<?xml version='1.0' encoding='utf-8'?>
<baltimore-city-law heading="Subtitle 34 – Inspections; Investigations">
  <section prefix="§" num="34-1" heading="Inspections required.">
    <para num="(a)" heading="In general.">Every active site having an approved erosion and sediment control plan should be inspected for compliance with the plan on an average of once every 2 weeks.</para>
    <para num="(b)" heading="Plan to be maintained on site.">The owner or developer must maintain a copy of the approved erosion and sediment control plan on site.</para>
    <annotation type="History">Ord. 13-095</annotation>
  </section>
  <section prefix="§" num="34-2" heading="By whom conducted.">
    <text>All inspections under this Division III must be conducted by:</text>
    <para num="(1)">the Department; or</para>
    <para num="(2)">the Department’s authorized representative.</para>
    <annotation type="History">Ord. 13-095</annotation>
  </section>
  <section prefix="§" num="34-3" heading="Reports on inspections.">
    <para num="(a)" heading="Required.">The Department must prepare a written report after every inspection.</para>
    <para num="(b)" heading="Contents.">The report must describe:<para num="(1)">the date and location of the site inspection;</para>
      <para num="(2)">whether the approved plan has been properly implemented and maintained;</para>
      <para num="(3)">practice deficiencies or erosion and sediment control plan deficiencies;</para>
      <para num="(4)">if a violation exists, the type of enforcement action taken; and</para>
      <para num="(5)">if applicable, a description of any modifications to the plan.</para>
    </para>
    <annotation type="History">Ord. 13-095</annotation>
  </section>
  <section prefix="§§" num="34-4 to 34-5" reserved="true" />
  <section prefix="§" num="34-6" heading="Right of entry.">
    <text>It is a condition of every grading or building permit that the Department has the right to enter property periodically to inspect for compliance with the approved plan and this Division III.</text>
    <annotation type="History">Ord. 13-095</annotation>
  </section>
  <section prefix="§" num="34-7" heading="Investigations.">
    <para num="(a)" heading="On complaint.">The Department must:<para num="(1)">accept and investigate complaints from interested persons about erosion and sediment control issues;</para>
      <para num="(2)">conduct an initial investigation within 3 working days from receipt of the complaint;</para>
      <para num="(3)">notify the complainant of the initial investigation and findings within 7 days from receipt of the complaint; and</para>
      <para num="(4)">take appropriate action when violations are discovered during the course of the complaint investigation.</para>
    </para>
    <para num="(b)" heading="On own initiative.">The Department may also undertake, on its own initiative, investigations of suspected erosion and sediment control issues on all properties.</para>
    <para num="(c)" heading="Posting of findings.">The Department must post on its website the Department’s findings on all investigations, whether initiated by interested persons or on the Department’s own initiative.</para>
    <annotation type="History">Ord. 13-095</annotation>
  </section>
</baltimore-city-law>