<?xml version='1.0' encoding='utf-8'?>
<chapter heading="Chapter 8. Buildings.">
  <article heading="Article I. General Requirements.">
    <section heading="Sec. 8-1. Scope and applicability.">
      <paragraph indent="1">(a)   Generally. This Chapter includes the rules and regulations adopted under Section 8-13 which have the force of law. It is known as the building code of Montgomery County. It controls all matters concerning the construction, alteration, addition, repair, removal, demolition, use, location. This Chapter also concerns the creation or alteration of certain ownership units, the occupancy and maintenance of all buildings and structures, on-site access facilities to such buildings and structures and their service equipment. This Chapter applies to existing or proposed buildings and structures in the County.</paragraph>
      <paragraph indent="1">(b)   Intent. The intent of this Chapter is to assure public safety, health and welfare as it is affected by building construction, structural strength, egress facilities, sanitary equipment, light, utilities and ventilation, occupancies, and fire safety. In general, the intent of this chapter is to secure safety to life and property from all hazards associated with the design, erection, repair, removal, demolition or use and occupancy of buildings, structures or premises.</paragraph>
      <paragraph indent="1">(c)   Applicability generally.</paragraph>
      <paragraph indent="2">(1)   This Chapter applies to the construction, raising, lowering, moving, demolition, or occupancy of all buildings and structures and their appurtenant construction, including vaults, area and street projections, on-site access facilities, accessory structures, and additions. It applies to public and private buildings, except where such buildings are otherwise specifically excluded by statute. It also applies to the creation or alteration of any ownership unit, and the closure of any private road.</paragraph>
      <paragraph indent="2">(2)   A building permit may only be issued for a building located on:</paragraph>
      <paragraph indent="3">(A)   a lot or parcel shown on a plat recorded in the County Land Records or on a parcel exempt from recording requirements under Section 50-3.3; and</paragraph>
      <paragraph indent="3">(B)   an area outside of any building restriction line and outside the area restricted under Section 50-4.3.K.</paragraph>
      <paragraph indent="1">(d)   Exemptions. All buildings or structures must be constructed, extended, repaired, removed, or altered under a permit that satisfies this Chapter, except for:</paragraph>
      <paragraph indent="2">(1)   ordinary repairs as defined in Section 8-3;</paragraph>
      <paragraph indent="2">(2)   a building or structure used exclusively for agricultural purposes on land used exclusively for agriculture; however, a permit under this Chapter is required for:</paragraph>
      <paragraph indent="3">(A)   a building or structure in which customers or other members of the public consume food or beverage, unless exempted under Maryland Code § 12-508 of the Public Safety Article, as amended; and</paragraph>
      <paragraph indent="3">(B)   an equestrian facility, building, or structure intended for use by participants or spectators at an equestrian event;</paragraph>
      <paragraph indent="2">(3)   the following public utility equipment:</paragraph>
      <paragraph indent="3">(A)   any structure and its attached cross arms carrying overhead electric power and energy transmission and distribution lines that carry 69,000 volts or less;</paragraph>
      <paragraph indent="3">(B)   equipment installed and maintained by a public utility under regulation by the State Public Service Commission; or</paragraph>
      <paragraph indent="3">(C)   poles or structures used for street lights, fire alarm boxes, traffic signals, or similar municipal equipment installed by the State or a local municipality.</paragraph>
      <paragraph indent="1">(e)   Matters not provided for. Any requirement essential for structural, fire or sanitary safety of an existing or proposed building or structure or essential for the safety of the building’s occupants and which is not specifically covered by this Chapter, must be determined by the director under Section 8-13.</paragraph>
      <paragraph indent="1">(f)   Zoning restrictions and referrals.</paragraph>
      <paragraph indent="2">(1)   When the provisions specified in this Chapter for structural, fire, and sanitary safety are more restrictive than those in Chapter 59, this Chapter controls the erection or alteration of buildings in respect to location, use, permissible area and height; but the more rigid requirements of either the building code or the zoning ordinance applies whenever they are in conflict.</paragraph>
      <paragraph indent="2">(2)   The Director must submit the application to the Planning Director for review for any building permit that requests:</paragraph>
      <paragraph indent="3">(A)   construction of a new principal structure; and</paragraph>
      <paragraph indent="3">(B)   construction that increases the gross floor area of an existing commercial structure.</paragraph>
