num="26-8" heading="Notice to State Administration.">
        <para num="(a)" heading="In general.">For each stormwater management practice completed, the Department must submit a notice of construction to the State Water Management Administration.</para>
        <para num="(b)" heading="When and how.">The notice must be submitted:<para num="(1)">within 45 days of construction completion; and</para>
          <para num="(2)">on the form that the Administration supplies.</para>
        </para>
        <para num="(c)" heading="Contents.">The notice must report, on a site-by-site basis, the type, number, total drainage area, and total impervious area treated by all environmental site design techniques and practices and structural stormwater management practices.</para>
        <annotation type="History">Ord. 02-367</annotation>
        <annotation type="History">Ord. 10-277</annotation>
      </section>
    </container>
    <container prefix="Subtitle" num="27" heading="Maintenance">
      <section prefix="§" num="27-1" heading="Maintenance responsibility.">
        <para num="(a)" heading="In general.">The maintenance of private stormwater management facilities is the responsibility of:<para num="(1)">the owner of the property; and</para>
          <para num="(2)">any other person in control of the property.</para>
        </para>
        <para num="(b)" heading="Scope of responsibility.">The owner of a property that contains private stormwater management facilities installed under this Division II or any other person in control of that property must, in perpetuity, maintain in good condition and promptly repair and restore all:<para num="(1)">environmental site design practices;</para>
          <para num="(2)">stormwater management facilities;</para>
          <para num="(3)">grade surfaces, walls, drains, dams, and structures;</para>
          <para num="(4)">vegetation;</para>
          <para num="(5)">erosion and sediment control measures; and</para>
          <para num="(6)">other protective devices.</para>
        </para>
        <para num="(c)" heading="Compliance with plan.">All maintenance, repairs, and restoration must be in accordance with the approved stormwater management plan.</para>
        <annotation type="History">Ord. 02-367</annotation>
        <annotation type="History">Ord. 10-277</annotation>
      </section>
      <section prefix="§" num="27-2" heading="Maintenance schedule.">
        <para num="(a)" heading="Required.">A maintenance schedule must be developed for the life of every stormwater management facility or system of environmental site design practices.</para>
        <para num="(b)" heading="Contents.">The schedule must specify:<para num="(1)">the maintenance to be completed;</para>
          <para num="(2)">the time for completing that maintenance; and</para>
          <para num="(3)">the person responsible for performing that maintenance.</para>
        </para>
        <para num="(c)" heading="Schedule to be part of approved plan.">The maintenance schedule must be printed on the approved stormwater management plan.</para>
        <annotation type="History">Ord. 02-367</annotation>
        <annotation type="History">Ord. 10-277</annotation>
      </section>
      <section prefix="§" num="27-3" heading="Maintenance agreement.">
        <para num="(a)" heading="Prerequisite for permit.">Before any grading or building permit may be issued for a project for which a private stormwater management facility is required, the owner must execute an inspection and maintenance agreement binding on all current and subsequent owners of land served by the facility.</para>
        <para num="(b)" heading="Coverage.">The agreement must provide for access to the facility, at all reasonable times, for regular inspections by the Department or its authorized representative to ensure that the facility is maintained in proper working condition to meet design standards.</para>
        <para num="(c)" heading="Performance bond.">
          <para num="(1)">A performance bond, with amount, terms, and provisions acceptable to the Department, must be provided.</para>
          <para num="(2)">The agreement must provide for forfeiture of the performance bond if, after written notice by the Department to correct any nonconformance with an approved plan&lt;strong&gt;&lt;em&gt;,&lt;/em&gt;&lt;/strong&gt; the owner fails to make satisfactory corrections within a reasonable time, not to exceed 30 days, unless extended for good cause shown.</para>
        </para>
        <para num="(d)" heading="Recordation.">The owner must record the agreement in the land records of Baltimore City.</para>
        <annotation type="History">Ord. 02-367</annotation>
        <annotation type="History">Ord. 10-277</annotation>
      </section>
      <section prefix="§" num="27-4" heading="Maintenance inspections.">
        <para num="(a)" heading="Periodic inspections required.">
          <para num="(1)">The Department must periodically inspect all environmental site design practices and structural stormwater management measures to ensure that preventative maintenance is being performed.</para>
          <para num="(2)">These inspections must be made:<para num="(i)">at least once during the 1&lt;sup&gt;st&lt;/sup&gt; year of operation; and</para>
            <para num="(ii)">at least once every 3 years following.</para>
          </para>
        </para>
        <para num="(b)" heading="Inspection reports.">
          <para num="(1)">The Department must maintain inspection reports for all stormwater management systems.</para>
          <para num="(2)">These inspection reports must include the following:<para num="(i)">the date of inspection;</para>
            <para num="(ii)">the name of the inspector;</para>
            <para num="(iii)">an assessment of the quality of the stormwater management system related to environmental site design treatment practice efficiency and the control of runoff to the maximum extent practicable;</para>
            <para num="(iv)">the condition of:<para num="A.">vegetation and filter media;</para>
              <para num="B.">fences and other safety devices;</para>
              <para num="C.">spillways, valves, and other control structures;</para>
              <para num="D.">embankments, slopes, and safety benches;</para>
              <para num="E.">reservoir and treatment areas;</para>
              <para num="F.">inlet and outlet channels and structures;</para>
              <para num="G.">underground drainage;</para>
              <para num="H.">sediment and debris accumulation in storage and forebay areas;</para>
              <para num="I.">any nonstructural practices to the extent practicable; and</para>
              <para num="J.">any other item that could affect the proper function of the stormwater management system; and</para>
            </para>
            <para num="(v)">a description of needed maintenance.</para>
          </para>
        </para>
        <annotation type="History">Ord. 02-367</annotation>
        <annotation type="History">Ord. 10-277</annotation>
      </section>
      <section prefix="§" num="27-5" heading="Deficiencies.">
        <para num="(a)" heading="Notice of deficiency.">The department must promptly notify the owner of any deficiencies discovered from a maintenance inspection.</para>
        <para num="(b)" heading="Owner to correct.">The owner must correct the deficiencies:<para num="(1)">within 30 days of the notice; or</para>
          <para num="(2)">by any other time to which the Department and the owner agree.</para>
        </para>
        <para num="(c)" heading="Reinspection.">The Department must conduct a subsequent inspection to ensure completion of all required repairs.</para>
        <para num="(d)" heading="Enforcement action.">If repairs are not made or are not done properly, the Department may take any enforcement action authorized by Subtitle 28 of &lt;cite data-path="|7"&gt;this article&lt;/cite&gt; or otherwise by law.</para>
        <para num="(e)" heading="Immediate danger to health or safety.">
          <para num="(1)">If, after an inspection by the Department, the condition of a stormwater management facility is determined to present an immediate danger to the public health or safety, the Department may take whatever action is necessary to protect the public and make the facility safe.</para>
          <para num="(2)">The Department may assess against the owner the costs incurred under this subsection.</para>
        </para>
        <annotation type="History">Ord. 02-367</annotation>
        <annotation type="History">Ord. 10-277</annotation>
      </section>
    </container>
    <container prefix="Subtitle" num="28" heading="Enforcement; Reviews; Penalties">
      <section prefix="§" num="28-1" heading="Violation notices.">
        <para num="(a)" heading="Notice required.">If a violation is found, the Department must provide written notice of the violation to:<para num="(1)">the developer or owner; and</para>
          <para num="(2)">the on-site personnel.</para>
        </para>
        <para num="(b)" heading="Contents.">A violation notice must describe:<para num="(1)">the nature of the violation; and</para>
          <para num="(2)">the required corrective action.</para>
        </para>
        <annotation type="History">Ord. 02-367</annotation>
      </section>
      <section prefix="§" num="28-2" heading="Enforcement of notice.">
        <para num="(a)" heading="In general.">The Department may take any one or a combination of the following actions to enforce a violation notice.</para>
        <para num="(b)" heading="Stop work order.">If a violation persists after issuance of a violation notice, the Department may issue a stop work order for the site.</para>
        <para num="(c)" heading="Bond forfeiture; other action.">If reasonable efforts to correct the violation have not been undertaken, the Department may:<para num="(1)">cause the performance bond or other securities to be forfeited; and</para>
          <para num="(2)">refer the matter for legal action.</para>
        </para>
        <para num="(d)" heading="Civil fines.">
          <para num="(1)">The Department may impose civil fines for minor infractions of this Division II.</para>
          <para num="(2)">A schedule of fines, not to exceed $500 for any one offense, shall be established and may be amended from time to time by the Department with the approval of the Baltimore City Board of Estimates.</para>
        </para>
        <annotation type="History">Ord. 02-367</annotation>
      </section>
      <section prefix="§§" num="28-3 to 28-4" reserved="true" />
      <section prefix="§" num="28-5" heading="Administrative review – In general.">
        <para num="(a)" heading="Right of appeal.">Any person aggrieved by the action of any official charged with the enforcement of this Division II, whether as the result of the disapproval of an application, the issuance of a violation notice, an alleged failure to properly enforce this Division II, or otherwise:<para num="(1)">may appeal the action to the Director of Public Works; and</para>
          <para num="(2)">on timely request, is entitled to a hearing on that appeal.</para>
        </para>
        <para num="(b)" heading="When and how taken.">The appeal must:<para num="(1)">be in writing;</para>
          <para num="(2)">state clearly the grounds on which the appeal is based;</para>
          <para num="(3)">if the person aggrieved desires a hearing on the appeal, contain an express statement to that effect; and</para>
          <para num="(4)">be filed with the Director within 10 days of the action in dispute.</para>
        </para>
        <annotation type="History">Ord. 02-367</annotation>
        <annotation type="History">Ord. 14-307</annotation>
        <annotation type="History">Ord. 19-332</annotation>
      </section>
      <section prefix="§" num="28-6" heading="Administrative review – Delegation of hearing authority.">
        <para num="(a)" heading="In general.">Hearings may be conducted by:<para num="(1)">the Director of Public Works; or</para>
          <para num="(2)">a hearing officer designated by the Director.</para>
        </para>
        <para num="(b)" heading="Scope of delegation.">The Director may delegate to a hearing officer the authority to issue:<para num="(1)">proposed or final findings of fact;</para>
          <para num="(2)">proposed or final conclusions of law;</para>
          <para num="(3)">proposed or final findings of fact and conclusions of law;</para>
          <para num="(4)">proposed or final orders; or</para>
          <para num="(5)">the final administrative decision of the Department.</para>
        </para>
        <annotation type="History">Ord. 02-367</annotation>
      </section>
      <section prefix="§" num="28-7" heading="Administrative review – Conduct of hearing.">
        <para num="(a)" heading="Notice.">
          <para num="(1)">The Director of Public Works must provide all parties reasonable written notice of the hearing.</para>
          <para num="(2)">The notice must state:<para num="(i)">the date, time, place, and nature of the hearing;</para>
            <para num="(ii)">the right of a party to be represented, at the party’s own expense, by an attorney or, if permitted by law, other representative;</para>
            <para num="(iii)">the right of a party to call witnesses and submit documents or other evidence under &lt;cite data-path="|7|§28-8"&gt;§ 28-8 of this subtitle&lt;/cite&gt;; and</para>
            <para num="(iv)">that failure to appear for the scheduled hearing may result in an adverse action against the party.</para>
          </para>
        </para>
        <para num="(b)" heading="Hearings to be open and informal.">Except as otherwise provided by law or by rule or regulation of the Department, all hearings must be:<para num="(1)">open to the public; and</para>
          <para num="(2)">conducted in an orderly but informal manner.</para>
        </para>
        <annotation type="History">Ord. 02-367</annotation>
      </section>
      <section prefix="§" num="28-8" heading="Administrative review – Evidence.">
        <para num="(a)" heading="In general.">Except as otherwise provided by this section or by rule or regulation of the Department, formal rules of evidence and trial procedures do not apply.</para>
        <para num="(b)" heading="Right to submit.">On a genuine issue of fact, a party is entitled to:<para num="(1)">call witnesses;</para>
          <para num="(2)">offer evidence, including rebuttal evidence;</para>
          <para num="(3)">cross-examine any witness that another party or the Department calls; and</para>
          <para num="(4)">present summation and argument.</para>
        </para>
        <para num="(c)" heading="Scope.">The Director or hearing officer:<para num="(1)">may admit probative evidence that reasonable and prudent individuals commonly accept in the conduct of their affairs and give probative effect to that evidence;</para>
          <para num="(2)">may not exclude evidence solely on the basis that it is hearsay;</para>
          <para num="(3)">must give effect to a privilege recognized by law;</para>
          <para num="(4)">may receive documentary evidence in the form of copies or excerpts or through incorporation by reference;</para>
          <para num="(5)">may take official notice of a fact that is judicially noticeable or that is general, technical, or scientific and within the specialized knowledge of the Department; and</para>
          <para num="(6)">may exclude evidence that is:<para num="(i)">incompetent;</para>
            <para num="(ii)">irrelevant;</para>
            <para num="(iii)">immaterial; or</para>
            <para num="(iv)">unduly repetitious.</para>
          </para>
        </para>
        <annotation type="History">Ord. 02-367</annotation>
      </section>
      <section prefix="§" num="28-9" heading="Administrative review – Final decisions.">
        <para num="(a)" heading="Form and contents.">A final decision must:<para num="(1)">be in writing; and</para>
          <para num="(2)">contain separate statements of:<para num="(i)">the findings of fact;</para>
            <para num="(ii)">the conclusions of law; and</para>
            <para num="(iii)">the decision or order.</para>
          </para>
        </para>
        <para num="(b)" heading="Distribution.">A copy of the final decision must be mailed or delivered to each party or that party’s attorney of record.</para>
        <annotation type="History">Ord. 02-367</annotation>
      </section>
      <section prefix="§" num="28-10" reserved="true" />
      <section prefix="§" num="28-11" heading="Judicial and appellate review.">
        <para num="(a)" heading="Judicial review.">A party aggrieved by a final decision of the Department under this Division II may seek judicial review of that decision by petition to the Circuit Court for Baltimore City in accordance with the Maryland Rules of Procedure.</para>
        <para num="(b)" heading="Appellate review.">A party to the judicial review may appeal the court’s final judgment to the Court of Special Appeals in accordance with the Maryland Rules of Procedure.</para>
        <annotation type="History">Ord. 02-367</annotation>
        <annotation type="History">Ord. 04-672</annotation>
        <annotation type="History">Ord. 19-332</annotation>
      </section>
      <section prefix="§" num="28-12" reserved="true" />
      <section prefix="§" num="28-13" heading="Criminal penalties.">
        <para num="(a)" heading="In general.">Any person who violates any provision of this Division II or of any rule or regulation adopted under or incorporated into this Division II is guilty of a misdemeanor and, on conviction, is subject to a fine of not more than $1,000 or imprisonment for not more than 1 year or both fine and imprisonment for each violation.</para>
        <para num="(b)" heading="Each day a separate offense.">Each day that a violation continues is a separate offense.</para>
        <annotation type="History">Ord. 02-367</annotation>
      </section>
    </container>
    <container prefix="Subtitles" num="29 to 30" />
  </container>
  <container prefix="Division" num="III" heading="Soil Erosion and Sediment Control">
    <container prefix="Subtitle" num="31" heading="Definitions; General Provisions">
      <section prefix="§" num="31-1" heading="Definitions.">
        <para num="(a)" heading="In general.">In this Division III, the following terms shall have the meanings indicated.</para>
        <para num="(b)" heading="Applicant.">“Applicant” means the person that executes the necessary forms to apply for a permit or approval to carry out construction of a project.</para>
        <para num="(c)" heading="Clear.">“Clear” means to remove the vegetative ground cover while leaving the root mat intact.</para>
        <para num="(d)" heading="Department.">“Department” means the Baltimore City Department of Public Works.</para>
        <para num="(e)" heading="Developer.">&lt;em&gt;See &lt;/em&gt;“Owner; developer”.</para>
        <para num="(f)" heading="Environmental site design.">“Environmental site design” means using small-scale stormwater management practices, nonstructural techniques, and better site planning to mimic natural hydrologic runoff characteristics and to minimize the impact of land development on water resources.</para>
        <para num="(g)" heading="Erosion.">“Erosion” means the process by which land surface is worn away by the action of wind, water, ice, or gravity.</para>
        <para num="(h)" heading="Erosion and sediment control.">“Erosion and sediment control” means a system of structural and vegetative measures that minimizes soil erosion and off-site sedimentation.</para>
        <para num="(i)" heading="Grade.">“Grade” means to disturb earth by any one or combination of methods, including excavating, filling, stockpiling, grubbing, or removing root mat or topsoil.</para>
        <para num="(j)" />
        <para num="(k)" heading="Interested person.">“Interested person” means a person who has a legal right that could be directly and adversely affected by a specific erosion or sediment control issue.</para>
        <para num="(l)" heading="Owner; developer.">
          <para num="(1)" heading="General.">“Owner” or “developer” means a person:<para num="(i)">undertaking activities covered by this Division III; or</para>
            <para num="(ii)">for whose benefit activities covered by this Division III are undertaken.</para>
          </para>
          <para num="(2)" heading="Exclusions.">“Owner” or “developer” does not include a general contractor or subcontractor that does not have a proprietary interest in the project.</para>
        </para>
        <para num="(m)" heading="Person.">
          <para num="(1)" heading="In general.">“Person” has the meaning stated in &lt;cite data-path="|general|1|1|1-107|(a)"&gt;§ 1-107(a) {“Person: In general”}&lt;/cite&gt; of the City Code’s &lt;cite data-path="|general"&gt;General Provisions Article&lt;/cite&gt;.</para>
          <para num="(2)" heading="Qualified inclusion of governmental entities.">Notwithstanding &lt;cite data-path="|general|1|1|1-107|(b)"&gt;§ 1-107(b) {“Person: Exclusion”}&lt;/cite&gt; of the &lt;cite data-path="|general"&gt;General Provisions Article&lt;/cite&gt;, in this Division III “person” also includes, except as used in &lt;cite data-path="|general|35|1|35-13|(b)"&gt;§ 35-13(b){“Criminal penalties”}&lt;/cite&gt;, a governmental entity or an instrumentality or unit of a governmental entity.</para>
        </para>
        <para num="(n)" heading="Responsible personnel.">“Responsible personnel” means any foreperson, superintendent, project engineer, or other individual who is in charge of:<para num="(1)">on-site clearing and grading operations; or</para>
          <para num="(2)">the implementation and maintenance of an erosion and sediment control plan.</para>
        </para>
