# § 26-2 Notices by applicant.

Current through 2026-07-17. Source: City of Balt., Md., Ord. 26-129. Published by the Baltimore City Department of Legislative Reference.

## § 26-2 Notices by applicant.

Balt., Md., Code art. 7, § 26-2 (2026)

The applicant must notify the Department:

(1) at least 48 hours before starting any work in conjunction with site development;

(2) at least 48 hours before starting any work in conjunction with the stormwater management plan; and

(3) on completion of the project.

*History: Ord. 02-367*