      <paragraph indent="2">(3)   The Planning Director must confirm in writing that the submitted application satisfied Chapter 59 and that the property has all necessary approvals and satisfied all necessary conditions required by the Planning Department and Planning Board and identify for each permit the amount of any school facility payment, transportation mobility area review payment or other development payment other than impact taxes that is required to be paid as a condition of building permit.</paragraph>
      <paragraph indent="2">(4)   A building permit application for a child lot in the Agricultural Reserve Zone may only be approved if the child for whom the lot is created is the owner of the lot in the County Land Records. A building permit for a detached house on a child lot must be issued only to:</paragraph>
      <paragraph indent="3">(A)   a child of the property owner;</paragraph>
      <paragraph indent="3">(B)   the spouse of a child of the property owner;</paragraph>
      <paragraph indent="3">(C)   a contractor for a child of the property owner; or</paragraph>
      <paragraph indent="3">(D)   a contractor for the spouse of a child of the property owner.</paragraph>
    </section>
    <section heading="Sec. 8-2. Definitions.">
      <paragraph indent="1">In this Chapter, the following words and phrases have the following meanings:</paragraph>
      <paragraph indent="1">Agricultural Purpose. A use or function in performance of the work or storage of the instruments or products of agriculture, as defined in Section 1.4.2 of Chapter 59. Agricultural purpose includes the business, administration, or management of agriculture and the processing of an agricultural product to prepare the product for market.</paragraph>
      <paragraph indent="1">Controlled materials. Materials which are certified by an accredited or authoritative agency as meeting accepted engineering standards for quality in accordance with detailed criteria set forth in regulations promulgated pursuant to provisions of this Chapter.</paragraph>
      <paragraph indent="1">Department. The Department of Permitting Services.</paragraph>
      <paragraph indent="1">Director. The Director of the Department of Permitting Services.</paragraph>
      <paragraph indent="1">International Building Code. A comprehensive performance code governing materials and methods of construction used in buildings and structures or parts of either, and their service equipment and systems, published periodically by the International Code Council, Inc., (ICC) or any successor body.</paragraph>
      <paragraph indent="1">On-site access facilities. Ramps, walkways, driveways and related pedestrian facilities located on a building site which provide a means of access for the public or the general work force to buildings and structures regulated by this Chapter.</paragraph>
      <paragraph indent="1">Ownership unit. An area of land shown on a record plat created only for the convenience of the owner under Section 7.1.D of Chapter 50 that reflects a deed, mortgage, or lease line but does not subdivide the underlying lot.</paragraph>
      <paragraph indent="1">Parent lot. A lot that is further divided by one or more ownership units.</paragraph>
      <paragraph indent="1">Person. Any person, corporation, partnership, joint venture, agency, unincorporated association, municipal corporation, County or state agency within the state or any combination thereof.</paragraph>
      <paragraph indent="1">Private Road. Any street, highway, avenue, lane, alley, or viaduct, or any segment of any of them, including any abutting sidewalk that has not been deeded, dedicated or otherwise permanently appropriated to the public for public use.</paragraph>
      <paragraph indent="1">Service equipment. The mechanical, electrical and elevator equipment, including piping, wiring, fixtures and other accessories, which provide sanitation, lighting, heating, ventilation, fire-fighting and transportation facilities essential for the habitable occupancy of the building or structure for its designated use and occupancy.</paragraph>
    </section>
    <section heading="Sec. 8-3. Ordinary repairs.">
      <paragraph indent="1">Ordinary repairs to buildings may be made without application or notice to the department; but such repairs shall not include the cutting away of any wall, partition or portion thereof, the removal or cutting of any structural beam or bearing support or the removal or change of any required means of egress or rearrangement of parts of a structure affecting the exitway requirements; nor shall ordinary repairs include addition to, alteration of, replacement or relocation of any standpipe, water supply, sewer, drainage, drain leader, gas, soil, waste, vent or similar piping, electric wiring or mechanical or other work affecting public health or general safety.</paragraph>
    </section>
    <section heading="Sec. 8-4. Installation of service equipment.">
      <paragraph indent="1">When the installation, extension, alteration, or repair of an elevator, moving stairway, mechanical equipment, refrigeration, air conditioning or ventilating apparatus, plumbing, gas piping, electric wiring, heating system, fire sprinkler system, or any other equipment is subject to a requirement of this Chapter, it shall be unlawful to use the equipment until the Director issues a certificate approving the work.</paragraph>
    </section>
    <section heading="Sec. 8-5. Maintenance.">