        <para num="(o)" heading="Sediment.">“Sediment” means soils or other surficial materials that are the product of erosion and are transported or deposited by the action of wind, water, ice, gravity, or artificial means.</para>
        <para num="(p)" heading="Site.">“Site” means any tract, lot, parcel of land, or area of construction, or any combination of tracts, lots, parcels of land, or areas of construction that are:<para num="(1)">in one ownership; or</para>
          <para num="(2)">in diverse ownership, but where:<para num="(i)">development is to be performed as part of a unit, subdivision or project; and</para>
            <para num="(ii)">either:<para num="A.">the tracts, lots, or parcels of land are contiguous; or</para>
              <para num="B.">the developer is a cooperative public-private undertaking.</para>
            </para>
          </para>
        </para>
        <para num="(q)" heading="Standards and Specifications.">“Standards and Specifications” means the &lt;em&gt;2011 Maryland Standards and Specifications for Soil Erosion and Sediment Control &lt;/em&gt;or any subsequent revisions.</para>
        <para num="(r)" heading="Stormwater.">“Stormwater” means water that originates from a precipitation event.</para>
        <para num="(s)" heading="Stormwater management system.">“Stormwater management system” means a system of natural areas, environmental site design practices, stormwater management practices, and any structure through which stormwater flows, infiltrates, or discharges from a site.</para>
        <annotation type="History">Ord. 13-095</annotation>
        <annotation type="History">Ord. 22-125</annotation>
      </section>
      <section prefix="§" num="31-2" heading="Rules of interpretation.">
        <para num="(a)" heading="In general.">In interpreting and applying this Division III, the following rules of interpretation apply:<para num="(i)">those contained in Subtitles 2 and 3 of the City Code’s &lt;cite data-path="|general"&gt;General Provisions Article&lt;/cite&gt;; and</para>
          <para num="(ii)">any additional rules contained in this section.</para>
        </para>
        <para num="(b)" heading="Conflicting provisions.">
          <para num="(1)" heading="Division sets minimum requirements.">In their interpretation and application the provisions of this Division III must be taken to be the minimum requirements for the promotion of the public health, safety, and general welfare.</para>
          <para num="(2)" heading="Most restrictive provision governs.">If any condition imposed by a provision of this Division III is either more or less restrictive than a comparable condition imposed by any other provision of this Division or by any other law, rule, or regulation of any kind, the condition that is the more restrictive governs.</para>
        </para>
        <annotation type="History">Ord. 13-095</annotation>
        <annotation type="History">Ord. 22-125</annotation>
      </section>
      <section prefix="§" num="31-3" heading="Incorporation by reference.">
        <para num="(a)" heading="In general.">For the purposes of this Division III, the following documents are incorporated by reference:<para num="(1)">the &lt;em&gt;2011 Maryland Standards and Specifications for Soil Erosion and Sediment Control &lt;/em&gt;or any subsequent revisions of it, which serves as the official City guide for soil erosion and sediment control principles, methods, and practices; and</para>
          <para num="(2)">the City’s Erosion and Sediment Control Manual, which supplements the State’s Standards and Specifications as it relates to soil erosion and sediment control principals, methods, and practices in the City.</para>
        </para>
        <para num="(b)" heading="Defined terms.">
          <para num="(1)">Terms used in the Standards and Specifications have the meanings ascribed to them in that document or otherwise by the Maryland Department of the Environment.</para>
          <para num="(2)">These terms include, among others:<para num="(i)">“Adverse impact”.</para>
            <para num="(ii)">“Grading unit”.</para>
            <para num="(iii)">“Maximum extent practicable”.</para>
            <para num="(iv)">“Watershed”.</para>
          </para>
        </para>
        <annotation type="History">Ord. 13-095</annotation>
      </section>
      <section prefix="§" num="31-4" heading="Purpose, goal, authority.">
        <para num="(a)" heading="Purpose.">The purpose of this Division III is to protect, maintain, and enhance the public health, safety, and general welfare by establishing minimum requirements and procedures to control the adverse impacts associated with land disturbances.</para>
        <para num="(b)" heading="Goal.">The goal of this Division III is to minimize soil erosion and prevent off-site sedimentation by using soil erosion and sediment control practices designed in accordance with governing law and regulations.</para>
        <para num="(c)" heading="Authority.">This Division III is adopted under the authority of State Environment Article, Title 4, Subtitle 1.</para>
        <annotation type="History">Ord. 13-095</annotation>
      </section>
      <section prefix="§" num="31-5" heading="Administration.">
        <para num="(a)" heading="In general.">The Baltimore City Department of Public Works is responsible for administering and enforcing this Division III.</para>
        <para num="(b)" heading="Rules and regulations.">Subject to Title 4 {“Administrative Procedure Act – Regulations”} of the &lt;cite data-path="|general"&gt;City General Provisions Article&lt;/cite&gt;, the Department may adopt rules and regulations to carry out this Division III.</para>
        <annotation type="History">Ord. 13-095</annotation>
        <annotation type="History">Text Conformed 02/16/21</annotation>
        <annotation type="Editor's Notes">By authority of Ordinance 20-431, Section 5, the Director of Legislative Reference, in consultation with the Law Department, has conformed the text of this subsection to refer to and reflect the requirements of the recently-enacted Administrative Procedure Act that, effective January 15, 2021, governs the proposal, adoption, and publication of administrative rules and regulations.</annotation>
      </section>
      <section prefix="§§" num="31-6 to 31-8" reserved="true" />
      <section prefix="§" num="31-8" heading="Prohibited conduct generally.">
        <text>Except as otherwise provided in this Division III, no person may disturb land without implementing soil erosion and sediment controls in accordance with this Division III and the Standards and Specifications.</text>
        <annotation type="History">Ord. 13-095</annotation>
      </section>
      <section prefix="§" num="31-9" heading="Exemptions.">
        <para num="(a)" heading="Definitions.">
          <para num="(1)" heading="In general.">In this section, the following terms have the meanings indicated.</para>
          <para num="(2)" heading="Agricultural land management practices.">
            <para num="(i)" heading="In general.">“Agricultural land management practices” means those methods and procedures used in the cultivation of land to further crop and livestock production and conservation of related soil and water resources.</para>
            <para num="(ii)" heading="Exclusions.">“Agricultural land management practices” does not include logging and timber removal operations.</para>
          </para>
          <para num="(3)" heading="Best management practice.">“Best management practice” means a structural device or nonstructural practice designed to temporarily store or treat stormwater runoff in order to mitigate flooding, reduce pollution, and provide other amenities.</para>
        </para>
        <para num="(b)" heading="Exempt activities.">The following activities are exempt from this Division III:<para num="(1)">agricultural land management practices;</para>
          <para num="(2)">agricultural best management practices;</para>
          <para num="(3)">clearing or grading activities that disturb less than 5,000 square feet of land area and disturb less than 100 cubic yards of earth; and</para>
          <para num="(4)">clearing or grading activities that are subject exclusively to State approval and enforcement under State law and regulations.</para>
        </para>
        <annotation type="History">Ord. 13-095</annotation>
      </section>
      <section prefix="§" num="31-10" heading="Variances.">
        <para num="(a)" heading="When authorized.">The Department may grant a variance from any requirement of this Division III if, because of exceptional circumstances applicable to the site, strict adherence to that requirement will result in exceptional hardship and not fulfill the intent of this Division III.</para>
        <para num="(b)" heading="Application for variance.">The application for variance must:<para num="(i)">be in the form that the Department requires;</para>
          <para num="(ii)">state the specific variance sought;</para>
          <para num="(iii)">explain why the variance is needed;</para>
          <para num="(iv)">contain any other information that the Department requires; and</para>
          <para num="(v)">be submitted to the Department with the applicant’s proposed site development plan.</para>
        </para>
        <annotation type="History">Ord. 13-095</annotation>
      </section>
    </container>
    <container prefix="Subtitle" num="32" heading="Erosion and Sediment Control Plans">
      <section prefix="§" num="32-1" heading="Definitions.">
        <para num="(a)" heading="In general.">In this subtitle, the following terms have the meanings indicated.</para>
        <para num="(b)" heading="Approval.">
          <para num="(1)" heading="In general.">“Approval” means a documented action by the Department following a comprehensive review to determine and acknowledge that submitted materials demonstrate compliance with the requirements of a specified stage in a project’s development process.</para>
          <para num="(2)" heading="Exclusions.">“Approval” does not include an acknowledgment by the Department that material has been received for review.</para>
        </para>
        <para num="(c)" heading="Drainage area.">“Drainage area” means an area, measured in a horizontal plane, that:<para num="(1)">contributes runoff to a single point; and</para>
          <para num="(2)">is enclosed by a ridge line.</para>
        </para>
        <para num="(d)" heading="Stabilization.">“Stabilization” means the protection of exposed soils from erosion by the application of seed and mulch, seed and matting, sod, other vegetative measures, or structural means.</para>
        <annotation type="History">Ord. 13-095</annotation>
      </section>
      <section prefix="§" num="32-2" heading="Plans required.">
        <text>Except as otherwise provided in this Division III, no person may grade land without erosion and sediment control plans approved by the Department.</text>
        <annotation type="History">Ord. 13-095</annotation>
      </section>
      <section prefix="§" num="32-3" heading="Review and approval of plans.">
        <para num="(a)" heading="Review and comment.">
          <para num="(1)">The Department must comprehensively review erosion and sediment control plans for each phase of the site design to determine compliance with this Division III.</para>
          <para num="(2)">For each plan phase, coordinated comments will be provided that reflect input from all appropriate agencies, including Planning, Zoning, and Public Works.</para>
          <para num="(3)">At each phase of project design, comments from the Department and other appropriate agencies must be addressed by the applicant and approval received before subsequent submissions.</para>
        </para>
        <para num="(b)" heading="Conditions.">In approving a plan, the Department may impose conditions that the Department considers necessary or appropriate to ensure:<para num="(1)">compliance with this Division III; and</para>
          <para num="(2)">the preservation of public health and safety.</para>
        </para>
        <para num="(c)" heading="Notification.">After the Department has completed its comprehensive review for each phase of site design, the Department must notify the applicant of either:<para num="(1)">the Department’s approval of the plan;</para>
          <para num="(2)">the Department’s disapproval of the plan, together with:<para num="(i)">the reasons for disapproval; and</para>
            <para num="(ii)">any modifications that the Department requires for approval; or</para>
          </para>
          <para num="(3)">if no decision has been made:<para num="(i)">the status of the review process; and</para>
            <para num="(ii)">the anticipated date of completion.</para>
          </para>
        </para>
        <para num="(d)" heading="Endorsement.">
          <para num="(1)">The final erosion and sediment control plan may not be considered approved without the inclusion of the Department’s dated signature on the plan.</para>
          <para num="(2)">Approved plans remain valid for 2 years from the date of approval, unless extended or renewed by the Department.</para>
        </para>
        <para num="(e)" heading="“Grandfathering” of approved plans.">
          <para num="(1)">Any plans that receive final approval after January 9, 2013, must be in compliance with the requirements of this Division III and the Standards and Specifications.</para>
          <para num="(2)">A plan that receives final approval on or before January 9, 2013, may be reapproved under its existing conditions, except for stabilization requirements, if grading activities begin on the site on or before January 9, 2015.</para>
          <para num="(3)">Stabilization practices on all sites must be in compliance with the requirements of this Division III and the Standards and Specifications on or before January 9, 2013, regardless of when an approved erosion and sediment control plan was approved.</para>
        </para>
        <annotation type="History">Ord. 13-095</annotation>
      </section>
      <section prefix="§" num="32-4" heading="Contents of plans.">
        <para num="(a)" heading="Submission.">An applicant is responsible for submitting erosion and sediment control plans that meet the requirements of the Department, this Division III, and all other applicable provisions of the Baltimore City Code.</para>
        <para num="(b)" heading="Tenor of plans.">The plans must include sufficient information to evaluate:<para num="(1)">the environmental characteristics of the affected areas;</para>
          <para num="(2)">the potential impacts of the proposed grading on water resources; and</para>
          <para num="(3)">the effectiveness and acceptability of measures proposed to minimize soil erosion and off-site sedimentation.</para>
        </para>
        <para num="(c)" heading="Minimum information.">At a minimum, applicants must submit the following information for the concept, site development, and final erosion and sediment control phases of project design:<para num="(1)">a letter of transmittal or application;</para>
          <para num="(2)">a vicinity map indicating north arrow, scale, site location, and other information necessary to easily locate the property;</para>
          <para num="(3)">plan submittals as specified in § 32-5 {“Concept plan”}, § 32-6 {“Site development plan”}, and § 32-7 Final ... plans”}; and</para>
          <para num="(4)">the name, address, and telephone number of:<para num="(i)">the owner of the property where the grading is proposed;</para>
            <para num="(ii)">the developer; and</para>
            <para num="(iii)">the applicant.</para>
          </para>
        </para>
        <annotation type="History">Ord. 13-095</annotation>
      </section>
      <section prefix="§" num="32-5" heading="Concept plan.">
        <para num="(a)" heading="In general.">The applicant must submit a concept plan that provides sufficient information for an initial assessment of the proposed project and whether erosion and sediment control can be provided according to this Division III.</para>
        <para num="(b)" heading="Minimum contents.">Plans submitted for concept approval must include:<para num="(1)">a map, at a scale specified by the Department, showing:<para num="(i)">the proposed limit of disturbance;</para>
            <para num="(ii)">topography;</para>
            <para num="(iii)">existing natural resources;</para>
            <para num="(iv)">wetlands;</para>
            <para num="(v)">floodplains;</para>
            <para num="(vi)">water bodies;</para>
            <para num="(vii)">highly erodible soils;</para>
            <para num="(viii)">natural drainage patterns; and</para>
            <para num="(ix)">any other sensitive areas to be protected during construction;</para>
          </para>
          <para num="(2)">a general description of the predominant soil types on the site, as described by the appropriate soil survey information available through the local soil conservation district or the USDA Natural Resources Soil Conservation Service;</para>
          <para num="(3)">the anticipated location of all:<para num="(i)">impervious areas;</para>
            <para num="(ii)">buildings;</para>
            <para num="(iii)">roadways;</para>
            <para num="(iv)">parking;</para>
            <para num="(v)">sidewalks;</para>
            <para num="(vi)">utilities; and</para>
            <para num="(vii)">other site improvements; and</para>
          </para>
          <para num="(4)">any other information that the Department requires.</para>
        </para>
        <annotation type="History">Ord. 13-095</annotation>
      </section>
      <section prefix="§" num="32-6" heading="Site development plan.">
        <para num="(a)" heading="In general.">Unless otherwise directed by the Department, after approval of the concept plan, the applicant must submit site development plans that reflect comments received during the previous review phase.</para>
        <para num="(b)" heading="Minimum contents.">Plans submitted for site development approval must be of sufficient detail to allow site development to be reviewed and must include:<para num="(1)">all information provided during the concept plan review phase;</para>
          <para num="(2)">drainage area maps that show, at a minimum scale of 1" = 200':<para num="(i)">existing, interim, and proposed topography;</para>
            <para num="(ii)">proposed improvements;</para>
            <para num="(iii)">standard symbols for proposed sediment control features; and</para>
            <para num="(iv)">pertinent drainage information, including provisions to protect downstream areas from erosion for a minimum of 200 feet downstream or to the next conveyance system;</para>
          </para>
          <para num="(3)">a proposed erosion and sediment control plan that contains:<para num="(i)">the existing and proposed topography and improvements, at a scale between 1" = 10' and 1" = 50' with 2 foot contours or other approved contour interval;</para>
            <para num="(ii)">interim contours for projects with more than minor grading, if required by the Department;</para>
            <para num="(iii)">scale, project, and sheet title, and north arrow on each plan sheet;</para>
            <para num="(iv)">the limit of disturbance, including:<para num="A.">limit of grading (grading units, if applicable); and</para>
              <para num="B.">initial, interim, and final phases;</para>
            </para>
            <para num="(v)">storm drainage features, including:<para num="A.">existing and proposed bridges, storm drains, culverts, outfalls, etc.;</para>
              <para num="B.">velocities and peak flow rates at outfalls for the 2-year and 10-year frequency storm events; and</para>
              <para num="C.">site conditions around points of all surface water discharge from the site;</para>
            </para>
            <para num="(vi)">any phasing necessary to limit earth disturbances and impacts to natural resources; and</para>
            <para num="(vii)">an overlay plan that shows the types and locations of stormwater practices and erosion and sediment control practices to be used;</para>
          </para>
          <para num="(4)">a narrative that indicates how proposed erosion and sediment control practices will be integrated with proposed stormwater management strategy using environmental site design in accordance with Division II of &lt;cite data-path="|7"&gt;this article&lt;/cite&gt;; and</para>
          <para num="(5)">any other information that the Department requires.</para>
        </para>
        <annotation type="History">Ord. 13-095</annotation>
      </section>
      <section prefix="§" num="32-7" heading="Final erosion and sediment control and stormwater management plans.">
        <para num="(a)" heading="In general.">After site development plan approval, the applicant must submit final erosion and sediment control plans and stormwater management plans that reflect the comments received during the previous review phase.</para>
        <para num="(b)" heading="Minimum contents.">Plans submitted for final approval must be of sufficient detail to allow all approvals and permits to be issued and must include:<para num="(1)">all information provided during the concept and site development plan review phase;</para>
          <para num="(2)">erosion and sediment control practices to minimize on-site erosion and prevent off-site sedimentation, including:<para num="(i)">the salvage and reuse of topsoil;</para>
            <para num="(ii)">phased construction and implementation of grading unit(s) to minimize disturbances, both in extent and duration;</para>
            <para num="(iii)">location and type of all proposed sediment control practices;</para>
            <para num="(iv)">design details and data for all erosion and sediment control practices; and</para>
            <para num="(v)">specifications for temporary and permanent stabilization measures, including at a minimum:<para num="A.">the “Standard Stabilization Note” on the plan stating:
