<baltimore-city-law heading="Subtitle 22 – Stormwater Management Plans">
  <section prefix="§" num="22-1" heading="Phased plans required.">
    <text>Except as otherwise expressly provided in this Division II, no person may develop any land unless:</text>
    <para num="(1)">the project is a single-lot residential construction that establishes stormwater management measures in accordance with a standard stormwater management plan prepared in accordance with the City’s Design Guidelines and approved by the Department; or</para>
    <para num="(2)">the person:<para num="(i)">establishes stormwater management measures that control or manage runoff
from the development; and</para>
      <para num="(ii)">incorporates those measures into phased stormwater management plans approved by the Department.</para>
    </para>
    <annotation type="History">Ord. 02-367</annotation>
    <annotation type="History">Ord. 10-277</annotation>
  </section>
  <section prefix="§" num="22-2" heading="Design and construction.">
    <text>These stormwater management measures must:</text>
    <para num="(1)">meet the requirements of the State’s Design Manual, this Division II, and the City’s Design Guidelines; and</para>
    <para num="(2)">be constructed according to:<para num="(i)">an approved plan for new development; or</para>
      <para num="(ii)">the policies stated in &lt;cite data-path="|7|§23-7"&gt;§ 23-7 of this Division II&lt;/cite&gt; for redevelopment.</para>
    </para>
    <annotation type="History">Ord. 02-367</annotation>
    <annotation type="History">Ord. 10-277</annotation>
  </section>
  <section prefix="§" num="22-3" heading="Minimum control requirements.">
    <para num="(a)" heading="In general.">The minimum control requirements for these management measures are as provided in this section and the State’s Design Manual.</para>
    <para num="(b)" heading="Volume sizing criteria.">
      <para num="(1)">The criteria in the State’s Design Manual for environmental site design to the maximum extent practicable and the use of environmental site design planning techniques and treatment practices must be exhausted before any structural best management practice or alternative practice is implemented.</para>
      <para num="(2)">Stormwater management plans for development projects subject to this Division II must be designed using environmental site design sizing criteria, recharge volume, water quality volume, and channel protection storage volume criteria according to the State’s Design Manual. The maximum-extent-practicable standard is met when channel stability is maintained, predevelopment groundwater recharge is replicated, nonpoint source pollution is minimized, and structural stormwater management practices or alternative practices are used only if determined to be absolutely necessary.</para>
    </para>
    <para num="(c)" heading="10-year frequency storm event.">Runoff from the 10-year frequency storm event must be controlled in accordance with the State’s Design Manual if the Department determines that additional stormwater management is necessary because historical flooding problems exist and downstream floodplain development and conveyance system design cannot be controlled.</para>
    <para num="(d)" heading="Additional control requirements.">The Department may require more than the minimum control requirements of the State’s Design Manual if:<para num="(1)">hydrologic or topographic conditions warrant; or</para>
      <para num="(2)">flooding, stream channel erosion, or water quality problems exist downstream from a proposed project.</para>
    </para>
    <para num="(e)" heading="Alternative minimum controls.">With the approval of the State Water Management Administration, the Department may adopt alternative minimum control requirements that will:<para num="(1)">implement environmental site design to the maximum extent practicable; and</para>
      <para num="(2)">control flood damages, accelerated stream erosion, water quality, and sedimentation.</para>
    </para>
    <para num="(f)" heading="Consistency with FHMA plans.">Where applicable, stormwater management and development plans must be consistent with watershed management plans and flood management plans approved by the State Water Management Administration under the Flood Hazard Management Act of 1976.</para>
    <annotation type="History">Ord. 02-367</annotation>
    <annotation type="History">Ord. 10-277</annotation>
  </section>
  <section prefix="§" num="22-4" heading="Environmental site design; Structural practices.">
    <para num="(a)" heading="In general.">
      <para num="(1)">In designing stormwater management measures, the following must be used, either alone or in combination:<para num="(i)">environmental site design techniques and practices; and</para>
        <para num="(ii)">structural practices.</para>
      </para>