      <paragraph indent="1">(a)   All buildings and structures and all parts thereof, both existing and new, shall be maintained in a safe and sanitary condition. All service equipment, means of egress, devices and safeguards which are required by this chapter in a building or which were required by a previous statute in a building when erected, altered or repaired, shall be maintained in good working order.</paragraph>
      <paragraph indent="1">(b)   It shall be unlawful for the owner of a building or his designated agent to fail to maintain the structure and its exitways in a safe and sanitary condition at all times.</paragraph>
    </section>
    <section heading="Sec. 8-6. Change in existing use.">
      <paragraph indent="1">(a)   Continuation of existing use. The legal use and occupancy of any structure existing on the effective date of this chapter or for which it had been heretofore approved, may be continued without change, except as may be specifically required herein or as may be deemed necessary by the director for the general safety and welfare of the occupants and the public.</paragraph>
      <paragraph indent="1">(b)   Change in use. It shall be unlawful to make any change in the use or occupancy of any structure which would subject it to any special provision of this chapter without approval of the director and his certification that such structure meets the intent of the provisions of law governing building construction for the proposed new use and occupancy and that  such change does not result in any greater hazard to public safety or welfare.</paragraph>
    </section>
    <section heading="Sec. 8-7. Existing buildings.">
      <paragraph indent="1">Except as provided in this section, existing buildings when altered or repaired as herein specified shall be made to conform to the full requirements of this chapter for new buildings:</paragraph>
      <paragraph indent="1">(a)   Alterations and damages over 25 percent. If the cost of alterations or repairs, as described herein, or damages by fire or other cause, is over twenty-five (25) percent of the physical value of the building, the director shall determine to what degree the portions so altered or repaired shall be made to conform to the requirements for new buildings.</paragraph>
      <paragraph indent="1">(b)   Alterations under 25 percent. If the cost of alterations or repairs described herein is twenty-five (25) percent or less of the physical value of the building, the director shall permit the restoration of the building to its condition previous to damage or deterioration with the same kind of materials as those of which the building was constructed; provided, that such construction does not endanger the general safety and public welfare and complies with other provisions of this chapter in respect to existing roofs.</paragraph>
      <paragraph indent="1">(c)   Increase in size. If the building is increased in floor area or number of stories, the entire building shall be made to conform with the requirements of this chapter with respect to means of egress, fire safety, light and ventilation.</paragraph>
      <paragraph indent="1">(d)   Part change in use. If a portion of the building is changed in occupancy or to a new use group and that portion is separated from the remainder of the building with the required vertical and horizontal fire divisions complying with the fire grading in this chapter, then the construction involved in the change shall be made to conform to the requirements for the new use and occupancy and the existing portion shall be made to comply with the exitway requirements of this chapter.</paragraph>
      <paragraph indent="1">(e)   Physical value. In applying the provisions of this section, the physical value of the building shall be determined by the director and be based on current replacement costs.</paragraph>
    </section>
    <section heading="Sec. 8-8. Conditional use approval.">
      <paragraph indent="1">For a site with a conditional use:</paragraph>
      <paragraph indent="1">(a)   The Department may allow minor adjustments during construction that the Planning Director has confirmed do not substantially alter the size, location, or external appearance of any approved building, structure, or use.</paragraph>
      <paragraph indent="1">(b)   Any change proposed during construction that would substantially alter the location or external appearance of any approved building, structure, or use requires an amendment under Article 59-7 of this Code.</paragraph>
    </section>
    <section heading="Sec. 8-9. Posted buildings.">
      <paragraph indent="1">(a)   Posted use and occupancy. Every building and structure and part thereof designed for and listed among high hazard, storage, mercantile, industrial or business use groups as determined in regulations promulgated pursuant to provisions of this chapter shall be posted on all floors by the owner with a suitably designed placard in a form designated by the director, which shall be securely fastened to the structure in a readily visible place, stating: the use group, the fire grading, the live load and the occupancy load.</paragraph>
      <paragraph indent="1">(b)   Posted occupancy load. Every building and structure and part thereof designed for a use listed among the assembly building or institutional building use groups as determined in regulations promulgated pursuant to provisions of this chapter shall be posted with an approved placard designating the maximum occupancy load.</paragraph>