“Following initial soil disturbance or re-disturbance, permanent or temporary stabilization must be completed within:<para num="1.">3 calendar days as to the surface of all perimeter dikes, swales, ditches, perimeter slopes, and all slopes steeper than 3 horizontal to 1 vertical (3:1); and</para>
                <para num="2.">7 calendar days as to all other disturbed or graded areas on the project site not under active grading.”;</para>
              </para>
              <para num="B.">details for areas requiring accelerated stabilization; and</para>
              <para num="C.">maintenance requirements as defined in the Standards and Specifications;</para>
            </para>
          </para>
          <para num="(3)">a sequence of construction that:<para num="(i)">describes the relationship between the implementation of controls and the maintenance of controls, including permanent and temporary stabilization, and the various stages or phases of earth disturbance and construction; and</para>
            <para num="(ii)">includes the following, at a minimum:<para num="A.">request for a pre-construction meeting with the Department;</para>
              <para num="B.">clearing and grubbing as necessary for the installation of perimeter controls;</para>
              <para num="C.">construction and stabilization of perimeter controls;</para>
              <para num="D.">remaining clearing and grubbing within installed perimeter controls;</para>
              <para num="E.">road grading;</para>
              <para num="F.">grading for the remainder of the site;</para>
              <para num="F.">utility installation and connections to existing structures;</para>
              <para num="G.">construction of buildings and roads;</para>
              <para num="H.">other construction;</para>
              <para num="I.">final grading, landscaping, and stabilization;</para>
              <para num="J.">installation of stormwater management measures;</para>
              <para num="K.">obtaining approval by the Department before removal of sediment controls; and</para>
              <para num="L.">removal of sediment controls and stabilization of areas that are disturbed by the removal;</para>
            </para>
          </para>
          <para num="(4)">a statement requiring the owner, developer, or representative to contact the Department or its agent at the following stages of the project or in accordance with the approved erosion and sediment control plan, grading permit, or building permit:<para num="(i)">before the start of earth disturbance;</para>
            <para num="(ii)">after the installation of perimeter erosion and sediment controls is complete, but before proceeding with any other earth disturbance or grading;</para>
            <para num="(iii)">before the start of another phase of construction or the opening of another grading unit; and</para>
            <para num="(iv)">before the removal of sediment control practices;</para>
          </para>
          <para num="(5)">certification by the owner or developer that:<para num="(i)">any clearing, grading, construction, or development will be done pursuant to the approved erosion and sediment control plan; and</para>
            <para num="(ii)">the responsible personnel involved in the construction project will have, before the project begins, a Certificate of Training from an MDE approved training program for the control of erosion and sediment; and</para>
            <para num="(iii)">the City Department of Public Works, City Department of Housing and Community Development, and Maryland Department of the Environment will be allowed right of entry for periodic on-site evaluation; and</para>
          </para>
          <para num="(6)">if required by the Department or the Maryland Department of the Environment, certification by a professional engineer, land surveyor, landscape architect, architect, or forester (for forest harvest operations only) registered in the State that the plans have been designed in accordance with erosion and sediment control laws, regulations, and standards; and</para>
          <para num="(7)">any additional information considered appropriate by the Department.</para>
        </para>
        <annotation type="History">Ord. 13-095</annotation>
      </section>
      <section prefix="§" num="32-8" heading="Modifications to plans.">
        <para num="(a)" heading="In general.">The Department may approve modifications to approved plans as necessary.</para>
        <para num="(b)" heading="Who may request.">Modifications may be requested by the owner or developer or by the Department.</para>
        <para num="(c)" heading="Minor modifications.">
          <para num="(1)">The Department may include in its Erosion and Sediment Control Manual a list of minor modifications that the Department may approve as field revisions.</para>
          <para num="(2)">The Maryland Department of the Environment must approve the list before its implementation.</para>
        </para>
        <annotation type="History">Ord. 13-095</annotation>
      </section>
      <section prefix="§" num="32-9" heading="Standard erosion and sediment control plan.">
        <para num="(a)" heading="Department may adopt.">The Department may include in its Erosion and Sediment Control Manual a standard erosion and sediment control plan for activities with minor earth disturbances, such as single-family residences, small commercial and other similar building sites, minor maintenance grading, and minor utility construction.</para>
        <para num="(b)" heading="Requirements.">
          <para num="(1)">A standard erosion and sediment control plan must meet the requirements of this Division III and the Standards and Specifications.</para>
          <para num="(2)">The Maryland Department of the Environment must approve the standard plan before its adoption.</para>
        </para>
        <annotation type="History">Ord. 13-095</annotation>
      </section>
    </container>
    <container prefix="Subtitle" num="33" heading="Permits; Fees; Security">
      <section prefix="§" num="33-1" heading="Approved plan prerequisite to permits.">
        <text>For any development that requires an erosion and sediment control plan under this Division III, a grading or building permit may not be issued or extended unless a final erosion and sediment control plan has been approved by the Department.</text>
        <annotation type="History">Ord. 13-095</annotation>
      </section>
      <section prefix="§" num="33-2" heading="Fees.">
        <para num="(a)" heading="Payable at each phase.">Non-refundable fees will be assessed and collected in advance by the Department for each phase of a development.</para>
        <para num="(b)" heading="Fee schedule.">
          <para num="(1)">The fees assessed under this Division III are in addition to the usual fees charged for grading and building permits.</para>
          <para num="(2)">Fees are assessed for plan reviews, administration and management of the approval process, inspections, and the like.</para>
          <para num="(3)">The amount of the fees are as set forth in the fee schedule established from time to time by the Board of Estimates.  The fee schedule shall be based on the relative complexity of a project.</para>
        </para>
        <annotation type="History">Ord. 13-095</annotation>
      </section>
      <section prefix="§" num="33-3" heading="Performance bond.">
        <para num="(a)" heading="Required.">For any development that requires an erosion and sediment control plan under this Division III, a grading or building permit may not be issued until the applicant posts a surety or cash bond or other means of security acceptable to the Department.</para>
        <para num="(b)" heading="Amount.">
          <para num="(1)">The amount of the security must be equal to at least the estimated cost of the installation, maintenance, and removal of the erosion and sediment controls shown on the approved plan.</para>
          <para num="(2)">This estimate must be prepared by the applicant and submitted with the plan.</para>
        </para>
        <para num="(c)" heading="Tenor.">The security required by this section must provide for forfeiture on failure to:<para num="(1)">complete all work specified in the approved erosion and sediment control plan;</para>
          <para num="(2)">comply with any provision of this Division III or of any other applicable law, rule, or regulation; or</para>
          <para num="(3)">comply with any applicable time limitations.</para>
        </para>
        <para num="(d)" heading="Release.">The security may not be released until the Department conducts a final inspection of the completed work.</para>
        <annotation type="History">Ord. 13-095</annotation>
      </section>
    </container>
    <container prefix="Subtitle" num="34" heading="Inspections; Investigations">
      <section prefix="§" num="34-1" heading="Inspections required.">
        <para num="(a)" heading="In general.">Every active site having an approved erosion and sediment control plan should be inspected for compliance with the plan on an average of once every 2 weeks.</para>
        <para num="(b)" heading="Plan to be maintained on site.">The owner or developer must maintain a copy of the approved erosion and sediment control plan on site.</para>
        <annotation type="History">Ord. 13-095</annotation>
      </section>
      <section prefix="§" num="34-2" heading="By whom conducted.">
        <text>All inspections under this Division III must be conducted by:</text>
        <para num="(1)">the Department; or</para>
        <para num="(2)">the Department’s authorized representative.</para>
        <annotation type="History">Ord. 13-095</annotation>
      </section>
      <section prefix="§" num="34-3" heading="Reports on inspections.">
        <para num="(a)" heading="Required.">The Department must prepare a written report after every inspection.</para>
        <para num="(b)" heading="Contents.">The report must describe:<para num="(1)">the date and location of the site inspection;</para>
          <para num="(2)">whether the approved plan has been properly implemented and maintained;</para>
          <para num="(3)">practice deficiencies or erosion and sediment control plan deficiencies;</para>
          <para num="(4)">if a violation exists, the type of enforcement action taken; and</para>
          <para num="(5)">if applicable, a description of any modifications to the plan.</para>
        </para>
        <annotation type="History">Ord. 13-095</annotation>
      </section>
      <section prefix="§§" num="34-4 to 34-5" reserved="true" />
      <section prefix="§" num="34-6" heading="Right of entry.">
        <text>It is a condition of every grading or building permit that the Department has the right to enter property periodically to inspect for compliance with the approved plan and this Division III.</text>
        <annotation type="History">Ord. 13-095</annotation>
      </section>
      <section prefix="§" num="34-7" heading="Investigations.">
        <para num="(a)" heading="On complaint.">The Department must:<para num="(1)">accept and investigate complaints from interested persons about erosion and sediment control issues;</para>
          <para num="(2)">conduct an initial investigation within 3 working days from receipt of the complaint;</para>
          <para num="(3)">notify the complainant of the initial investigation and findings within 7 days from receipt of the complaint; and</para>
          <para num="(4)">take appropriate action when violations are discovered during the course of the complaint investigation.</para>
        </para>
        <para num="(b)" heading="On own initiative.">The Department may also undertake, on its own initiative, investigations of suspected erosion and sediment control issues on all properties.</para>
        <para num="(c)" heading="Posting of findings.">The Department must post on its website the Department’s findings on all investigations, whether initiated by interested persons or on the Department’s own initiative.</para>
        <annotation type="History">Ord. 13-095</annotation>
      </section>
    </container>
    <container prefix="Subtitle" num="35" heading="Enforcement; Reviews; Penalties">
      <section prefix="§" num="35-1" heading="Violation notices.">
        <para num="(a)" heading="Notice required.">If a violation is found, the Department must provide written notice of the violation to:<para num="(1)">the owner or developer; and</para>
          <para num="(2)">the responsible personnel.</para>
        </para>
        <para num="(b)" heading="Contents.">The notice must describe:<para num="(1)">the nature of the violation;</para>
          <para num="(2)">the required corrective action; and</para>
          <para num="(3)">the time period within which the violation must be corrected.</para>
        </para>
        <para num="(c)" heading="Posting of violation notices.">The Department must post on its website a copy of all notices of violations issued under this section.</para>
        <annotation type="History">Ord. 13-095</annotation>
      </section>
      <section prefix="§" num="35-2" heading="Enforcement of notice.">
        <para num="(a)" heading="In general.">Any one or a combination of the following actions may be taken to enforce a violation notice.</para>
        <para num="(b)" heading="Stop work order.">If a violation persists after issuance of a violation notice, the Department may issue a stop work order for the site.</para>
        <para num="(c)" heading="Bond forfeiture; other action.">If reasonable efforts to correct the violation have not been undertaken, the Department may:<para num="(1)">cause the performance bond or other security to be forfeited; and</para>
          <para num="(2)">refer the matter for legal action, including pursuit of criminal and civil penalties under &lt;cite data-path="|7|§35-9"&gt;§ 35-9 of this subtitle&lt;/cite&gt;.</para>
        </para>
        <para num="(d)" heading="Civil liability.">In addition to any other sanction under this Division III, a person who fails to install or maintain erosion and sediment controls in accordance with an approved plan is liable in a civil action to the City or the State, as the case may be, for damages in an amount equal to double the cost of installing or maintaining the controls.</para>
        <annotation type="History">Ord. 13-095</annotation>
      </section>
      <section prefix="§" num="35-3" heading="Injunctive relief.">
        <text>Any State or City agency or any interested person may seek an injunction against any person who violates or threatens to violate any provision of this Division III.</text>
      </section>
      <section prefix="§" num="35-4" reserved="true" />
      <section prefix="§" num="35-5" heading="Administrative review – In general.">
        <para num="(a)" heading="Right of appeal.">Any person aggrieved by the action of any official charged with the enforcement of this Division III, whether as the result of the disapproval of an application, the issuance of a violation notice, an alleged failure to properly enforce this Division III, or otherwise:<para num="(1)">may appeal the action to the Director of Public Works;</para>
          <para num="(2)">on timely request, is entitled to a hearing on that appeal.</para>
        </para>
        <para num="(b)" heading="When and how taken.">The appeal must:<para num="(1)">be in writing;</para>
          <para num="(2)">clearly state the grounds on which the appeal is based;</para>
          <para num="(3)">if the person aggrieved desires a hearing on the appeal, contain an express statement to that effect; and</para>
          <para num="(4)">be filed with the Director within 10 days of the action in dispute.</para>
        </para>
        <annotation type="History">Ord. 13-095</annotation>
        <annotation type="History">Ord. 14-307</annotation>
      </section>
      <section prefix="§" num="35-6" heading="Administrative review – Delegation of hearing authority.">
        <para num="(a)" heading="In general.">Hearings may be conducted by:<para num="(1)">the Director of Public Works; or</para>
          <para num="(2)">a hearing officer designated by the Director.</para>
        </para>
        <para num="(b)" heading="Scope of delegation.">The Director may delegate to a hearing officer the authority to issue:<para num="(1)">proposed or final findings of fact;</para>
          <para num="(2)">proposed or final conclusions of law;</para>
          <para num="(3)">proposed or final findings of fact and conclusions of law;</para>
          <para num="(4)">proposed or final orders; or</para>
          <para num="(5)">the final administrative decision of the Department.</para>
        </para>
        <annotation type="History">Ord. 13-095</annotation>
        <annotation type="History">Ord. 15-331</annotation>
      </section>
      <section prefix="§" num="35-7" heading="Administrative review – Conduct of hearing.">
        <para num="(a)" heading="Notice.">
          <para num="(1)">The Director of Public Works must provide all parties reasonable written notice of the hearing.</para>
          <para num="(2)">The notice must state:<para num="(i)">the date, time, place, and nature of the hearing;</para>
            <para num="(ii)">the right of a party to be represented, at the party’s own expense, by an attorney or, if permitted by law, other representative;</para>
            <para num="(iii)">the right of a party to call witnesses and submit documents or other evidence under &lt;cite data-path="|7|§35-8"&gt;§ 35-8 of this subtitle&lt;/cite&gt;; and</para>
            <para num="(iv)">that failure of a party to appear for the scheduled hearing may result in an adverse action against the party.</para>
          </para>
        </para>
        <para num="(b)" heading="Hearings to be open and informal.">Except as otherwise provided by law or by rule or regulation of the Department, all hearings must be:<para num="(1)">open to the public; and</para>
          <para num="(2)">conducted in an orderly but informal manner.</para>
        </para>
        <annotation type="History">Ord. 13-095</annotation>
      </section>
      <section prefix="§" num="35-8" heading="Administrative review – Evidence.">
        <para num="(a)" heading="In general.">Except as otherwise provided by this section or by rule or regulation of the Department, formal rules of evidence and trial procedures do not apply.</para>
        <para num="(b)" heading="Right to submit.">A party is entitled to:<para num="(1)">call witnesses;</para>
          <para num="(2)">offer evidence, including rebuttal evidence;</para>
          <para num="(3)">cross-examine any witness that another party or the Department calls; and</para>
          <para num="(4)">present summation and argument.</para>
        </para>
        <para num="(c)" heading="Scope.">The Director or hearing officer:<para num="(1)">may admit probative evidence that reasonable and prudent individuals commonly accept in the conduct of their affairs and give probative effect to that evidence;</para>
          <para num="(2)">may not exclude evidence solely on the basis that it is hearsay;</para>
          <para num="(3)">must give effect to a privilege recognized by law;</para>
          <para num="(4)">may receive documentary evidence in the form of copies or excerpts or through incorporation by reference;</para>
          <para num="(5)">may take official notice of a fact that is judicially noticeable or that is general, technical, or scientific and within the specialized knowledge of the Department; and</para>
          <para num="(6)">may exclude evidence that is:<para num="(i)">incompetent;</para>
            <para num="(ii)">irrelevant;</para>
            <para num="(iii)">immaterial; or</para>
            <para num="(iv)">unduly repetitious.</para>
          </para>
        </para>
        <annotation type="History">Ord. 13-095</annotation>
      </section>
      <section prefix="§" num="35-9" heading="Administrative review – Final decisions.">
        <para num="(a)" heading="Form and contents.">The final decision must:<para num="(1)">be in writing; and</para>
          <para num="(2)">contain separate statements of:<para num="(i)">the findings of fact;</para>
            <para num="(ii)">the conclusions of law; and</para>
            <para num="(iii)">the decision or order.</para>
          </para>
        </para>
        <para num="(b)" heading="Distribution.">A copy of the final decision must be mailed or delivered to each party or that party’s attorney of record.</para>
        <annotation type="History">Ord. 13-095</annotation>
        <annotation type="History">Ord. 15-331</annotation>
      </section>
      <section prefix="§" num="35-10" reserved="true" />
      <section prefix="§" num="35-11" heading="Judicial and appellate review.">
        <para num="(a)" heading="Judicial review.">A party aggrieved by a final decision of the Department under this Division III may seek judicial review of that decision by petition to the Circuit Court for Baltimore City in accordance with the Maryland Rules of Procedure.</para>
        <para num="(b)" heading="Appellate review.">A party to the judicial review may appeal the court’s final judgment to the Court of Special Appeals in accordance with the Maryland Rules of Procedure.</para>
        <annotation type="History">Ord. 13-095</annotation>
        <annotation type="History">Ord. 19-332</annotation>
      </section>
      <section prefix="§" num="35-12" reserved="true" />
      <section prefix="§" num="35-13" heading="Penalties.">
        <para num="(a)" heading="Civil fines.">
          <para num="(1)">The Department may impose civil fines for violations of this Division III.</para>
          <para num="(2)">The amount of the fines are as set forth in the fine schedule established from time to time by the Department with the approval of the Board of Estimates.</para>