      <para num="(2)">The applicant must demonstrate that environmental site design has been implemented to the maximum extent practicable before the use of a structural best management practice or alternative practice may be considered in developing the stormwater management plan.</para>
      <para num="(3)">Stormwater management measures, their selection, basic design criteria, methodologies, and construction specifications:<para num="(i)">must comply with the State’s Design Manual and the City’s Design Guidelines; and</para>
        <para num="(ii)">are subject to approval of the Department and the State Water Management Administration.</para>
      </para>
      <para num="(4)">Environmental site design techniques and practices and structural stormwater management measures used to satisfy the minimum control requirements of &lt;cite data-path="|7|§22-3"&gt;§ 22-3 of this subtitle&lt;/cite&gt;:<para num="(i)">must have easements, as described in &lt;cite data-path="|7|§25-1|(b)|(1)"&gt;§ 25-1(b)(1) of this Division II&lt;/cite&gt;, recorded in the land records of Baltimore City;</para>
        <para num="(ii)">must have a recorded inspection and maintenance agreement, as described in &lt;cite data-path="|7|§27-3"&gt;§ 27-3 of this Division II&lt;/cite&gt;; and</para>
        <para num="(iii)">may not be altered without the Department’s prior approval.</para>
      </para>
    </para>
    <para num="(b)" heading="Environmental site design planning techniques and practices.">
      <para num="(1)">The following planning techniques must be applied according to the State’s Design Manual to satisfy the applicable minimum control requirements of &lt;cite data-path="|7|§22-3"&gt;§ 22-3 of this subtitle&lt;/cite&gt;:<para num="(i)">preserving and protecting natural resources;</para>
        <para num="(ii)">conserving natural drainage patterns;</para>
        <para num="(iii)">minimizing impervious area;</para>
        <para num="(iv)">reducing runoff volume;</para>
        <para num="(v)">using environmental site design practices to maintain 100% of the annual predevelopment groundwater recharge volume;</para>
        <para num="(vi)">using green roofs, permeable pavement, reinforced turf, and other alternative surfaces;</para>
        <para num="(vii)">limiting soil disturbance, mass grading, and compaction;</para>
        <para num="(viii)">clustering development; and</para>
        <para num="(ix)">other practices approved by the Department.</para>
      </para>
      <para num="(2)">The following environmental site design treatment practices must be designed according to the State’s Design Manual and the City’s Design Guidelines to satisfy the applicable minimum control requirements established in &lt;cite data-path="|7|§22-3"&gt;§ 22-3 of this subtitle&lt;/cite&gt;:<para num="(i)">disconnection of rooftop runoff;</para>
        <para num="(ii)">disconnection of non-rooftop runoff;</para>
        <para num="(iii)">sheetflow to conservation areas;</para>
        <para num="(iv)">rainwater harvesting;</para>
        <para num="(v)">submerged gravel wetlands;</para>
        <para num="(vi)">landscape infiltration;</para>
        <para num="(vii)">infiltration berms;</para>
        <para num="(viii)">dry wells;</para>
        <para num="(ix)">micro-bioretention;</para>
        <para num="(x)">rain gardens;</para>
        <para num="(xi)">swales;</para>
        <para num="(xii)">enhanced filters; and</para>
        <para num="(xiii)">other practices approved by the Department.</para>
      </para>
      <para num="(3)">The use of environmental site design planning techniques and treatment practices may not conflict with existing State or local laws, ordinances, regulations, or policies.</para>
    </para>
    <para num="(c)" heading="Structural stormwater management measures.">
      <para num="(1)">The following structural stormwater management practices must be designed to satisfy the applicable minimum control requirements of &lt;cite data-path="|7|§22-3"&gt;§ 22-3 of this subtitle&lt;/cite&gt;.<para num="(i)">stormwater management ponds;</para>
        <para num="(ii)">stormwater management wetlands;</para>
        <para num="(iii)">stormwater management infiltration;</para>
        <para num="(iv)">stormwater management filtering systems;</para>
        <para num="(v)">stormwater management open channel systems; and</para>
        <para num="(vi)">other practices provided in the State’s Design Manual.</para>
      </para>
      <para num="(2)">In selecting structural practices, consideration must be given to the performance criteria specified in the State’s Design Manual for:<para num="(i)">general feasibility;</para>
        <para num="(ii)">conveyance;</para>
        <para num="(iii)">pretreatment;</para>
        <para num="(iv)">treatment and geometry;</para>
        <para num="(v)">environment and landscaping; and</para>
        <para num="(vi)">maintenance.</para>
      </para>