      <paragraph indent="1">(c)   Replacement of posted signs. All posting signs shall be furnished by the owner and shall be of permanent design; they shall not be removed or defaced and, if lost, removed or defaced, shall be immediately replaced.</paragraph>
      <paragraph indent="1">(d)   Periodic inspection. The director may periodically inspect all existing buildings and structures except one- and two-family dwellings, for compliance with the law in respect to posting, or he may accept the report of such inspection from an authorized licensed professional engineer or architect and such inspection and report shall specify any violation of the requirements of this chapter in respect to the posting of floor load, fire grading, occupancy load and use group of the building.</paragraph>
    </section>
    <section heading="Sec. 8-10. Unsafe buildings.">
      <paragraph indent="1">(a)   Right of condemnation. All buildings or structures that are or hereafter shall become unsafe, unsanitary or deficient in adequate exitway facilities or which constitute a fire hazard or are otherwise dangerous to human life or the public welfare or which by reason of illegal or improper use, occupancy or maintenance shall be deemed unsafe buildings or structures. All unsafe buildings shall be taken down and removed or made safe and secure, as the director may deem necessary and as provided in this section. A vacant building, unguarded or open at door or window, shall be deemed a fire hazard and unsafe within the meaning of this chapter.</paragraph>
      <paragraph indent="1">(b)   Examination and record of damaged building. The director shall examine every building or structure reported as dangerous, unsafe structurally or constituting a fire hazard and he shall cause the report to be filed in a docket of unsafe structures and premises, stating the use of the building, the nature and estimated amount of damages, if any, caused by collapse or failure.</paragraph>
      <paragraph indent="1">(c)   Notice of unsafe building. If an unsafe condition is found in a building or structure, the director shall serve on the owner, agent or person in control of the building or structure a written notice describing the building or structure deemed unsafe and specifying the required repairs or improvements to be made to render the building or structure safe and secure or requiring the unsafe building or structure or portion thereof to be demolished within a stipulated time. Such notice shall require the person thus notified to immediately notify the director of his acceptance or rejection of the terms of the order.</paragraph>
      <paragraph indent="1">(d)   Restoration of unsafe building. A building or structure condemned by the director may be restored to safe condition; provided, that no change of use or occupancy is contemplated or compelled by reason of such reconstruction or restoration; except, that if the damage or cost of reconstruction or restoration is in excess of fifty (50) percent of its replacement value, exclusive of foundations, such building shall be made to comply in all respects with the requirements for materials and methods of construction of buildings hereafter erected.</paragraph>
      <paragraph indent="1">(e)   Posting "unsafe" notice. If the person addressed with an "unsafe" notice cannot be found within the county after diligent search, then such notice shall be sent by registered or certified mail to the last known address of such person and a copy of the ``unsafe'' notice shall be posted in a conspicuous place on the premises and such procedure shall be deemed the equivalent of personal notice.</paragraph>
      <paragraph indent="1">(f)   Disregard of "unsafe" notice. Upon refusal or neglect of the person served with an "unsafe" notice to comply with the requirements of the order to abate the unsafe condition, the county attorney shall be advised of all the facts and he shall institute the appropriate action to compel compliance.</paragraph>
    </section>
  </article>
  <article heading="Article II. Administration.">
    <section heading="Sec. 8-11. Generally.">
      <paragraph indent="1">The Director enforces and administers this Chapter.</paragraph>
    </section>
    <section heading="Sec. 8-12. Duties and responsibilities.">
      <paragraph indent="1">The Director shall enforce all the provisions of this Chapter and shall act on any question relative to the mode or manner of construction and the materials to be used in the erection, addition to, alteration, repair, removal, demolition, installation of service equipment and the location, use, occupancy and maintenance of all buildings and structures, except as may otherwise be specifically provided for by statutory requirements or as herein provided:</paragraph>
      <paragraph indent="1">(a)   Applications and permits. He shall receive applications and issue permits for the erection and alteration of buildings and structures and inspect the premises for which such permits have been issued and enforce compliance with the provisions of this Chapter;</paragraph>