          <para num="(3)">No fine may exceed $1,000 for any1 offense.</para>
        </para>
        <para num="(b)" heading="Criminal penalties.">Any person who violates any provision of this Division III or of any rule or regulation adopted under or incorporated into this Division III is guilty of a misdemeanor and, on conviction, is subject to a fine of not more than $1,000 or imprisonment for not more than 1 year or both fine and imprisonment for each offense.</para>
        <para num="(c)" heading="Each day a separate offense.">Each day that a violation continues is a separate offense.</para>
        <annotation type="History">Ord. 13-095</annotation>
      </section>
    </container>
    <container prefix="Subtitles" num="36 to 40" />
  </container>
  <container prefix="Division" num="IV" heading="Forest and Tree Conservation">
    <container prefix="Subtitle" num="41" heading="Purpose; Definitions; General Provisions">
      <section prefix="§" num="41-1" heading="Purpose.">
        <text>The purpose of this Division IV is to:</text>
        <para num="(1)">encourage the preservation and enhancement of the City’s urban forests;</para>
        <para num="(2)">replace and increase tree cover in non-forest areas within the City;</para>
        <para num="(3)">establish procedures, standards and requirements that protect trees and forests during and after development activity and minimize tree loss due to development activity;</para>
        <para num="(4)">establish procedures, standards and requirements for afforestation, reforestation, and specimen tree mitigation within the City; and</para>
        <para num="(5)">meet the requirements of the Natural Resources Article, Sections 5-1601 through 5-1612 of the Annotated Code of Maryland.</para>
        <annotation type="History">Ord. 20-401</annotation>
      </section>
      <section prefix="§" num="41-2" heading="Definitions.">
        <para num="(a)" heading="In general.">In this Division IV, the following terms have the meanings indicated.</para>
        <para num="(b)" heading="Afforestation.">“Afforestation” means:<para num="(1)">the establishment of forest cover on an area from which it has always or very long been absent, or</para>
          <para num="(2)">the planting of open areas which are not presently in forest cover; and</para>
          <para num="(3)">establishment of a forest according to procedures set forth in the Baltimore City Forest Conservation Manual.</para>
        </para>
        <para num="(c)" heading="Baltimore City Forest Conservation Manual.">“Baltimore City Forest Conservation Manual” (“Manual”) includes the State Forest Conservation Manual and the Baltimore City Forest Conservation Supplement to the State Forest Conservation Manual.</para>
        <para num="(d)" heading="Clear.">“Clear” means removal of any woody plant, wherein the stump and root mass are physically removed.</para>
        <para num="(e)" heading="Critical root zone.">“Critical root zone” means a circular region measured outward from a tree trunk representing the area of the roots that must be maintained or protected for the tree’s survival.  Critical root zone shall be measured as one foot of radial distance for every inch of tree diameter (DBH) measured at 4.5 feet above the ground with a minimum radius of 8 feet.  For specimen trees the critical root zone shall be measured as 1.5 feet of radial distance for every inch of tree diameter.</para>
        <para num="(f)" heading="Cut.">“Cut” means the removal of a woody plant, wherein the stump and root mass remain in place and intact.</para>
        <para num="(g)" heading="Declaration of intent.">“Declaration of intent” means a document whose purpose is to verify that the proposed activity is exempt under the provisions of the Natural Resources Article and this Division IV.</para>
        <para num="(h)" heading="Department.">“Department” means the Baltimore City Department of Planning.</para>
        <para num="(i)" heading="Forest.">“Forest” includes:<para num="(1)">a biological community dominated by trees and other woody plants covering a land area of 4,000 square feet or greater.  This area must have a live tree density of at least 100 trees per acre, with at least 50% of those trees having a 2-inch or greater diameter at 4.5 feet above the ground;</para>
          <para num="(2)">areas that have been cut, but not cleared; and</para>
          <para num="(3)">“forest” does not include orchards or Christmas tree plantations.</para>
        </para>
        <para num="(j)" heading="Forest conservation.">“Forest conservation” means the retention of existing forest or the creation of new forest as prescribed by the Department of Planning and the Baltimore City Forest Conservation Manual.</para>
        <para num="(k)" heading="Forest conservation plan.">“Forest conservation plan” means a plan approved pursuant to Subtitles 42 and 44 of this Division IV and the requirements of the Baltimore City Forest Conservation Manual.</para>
        <para num="(l)" heading="Forest stand delineation.">“Forest stand delineation” means the description of the existing vegetation on a site proposed for development, prepared according to the requirements of the Baltimore City Forest Conservation Technical Manual and this Division IV.</para>
        <para num="(m)" heading="Person.">
          <para num="(1)" heading="In general.">“Person” has the meaning stated in &lt;cite data-path="|general|1|1|1-107|(a)"&gt;§ 1-107(a) {“Person: In general”}&lt;/cite&gt; of the City Code’s &lt;cite data-path="|general"&gt;General Provisions Article&lt;/cite&gt;.</para>
          <para num="(2)" heading="Inclusion of governmental entities.">Notwithstanding &lt;cite data-path="|general|1|1|1-107|(b)"&gt;§ 1-107(b) {“Person: Exclusion”}&lt;/cite&gt; of the &lt;cite data-path="|general"&gt;General Provisions Article&lt;/cite&gt;, in this Division IV “person” also includes a governmental entity or an instrumentality or unit of a governmental entity.</para>
        </para>
        <para num="(n)" heading="Reforest; reforestation.">“Reforest” or “reforestation” means to create a biological community dominated by trees and other woody plants containing at least 100 trees per acre with at least 50% of those trees having the potential of attaining a 2-inch or greater diameter measured at 4.5 feet above the ground within 5 years and includes afforestation or establishment of a forest according to procedures set forth in the Baltimore City Forest Conservation Manual.</para>
        <para num="(o)" heading="Regulated activity.">“Regulated activity” means any activity subject to the requirements of &lt;cite data-path="|7|§42-1"&gt;§ 42-1 of this Division IV&lt;/cite&gt;.</para>
        <para num="(p)" heading="Retention.">“Retention” means the deliberate holding and protecting of existing trees, shrubs, or plants on the site according to established standards in the Baltimore City Forest Conservation Manual.</para>
        <para num="(q)" heading="Specimen tree.">“Specimen tree” means a tree having a diameter measured at 4.5 feet above the ground of 20 inches or more or trees having 75% or more of the diameter of the current state champion tree of that species.</para>
        <para num="(r)" heading="Tree.">“Tree” means a large, woody plant having 1 or several self-supporting stems or trunks and numerous branches that reach a height of at least 20 feet at maturity.</para>
        <annotation type="Prior Codifications">City Code, 1976/83, art. 9A, §1-1(a), (b), (d), (f) - (l), (p) - (s), (v)</annotation>
        <annotation type="History">Ord. 93-170</annotation>
        <annotation type="History">Ord. 20-401</annotation>
        <annotation type="History">Ord. 22-125</annotation>
      </section>
      <section prefix="§" num="41-3" heading="Statutory references.">
        <text>Whenever a provision of this Division IV refers to any portion of the Maryland Code, the Code of Maryland Regulations &lt;em&gt;{COMAR}&lt;/em&gt;, and the State Forest Conservation Manual, the reference applies to any subsequent amendment to that portion of the code, regulations, or manual unless the referring provision expressly provides otherwise.</text>
        <annotation type="Prior Codifications">City Code, 1976/83, art. 9A, §1-2</annotation>
        <annotation type="History">Ord. 93-170</annotation>
        <annotation type="History">Ord. 20-401</annotation>
      </section>
      <section prefix="§" num="41-4" heading="Scope of Division – In general.">
        <para num="(1)">Except as provided in &lt;cite data-path="|7|§41-5"&gt;§ 41-5 of this subtitle&lt;/cite&gt;, this Division IV applies to:<para num="(i)">any person making application for a grading or building permit on a parcel or parcels of land for a total area of 5,000 square feet or greater;</para>
          <para num="(ii)">any person making application for a subdivision or development plan on a parcel or parcels of land for a total area of greater than 5,000 square feet; and</para>
          <para num="(iii)">a public utility not exempt under &lt;cite data-path="|7|§41-5|(b)|(3)"&gt;§ 41-5(b)(3) of this subtitle&lt;/cite&gt;.</para>
        </para>
        <para num="(2)">All subdivision or development plan approvals subject to this Division IV shall be conditioned on approval of a concept Forest Conservation Plan.  All grading or building permits subject to this Division IV shall be issued conditioned on approval of and compliance with a Forest Conservation Plan.</para>
        <annotation type="Prior Codifications">City Code, 1976/83, art. 9A, §2-1</annotation>
        <annotation type="History">Ord. 93-170</annotation>
        <annotation type="History">Ord. 20-401</annotation>
      </section>
      <section prefix="§" num="41-5" heading="Scope of Division – Exemptions.">
        <para num="(a)" heading="Definitions.">
          <para num="(1)" heading="Commercial logging or timber harvesting operations.">“Commercial logging or timber harvesting operations” means those activities which result in the cutting and removing of tree stems from a site for commercial purposes, leaving the root mass intact.</para>
          <para num="(2)" heading="Timber harvesting.">
            <para num="(i)">“Timber harvesting” means a tree-cutting operation affecting 1 or more acres of forest or developed woodland within a 1-year interval that disturbs 5,000 square feet or more of forest floor.</para>
            <para num="(ii)">“Timber harvesting” does not include grubbing and clearing of root mass.</para>
          </para>
        </para>
        <para num="(b)" heading="Exempted activities.">This Division IV does not apply to:<para num="(1)">any highway construction activity that is subject to &lt;cite data-doc="Md. Code" data-path="gnr|5-103"&gt;State Natural Resources Article § 5-103&lt;/cite&gt;;</para>
          <para num="(2)">commercial logging and timber harvesting operations, subject to the forest conservation and management program under &lt;cite data-doc="Md. Code" data-path="gtp|8-211"&gt;State Tax-Property Article § 8-211&lt;/cite&gt;:<para num="(i)">that were completed before July 1, 1991; or</para>
            <para num="(ii)">were completed on or after July 1, 1991, on property which:<para num="(A)">is the subject of a declaration of intent signed by the land owner and approved by the Department of Public Works and the Maryland Department of Natural Resource’s Project Forester’s Office as provided in &lt;cite data-doc="Code of Maryland Regulations" data-path="08.19.01.05"&gt;COMAR 08.19.01.05&lt;/cite&gt;; and</para>
              <para num="(B)">has not been the subject of an application for a grading permit for development within 5 years after a logging or timber harvesting operation, but after this 5-year period the property shall be subject to this Division IV;</para>
            </para>
          </para>
          <para num="(3)">the cutting or clearing of public utility rights-of-way or land for electric generating stations regulated under State Public Utility Companies Article, Title 7, if:<para num="(i)">required certificates of public convenience and necessity have been issued in accordance with &lt;cite data-doc="Md. Code" data-path="gnr|5-1603"&gt;State Natural Resources Article § 5-1603(f)&lt;/cite&gt;; and</para>
            <para num="(ii)">the cutting or clearing of the forest is conducted so as to minimize the loss of forest;</para>
          </para>
          <para num="(4)">routine maintenance or emergency repairs of public utility rights-of-way, if:<para num="(i)">the right-of-way existed before the effective date of the State or this program; or</para>
            <para num="(ii)">the right-of-way’s initial construction was approved under this Division IV;</para>
          </para>
          <para num="(5)">any noncoal surface mining regulated under Title 7, Subtitle 6A, of the State Natural Resources Article;</para>
          <para num="(6)">any preliminary plan of subdivision or any grading or sediment control plan approved before July 1, 1991;</para>
          <para num="(7)">areas covered by the Chesapeake Bay Critical Area Protection Law;</para>
          <para num="(8)">a real estate transfer to provide a security, leasehold, or other legal or equitable interest, including a transfer of title, a portion of a lot or parcel, if:<para num="(i)">the transfer does not involve a change in land use or new development or development, with associated land disturbing activities; and</para>
            <para num="(ii)">both the grantor and grantee file a declaration of intent;</para>
          </para>
          <para num="(9)">any activity conducted on a single lot of any size provided that the activity:<para num="(i)">does not result in the cumulative cutting or clearing of 5,000 square feet or greater of forest; and</para>
            <para num="(ii)">does not include an application for a grading or building permit for disturbance of 5,000 square feet or greater; or</para>
          </para>
          <para num="(10)">an activity required for the purpose of constructing a dwelling house intended for the use of the owner, or a child or a grandchild of the owner, if the activity:<para num="(i)">does not result in the cumulative cutting or clearing of 20,000 square feet or greater of forest;</para>
            <para num="(ii)">does not include an application for a grading or sediment and erosion control permit of 20,000 square feet or greater; and</para>
            <para num="(iii)">is the subject of a declaration of intent filed with the Department pursuant to &lt;cite data-path="|7|§42-7"&gt;§ 42-7 of this Division IV&lt;/cite&gt;.</para>
          </para>
        </para>
        <annotation type="Prior Codifications">City Code, 1976/83, art. 9A, §1-1(e), (t) and §2-2</annotation>
        <annotation type="History">Ord. 93-170</annotation>
        <annotation type="History">Ord. 04-672</annotation>
        <annotation type="History">Ord. 20-401</annotation>
      </section>
    </container>
    <container prefix="Subtitle" num="42" heading="General Requirements">
      <section prefix="§" num="42-1" heading="In general.">
        <para num="(a)" heading="Required delineations, plans, and methods.">Any person subject to this Division IV:<para num="(1)">shall submit to the Department:<para num="(i)">a forest stand delineation for the property on which the development is located according to guidelines set forth in the Baltimore City Forest Conservation Manual and this Division IV; and</para>
            <para num="(ii)">a forest conservation plan for the property on which the development is located according to guidelines set forth in the Manual and this Division IV; and</para>
          </para>
          <para num="(2)">shall use methods provided in the Manual to protect retained forest and trees during construction.</para>
        </para>
        <para num="(b)" heading="City agencies using state funds.">If a City agency using state funds makes application to conduct a regulated activity, the provisions of &lt;cite data-doc="Code of Maryland Regulations" data-path="08.19.04.01|D."&gt;COMAR 08.19.04.01D&lt;/cite&gt; apply.</para>
        <annotation type="Prior Codifications">City Code, 1976/83, art. 9A, §3-1</annotation>
        <annotation type="History">Ord. 93-170</annotation>
        <annotation type="History">Ord. 20-401</annotation>
      </section>
      <section prefix="§" num="42-2" heading="Preparation of plans.">
        <text>The forest stand delineation, the forest conservation plan, including preliminary and final plan, and the afforestation plan shall be prepared by a licensed forester, licensed landscape architect, or other qualified professional as provided in &lt;cite data-doc="Code of Maryland Regulations" data-path="08.19.06.01|B."&gt;COMAR 08.19.06.01B&lt;/cite&gt;.</text>
        <annotation type="Prior Codifications">City Code, 1976/83, art. 9A, §3-2</annotation>
        <annotation type="History">Ord. 93-170</annotation>
      </section>
      <section prefix="§" num="42-3" heading="Authorized signatory.">
        <para num="(a)" heading="Who must sign.">The forest stand delineation, preliminary and final forest conservation plans and afforestation/reforestation plans shall be signed by:<para num="(1)">an officer of the corporation or an authorized agent of a corporation;</para>
          <para num="(2)">an authorized official of a federal, state, or local government;</para>
          <para num="(3)">a partner of an association or partnership; or</para>
          <para num="(4)">an individual applicant.</para>
        </para>
        <para num="(b)" heading="Responsibility of signatory.">The individual who signs an application is responsible for the truth, accuracy, and completeness of all information in the application.</para>
        <annotation type="Prior Codifications">City Code, 1976/83, art. 9A, §3-6</annotation>
        <annotation type="History">Ord. 93-170</annotation>
      </section>
      <section prefix="§" num="42-4" heading="Review.">
        <text>The Department shall review an application for a forest stand delineation, forestation and deforestation plans, and preliminary and final forest conservation plans to determine whether they are complete and correct, and shall acknowledge receipt of the application in writing by regular first class mail or email.</text>
        <annotation type="Prior Codifications">City Code, 1976/83, art. 9A, §3-3</annotation>
        <annotation type="History">Ord. 93-170</annotation>
        <annotation type="History">Ord. 20-401</annotation>
      </section>
      <section prefix="§" num="42-5" heading="Completeness of application.">
        <text>The Department shall consider a forest stand delineation, preliminary and final forest conservation plans, and afforestation plans complete if they contain all of the required information listed in the Baltimore City Forest Conservation Manual.</text>
        <annotation type="Prior Codifications">City Code, 1976/83, art. 9A, §3-4</annotation>
        <annotation type="History">Ord. 93-170</annotation>
      </section>
      <section prefix="§" num="42-6" heading="Notification of completeness.">
        <para num="(a)" heading="To be given within 45 days.">Within 45 calendar days after receipt of the forest stand delineation, the preliminary and final forest conservation plans, and the afforestation plan, the Department shall notify the applicant by mail or email whether the application is complete and correct or if additional information is required.</para>
        <para num="(b)" heading="Effect of failure to notify.">If the Department fails to notify the applicant within 45 days, any plan submitted shall be treated as complete and correct.</para>
        <para num="(c)" heading="Additional information; extension of review.">The Department may require further information or provide for an additional 15 calendar days for review of an application under extenuating circumstances.</para>
        <annotation type="Prior Codifications">City Code, 1976/83, art. 9A, §3-5</annotation>
        <annotation type="History">Ord. 93-170</annotation>
        <annotation type="History">Ord. 20-401</annotation>
      </section>
      <section prefix="§" num="42-7" heading="Declaration of intent.">
        <para num="(a)" heading="Required for exemption.">A person seeking an exemption under § 41-4 &lt;em&gt;{§ 41-5} &lt;/em&gt;of this Division IV shall file a declaration of intent with the Department.</para>
        <para num="(b)" heading="Compliance with COMAR.">The declaration of intent shall be as specified in &lt;cite data-doc="Code of Maryland Regulations" data-path="08.19.01.05"&gt;COMAR 08.19.01.05&lt;/cite&gt;.</para>
        <para num="(c)" heading="Effective term.">The declaration of intent is effective for 5 years.</para>
        <annotation type="Prior Codifications">City Code, 1976/83, art. 9A, §3-7</annotation>
        <annotation type="History">Ord. 93-170</annotation>
      </section>
      <section prefix="§" num="42-8" heading="Area subject to calculations.">
        <text>For a grading or building permit application for an area 40,000 square feet or greater in size, only the area of disturbance is subject to reforestation and afforestation calculations, unless the grading or building permit is part of a master plan, development plan, planned unit development, or subdivision for which the entire master plan, development plan, planned unit development, or subdivision is subject to reforestation and afforestation calculations.</text>
        <annotation type="Prior Codifications">City Code, 1976/83, art. 9A, §3-8</annotation>
        <annotation type="History">Ord. 93-170</annotation>
        <annotation type="History">Ord. 20-401</annotation>
      </section>
    </container>
    <container prefix="Subtitle" num="43" heading="Forest Stand Delineation">
      <section prefix="§" num="43-1" heading="Time for submission.">
        <para num="(a)" heading="In general.">A forest stand delineation for the affected area shall be submitted:<para num="(1)">at the initial stages of subdivision or site plan approval;</para>
