# Subtitle 45 – Reforestation, Afforestation, and Specimen Tree Mitigation

Current through 2026-07-17. Source: City of Balt., Md., Ord. 26-129. Published by the Baltimore City Department of Legislative Reference.

## § 45-1 Preference for retention.

Balt., Md., Code art. 7, § 45-1 (2026)

After every reasonable effort to minimize the cutting of trees and other woody plants is exhausted in the development of a subdivision plan, and/or grading and sediment control plans, the forest conservation plan shall provide for reforestation, afforestation, and/or specimen tree mitigation.

*History: Ord. 93-170*

*History: Ord. 20-401*

## § 45-2 Required sequence.

Balt., Md., Code art. 7, § 45-2 (2026)

(a)

  (1) “Off-site” means not on the same property as the activity which is proposed, is occurring, or which has occurred.

  (2) “On-site” means the area located within the legal boundary of the property on which the regulated activity is proposed, is occurring, or has occurred.

(b) The required sequence for reforestation, afforestation, or specimen tree mitigation, after techniques for retaining existing forest on the site have been exhausted, is as follows:

  (1) on-site reforestation, afforestation, and/or specimen tree mitigation, as specified in the Baltimore City Forest Conservation Manual;

  (2) off-site reforestation, afforestation, and/or specimen tree mitigation within the City shall be as specified for on-site reforestation or specimen tree mitigation;

  (3) use of appropriate credits generated by a forest mitigation bank in the City; and

  (4) payment into the City Forest Conservation Fund.

*History: Ord. 93-170*

*History: Ord. 20-401*

## § 45-3 Reforestation, etc., guidelines; time limits.

Balt., Md., Code art. 7, § 45-3 (2026)

(a) Persons required to conduct reforestation, afforestation, or specimen tree mitigation shall follow the priority guidelines outlined in the Baltimore City Forest Conservation Manual.

(b) A person required to conduct reforestation, afforestation, or specimen tree mitigation under this Division IV shall accomplish the action within 1 year or 2 growing seasons following the issuance of a grading permit, allowing for phasing in the plan.

*History: Ord. 93-170*

*History: Ord. 20-401*

## § 45-4 Security required.

Balt., Md., Code art. 7, § 45-4 (2026)

Before the issuance of a grading or building permit, a person required to conduct afforestation, reforestation, or specimen tree mitigation under this Division IV shall furnish financial security in the form of a bond, an irrevocable letter of credit, or other security approved by the Department, as provided in the Baltimore City Conservation Supplement to the State Conservation Manual.