      <para num="(3)">Structural practices must accommodate the unique hydrologic or geologic regions of the site.</para>
    </para>
    <para num="(d)" heading="Alternative practices.">
      <para num="(1)">Alternative structural and nonstructural stormwater management practices may be used for new development water quality control if they:<para num="(i)">meet the performance criteria established in the State’s Design Manual; and</para>
        <para num="(ii)">are approved by the State Water Management Administration.</para>
      </para>
      <para num="(2)">Practices used for redevelopment projects must be approved by the Department.</para>
    </para>
    <para num="(e)" heading="Impact analysis.">
      <para num="(1)">For the purposes of modifying the minimum control requirements or design criteria, the applicant must submit to the Department an analysis of the impacts of stormwater flows downstream in the watershed.</para>
      <para num="(2)">The analysis must include the hydrologic and hydraulic calculations necessary to determine the impact of hydrograph timing modifications of the proposed development upon a dam, highway, structure, or natural point of restricted streamflow.</para>
      <para num="(3)">The point of investigation is to be established, with the Department’s concurrence, downstream of the first downstream tributary whose drainage area equals or exceeds the contributing area to the project or stormwater management facility.</para>
    </para>
    <annotation type="History">Ord. 02-367</annotation>
    <annotation type="History">Ord. 10-277</annotation>
  </section>
  <section prefix="§" num="22-5" heading="Contents of plan.">
    <para num="(a)" heading="In general.">
      <para num="(1)">For any proposed development, the applicant must submit phased stormwater management plans to the Department for review and approval.</para>
      <para num="(2)">At a minimum, plans must be submitted for the concept, site development, and final stormwater management construction phases of project design.</para>
      <para num="(3)">Each plan must:<para num="(i)">include the minimum content specified in &lt;cite data-path="|7|§22-3"&gt;§ 22-3 {“Minimum control requirements”} of this subtitle&lt;/cite&gt;; and</para>
        <para num="(ii)">meet the requirements of the State’s Design Manual, the City’s Design Guidelines, and &lt;cite data-path="|7|§22-4"&gt;§ 22-4 {“Environmental site design; Structural practices”} of this subtitle&lt;/cite&gt;.</para>
      </para>
    </para>
    <para num="(b)" heading="Concept plan.">
      <para num="(1)">The applicant must submit a concept plan that provides sufficient information for an initial assessment of the proposed project and whether stormwater management can be provided according to &lt;cite data-path="|7|§22-4"&gt;§ 22-4 {“Environmental site design; Structural practices”} of this subtitle&lt;/cite&gt; and the State’s Design Manual.</para>
      <para num="(2)">Plans submitted for concept approval must include the following, minimum information:<para num="(i)">a map that shows, at a scale specified by the Department:<para num="A.">site location;</para>
          <para num="B.">existing natural features;</para>
          <para num="C.">water and other sensitive resources;</para>
          <para num="D.">topography; and</para>
          <para num="E.">natural drainage patterns;</para>
        </para>
        <para num="(ii)">the anticipated location of all:<para num="A.">impervious areas;</para>
          <para num="B.">buildings;</para>
          <para num="C.">roadways;</para>
          <para num="D.">parking;</para>
          <para num="E.">sidewalks;</para>
          <para num="F.">utilities; and</para>
          <para num="G.">other site improvements;</para>
        </para>
        <para num="(iii)">the location of:<para num="A.">the proposed limit of disturbance;</para>
          <para num="B.">erodible soils;</para>
          <para num="C.">steep slopes; and</para>
          <para num="D.">areas to be protected during construction;</para>
        </para>
        <para num="(iv)">preliminary estimates of:<para num="A.">stormwater management requirements;</para>
          <para num="B.">the selection and location of environmental site design practices to be used; and</para>
          <para num="C.">the location of all points of discharge from the site;</para>
        </para>
        <para num="(v)">a narrative that supports the concept design and describes how environmental site design will be implemented to the maximum extent practicable; and</para>
        <para num="(vi)">any other information the Department requires.</para>
      </para>
    </para>
    <para num="(c)" heading="Site development plan.">
      <para num="(1)">After approval of the concept plan, the applicant must submit, unless exempted by the Department, at the Department’s discretion, site development plans that reflect comments received during the previous review phase.</para>