      <paragraph indent="1">(b)   Building notices and orders. He shall issue all necessary notices or orders to remove illegal or unsafe conditions, to require the necessary safeguards during construction, to require adequate exitway facilities in existing buildings and structures and to ensure compliance with all the code requirements for the safety, health and general welfare of the public;</paragraph>
      <paragraph indent="1">(c)   Inspections. The Director must make all the required inspections or may accept reports of inspection by authoritative and recognized services or individuals, and all reports of those inspections must be in writing and certified by a responsible officer of the authoritative service or by the responsible individual; or the Director may engage expert opinion as necessary to report upon unusual technical issues that may arise, subject to the approval of the appointing authority. On the request of the Director of Housing and Community Affairs, under the authority of Chapter 26, the Director must investigate complaints of defects in construction that may violate Chapter 26.</paragraph>
      <paragraph indent="1">(d)   Research and investigations. The Director must investigate new developments in the building industry.  Subject to local climatic or other conditions, the Director must accredit tests meeting the functional requirements of this Chapter conducted by accredited authoritative agencies listed in applicable regulations. The Director also may accept duly authenticated reports from the International Code Council, Inc., or from recognized authoritative sources of all new materials and methods of construction proposed for use which are not specifically provided for in this Chapter.  The costs of all tests or other investigations required under this subsection must be paid by the applicant.</paragraph>
      <paragraph indent="1">(e)   Department records. He shall keep official records of applications received, permits and certificates issued, fees collected, reports of inspections, and notices and orders issued. File copies of all papers in connection with building operations shall be retained in the official records so long as the building or structure to which they relate remains in existence; and</paragraph>
      <paragraph indent="1">(f)   Hearings. Prior to the issuance of notices, orders and permits hereunder, the Director may, upon request, provide all interested parties with an opportunity for hearing after reasonable notice as specified in Section 8-15(c) of this Chapter. The notice shall state the time, place and issues involved. If the Director holds a hearing on a decision of the Department, the time for appeal to the Board of Appeals shall be stayed until a decision is made by the Director or until the Director has acted on a request for reconsideration, if any. A copy of the Director's decision or order shall be delivered or mailed promptly to each party to the hearing or to that party's attorney of record. Any party to a hearing conducted by the Director may, within ten (10) days following a decision by the Director, request in writing that the Director reconsider such decision;</paragraph>
      <paragraph indent="1">(g)   Annual report. At least annually, the Director shall compile a written statement of all permits and certificates issued, orders promulgated and materials approved. Interim reports shall be submitted as required.</paragraph>
    </section>
    <section heading="Sec. 8-13. Regulations.">
      <paragraph indent="1">(a)   The Director may recommend regulations for the administration of this Chapter including a schedule of fees and may, at the Director’s discretion, hold public hearings as part of this regulation-making process. Regulations, as amended, must not conflict with or waive any provisions of this Chapter. Such regulations must be at least as restrictive as the requirements of this Chapter. All regulations must be adopted by the County Executive under Method (2) of Section 2A-15. The County Executive must promptly forward to the County Council a copy of any new fee schedule for use in budgetary planning activities. Such fees may be based on area, estimated cost of construction, or a minimal set fee per category. The budget estimate of all fees must be equal to the cost of administering this Code.</paragraph>
      <paragraph indent="1">(b)   The Director must hold at least one public hearing, after adequate public notice, before recommending to the Executive any regulations adopted under this Chapter. All regulations, related to the construction or demolition must be based on the latest edition of the ICC International Building Code and any local amendments to that Code.</paragraph>
    </section>
    <section heading="Sec. 8-14. Standards applicable.">
      <paragraph indent="1">(a)   The edition of the ICC International Building Code designated under Section 8-13 is the basic County building code.  The construction, alteration, addition, repair, removal, demolition, use, location, occupancy, and maintenance of all buildings and structures or parts thereof, on-site access facilities to buildings and structures, and their service equipment must meet the standards and requirements in that Code, or as amended under Section 8-13.</paragraph>
      <paragraph indent="1">(b)   The closure of any private road must meet the standards and requirements of Chapter 22 and Chapter 49.</paragraph>
    </section>
    <section heading="Sec. 8-14A. Energy performance standards for county buildings.">