          <para num="(2)">before a grading or building permit application is submitted; or</para>
          <para num="(3)">before a sediment and erosion control application is submitted.</para>
        </para>
        <para num="(b)" heading="Effect of failure to submit.">If the forest stand delineation is not submitted at this time, no action will be taken on an application request for subdivision, site plan, building, grading, or sediment and erosion control approval.</para>
        <annotation type="Prior Codifications">City Code, 1976/83, art. 9A, §4-1</annotation>
        <annotation type="History">Ord. 93-170</annotation>
        <annotation type="History">Ord. 20-401</annotation>
      </section>
      <section prefix="§" num="43-2" heading="Simplified delineation – When authorized.">
        <text>A simplified forest stand delineation may be submitted for an area:</text>
        <para num="(1)">when no forest cover will be disturbed during any construction activity;</para>
        <para num="(2)">when an area is designated to be protected under a long term protective agreement;</para>
        <para num="(3)">when there is no existing forest on the site; or</para>
        <para num="(4)">when approved by the Department.</para>
        <annotation type="Prior Codifications">City Code, 1976/83, art. 9A, §4-2</annotation>
        <annotation type="History">Ord. 93-170</annotation>
      </section>
      <section prefix="§" num="43-3" heading="Simplified delineation – Requirements.">
        <text>The Department shall consider a simplified forest stand delineation complete if it includes:</text>
        <para num="(1)">a topographic map delineating intermittent and perennial streams and steep slopes over 25%;</para>
        <para num="(2)">a soils map;</para>
        <para num="(3)">location of 100-year floodplain; and</para>
        <para num="(4)">any other information necessary for the Department to review the application.</para>
        <annotation type="Prior Codifications">City Code, 1976/83, art. 9A, §4-3</annotation>
        <annotation type="History">Ord. 93-170</annotation>
      </section>
      <section prefix="§" num="43-4" heading="Effective term.">
        <text>An approved forest stand delineation may remain in effect for a period not longer than 5 years.</text>
        <annotation type="Prior Codifications">City Code, 1976/83, art. 9A, §4-4</annotation>
        <annotation type="History">Ord. 93-170</annotation>
      </section>
    </container>
    <container prefix="Subtitle" num="44" heading="Forest Conservation Plan">
      <section prefix="§" num="44-1" heading="Preliminary plan.">
        <para num="(a)" heading="Concurrent review.">The review of a preliminary forest conservation plan shall be concurrent with the review of the preliminary site plan.</para>
        <para num="(b)" heading="Modifications.">A preliminary forest conservation plan may be modified during the different stages of the review process, provided the Department approves the changes.</para>
        <annotation type="Prior Codifications">City Code, 1976/83, art. 9A, §§5-1, 5-2</annotation>
        <annotation type="History">Ord. 93-170</annotation>
      </section>
      <section prefix="§" num="44-2" heading="Retention of existing forest and specimen trees.">
        <text>In developing a forest conservation plan, the applicant shall give priority to techniques for retaining existing forest and specimen trees on the site.  If existing forest or specimen trees on the site subject to a forest conservation plan cannot be retained, the applicant shall demonstrate to the satisfaction of the Department how techniques for retention have been exhausted.</text>
        <annotation type="Prior Codifications">City Code, 1976/83, art. 9A, §6-1</annotation>
        <annotation type="History">Ord. 93-170</annotation>
        <annotation type="History">Ord. 20-401</annotation>
      </section>
      <section prefix="§" num="44-3" heading="Impacts to specimen trees and forests on adjacent properties.">
        <text>The Department may only approve clearing or significant critical root zone impacts to specimen trees or forests on adjacent properties if the applicant submits written notification of the proposed clearing or significant critical root zone impacts to the owners.</text>
        <annotation type="History">Ord. 20-401</annotation>
      </section>
      <section prefix="§" num="44-4" heading="Revocation of plan – Grounds.">
        <text>The Department, its designee, or other responsible agency at the request of the Department, may revoke an approved forest conservation plan, including a reforestation and afforestation plan, if it finds that:</text>
        <para num="(1)">any provision of the plan has been violated;</para>
        <para num="(2)">approval of the plan was obtained through fraud, misrepresentation, a false or misleading statement, or omission of a relevant or material fact; or</para>
        <para num="(3)">changes in the development or in the condition of the site necessitate preparation of a new or amended plan.</para>
        <annotation type="Prior Codifications">City Code, 1976/83, art. 9A, §6-2</annotation>
        <annotation type="History">Ord. 93-170</annotation>
        <annotation type="History">Ord. 20-401</annotation>
      </section>
      <section prefix="§" num="44-5" heading="Revocation of plan – Notice and hearing.">
        <text>Prior to revoking approval of a forest conservation plan, the Department shall notify the owner and/or developer in writing and provide an opportunity for hearing before the Baltimore City Planning Commission.</text>
        <annotation type="Prior Codifications">City Code, 1976/83, art. 9A, §6-3</annotation>
        <annotation type="History">Ord. 93-170</annotation>
        <annotation type="History">Ord. 20-401</annotation>
      </section>
      <section prefix="§" num="44-6" heading="Cutting prohibited pending approval.">
        <text>If a forest conservation plan is required by this Division IV, a person shall not cut, clear, or grade on the development site until the Department has approved the plan.  All grading or building permits, and subdivision or development plan approvals shall be issued conditioned on approval of, and compliance with a Forest Conservation Plan.</text>
        <annotation type="Prior Codifications">City Code, 1976/83, art. 9A, §6-4</annotation>
        <annotation type="History">Ord. 93-170</annotation>
        <annotation type="History">Ord. 20-401</annotation>
      </section>
      <section prefix="§" num="44-7" heading="Approval of plan alteration.">
        <text>The plan cannot be altered without first obtaining approval from the Department.</text>
        <annotation type="Prior Codifications">City Code, 1976/83, art. 9A, §6-5</annotation>
        <annotation type="History">Ord. 93-170</annotation>
        <annotation type="History">Ord. 20-401</annotation>
      </section>
      <section prefix="§" num="44-8" heading="Modification of a forest conservation easement.">
        <para num="(a)" heading="Process for reviewing and approving/denying modifications.">The following review and approval paths will apply to forest conservation easement modifications:<para num="(1)">Expansion of an easement with no reduction to the easement can be reviewed and approved through the standard forest conservation review process.</para>
          <para num="(2)">Less than 5,000 square feet of modification to an easement of at least 15,000 square. feet in size can be reviewed and approved through the standard forest conservation review process.</para>
          <para num="(3)">5,000 square feet or greater modification to an easement of at least 15,000 square feet in size must be approved by the Planning Commission.</para>
          <para num="(4)">Any amount of modification to an easement established as part of a previous approval by the Planning Commission must be approved by the Planning Commission.</para>
          <para num="(5)">No modification will be permitted to reduce an easement to less than 10,000 square feet in size if the easement is to remain.</para>
          <para num="(6)">The applicant will need to submit:<para num="(i)">a new Forest Stand Delineation if the Forest Stand Delineation on record is more than 5 years old;</para>
            <para num="(ii)">a new Forest Conservation Plan identifying the proposed easement modification(s); the plan must demonstrate that the proposed modifications enhance or have no adverse effect on public safety and the public benefit, and enhance or appropriately offset any adverse effect on the conservation attributes of the property;</para>
            <para num="(iii)">information describing how the request meets one or more of the “Conditions and Circumstances Under Which an Easement Modification May Be Considered” and all applicable “Criteria for Approval of an Easement Modification” as listed below; and</para>
            <para num="(iv)">a request to the Planning Commission for Forest Conservation Easement modification, for modifications requiring Planning Commission approval.</para>
          </para>
          <para num="(7)">Once a request requiring Planning Commission approval has been accepted and scheduled for Planning Commission review, the applicant must meet all Planning Commission hearing requirements.</para>
        </para>
        <para num="(b)" heading="Conditions and circumstances.">Conditions and circumstances under which an easement modification may be considered {are listed below}.<para num="(1)">Expansion of an easement.</para>
          <para num="(2)">Correction of oversight or error.</para>
          <para num="(3)">Modification to address an environmental problem or public safety issue.</para>
          <para num="(4)">Modification to accomplish a public benefit.</para>
        </para>
        <para num="(c)" heading="Criteria for approval of an easement modification.">The applicant must demonstrate that the modified easement will meet state and local forest conservation standards.<para num="(1)">In the case of a correction of an oversight or error, the applicant must demonstrate that an oversight or error exists in the recorded easement documents.</para>
          <para num="(2)">In the case of a modification to address an environmental problem or public safety issue, the applicant must demonstrate existence and extent of the environmental or public safety issue.</para>
          <para num="(3)">In the case of a modification to accomplish a public benefit, the applicant must demonstrate and quantify the public benefit that would result from the modification.</para>
          <para num="(4)">In cases where a proposed modification would result in removal of a portion of the existing easement, the applicant must demonstrate that, in identifying the proposed solution, all potential options for retaining the easement intact were exhausted.</para>
          <para num="(5)">In cases where a proposed modification would result in removal of a portion of the existing easement, the applicant must demonstrate that the mitigation proposed meets the requirements as calculated using the state Forest Conservation Worksheet and that the mitigation proposed follows the required sequence for mitigation as listed under Subtitle 45 of &lt;cite data-path="|7"&gt;Article 7&lt;/cite&gt;, Division IV of the City Code.  A fee in lieu will only be considered as a last resort.</para>
          <para num="(6)">Proposals to completely remove or eliminate an easement will not be considered unless the existing easement is replaced with an on- or off-site easement of equivalent quality and of a size determined using the State Forest Conservation Worksheet.</para>
          <para num="(7)">Equivalent quality will be determined by the Department of Planning through a comparison of the existing and proposed easements, including the presence of priority forest, forest stand maturity, health, and species diversity, and the extent of non-native invasive vegetation.</para>
          <para num="(8)">No modification will be permitted to reduce an easement to less than 10,000 square feet in size, and minimum dimensions must meet the standards established in the State Forest Conservation Technical Manual.</para>
        </para>
        <para num="(d)" heading="Steps following approval of a forest conservation easement modification.">
          <para num="(1)">Submit a new draft record plat and draft easement agreement for approval.  The agreement should cite any terms or conditions associated with approval by the Department or the Planning Commission.</para>
          <para num="(2)">Provide a draft bond for any on-site or off-site mitigation requirements approved by the Planning Commission and work with the Department of Planning to prepare a draft MOU defining the terms for completing the mitigation and releasing the bond.</para>
          <para num="(3)">Once the draft bond has been approved, execute the bond and associated MOU and provide the original to the Department of Planning.</para>
          <para num="(4)">Once the record plat and easement agreement have been approved by the Department of Planning, record the new plat and agreement with the Circuit Court for Baltimore City, Land Records and Licenses Division.</para>
          <para num="(5)">Satisfy all mitigation requirements required.  Notify Department of Planning staff for inspections once mitigation has been installed and again before the two-year maintenance and establishment period concludes.  Once all mitigation and maintenance requirements have been satisfied, the Department of Planning will arrange to release the bond.</para>
        </para>
        <annotation type="History">Ord.  20-401</annotation>
      </section>
    </container>
    <container prefix="Subtitle" num="45" heading="Reforestation, Afforestation, and Specimen Tree Mitigation">
      <section prefix="§" num="45-1" heading="Preference for retention.">
        <text>After every reasonable effort to minimize the cutting of trees and other woody plants is exhausted in the development of a subdivision plan, and/or grading and sediment control plans, the forest conservation plan shall provide for reforestation, afforestation, and/or specimen tree mitigation.</text>
        <annotation type="Prior Codifications">City Code, 1976/83, art. 9A, §7-1</annotation>
        <annotation type="History">Ord. 93-170</annotation>
        <annotation type="History">Ord. 20-401</annotation>
      </section>
      <section prefix="§" num="45-2" heading="Required sequence.">
        <para num="(a)" heading="Definitions.">
          <para num="(1)" heading="Off-site.">“Off-site” means not on the same property as the activity which is proposed, is occurring, or which has occurred.</para>
          <para num="(2)" heading="On-site.">“On-site” means the area located within the legal boundary of the property on which the regulated activity is proposed, is occurring, or has occurred.</para>
        </para>
        <para num="(b)" heading="Sequence for reforestation, etc.">The required sequence for reforestation, afforestation, or specimen tree mitigation, after techniques for retaining existing forest on the site have been exhausted, is as follows:<para num="(1)">on-site reforestation, afforestation, and/or specimen tree mitigation, as specified in the Baltimore City Forest Conservation Manual;</para>
          <para num="(2)">off-site reforestation, afforestation, and/or specimen tree mitigation within the City shall be as specified for on-site reforestation or specimen tree mitigation;</para>
          <para num="(3)">use of appropriate credits generated by a forest mitigation bank in the City; and</para>
          <para num="(4)">payment into the City Forest Conservation Fund.</para>
        </para>
        <annotation type="Prior Codifications">City Code, 1976/83, art. 9A, §1-1(n), (o) and §7-2</annotation>
        <annotation type="History">Ord. 93-170</annotation>
        <annotation type="History">Ord. 20-401</annotation>
      </section>
      <section prefix="§" num="45-3" heading="Reforestation, etc., guidelines; time limits.">
        <para num="(a)" heading="Priority guidelines in Manual.">Persons required to conduct reforestation, afforestation, or specimen tree mitigation shall follow the priority guidelines outlined in the Baltimore City Forest Conservation Manual.</para>
        <para num="(b)" heading="Period for reforestation, etc.">A person required to conduct reforestation, afforestation, or specimen tree mitigation under this Division IV shall accomplish the action within 1 year or 2 growing seasons following the issuance of a grading permit, allowing for phasing in the plan.</para>
        <annotation type="Prior Codifications">City Code, 1976/83, art. 9A, §7-3</annotation>
        <annotation type="History">Ord. 93-170</annotation>
        <annotation type="History">Ord. 20-401</annotation>
      </section>
      <section prefix="§" num="45-4" heading="Security required.">
        <text>Before the issuance of a grading or building permit, a person required to conduct afforestation, reforestation, or specimen tree mitigation under this Division IV shall furnish financial security in the form of a bond, an irrevocable letter of credit, or other security approved by the Department, as provided in the Baltimore City Conservation Supplement to the State Conservation Manual.</text>
        <annotation type="Prior Codifications">City Code, 1976/83, art. 9A, §10-1</annotation>
        <annotation type="History">Ord. 93-170</annotation>
        <annotation type="History">Ord. 20-401</annotation>
      </section>
    </container>
    <container prefix="Subtitle" num="46" heading="Forest Conservation Fund">
      <section prefix="§" num="46-1" heading="Forest Conservation Fund established.">
        <text>There is hereby created a Baltimore City Forest Conservation Fund that meets the requirements of &lt;cite data-doc="Md. Code" data-path="gnr|5-1610"&gt;Natural Resources Article, §5-1610(h-l), Annotated Code of Maryland&lt;/cite&gt;.</text>
        <annotation type="Prior Codifications">City Code, 1976/83, art. 9A, §9-1</annotation>
        <annotation type="History">Ord. 93-170</annotation>
        <annotation type="History">Ord. 20-401</annotation>
      </section>
      <section prefix="§" num="46-2" heading="When payments in lieu permitted.">
        <text>If reforestation, afforestation, or specimen tree mitigation is not possible, and appropriate credits generated by a forest mitigation bank in the City are not available, the applicant may make payment into the Forest Conservation Fund.  Payment may be accepted into the Conservation Fund under the following circumstances:</text>
        <para num="(1)">satisfying all or a portion of the required reforestation, afforestation, or specimen tree mitigation on site is technically infeasible;</para>
        <para num="(2)">an acceptable planting site cannot be found on other land within Baltimore City; and</para>
        <para num="(3)">appropriate credits generated by a forest mitigation bank in the City are not available.</para>
        <annotation type="Prior Codifications">City Code, 1976/83, art. 9A, §8-1</annotation>
        <annotation type="History">Ord. 93-170</annotation>
        <annotation type="History">Ord. 20-401</annotation>
      </section>
      <section prefix="§" num="46-3" heading="Contribution rate.">
        <para num="(a)" heading="In lieu of reforestation or afforestation.">A person permitted by &lt;cite data-path="|7|§46-2"&gt;§ 46-2 of this subtitle&lt;/cite&gt; to contribute to this fund in lieu of reforestation or afforestation shall make a payment to the Baltimore City Conservation Fund of $60,000 per acre of the area requiring planting or at a rate  determined and adjusted periodically by the Planning Commission and approved by the Board of Estimates.</para>
        <para num="(b)" heading="In lieu of specimen tree mitigation.">A person permitted by &lt;cite data-path="|7|§46-2"&gt;§ 46-2 of this subtitle&lt;/cite&gt; to contribute to this fund in lieu of specimen tree mitigation shall make a payment to the Baltimore City Conservation Fund of $300 per inch of required mitigation, or at a rate as determined and adjusted periodically by the Planning Commission and approved by the Board of Estimates.</para>
        <annotation type="Prior Codifications">City Code, 1976/83, art. 9A, §9-2</annotation>
        <annotation type="History">Ord. 93-170</annotation>
        <annotation type="History">Ord. 20-401</annotation>
      </section>
      <section prefix="§" num="46-4" heading="When payable.">
        <text>Money contributed in lieu of afforestation, reforestation, or specimen tree mitigation  shall be paid at the time of the issuance of the grading or building permit for the development project.</text>
        <annotation type="Prior Codifications">City Code, 1976/83, art. 9A, §9-3</annotation>
        <annotation type="History">Ord. 93-170</annotation>
        <annotation type="History">Ord. 20-401</annotation>
      </section>
      <section prefix="§" num="46-5" heading="Period for City reforestation, etc.">
        <para num="(a)" heading="Period for City action.">The City shall accomplish the reforestation or afforestation for the equivalent number of acres for which the money is deposited within 2 years or 3 growing seasons, whichever is a greater time period, after receipt of the money.</para>
        <para num="(b)" heading="Refund.">At the end of that time, any part that has not been used to meet the afforestation or reforestation requirements shall be returned to the person who provided the money.</para>
        <annotation type="Prior Codifications">City Code, 1976/83, art. 9A, §9-4</annotation>
        <annotation type="History">Ord. 93-170</annotation>
        <annotation type="History">Ord. 20-401</annotation>
      </section>
      <section prefix="§" num="46-6" heading="Management of Fund.">