      <para num="(2)">Plans submitted for site development approval must be of sufficient detail to allow site development to be reviewed.</para>
      <para num="(3)">These plans must include the following, minimum information:<para num="(i)">all information provided during the concept plan review phase;</para>
        <para num="(ii)">final site layout, including:<para num="A.">exact impervious area locations and acreages;</para>
          <para num="B.">proposed topography;</para>
          <para num="C.">delineated drainage areas at all points of discharge from the site; and</para>
          <para num="D.">stormwater volume computations for environmental site design practices and quantity control structures;</para>
        </para>
        <para num="(iii)">a narrative that:<para num="A.">supports the site development design;</para>
          <para num="B.">describes how environmental site design will be used to meet the minimum control requirements; and</para>
          <para num="C.">justifies any proposed structural stormwater management or alternative practice measure; and</para>
        </para>
        <para num="(iv)">any other information the Department requires.</para>
      </para>
    </para>
    <para num="(d)" heading="Final stormwater management plans.">
      <para num="(1)">After site development approval, the applicant must submit final stormwater management plans that reflect the comments received during the previous review phase.</para>
      <para num="(2)">Stormwater management plans submitted for final approval must be in the form of construction drawings, in sufficient detail to allow all approvals and permits to be issued, and accompanied by a report that includes sufficient information to evaluate the effectiveness of the proposed runoff control design.</para>
    </para>
    <para num="(e)" heading="Waivers and variances.">The plan must be accompanied by an application for any waiver or variance sought under Subtitle 23 or Subtitle 24.</para>
    <annotation type="History">Ord. 02-367</annotation>
    <annotation type="History">Ord. 10-277</annotation>
    <annotation type="History">Ord. 13- 095</annotation>
  </section>
  <section prefix="§" num="22-6" heading="Report for final plan.">
    <text>The report submitted for final stormwater management plan approval must contain the following, minimum information:</text>
    <para num="(1)">a brief narrative description of the project;</para>
    <para num="(2)">geotechnical investigations, including soil maps, borings, site specific recommendations, and any additional information necessary to evaluate the final stormwater management design;</para>
    <para num="(3)">descriptions of all water courses, impoundments, and wetlands on or adjacent to the site or into which stormwater directly flows;</para>
    <para num="(4)">drainage area maps that show pre- development and post-development runoff flow path segmentation and land use;</para>
    <para num="(5)">hydrologic computations of the applicable environmental site design and unified sizing criteria, according to the State’s Design Manual, for all points of discharge from the site;</para>
    <para num="(6)">hydraulic computations for all environmental site design practices and structural stormwater management measures to be used;</para>
    <para num="(7)">structural computations;</para>
    <para num="(8)">volume sizing computations, according to the State’s Design Manual, that support the final stormwater management design; and</para>
    <para num="(9)">any other information that the Department requires.</para>
    <annotation type="History">Ord. 02-367</annotation>
    <annotation type="History">Ord. 10-277</annotation>
  </section>
  <section prefix="§" num="22-7" heading="Construction drawings for final plan.">
    <para num="(a)" heading="In general.">The construction drawings submitted for final stormwater management plan approval must include the following:<para num="(1)">a vicinity map;</para>
      <para num="(2)">a topography survey that shows existing and proposed contours, including the area necessary to determine downstream analysis for proposed stormwater management facilities;</para>
      <para num="(3)">any proposed improvements, including the location of buildings or other structures, impervious surfaces, storm drainage facilities, and all grading;</para>
      <para num="(4)">the location of existing and proposed structures and utilities;</para>
      <para num="(5)">any easements and rights-of-way;</para>
      <para num="(6)">the delineation, if applicable, of:<para num="(i)">the 100-year floodplain; and</para>
        <para num="(ii)">any on-site wetlands;</para>
      </para>
      <para num="(7)">structural and construction details, including representative cross sections, for all components of:<para num="(i)">the proposed drainage system or systems; and</para>
