  <section prefix="§" num="26-1" heading="By whom conducted.">
    <text>All inspections under this Division II must be:</text>
    <para num="(1)">conducted by an authorized representative of the Department; or</para>
    <para num="(2)">certified by a professional engineer licensed in this State.</para>
    <annotation type="History">Ord. 02-367</annotation>
    <annotation type="History">Ord. 10-277</annotation>
  </section>
  <section prefix="§" num="26-2" heading="Notices by applicant.">
    <text>The applicant must notify the Department:</text>
    <para num="(1)">at least 48 hours before starting any work in conjunction with site development;</para>
    <para num="(2)">at least 48 hours before starting any work in conjunction with the stormwater management plan; and</para>
    <para num="(3)">on completion of the project.</para>
    <annotation type="History">Ord. 02-367</annotation>
    <annotation type="History">Ord. 10-277</annotation>
  </section>
  <section prefix="§" num="26-3" heading="Inspections during construction.">
    <para num="(a)" heading="In general.">At a minimum, regular inspections must be made and documented, at the stages of construction specified in this section, for each environmental site design planning technique and practice and each structural and nonstructural stormwater management practice.</para>
    <para num="(b)" heading="Ponds.">For ponds:<para num="(1)">On completion of excavation to sub-foundation and, when required, installation of structural supports or reinforcement for structures, including:<para num="(i)">core trenches for structural embankments;</para>
        <para num="(ii)">inlet and outlet structures, anti-seep collars or diaphragms, and watertight connectors on pipes; and</para>
        <para num="(iii)">trenches for enclosed storm drainage facilities;</para>
      </para>
      <para num="(2)">during placement of structural fill or concrete and installation of piping and catch basins;</para>
      <para num="(3)">during backfill of foundations and trenches;</para>
      <para num="(4)">during embankment construction; and</para>
      <para num="(5)">on completion of final grading and establishment of permanent stabilization.</para>
    </para>
    <para num="(c)" heading="Wetlands.">For wetlands:<para num="(1)">at the stages specified in subsection (b) of this section for pond construction;</para>
      <para num="(2)">during and after wetland reservoir area planting; and</para>
      <para num="(3)">during the second growing season to verify a vegetation survival rate of at least 50%.</para>
    </para>
    <para num="(d)" heading="Infiltration trenches.">For infiltration trenches:<para num="(1)">during excavation to subgrade;</para>
      <para num="(2)">during placement and backfill of underdrain systems and observation wells;</para>
      <para num="(3)">during placement of geotextiles and all filter media;</para>
      <para num="(4)">during construction of appurtenant conveyance systems, such as diversion structures, pre-filters and filters, inlets, outlets, and flow distribution structures; and</para>
      <para num="(5)">on completion of final grading and establishment of permanent stabilization.</para>
    </para>
    <para num="(e)" heading="Infiltration basins.">For infiltration basins:<para num="(1)">at the stages specified in subsection (b) of this section for pond construction; and</para>
      <para num="(2)">during placement and backfill of underdrain systems.</para>
    </para>
    <para num="(f)" heading="Filtering systems.">For filtering systems:<para num="(1)">during excavation to subgrade;</para>
      <para num="(2)">during placement and backfill of underdrain systems;</para>
      <para num="(3)">during placement of geotextiles and all filter media;</para>
      <para num="(4)">during construction of appurtenant conveyance systems, such as flow diversion structures, pre-filters and filters, inlets, outlets, orifices, and flow distribution structures; and</para>
      <para num="(5)">on completion of final grading and establishment of permanent stabilization.</para>
    </para>
    <para num="(g)" heading="Open channel systems.">For open channel systems:<para num="(1)">during excavation to subgrade;</para>
      <para num="(2)">during placement and backfill of underdrain systems for dry swales;</para>
      <para num="(3)">during installation of diaphragms, check dams, or weirs; and</para>
      <para num="(4)">on completion of final grading and establishment of permanent stabilization.</para>
    </para>
    <para num="(h)" heading="Environmental site design and nonstructural practices.">For environmental site design and nonstructural practices:<para num="(1)">on completion of final grading;</para>
      <para num="(2)">on establishment of permanent stabilization; and</para>
      <para num="(3)">before issuance of an occupancy permit under the &lt;cite data-path="|building-codes|II"&gt;Building Code&lt;/cite&gt; and a use permit under the Zoning Code.</para>
    </para>
    <annotation type="History">Ord. 02-367</annotation>
    <annotation type="History">Ord. 10-277</annotation>
  </section>
  <section prefix="§" num="26-4" heading="Inspection reports.">
    <para num="(a)" heading="Reports required.">Written reports must be made of all inspections conducted during construction.</para>
    <para num="(b)" heading="Scope.">Each inspection report must specify:<para num="(1)">the date and location of the inspection;</para>
      <para num="(2)">whether the construction complies with the approved stormwater management plan;</para>
      <para num="(3)">any variations from the approved construction specifications;</para>
      <para num="(4)">any violations found; and</para>
      <para num="(5)">any other information that the Department requires.</para>
    </para>
    <para num="(c)" heading="Notice to applicant.">The Department must provide the applicant with the results of each inspection report as soon as possible after the inspection.</para>
    <annotation type="History">Ord. 02-367</annotation>
    <annotation type="History">Ord. 10-277</annotation>
  </section>
  <section prefix="§" num="26-5" heading="Work stoppage pending inspection.">
    <text>At the completion of each construction stage for which an inspection is required, no further work may be done until the Department inspects and approves the work completed to date.</text>
    <annotation type="History">Ord. 02-367</annotation>
  </section>
  <section prefix="§" num="26-6" heading="Final inspection.">
    <text>A final inspection must be conducted after construction is completed.</text>
    <annotation type="History">Ord. 02-367</annotation>
  </section>
  <section prefix="§" num="26-7" heading="As-built certification.">
    <para num="(a)" heading="Required.">Once construction is complete, the applicant must submit to the Department an as-built plan certification by a professional engineer or professional land surveyor licensed in the State.</para>
    <para num="(b)" heading="Tenor.">The certification must certify that the completed stormwater management practices and conveyance systems comply with the specifications contained in the approved plan.</para>
    <para num="(c)" heading="Contents.">The certification must include:<para num="(1)">a set of drawings that compare the approved stormwater management plan with what has been constructed; and</para>
      <para num="(2)">any other information that the Department requires.</para>
    </para>
    <annotation type="History">Ord. 02-367</annotation>
    <annotation type="History">Ord. 10-277</annotation>
  </section>
  <section prefix="§" num="26-8" heading="Notice to State Administration.">
    <para num="(a)" heading="In general.">For each stormwater management practice completed, the Department must submit a notice of construction to the State Water Management Administration.</para>
    <para num="(b)" heading="When and how.">The notice must be submitted:<para num="(1)">within 45 days of construction completion; and</para>
      <para num="(2)">on the form that the Administration supplies.</para>
    </para>
    <para num="(c)" heading="Contents.">The notice must report, on a site-by-site basis, the type, number, total drainage area, and total impervious area treated by all environmental site design techniques and practices and structural stormwater management practices.</para>
    <annotation type="History">Ord. 02-367</annotation>
    <annotation type="History">Ord. 10-277</annotation>
  </section>