        <para num="(a)" heading="In general.">Money contributed under this title:<para num="(1)">may be used only for reforestation and afforestration, including site identification, acquisition, preparation, management, and maintenance of existing forests, and achieving urban canopy goals;</para>
          <para num="(2)">shall be deposited in a separate Forest Conservation Fund; and</para>
          <para num="(3)">shall not revert to the General Fund.</para>
        </para>
        <para num="(b)" heading="Site selection.">Sites selected for use of funds shall be located in the City of Baltimore.</para>
        <annotation type="Prior Codifications">City Code, 1976/83, art. 9A, §9-5</annotation>
        <annotation type="History">Ord. 93-170</annotation>
        <annotation type="History">Ord. 20-401</annotation>
      </section>
    </container>
    <container prefix="Subtitle" num="47" heading="Variances">
      <section prefix="§" num="47-1" heading="“Variance” defined; When request required.">
        <text>“Variance” means the process of obtaining approval for a forest conservation plan that does not strictly conform to the standards and requirements set forth in this Division IV.  A variance must be requested in advance of approval of a Forest Conservation Plan and in advance of any activity requiring approval of a Forest Conservation Plan.</text>
        <annotation type="Prior Codifications">City Code, 1976/83, art. 9A, §9-5</annotation>
        <annotation type="History">Ord. 93-170</annotation>
        <annotation type="History">Ord. 20-401</annotation>
      </section>
      <section prefix="§" num="47-2" heading="When authorized.">
        <text>Variances from this Division IV may be granted by the Planning Commission, if the applicant demonstrates that enforcement would result in unwarranted hardship to the applicant.</text>
        <annotation type="Prior Codifications">City Code, 1976/83, art. 9A, §11-1</annotation>
        <annotation type="History">Ord. 93-170</annotation>
      </section>
      <section prefix="§" num="47-3" heading="Applications.">
        <text>An applicant for a variance shall:</text>
        <para num="(1)">describe the special conditions peculiar to the property which would cause the unwarranted hardship;</para>
        <para num="(2)">describe how enforcement of these rules will deprive the applicant of rights commonly enjoyed by others in similar areas;</para>
        <para num="(3)">verify that the granting of the variance will not confer on the applicant a special privilege that would be denied to other applicants;</para>
        <para num="(4)">verify that the variance request is not based on conditions or circumstances which are the result of actions by the applicant;</para>
        <para num="(5)">verify that the need for the variance is not as a result of a violation of any portion of Division IV;</para>
        <para num="(6)">verify that the request does not arise from a condition relating to land or building use, either permitted or nonconforming, on a neighboring property;</para>
        <para num="(7)">verify that the granting of a variance will not adversely affect water quality; and</para>
        <para num="(8)">such other criteria that, subject to Title 4 {“Administrative Procedure Act – Regulations”} of the &lt;cite data-path="|general"&gt;City General Provisions Article&lt;/cite&gt;, the Planning Commission may set by rule or regulation.</para>
        <annotation type="Prior Codifications">City Code, 1976/83, art. 9A, §11-2</annotation>
        <annotation type="History">Ord. 93-170</annotation>
        <annotation type="History">Ord. 20-401</annotation>
        <annotation type="History">Text Conformed 02/16/21</annotation>
        <annotation type="Editor's Notes">By authority of Ordinance 20-431, Section 5, the Director of Legislative Reference, in consultation with the Law Department, has conformed the text of this item (8) to refer to and reflect the requirements of the recently-enacted Administrative Procedure Act that, effective January 15, 2021, governs the proposal, adoption, and publication of administrative rules and regulations.</annotation>
      </section>
    </container>
    <container prefix="Subtitle" num="48" heading="Enforcement; Penalties">
      <section prefix="§" num="48-1" heading="HCD to enforce.">
        <text>This Division IV may be enforced by the Department of Housing and Community Development in the manner provided in § 104 {“Duties and powers of Building Official”} of the Baltimore City &lt;cite data-path="|building-codes|II"&gt;Building Code&lt;/cite&gt;.</text>
        <annotation type="Prior Codifications">City Code, 1976/83, art. 9A, §12-1(a)</annotation>
        <annotation type="History">Ord. 93-170</annotation>
        <annotation type="History">Ord. 02-475</annotation>
        <annotation type="History">Ord. 13-093</annotation>
      </section>
      <section prefix="§" num="48-2" heading="Fines.">
        <para num="(a)" heading="Imposition.">A person found to be in noncompliance with this Division IV, or the regulations adopted thereunder, the forest conservation plan, or the associated 2-year maintenance agreement, shall be fined a penalty of $120,000 per acre of the area found to be in noncompliance with required forest conservation, or at a rate as determined and adjusted periodically by the Planning Commission and approved by the Board of Estimates.</para>
        <para num="(b)" heading="Use of funds.">Money collected under subsection (a) of this section shall be deposited in the Forest Conservation Fund established by the Director of Finance, and may be used by the City for purposes related to implementing this Division IV.</para>
        <annotation type="Prior Codifications">City Code, 1976/83, art. 9A, §12-1(b), (c)</annotation>
        <annotation type="History">Ord. 93-170</annotation>
        <annotation type="History">Ord. 20-401</annotation>
      </section>
      <section prefix="§" num="48-3" heading="Civil penalties.">
        <para num="(a)" heading="In general.">In addition, any person who violates any provision of this Division IV or any regulation or order adopted or issued thereunder, is liable for a penalty not exceeding $1,000 per violation, which may be recovered in a civil action brought by the City.</para>
        <para num="(b)" heading="Each day a separate offense.">Each day a violation continues is a separate violation.</para>
        <annotation type="Prior Codifications">City Code, 1976/83, art. 9A, §12-2</annotation>
        <annotation type="History">Ord. 93-170</annotation>
      </section>
      <section prefix="§" num="48-4" heading="Injunctions.">
        <text>The Department may request the City Solicitor to seek an injunction requiring a person to cease violation of this title and to take corrective action to restore or reforest an area.</text>
        <annotation type="Prior Codifications">City Code, 1976/83, art. 9A, §12-3</annotation>
        <annotation type="History">Ord. 93-170</annotation>
      </section>
    </container>
    <container prefix="Subtitles" num="49 to 50" />
  </container>
  <container prefix="Division" num="V" heading="City Parks and Trees">
    <container prefix="Subtitle" num="51" heading="Department Jurisdiction">
      <section prefix="§" num="51-1" heading="Cahill Recreation Center.">
        <text>The Department of Recreation and Parks is hereby authorized and directed to assume and hereafter exercise, exclusively, control of the property formerly known as Mt. Holly Inn, and all lands adjacent thereto, and all appurtenances thereto, which property was conveyed by Winfield S. Cahill and wife to the Mayor and City Council of Baltimore on July 27, 1939, said property to be hereafter used for park purposes.</text>
        <annotation type="Prior Codifications">City Code, 1950, art. 30, §1</annotation>
        <annotation type="Prior Codifications">1966, art. 21, §1</annotation>
        <annotation type="Prior Codifications">1976/83, art. 21, §1</annotation>
        <annotation type="History">Ord. 40-121</annotation>
      </section>
      <section prefix="§" num="51-2" heading="Venable Park.">
        <para num="(a)" heading="Department jurisdiction.">The Department of Recreation and Parks is hereby authorized and directed to assume jurisdiction, for park purposes, over the following described part of Venable Park lying south of Thirty-Third Street:</para>
        <para num="(b)" heading="School Board jurisdiction.">The Board of School Commissioners is hereby authorized and directed to assume jurisdiction, for school purposes, over all that part of Venable Park lying south of Thirty-Third Street not embraced in the piece or parcel of land described in subsection (a) hereof.</para>
        <annotation type="Prior Codifications">City Code, 1950, art. 30, §§10, 11</annotation>
        <annotation type="Prior Codifications">1966, art. 21, §§12, 13</annotation>
        <annotation type="Prior Codifications">1976/83, art. 21, §§10, 11</annotation>
        <annotation type="History">Ord. 41-369</annotation>
      </section>
      <section prefix="§" num="51-3" heading="Park Avenue Squares.">
        <text>The City will:</text>
        <para num="(1)">before July 1, 1897, plant with grass, trees, and shrubs, improve, and thereafter maintain the squares now laid out in the center of Park Avenue; and</para>
        <para num="(2)">at all times thereafter, prevent their being overgrown with weeds or becoming unsightly.</para>
        <annotation type="Prior Codifications">City Code, 1927, art. 29, §8</annotation>
        <annotation type="Prior Codifications">1950, art. 30, §7</annotation>
        <annotation type="Prior Codifications">1966, art. 21, §9</annotation>
        <annotation type="Prior Codifications">1976/83, art. 21, §8</annotation>
        <annotation type="History">Ord. 1897-056</annotation>
      </section>
      <section prefix="§" num="51-4" reserved="true" />
      <section prefix="§" num="51-5" heading="Report on closings and other public-access restrictions.">
        <para num="(a)" heading="Annual report required.">On or before March 30 of each year, the Department of Recreation and Parks shall submit to the City Council a written report on all closings of and other public-access restrictions imposed on all parks, squares, and recreational facilities operated by or under the auspices of the Department.</para>
        <para num="(b)" heading="Contents.">The report shall:<para num="(1)">include a summary of all closings and public-access restrictions that occurred during the preceding calendar year; and</para>
          <para num="(2)">specify:<para num="(i)">the number of hours of each closing or restriction;</para>
            <para num="(ii)">whether the closing or restriction was pursuant to a permit and, if so, the type of permit; and</para>
            <para num="(iii)">whether the closing or restriction was necessitated by an emergency and, if so, the nature of that emergency.</para>
          </para>
        </para>
        <annotation type="History">Ord. 08-074</annotation>
      </section>
    </container>
    <container prefix="Subtitle" num="52" heading="Protective Measures">
      <section prefix="§" num="52-1" heading="Obstructions in parks and squares.">
        <para num="(a)" heading="Prohibited conduct.">No stand or obstruction to the public view shall be erected in any of the public parks or squares of the City or upon the footway belonging to any public building by any person or persons whomsoever (other than the Mayor and City Council of Baltimore).</para>
        <para num="(b)" heading="Penalties.">Anyone violating this section shall be fined $50 for each offense.</para>
        <annotation type="Prior Codifications">City Code, 1893, art. 37, §14</annotation>
        <annotation type="Prior Codifications">art. 46, §34</annotation>
        <annotation type="Prior Codifications">1927, art. 29, §10</annotation>
        <annotation type="Prior Codifications">1950, art. 30, §3</annotation>
        <annotation type="Prior Codifications">1966, art. 21, §3</annotation>
        <annotation type="Prior Codifications">1976/83, art. 21, §2</annotation>
        <annotation type="History">Ord. 1889-151</annotation>
      </section>
      <section prefix="§" num="52-2" heading="Glass containers.">
        <para num="(a)" heading="Prohibited conduct.">Except as permitted by the Director of the Department of Recreation and Parks permits, a person shall not carry or possess any glass beverage container on any property under the control of the Department of Recreation and Parks.</para>
        <para num="(b)" heading="Penalties.">Any person who violates the provisions of this section shall be guilty of a misdemeanor and, upon conviction, shall be subject to a fine of not more than $100.</para>
        <annotation type="Prior Codifications">City Code, 1976/83, art. 19, §30A</annotation>
        <annotation type="History">Ord. 87-894</annotation>
      </section>
      <section prefix="§" num="52-3" heading="Defacement, etc., of monuments.">
        <para num="(a)" heading="Prohibited conduct.">It shall be unlawful for any person to deface, injure, damage, or trespass upon any public or private monument, statue, or memorial, their ornamental figures or sculpture, or the enclosure or railing around them, or any of them, in the City of Baltimore.</para>
        <para num="(b)" heading="Liability and penalties.">
          <para num="(1)">Any person violating the provisions of this section:<para num="(i)">shall be guilty of a misdemeanor and, upon conviction thereof, shall be subject to a fine of not more than $500 for each such violation; and</para>
            <para num="(ii)">shall, in addition thereto, be liable to pay all expenses in repairing the said defacements, injuries, or damages.</para>
          </para>
          <para num="(2)">In addition to a fine or in lieu of a fine, a judge may sentence a person convicted under this section to perform community service on behalf of the City of Baltimore, which may include cleaning property of trash and litter.</para>
        </para>
        <annotation type="Prior Codifications">City Code, 1879, art. 45, §1</annotation>
        <annotation type="Prior Codifications">1893, art. 46, §1</annotation>
        <annotation type="Prior Codifications">1927, art. 29, §23</annotation>
        <annotation type="Prior Codifications">1950, art. 30, §4</annotation>
        <annotation type="Prior Codifications">1966, art. 21, §5</annotation>
        <annotation type="Prior Codifications">1976/83, art. 21, §4</annotation>
        <annotation type="History">Ord. 49-629</annotation>
        <annotation type="History">Ord. 91-664</annotation>
      </section>
      <section prefix="§" num="52-4" heading="Mount Vernon Place – Ornamental structures.">
        <text>It shall not be lawful for any person to erect or set up any portico, steps, or any other ornamental structure whatever, on Mount Vernon Place, a greater distance into the place than 9 feet, measuring from the building line thereof.</text>
        <annotation type="Prior Codifications">City Code, 1879, art. 45, §43</annotation>
        <annotation type="Prior Codifications">1893, art. 46, §21</annotation>
        <annotation type="Prior Codifications">1927, art. 29, §27</annotation>
        <annotation type="Prior Codifications">1950, art. 30, §5</annotation>
        <annotation type="Prior Codifications">1966, art. 21, §6</annotation>
        <annotation type="Prior Codifications">1976/83, art. 21, §5</annotation>
        <annotation type="History">Rev. Ords. 1858-059</annotation>
      </section>
      <section prefix="§" num="52-5" heading="Mount Vernon Place – Injuring grass or shrubs.">
        <para num="(a)" heading="Prohibited conduct.">It shall not be lawful for any person or persons to walk upon or otherwise injure the grass, trees, or shrubbery upon the squares around Washington Monument, known as Mount Vernon Place and Washington Place.</para>
        <para num="(b)" heading="Penalties.">All persons guilty of violating this section shall be subject to a fine of $1 for every offense; said fines to be collected as other fines and penalties are collected.</para>
        <annotation type="Prior Codifications">City Code, 1893, art. 46, §23</annotation>
        <annotation type="Prior Codifications">1927, art. 29, §28</annotation>
        <annotation type="Prior Codifications">1950, art. 30, §6</annotation>
        <annotation type="Prior Codifications">1966, art. 21, §7</annotation>
        <annotation type="Prior Codifications">1976/83, art. 21, §6</annotation>
        <annotation type="History">Ord. 1882-50</annotation>
      </section>
      <section prefix="§" num="52-6" heading="Battle Monument, etc.">
        <para num="(a)" heading="Prohibited conduct.">It shall not be lawful for any person or persons whomsoever, or for any body corporate, to deposit or cause to be deposited in the space around the Battle Monument, in Liberty Triangle, McLane Place, or Hopkins Place, any dirt, sand, stones, lumber, tools, or other material.</para>
        <para num="(b)" heading="Penalties.">Any person or persons or body corporate violating the provisions of this section, shall forfeit and pay:<para num="(1)">the sum of $10 for each and every offense; and</para>
          <para num="(2)">the additional sum of $10 for each and every day that any article or articles deposited upon said space in violation of the provisions of this section shall remain thereon.</para>
        </para>
        <annotation type="Prior Codifications">City Code, 1893, art. 46, §36</annotation>
        <annotation type="Prior Codifications">1927, art. 29, §31</annotation>
        <annotation type="Prior Codifications">1950, art. 30, §8</annotation>
        <annotation type="Prior Codifications">1966, art. 21, §10</annotation>
        <annotation type="Prior Codifications">1976/83, art. 21, §9</annotation>
        <annotation type="History">Ord. 1892-032</annotation>
        <annotation type="History">Ord. 14-495</annotation>
      </section>
      <section prefix="§" num="52-7" heading="Herring Run Park.">
        <para num="(a)" heading="Prohibited conduct.">
          <para num="(1)">It is unlawful any person to ride or permit a horse to be in any portion of Herring Run Park, other than on the bridle paths provided for such purpose.</para>
          <para num="(2)">It is unlawful for any person, firm, or corporation who or which owns or has control of a horse to turn over the animal to the custody of any person in the Park without instructions to keep the animal on the bridle paths as required in this section.</para>
        </para>
        <para num="(b)" heading="Penalties.">A violation of the provisions of this section is a misdemeanor, subject upon conviction to a fine in a maximum amount of $100.</para>
        <annotation type="Prior Codifications">City Code, 1966, art. 21, §4</annotation>
        <annotation type="Prior Codifications">1976/83, art. 21, §3</annotation>
        <annotation type="History">Ord. 59-1811</annotation>
      </section>
    </container>
    <container prefix="Subtitle" num="53" heading="Trees along City Streets, etc.">
      <section prefix="§" num="53-1" heading="Definitions.">
        <para num="(a)" heading="In general.">In this subtitle, the following terms have the meanings indicated.</para>
        <para num="(b)" heading="Breast height.">“Breast height” means 4.5 feet off of the ground.</para>
        <para num="(c)" heading="Caliper inch.">“Caliper inch” means 6 inches off of the ground.</para>
        <para num="(d)" heading="Inch-for-inch replacement.">“Inch-for-inch replacement” means the tree removal and replacement standard used by the Department of Recreation and Parks that requires a person to plant a tree or trees with an equal or greater sum diameter, as measured in inches, to the sum diameter of all trees removed by that person, as measured in inches.</para>
        <para num="(e)" heading="Permit holder.">“Permit holder” means a person to whom the Department of Recreation and Parks has issued a written permit to remove a tree under subsection (c) of &lt;cite data-path="7|§53-15"&gt;§ 53-15 {“Tree Removal - Street”}&lt;/cite&gt; or &lt;cite data-path="7|§53-16"&gt;§ 53-16 {“Tree Removal - Parks”}&lt;/cite&gt; of this subtitle.</para>
        <para num="(f)" heading="Root zone.">“Root zone” means a circular region, measured outward from a tree’s trunk, that represents the essential area of the tree’s roots that must be maintained or protected for the tree’s survival.</para>
        <para num="(g)" heading="Tree.">The word “trees”, as used in this subtitle, shall not be construed to include shrubs that do not grow higher than 15 feet.</para>
        <annotation type="Prior Codifications">City Code, 1927, art. 45, §185</annotation>
        <annotation type="Prior Codifications">1950, art. 35, §101</annotation>
        <annotation type="Prior Codifications">1966, art. 26, §104</annotation>
        <annotation type="Prior Codifications">1976/83, art. 26 § 109</annotation>
        <annotation type="History">Ord. 12-154</annotation>
        <annotation type="History">Ord. 46-396</annotation>
        <annotation type="History">Ord. 22-125</annotation>
        <annotation type="History" />
      </section>
      <section prefix="§" num="53-2" heading="Jurisdiction of Department of Recreation and Parks.">
        <para num="(a)" heading="Regulating planting, etc.">The Department of Recreation and Parks, in consultation with the Department of Transportation, is authorized and directed to regulate the planting, protection, removal, and controlling of all trees planted and to be planted in the parks or streets of Baltimore.</para>
        <para num="(b)" heading="Enforcing protective laws.">The statutes and ordinances for the protection of trees in the streets, lanes, or alleys shall be strictly observed by the Departments of Public Works, Transportation, General Services, and Recreation and Parks, as well as all other agencies of the City, within their respective authority.</para>
