§ 23-5 Phased development projects.

Current through 2026-07-17. Source: City of Balt., Md., Ord. 26-129. Published by the Baltimore City Department of Legislative Reference.

Balt., Md., Code art. 7, § 23-5 (2026)

§ 23-5 Phased development projects.Copy Citation

The Department may grant a quantitative and qualitative control waiver for a phased development project if:
(1)
by May 4, 2010, a stormwater system has been constructed that is designed to meet:
(i)
the regulatory requirements for stormwater adopted in 2000 by the Maryland Department of the Environment; and
(ii)
the requirements of this Division II, as in effect on July 27, 2002; or
(2)
for future phases of a phased development project that are constructed after May 4, 2010:
(i)
the regulatory requirements for stormwater adopted in 2009 by the Maryland Department of the Environment cannot be met; and
(ii)
the applicant demonstrates that all reasonable efforts were made to incorporate environmental site design into these phases of the development.