§ 26-8 Notice to State Administration.
Current through 2026-07-17. Source: City of Balt., Md., Ord. 26-129. Published by the Baltimore City Department of Legislative Reference.
Balt., Md., Code art. 7, § 26-8 (2026)
§ 26-8 Notice to State Administration.LinkCopy Citation
(a)In general.
For each stormwater management practice completed, the Department must submit a notice of construction to the State Water Management Administration.
(b)When and how.
The notice must be submitted:
(1)
within 45 days of construction completion; and
(2)
on the form that the Administration supplies.
(c)Contents.
The notice must report, on a site-by-site basis, the type, number, total drainage area, and total impervious area treated by all environmental site design techniques and practices and structural stormwater management practices.
History: Ord. 02-367
History: Ord. 10-277