        <annotation type="Prior Codifications">City Code, 1927, art. 45, §§174, 175(2nd par.)</annotation>
        <annotation type="Prior Codifications">1950, art. 35, §§91, 92(2nd par.)</annotation>
        <annotation type="Prior Codifications">1966, art. 26, §§94, 95(2nd par.)</annotation>
        <annotation type="Prior Codifications">1976/83, art. 26, §§101, 102(2nd par.)</annotation>
        <annotation type="History">Ord. 12-154</annotation>
        <annotation type="History">Ord. 46-396</annotation>
        <annotation type="History">Ord. 76-139</annotation>
        <annotation type="History">Ord. 15-435</annotation>
        <annotation type="History" />
      </section>
      <section prefix="§" num="53-3" heading="Additional duties of Department of Recreation and Parks.">
        <text>It is the duty of the Department of Recreation and Parks:</text>
        <para num="(1)">to encourage the preservation, culture, and planting of shade and ornamental trees in the City’s parks and streets;</para>
        <para num="(2)">to prune, spray, cultivate, and otherwise maintain these trees;</para>
        <para num="(3)">to trim or direct the time and method of trimming these trees; and</para>
        <para num="(4)">to take all other measures that it considers necessary and reasonable for the control and extermination of insects and other pests and plant diseases that may injuriously affect trees in the City’s parks and streets.</para>
        <annotation type="Prior Codifications">City Code, 1927, art. 45, §175(1st par.)</annotation>
        <annotation type="Prior Codifications">1950, art. 35, §92(1st par.)</annotation>
        <annotation type="Prior Codifications">1966, art. 26, §95(1st par.)</annotation>
        <annotation type="Prior Codifications">1976/83, art. 26, §102(1st par.)</annotation>
        <annotation type="History">Ord. 12-154</annotation>
        <annotation type="History">Ord. 46-396</annotation>
        <annotation type="History">Ord. 76-139</annotation>
        <annotation type="History">Ord. 15-435</annotation>
        <annotation type="History" />
      </section>
      <section prefix="§" num="53-4" heading="Planting and care program.">
        <para num="(a)" heading="Program mandated.">The Department of Recreation and Parks shall initiate and maintain a program of planting and caring for trees along the streets, alleys, lanes, and other public ways and in parks, squares, and other public places of this City.</para>
        <para num="(b)" heading="Scope and implementation.">
          <para num="(1)">The program shall include at public expense the full cost of acquiring and planting the trees, including the cost of digging holes and preparing for the planting.</para>
          <para num="(2)">The size and scope of the program shall be determined from time to time by the amount of funds appropriated and authorized therefor.</para>
          <para num="(3)">It is the legislative intent that this program be vigorously implemented and pursued, and that a large and increasing number of trees be grown and preserved in and along all such public ways and public places in the entire City.</para>
        </para>
        <para num="(c)" heading="Spacing.">Trees shall be planted and preserved at intervals of not more than 30 feet from the next contiguous tree or trees, except where requested by a property owner.</para>
        <para num="(d)" heading="Species and varieties.">Species and varieties shall be planted and preserved as most suitable for the particular area by means of availability, long life, full foliage and limb structure, beauty, and the specific request of property owners, except where the request of the property owner as to variety of the tree is not practicable in the opinion of the City Arborist.</para>
        <annotation type="Prior Codifications">City Code, 1966, art. 26, §108</annotation>
        <annotation type="Prior Codifications">1976/83, art. 26, §113</annotation>
        <annotation type="History">Ord. 65-434</annotation>
      </section>
      <section prefix="§" num="53-5" heading="Public notice of tree removal.">
        <para num="(a)" heading="Notice required.">Unless notice is given as required by this section, the City may not:<para num="(1)">remove or destroy a tree along one of the streets in this City; or</para>
          <para num="(2)">permit any person to remove or destroy a  tree  along one of the streets in this City.</para>
        </para>
        <para num="(b)" heading="Form and content.">The notice required by &lt;cite data-path="7|§53-5|(a)"&gt;§ 53-5(a)&lt;/cite&gt;:<para num="(1)">must consist of a durable and legible statement of the intent, affixed to and easily visible on the tree for not less than 5 days immediately preceding the contemplated removal or destruction; and</para>
          <para num="(2)">must state:<para num="(i)">the reason for the intended removal or destruction of the tree; and</para>
            <para num="(ii)">the person or persons to whom inquiries or protests thereon may be directed.</para>
          </para>
        </para>
        <para num="(c)" heading="Exception for emergency.">
          <para num="(1)">In the event of an emergency situation, such as a fallen tree or some other condition or occurrence requiring an immediate removal or destruction of a tree along one of these public ways, the City or any person it permits may remove or destroy the tree without complying with the foregoing provisions of this section.</para>
          <para num="(2)">But in this event, the City or the person it permitted promptly shall notify the City Council of the circumstances, conditions, and justification under which the tree was thus removed or destroyed.</para>
        </para>
        <annotation type="Prior Codifications">City Code, 1966, art. 26, §107</annotation>
        <annotation type="Prior Codifications">1976/83, art. 26, §112</annotation>
        <annotation type="History">Ord. 64-433</annotation>
        <annotation type="History">Ord. 11-524</annotation>
        <annotation type="History" />
      </section>
      <section prefix="§§" num="53-6 to 53-10" reserved="true" />
      <section prefix="§" num="53-11" heading="Permit requirements – Planting trees.">
        <para num="(a)" heading="Permit required.">No person may plant any tree in any street, lane, or alley without:<para num="(1)">first having obtained a written permit issued by the Department of Transportation, in consultation with the Department of Recreation and Parks, setting forth the conditions under which trees will be planted, including their kind and variety; and</para>
          <para num="(2)">in all respects complying with the conditions of the permit.</para>
        </para>
        <para num="(b)" heading="Court-ordered plantings.">Any person determined by a court of competent jurisdiction to have unlawfully removed or destroyed a tree in any street, lane, or alley and required to replace the tree as directed by such court shall be granted a permit for its replacement as provided in this section.</para>
        <annotation type="Prior Codifications">City Code, 1927, art. 35, §176</annotation>
        <annotation type="Prior Codifications">1950, art. 35, §93</annotation>
        <annotation type="Prior Codifications">1966, art. 26, §96</annotation>
        <annotation type="Prior Codifications">1976/83, art. 26, §§103, 104A</annotation>
        <annotation type="History">Ord. 12-154</annotation>
        <annotation type="History">Ord. 46-396</annotation>
        <annotation type="History">Ord. 76-139</annotation>
        <annotation type="History">Ord. 90-576</annotation>
        <annotation type="History">Ord. 15-435</annotation>
      </section>
      <section prefix="§" num="53-12" heading="Permit requirements – Treating trees.">
        <para num="(a)" heading="Permit required.">No person may spray, mulch, fertilize, or otherwise treat, remove, destroy, break, cut, or trim any tree, or any part of a tree, in any street, lane, or alley without first having obtained a written permit issued by the Department of Transportation, in consultation with the Department of Recreation and Parks.</para>
        <para num="(b)" heading="Department to direct utilities, etc.">No cutting or trimming of any tree in any street, lane, or alley in connection with the work of any other City department or of any public service corporation or other person having a right to use the street, lane, or alley may be done except in the manner directed by the Department of Transportation, in consultation with the Department of Recreation and Parks.</para>
        <annotation type="Prior Codifications">City Code, 1927, art. 45, §177</annotation>
        <annotation type="Prior Codifications">1950, art. 35, §94</annotation>
        <annotation type="Prior Codifications">1966, art. 26, §97</annotation>
        <annotation type="Prior Codifications">1976/83, art. 26, §104</annotation>
        <annotation type="History">Ord. 12-154</annotation>
        <annotation type="History">Ord. 46-396</annotation>
        <annotation type="History">Ord. 76-139</annotation>
        <annotation type="History">Ord. 15-435</annotation>
      </section>
      <section prefix="§" num="53-13" heading="Permit requirements - Impeding roots.">
        <text>No person may, without first having received a written permit issued by the Department of Transportation, in consultation with the Department of Recreation and Parks, place or maintain upon the ground in any street, lane, or alley, any stone, cement, or other substance or structure that will impede the free entrance of water and air to the roots of any tree without leaving an open space of ground outside the trunk of the tree, in area not less than  32 square feet.</text>
        <annotation type="Prior Codifications">City Code, 1927, art. 45, §181</annotation>
        <annotation type="Prior Codifications">1950, art. 35, §99</annotation>
        <annotation type="Prior Codifications">1966, art. 26, §102</annotation>
        <annotation type="Prior Codifications">1976/83, art. 26, §107</annotation>
        <annotation type="History">Ord. 12-154</annotation>
        <annotation type="History">Ord. 46-396</annotation>
        <annotation type="History">Ord. 76-139</annotation>
        <annotation type="History">Ord. 77-310</annotation>
        <annotation type="History">Ord. 15-435</annotation>
        <annotation type="History" />
      </section>
      <section prefix="§" num="53-14" heading="Permit requirements – Time for completing work.">
        <text>All work covered by a permit issued under this subtitle shall be completed within 30 days from the date shown on the permit.</text>
        <annotation type="Prior Codifications">City Code, 1927, art. 45, §184</annotation>
        <annotation type="Prior Codifications">1950, art. 35, §100</annotation>
        <annotation type="Prior Codifications">1966, art. 26, §103</annotation>
        <annotation type="Prior Codifications">1976/83, art. 26, §108</annotation>
        <annotation type="History">Ord. 12-154</annotation>
        <annotation type="History">Ord. 46-396</annotation>
        <annotation type="History">Ord. 76-139</annotation>
        <annotation type="History">Ord. 15-435</annotation>
      </section>
      <section prefix="§" num="53-15" heading="Tree removal - Street.">
        <para num="(a)" heading="Permit required.">
          <para num="(1)" heading="In general.">Unless otherwise authorized in writing by the Director of the Department of Recreation and parks or the Director’s designee, a person may not remove a tree in or along a public street without first having been issued a written permit to do so by the Department of Recreation and Parks.</para>
          <para num="(2)" heading="Determination.">Within 20 business days of receiving a request for a permit under this section, the Department of Recreation and Parks shall:<para num="(i)">approve, deny, or request additional information regarding  the permit;</para>
            <para num="(ii)">determine whether mitigation under subsection (d) is required; and</para>
            <para num="(iii)">notify the applicant of the Department of Recreation and Parks’ determination.</para>
          </para>
        </para>
        <para num="(b)" heading="Removal by licensed experts.">Any tree removal permitted under this section must be completed by a licensed tree expert in accordance with Title 5, Subtitle 4, Part III {“Tree Experts”} of the State Natural Resources Article.</para>
        <para num="(c)" heading="Notice.">Prior to removing a tree or trees pursuant to a permit issued under this section, the Department of Recreation and Parks must give public notice in the manner described in &lt;cite data-path="7|§53-5"&gt;§ 53-5 {“Public notice of tree removal”}&lt;/cite&gt;.</para>
        <para num="(d)" heading="Mitigation.">
          <para num="(1)" heading="In general.">A tree greater than 1 inch diameter at breast height that has been approved by the Department of Recreation and Parks for removal under this section shall be mitigated as provided in this subsection.</para>
          <para num="(2)" heading="Procedures.">If the Department of Recreation and Parks requires that a tree be mitigated under this section, the mitigation shall be an inch-for-inch replacement, to be measured as follows:<para num="(i)">for the removed tree, at the diameter at breast  height; and</para>
            <para num="(ii)">for the replacement tree, at the caliper  inch.</para>
          </para>
          <para num="(3)" heading="Methods of mitigation.">If the Department of Recreation and Parks requires mitigation under this subsection, the permit holder may accomplish the mitigation by:<para num="(i)">planting replacement trees at the site or sites of the removal, as approved by the Department of Recreation and Parks; or</para>
            <para num="(ii)">if mitigation inches required under this subsection cannot be replanted at the site or sites of removal, planting trees at another site or sites only as approved by the Department of Recreation and Parks.</para>
          </para>
          <para num="(4)" heading="Fee-in-lieu of mitigation.">If a permit holder cannot accomplish mitigation using a method described in paragraph (2) of this subsection, the permit holder shall pay a fee-in-lieu of mitigation to the Director of Finance in an amount approved by the Board of Estimates.</para>
          <para num="(5)" heading="Exemptions from mitigation requirements.">The Department of Recreation and Parks may exempt a tree from the mitigation requirements of this subsection if the Department of Recreation and Parks determines that the tree is:<para num="(i)">dead;</para>
            <para num="(ii)">dying;</para>
            <para num="(iii)">diseased or otherwise infected and contagious; or</para>
            <para num="(iv)">at high risk of death, disease, or failure, as determined by the Baltimore City Forestry Division of the Department of Recreation and Parks.</para>
          </para>
        </para>
        <annotation type="History" />
      </section>
      <section prefix="§" num="53-16" heading="Tree removal - Parks.">
        <para num="(a)" heading="Permit required.">
          <para num="(1)" heading="In general.">Unless otherwise authorized in writing by the Director of the Department of Recreation and parks or the Director’s designee, a person may not remove a tree in a public park without first having been issued a written permit to do so by the Department of Recreation and Parks.</para>
          <para num="(2)" heading="Determination.">Within 20 business days of receiving a request for a permit under this section, the Department of Recreation and Parks shall:<para num="(i)">approve, deny, or request more information regarding the permit;</para>
            <para num="(ii)">determine whether mitigation under subsection (c) is required; and</para>
            <para num="(iii)">notify the applicant of the Department of Recreation and Parks’ determination.</para>
          </para>
        </para>
        <para num="(b)" heading="Removal by licensed experts.">Any tree removal permitted under this section must be completed by a licensed tree expert in accordance with Title 5, Subtitle 4, Part III {“Tree Experts”} of the State Natural Resources Article.</para>
        <para num="(c)" heading="Mitigation.">
          <para num="(1)" heading="In general.">A tree approved by the Department of Recreation and Parks for removal under this section shall be mitigated as provided in this subsection if:<para num="(i)">the tree measures 8 inches or greater in diameter at breast  height; or</para>
            <para num="(ii)">the tree was deliberately planted and measures 1 inch or greater in diameter.</para>
          </para>
          <para num="(2)" heading="Procedures.">If the Department of Recreation and Parks requires that a tree be mitigated under this section, the mitigation shall be an inch-for-inch replacement, to be measured as follows:<para num="(i)">for the removed tree, at the diameter at breast  height; and</para>
            <para num="(ii)">for the replacement tree, at the caliper  inch.</para>
          </para>
          <para num="(3)" heading="Methods of mitigation.">If the Department of Recreation and Parks requires mitigation under this subsection, the permit holder may accomplish the mitigation by:<para num="(i)">planting replacement trees at the site or sites of the removal, as approved by the Department of Recreation and Parks; or</para>
            <para num="(ii)">if mitigation inches required under this subsection cannot be replanted at the site or sites of removal, planting trees at another site or sites only as approved by the Department of Recreation and Parks.</para>
          </para>
          <para num="(4)" heading="Fee-in-lieu of mitigation.">
            <para num="(i)" heading="In general.">If a permit holder cannot accomplish mitigation using a method described in paragraph (3) of this subsection, the permit holder shall pay a fee-in-lieu of mitigation to the Director of Finance.</para>
            <para num="(ii)" heading="Amount.">The fee-in-lieu of mitigation shall be a standard amount or unit, as approved by the Board of Estimates and updated as necessary.</para>
          </para>
          <para num="(5)" heading="Exemptions from mitigation requirements.">The Department of Recreation and Parks may exempt a tree from the mitigation requirements of this subsection if the Department of Recreation and Parks determines that the tree is:<para num="(i)">dead;</para>
            <para num="(ii)">dying;</para>
            <para num="(iii)">diseased or otherwise infected and contagious; or</para>
            <para num="(iv)">at high risk of death, disease, or failure, as determined by the Baltimore City Forestry Division of the Department of Recreation and Parks.</para>
          </para>
        </para>
        <annotation type="History" />
      </section>
      <section prefix="§§" num="53-15 to 53-20" reserved="true" />
      <section prefix="§" num="53-21" heading="Injuring or defacing trees, etc.">
        <para num="(a)" heading="Horses or other animals.">No person shall fasten any horse or other animal to any tree or shrub in any street, lane, or alley, nor shall any person cause or permit any horse or other animal to stand or be near enough to any tree, plant, or shrub to bite or rub against it or in any manner injure or deface the same.</para>
        <para num="(b)" heading="Attaching items.">Nor shall any person attach or place any rope, wire, sign, poster, handbill, or other thing or substance on any tree or shrub in any street, lane, or alley or on any guard or protection of the same.</para>
        <para num="(c)" heading="Injuring, etc., protective devices.">Nor shall any person remove, injure, or misuse any guard or device placed or intended to protect any tree, plant, or shrub  in any park or street.</para>
        <para num="(d)" heading="Injuring, etc., tree and root zone.">Nor shall any person remove, damage, injure, or otherwise harm any tree or the root zone of a tree beneath the ground.</para>
        <annotation type="Prior Codifications">City Code, 1927, art. 45, §178</annotation>
        <annotation type="Prior Codifications">1950, art. 35, §95</annotation>
        <annotation type="Prior Codifications">1966, art. 26, §98</annotation>
        <annotation type="Prior Codifications">1976/83, art. 26, §105</annotation>
        <annotation type="History">Ord. 12-154</annotation>
        <annotation type="History">Ord. 46-396</annotation>
        <annotation type="History" />
      </section>
      <section prefix="§" num="53-22" heading="Breaking or hurting trees, etc.">
        <para num="(a)" heading="In general.">If any person or persons shall willfully break, pull down, hurt, or destroy any tree or trees, or enclosure around the same, which are now or may hereafter be planted in any of the streets, lanes, or alleys of the City, or in any other public grounds within the City, such person or persons:<para num="(1)">shall be subject to a penalty as provided in &lt;cite data-path="|7|§53-26"&gt;§ 53-26 of this subtitle&lt;/cite&gt;; and</para>
          <para num="(2)">may be required to replace any such tree or trees or enclosure around the same.</para>
        </para>
        <para num="(b)" heading="Exception.">Provided always, that nothing herein contained shall be so construed as to prevent the Department of Recreation and Parks from removing any tree or trees, or part thereof, which he may deem so situated or in such condition as to render same unsafe or as to obstruct the footways or roadways.</para>
        <annotation type="Prior Codifications">City Code, 1879, art. 47, §122</annotation>
        <annotation type="Prior Codifications">1893, art. 48, §142</annotation>
        <annotation type="Prior Codifications">1927, art. 32, §59</annotation>
        <annotation type="Prior Codifications">1950, art. 35, §96</annotation>
        <annotation type="Prior Codifications">1966, art. 26, §99</annotation>