        <para num="(ii)">stormwater management facilities;</para>
      </para>
      <para num="(8)">all necessary construction specifications;</para>
      <para num="(9)">a sequence of construction;</para>
      <para num="(10)">data for:<para num="(i)">total site area;</para>
        <para num="(ii)">disturbed area;</para>
        <para num="(iii)">new impervious area; and</para>
        <para num="(iv)">total impervious area;</para>
      </para>
      <para num="(11)">a table that shows the environmental site design and unified sizing criteria volumes required by the State’s Design Manual;</para>
      <para num="(12)">a table of materials to be used for stormwater management facility planting;</para>
      <para num="(13)">all soil boring logs and locations;</para>
      <para num="(14)">a maintenance inspection and maintenance activity schedule;</para>
      <para num="(15)">a proposed construction and inspection schedule;</para>
      <para num="(16)">an as-built certification signature block, to be executed after the project is completed; and</para>
      <para num="(17)">any other information that the Department requires.</para>
    </para>
    <para num="(b)" heading="Certification of compliance.">The applicant must certify on the drawings that all grading, drainage, construction, and development will be done in strict accordance with the approved plan.</para>
    <annotation type="History">Ord. 02-367</annotation>
    <annotation type="History">Ord. 10-277</annotation>
  </section>
  <section prefix="§" num="22-8" heading="Preparation of plan.">
    <para num="(a)" heading="In general.">The design of all stormwater management plans must be prepared by a professional engineer, professional land surveyor, or landscape architect licensed in the State.</para>
    <para num="(b)" heading="Professional engineer only.">If stormwater best management practices require a dam safety permit from the Maryland Department of the Environment or small pond approval from the City, the plan must be prepared by a professional engineer licensed in the State.</para>
    <annotation type="History">Ord. 02-367</annotation>
    <annotation type="History">Ord. 10-277</annotation>
  </section>
  <section prefix="§" num="22-9" heading="Easements for runoff.">
    <para num="(a)" heading="Easement.">If a stormwater management plan involves directing some or all runoff from the site, the applicant is responsible for obtaining from adjacent property owners any needed easements or property interests for water flow.</para>
    <para num="(b)" heading="Plan creates no right.">Approval of a stormwater management plan does not create or affect any right to direct runoff onto adjacent property without that property owner’s permission.</para>
    <annotation type="History">Ord. 02-367</annotation>
    <annotation type="History">Ord. 10-277</annotation>
  </section>
  <section prefix="§" num="22-10" heading="Review and approval of plan.">
    <para num="(a)" heading="Review and comment.">
      <para num="(1)">The Department must perform a comprehensive review of the plans for each phase of site design to determine compliance with this Division II.</para>
      <para num="(2)">For each plan phase, coordinated comments will be provided that reflect input from all appropriate agencies, including Planning, Zoning, and Public Works.</para>
      <para num="(3)">At each phase of project design, comments from the Department and other appropriate agencies must be addressed by the applicant and approval received before subsequent submissions.</para>
    </para>
    <para num="(b)" heading="Conditions.">In approving a plan, the Department may impose any conditions that it considers necessary or appropriate to:<para num="(1)">ensure compliance with this Division II; and</para>
      <para num="(2)">preserve the public health and safety.</para>
    </para>
    <para num="(c)" heading="Notification.">After the Department has completed its comprehensive review for each phase of site design, the Department must notify the applicant of:<para num="(1)">the Department’s approval of the plan;</para>
      <para num="(2)">the Department’s disapproval of the plan, together with:<para num="(i)">the reasons for disapproval; and</para>
        <para num="(ii)">any modifications that the Department requires for approval; or</para>
      </para>
      <para num="(3)">if no decision has yet been made:<para num="(i)">the status of the review process; and</para>
        <para num="(ii)">the anticipated date of completion.</para>
      </para>
    </para>
    <para num="(d)" heading="Endorsement.">A stormwater management plan is not valid until the plan has been endorsed and dated by the Department.</para>
    <annotation type="History">Ord. 02-367</annotation>
    <annotation type="History">Ord. 10-277</annotation>
  </section>
</baltimore-city-law>