        <annotation type="Prior Codifications">1976/83, art. 26, §106</annotation>
        <annotation type="History">Ord. 50-1243</annotation>
        <annotation type="History">Ord. 76-139</annotation>
        <annotation type="History">Ord. 90-576</annotation>
      </section>
      <section prefix="§" num="53-23" heading="Inconsistent ordinances.">
        <text>All ordinances and parts of ordinances heretofore passed which are inconsistent with this subtitle, or any of its provisions, are hereby repealed to the extent of such inconsistency.</text>
        <annotation type="Prior Codifications">City Code, 1927, art. 45, §186</annotation>
        <annotation type="Prior Codifications">1950, art. 35, §102</annotation>
        <annotation type="Prior Codifications">1966, art. 26, §105</annotation>
        <annotation type="Prior Codifications">1976/83, art. 26, §110</annotation>
        <annotation type="History">Ord. 12-154</annotation>
        <annotation type="History">Ord. 46-396</annotation>
      </section>
      <section prefix="§§" num="53-24 to 53-25" reserved="true" />
      <section prefix="§" num="53-26" heading="Penalties.">
        <text>Any person who violates any provision of §§ 53-11, 53-12, 53-13, 53-21, or 53-22 of this subtitle is guilty of a misdemeanor and, on conviction, is subject to a fine of not more than $500 for each offense.</text>
        <annotation type="Prior Codifications">City Code, 1927, art. 45, §187</annotation>
        <annotation type="Prior Codifications">1950, art. 35, §103</annotation>
        <annotation type="Prior Codifications">1966, art. 26, §106</annotation>
        <annotation type="Prior Codifications">1976/83, art. 26, §111</annotation>
        <annotation type="History">Ord. 12-154</annotation>
        <annotation type="History">Ord. 46-396</annotation>
        <annotation type="History">Ord. 76-139</annotation>
        <annotation type="History">Ord. 90-576</annotation>
        <annotation type="History">Ord. 15-435</annotation>
      </section>
    </container>
    <container prefix="Subtitle" num="54" heading="Youth Athletic Protection">
      <section prefix="§" num="54-1" heading="Definitions.">
        <para num="(a)" heading="In general.">In this subtitle, the following terms have the meanings indicated.</para>
        <para num="(b)" heading="Abuse.">“Abuse” has the meaning stated in Title 5, Subtitle 7 of the State Family Law Article {“Definitions: Abuse”}.</para>
        <para num="(c)" heading="Automated external defibrillator.">“Automated external defibrillator” means a medical device, approved by the United States Food and Drug Administration that:<para num="(1)">is capable of recognizing the presence or absence in an individual of ventricular fibrillation and rapid ventricular tachycardia;</para>
          <para num="(2)">is capable of determining, without intervention, whether defibrillation should be performed on an individual;</para>
          <para num="(3)">on determining that defibrillation should be performed, automatically charges and requests delivery of an electrical impulse to an individual’s heart; and</para>
          <para num="(4)">delivers an appropriate electrical impulse to a patient’s heart to perform defibrillation.</para>
        </para>
        <para num="(d)" heading="Coach.">“Coach” means an individual over the age of 18 who, whether paid or unpaid:<para num="(1)">is responsible for leading or assisting in leading a youth sports program; and</para>
          <para num="(2)">has routine and consistent contact throughout an athletic season with youth athletes participating in a youth sports program.</para>
        </para>
        <para num="(e)" heading="Concussion.">“Concussion” means a traumatic injury to the brain causing an immediate, short-lived change in mental status or an alteration of normal consciousness resulting from:<para num="(1)">a fall;</para>
          <para num="(2)">a violent blow to the head or body; or</para>
          <para num="(3)">the shaking or spinning of the head or body.</para>
        </para>
        <para num="(f)" heading="Department.">“Department” means the Baltimore City Department of Recreation and Parks.</para>
        <para num="(g)" heading="Facility.">“Facility” means any outdoor or indoor athletic space under the management of the Department.</para>
        <para num="(h)" heading="Heat Exhaustion.">“Heat exhaustion” means a reaction to excessive heat marked by prostration, weakness, and collapse resulting from dehydration.</para>
        <para num="(i)" heading="Heat stroke.">“Heat stroke” means a severe illness caused by exposure to excessively high temperatures and characterized by:<para num="(1)">severe headache;</para>
          <para num="(2)">high fever with a dry, hot skin;</para>
          <para num="(3)">tachycardia; and</para>
          <para num="(4)">in serious cases, collapse, coma, or death.</para>
        </para>
        <para num="(j)" heading="Neglect.">“Neglect” has the meaning stated in Title 5, Subtitle 7 of the State Family Law Article {“Definitions: Neglect”}.</para>
        <para num="(k)" heading="Sudden cardiac arrest.">“Sudden cardiac arrest” means a condition in which the heart suddenly and unexpectedly stops beating.</para>
        <para num="(l)" heading="Youth athlete.">“Youth athlete” means any individual under the age of 18 who participates in a youth sports program in a non-supervisory role.</para>
        <para num="(m)" heading="Youth sports program.">“Youth sports program” means a program or event, including instruction, practice, or competition, organized for youth athletes under the age of 18 years:<para num="(1)">conducted by the Department; or</para>
          <para num="(2)">conducted by a recreational athletic organization or any other person required to obtain a permit to use a Department facility.</para>
        </para>
        <annotation type="History">Ord.19-305</annotation>
        <annotation type="History">Ord. 22-125</annotation>
      </section>
      <section prefix="§" num="54-2" reserved="true">
        <annotation type="Editor's Notes">See &lt;cite data-path="|general"&gt;City General Provisions Article&lt;/cite&gt;, &lt;cite data-path="|general|1|1|1-104"&gt;§ 1-104&lt;/cite&gt;, for the Code-wide standard uses of mandatory terms  (“must” and “shall”), prohibitory terms (“may not”, “must not”, and “no ... may”), and permissive terms  (“may”).</annotation>
      </section>
      <section prefix="§" num="54-3" heading="Rules and regulations.">
        <text>Subject to Title 4 {“Administrative Procedure Act – Regulations”} of the &lt;cite data-path="|general"&gt;City General Provisions Article&lt;/cite&gt;, the Department must adopt rules and regulations to carry out this subtitle.</text>
        <annotation type="History">Ord.19-305</annotation>
        <annotation type="History">Text Conformed 02/16/21</annotation>
        <annotation type="Editor's Notes">By authority of Ordinance 20-431, Section 5, the Director of Legislative Reference, in consultation with the Law Department, has conformed the text of this section to refer to and reflect the requirements of the recently-enacted Administrative Procedure Act that, effective January 15, 2021, governs the proposal, adoption, and publication of administrative rules and regulations.</annotation>
      </section>
      <section prefix="§" num="54-4" heading="Training required.">
        <para num="(a)" heading="In general.">Before acting as a coach for a youth sports program, an individual must have successfully completed within the last 24 months training approved in advance by the Department in:<para num="(1)">concussion risk and management;</para>
          <para num="(2)">heat exhaustion risk and management;</para>
          <para num="(3)">heat stroke risk and management;</para>
          <para num="(4)">operation of an automated external defibrillator;</para>
          <para num="(5)">sudden cardiac arrest risk and management; and</para>
          <para num="(6)">identification and reporting of abuse and neglect.</para>
        </para>
        <para num="(b)" heading="Permits for facility use.">The Department may not issue a permit to any youth sports program for the use of any Department facility unless the applicant has submitted adequate documentation that all coaches associated with the program have complied with this section.</para>
        <para num="(c)" heading="Department to maintain a list.">In consultation and collaboration with the Baltimore City Department of Health, the Department must maintain a list of training courses or programs that would satisfy the requirements of this section.</para>
        <para num="(d)" heading="Department training program.">The Department may collaborate with the Baltimore City Department of Health to develop its own training program to satisfy the requirements of this section.</para>
        <para num="(e)" heading="Other training programs.">For the purposes of conducting tournaments or other similar sporting events, the Department must accept training substantially equivalent to the training required by this section from any regional, local, state, or national youth sports organization using a Department facility under a permit issued to another youth sports program.</para>
        <annotation type="History">Ord.19-305</annotation>
      </section>
      <section prefix="§" num="54-5" heading="Removal from play.">
        <para num="(a)" heading="Disqualifying medical condition defined.">For the purposes of this section, “disqualifying medical condition” means:<para num="(1)">a concussion;</para>
          <para num="(2)">heat exhaustion;</para>
          <para num="(3)">heat stroke; or</para>
          <para num="(4)">sudden cardiac arrest.</para>
        </para>
        <para num="(b)" heading="In general.">A youth athlete who is suspected of sustaining or undergoing a disqualifying medical condition must be immediately removed from physical participation in any athletic activity by a coach or a member of the coach’s staff.</para>
        <para num="(c)" heading="Return to physical participation.">A youth athlete who has been removed from an athletic activity may not return to physical participation until the youth athlete has been evaluated by a licensed or certified health-care provider and receives written clearance to return to physical participation from that provider.</para>
        <annotation type="History">Ord.19-305</annotation>
      </section>
      <section prefix="§" num="54-6" heading="Automated external defibrillators.">
        <para num="(a)" heading="In general.">The Department must make an automated external defibrillator available to any youth sports program holding a permit for use of any Department facility.</para>
        <para num="(b)" heading="No requirement to assist.">Nothing in this section imposes any duty or obligation on any person to provide assistance with an automated external defibrillator to a victim of a medical emergency.</para>
        <annotation type="History">Ord.19-305</annotation>
      </section>
      <section prefix="§" num="54-7" reserved="true" />
      <section prefix="§" num="54-8" heading="Civil liability of Department, etc.">
        <text>Nothing in this subtitle may be construed to create, establish, expand, reduce, contract, or eliminate any civil liability on the part of the Department, its employees, any youth sports programs, or any coaches.</text>
        <annotation type="History">Ord.19-305</annotation>
      </section>
    </container>
    <container prefix="Subtitles" num="55 to 60" />
  </container>
  <container prefix="Division" num="VI" heading="Miscellaneous">
    <container prefix="Subtitle" num="61" heading="Inactive Quarries">
      <section prefix="§" num="61-1" heading="Fencing required.">
        <para num="(a)" heading="In general.">All quarries which have been abandoned and are not actively operated shall be enclosed by a fence not less than 6 feet in height.</para>
        <para num="(b)" heading="Manner of construction and materials.">Said fence:<para num="(1)">to be constructed in such manner and of such materials as in the judgment of the Commissioner of Housing and Community Development will prevent any persons from entering upon the said quarry; and</para>
          <para num="(2)">to be provided with a gate which shall be securely closed, except at such times when persons duly authorized persons are upon said premises.</para>
        </para>
        <annotation type="Prior Codifications">City Code, 1927, art. 32, §125</annotation>
        <annotation type="Prior Codifications">1950, art. 24, §168</annotation>
        <annotation type="Prior Codifications">1966, art. 19, §105</annotation>
        <annotation type="Prior Codifications">1976/83, art. 19, §123</annotation>
        <annotation type="History">Ord. 24-231</annotation>
        <annotation type="History">Ord. 77-573</annotation>
      </section>
      <section prefix="§" num="61-2" heading="Maintenance of fences.">
        <para num="(a)" heading="Maintenance required.">Said fence shall at all times be kept in repair.</para>
        <para num="(b)" heading="Notice of noncompliance.">The Commissioner of Housing and Community Development is authorized and directed to immediately notify the owners, agents, or persons in possession of any such quarry to comply with the terms hereof.</para>
        <annotation type="Prior Codifications">City Code, 1927, art. 32, §126</annotation>
        <annotation type="Prior Codifications">1950, art. 24, §169</annotation>
        <annotation type="Prior Codifications">1966, art. 19, §106</annotation>
        <annotation type="Prior Codifications">1976/83, art. 19, §124</annotation>
        <annotation type="History">Ord. 24-231</annotation>
        <annotation type="History">Ord. 77-573</annotation>
      </section>
      <section prefix="§" num="61-3" heading="Administrative enforcement.">
        <para num="(a)" heading="Commissioner to correct.">Upon the failure of any such owners, agents, or persons in possession of any abandoned quarry to comply with the terms hereof within 10 days after being notified by the Commissioner of Housing and Community Development, the Commissioner shall forthwith enter upon the said premises and erect a fence or repair an existing fence, as the case may be.</para>
        <para num="(b)" heading="Costs lien on property.">The Commissioner is further directed to certify to the collector of taxes the costs of erecting such fence or of making such repairs which shall be a lien upon the property and shall be collected in the same manner as taxes.</para>
        <annotation type="Prior Codifications">City Code, 1927, art. 32, §127</annotation>
        <annotation type="Prior Codifications">1950, art. 24, §170</annotation>
        <annotation type="Prior Codifications">1966, art. 19, §107</annotation>
        <annotation type="Prior Codifications">1976/83, art. 19, §125</annotation>
        <annotation type="History">Ord. 24-231</annotation>
        <annotation type="History">Ord. 77-573</annotation>
      </section>
      <section prefix="§" num="61-4" heading="Penalties.">
        <text>Any owners, agents, or persons in possession of any such quarry who shall fail to comply with the terms of this subtitle within 10 days after being notified by the Commissioner of Housing and Community Development to fence any such quarry or repair an existing fence shall be guilty of a misdemeanor and, upon conviction, shall be imprisoned for not more than 30 days or fined not more than $100 or both, said fine or fines to be collected and disposed of as other fines.</text>
        <annotation type="Prior Codifications">City Code, 1927, art. 32, §128</annotation>
        <annotation type="Prior Codifications">1950, art. 24, §171</annotation>
        <annotation type="Prior Codifications">1966, art. 19, §108</annotation>
        <annotation type="Prior Codifications">1976/83, art. 19, §126</annotation>
        <annotation type="History">Ord. 24-231</annotation>
        <annotation type="History">Ord. 77-573</annotation>
      </section>
    </container>
    <container prefix="Subtitle" num="62" heading="Plastic Bag Reduction">
      <section prefix="§" num="62-1" heading="Definitions.">
        <para num="(a)" heading="In general.">In this subtitle, the following words have the meanings indicated.</para>
        <para num="(b)" heading="Dealer.">
          <para num="(1)" heading="“Person” defined.">In this subsection:<para num="(i)">“person” has the meaning stated in &lt;cite data-path="|general|1|1|1-107|(a)"&gt;§ 1-107(a) {“Person: In general”}&lt;/cite&gt; of the City Code’s &lt;cite data-path="|general"&gt;General Provisions Article&lt;/cite&gt;; but</para>
            <para num="(ii)">notwithstanding § 1-107(b) {“Person: Exclusion”} of that article, “person” also includes a governmental entity or an instrumentality or unit of a governmental entity.</para>
          </para>
          <para num="(2)" heading="“Dealer” defined.">
            <para num="(i)" heading="In general.">“Dealer” means any person engaged in the retail sale of goods.</para>
            <para num="(ii)" heading="Inclusions.">“Dealer” includes any:<para num="(A)">supermarket;</para>
              <para num="(B)">convenience store;</para>
              <para num="(C)">restaurant;</para>
              <para num="(D)">shop;</para>
              <para num="(E)">service station; or</para>
              <para num="(F)">other sales outlet.</para>
            </para>
          </para>
        </para>
        <para num="(c)" heading="Plastic checkout bag.">
          <para num="(1)">“Plastic checkout bag” means any plastic bag that is:<para num="(i)">supplied by a dealer at the point of sale, pickup, or delivery to carry purchased items; and</para>
            <para num="(ii)">less than 4 mils thick.</para>
          </para>
          <para num="(2)">“Plastic checkout bag” does not include a compostable plastic bag that:<para num="(i)">is certified and labeled as meeting the ASTM D6400 standard specification by a recognized verification entity; and</para>
            <para num="(ii)">is capable of undergoing biological decomposition in a compost site such that the material breaks down into carbon dioxide, water, inorganic compounds, and biomass at a rate consistent with known compostable materials.</para>
          </para>
        </para>
        <annotation type="History">Ord. 20-337</annotation>
        <annotation type="History">Ord. 22-125</annotation>
      </section>
      <section prefix="§" num="62-2" reserved="true" />
      <section prefix="§" num="62-3" heading="Prohibited conduct.">
        <text>Except as provided in &lt;cite data-path="|7|§62-4"&gt;§ 62-4 {“Exemption: Bags for certain products”} of this subtitle&lt;/cite&gt;, no dealer may supply customers with plastic checkout bags.</text>
        <annotation type="History">Ord. 20-337</annotation>
      </section>
      <section prefix="§" num="62-4" heading="Exemption: Bags for certain products.">
        <text>This subtitle does not apply to a plastic checkout bag solely used to contain:</text>
        <para num="(1)">fresh fish and fresh fish products;</para>
        <para num="(2)">fresh meat and fresh meat products;</para>
        <para num="(3)">fresh poultry and fresh poultry products;</para>
        <para num="(4)">otherwise unpackaged fruits, nuts, or vegetables;</para>
        <para num="(5)">otherwise unpackaged confectionery;</para>
        <para num="(6)">otherwise unpackaged fresh cheese;</para>
        <para num="(7)">otherwise unpackaged baked goods;</para>
        <para num="(8)">ice;</para>
        <para num="(9)">food and goods obtained at a farmers’ market;</para>
        <para num="(10)">prescription drugs obtained from a pharmacy;</para>
        <para num="(11)">newspapers; or</para>
        <para num="(12)">dry-cleaned goods.</para>
        <annotation type="History">Ord. 20-337</annotation>
      </section>
      <section prefix="§§" num="62-5 to 62-6" reserved="true" />
      <section prefix="§" num="62-7" heading="Data Reporting.">
        <text>The Baltimore City Department of Information Technology, using available data from the 311 system and the Environmental Control Board, shall publish data on the Open Baltimore web portal that reflects:</text>
        <para num="(1)">the number of complaints received by the City of Baltimore under this subtitle; and</para>
        <para num="(2)">the number of citations issued under this subtitle.</para>
        <annotation type="History">Ord. 20-337</annotation>
      </section>
      <section prefix="§§" num="62-8 to 62-9" reserved="true" />
      <section prefix="§" num="62-10" heading="Enforcement by citation.">
        <para num="(a)" heading="In general.">In addition to any other civil or criminal remedy or enforcement procedure, this subtitle may be enforced by issuance of an environmental citation as authorized by City Code &lt;cite data-path="|1"&gt;Article 1&lt;/cite&gt;, subtitle 40 {“Environmental Control Board”}.</para>
        <para num="(b)" heading="Process not exclusive.">The issuance of an environmental citation does not preclude pursuing any other civil or criminal remedy or enforcement action authorized by law.</para>
        <annotation type="History">Ord. 20-337</annotation>
      </section>
      <section prefix="§" num="62-11" heading="Criminal penalties.">
        <para num="(a)" heading="In general.">Any dealer who violates any provision of this subtitle after having twice received an environmental citation, each resulting in any final disposition other than not guilty, is guilty of a misdemeanor and, on conviction, is subject to a fine of not more than $1,000 for each offense.</para>
        <para num="(b)" heading="Each bag a separate offense.">Each plastic checkout bag supplied to a customer in violation of this subtitle is a separate offense.</para>
        <annotation type="History">Ord. 20-337</annotation>
      </section>
    </container>
  </container>
</baltimore-city-law>