      <paragraph indent="1">(a)   In this section, "County building" means any building for which the County government finances all or part of the cost of construction.</paragraph>
      <paragraph indent="1">(b)   All County buildings contracted for design after September 1, 1985, must meet the energy performance standards required under this section.</paragraph>
      <paragraph indent="1">(c)   The County Executive must adopt regulations under method (2) to establish:</paragraph>
      <paragraph indent="2">(1)   Minimum building energy performance standards that meet or exceed the energy performance standards established by the State of Maryland under State law;</paragraph>
      <paragraph indent="2">(2)   A procedure for evaluating and monitoring the appropriateness and effectiveness of the standards;</paragraph>
      <paragraph indent="2">(3)   A procedure for evaluating building life cycle costs during the design development phase; and</paragraph>
      <paragraph indent="2">(4)   An incentive program which gives the County Executive the discretion to award bonuses if the building actually performs better than the energy performance standards required under this section.</paragraph>
      <paragraph indent="1">(d)    The Director of General Services may grant a variance or modification of an energy performance standard if:</paragraph>
      <paragraph indent="2">(1)   The architect applies for the variance or modification in writing; and</paragraph>
      <paragraph indent="2">(2)   The Director gives notice of and a chance to comment on the application to:</paragraph>
      <paragraph indent="3">(A)   The County Council;</paragraph>
      <paragraph indent="3">(B)   The Department of Permitting Services; and</paragraph>
      <paragraph indent="3">(C)   The energy conservation advisory committee.</paragraph>
      <paragraph indent="1">Sec. 2. Any responsibility or right granted by law, ordinance, regulation, delegation of authority, contract, or other document to the Department of Public Works and Transportation in connection with designing, building, and maintaining County facilities (except maintaining or renovating public parking facilities under Chapter 60, as provided for under Section 1 of this Act), maintaining County vehicles and equipment, acquiring and disposing of real property not associated with roads, bridges, and other related transportation facilities, and operating mail, printing, and duplication services, is transferred to the Department of General Services.</paragraph>
      <paragraph indent="1">Sec. 3. Any regulation in effect when this Act takes effect that implements a function transferred to another Department or Office under Section 1 of this Act continues in effect, but any reference in any regulation to the Department from which the function was transferred must be treated as referring to the Department to which the function is transferred.  The transfer of a function under this Act does not affect any right of a party to any legal proceeding begun before this Act took effect.</paragraph>
    </section>
    <section heading="Sec. 8-14B. County buildings - energy unit savings plans, energy cost savings plans, and energy performance contracts.">
      <paragraph indent="1">(a)   Definitions.  In this Section, the following words have the meanings indicated:</paragraph>
      <paragraph indent="2">County building means a building which is owned or leased by the County.</paragraph>
      <paragraph indent="2">Energy baseline means the amount of energy consumed each year by a County building based on historical metered data, engineering calculations, submetering of buildings or energy consuming systems, building load simulation models, statistical regression analysis, or any combination of those methods.</paragraph>
      <paragraph indent="2">Energy cost savings plan means a plan to reduce a County building’s energy costs, including related operation and maintenance costs.</paragraph>
      <paragraph indent="2">Energy performance contract means a contract which provides for the performance of services for the design, acquisition, installation, testing, operation, maintenance, or repair of an identified energy conservation measure or series of measures in a County building.</paragraph>
      <paragraph indent="2">ENERGY STAR rating means the ENERGY STAR rating developed by the federal Environmental Protection Agency which reflects a building’s energy efficiency.</paragraph>
      <paragraph indent="2">Energy unit savings plan means a plan to reduce the amount of energy used by a County building, as measured in kilowatt hours or British thermal units.</paragraph>
      <paragraph indent="2">National energy performance rating system means the rating system developed by the federal Environmental Protection Agency under which a building may obtain the ENERGY STAR rating.</paragraph>
      <paragraph indent="2">Office of Energy and Sustainability or Office means the Office of Energy and Sustainability in the Department of General Services created under Section 18A-14.</paragraph>
      <paragraph indent="1">(b)   Requirements.  The Office of Energy and Sustainability must:</paragraph>
      <paragraph indent="2">(1)   develop an energy baseline, energy unit savings plan, and energy cost savings plan for each County building;</paragraph>
      <paragraph indent="2">(2)   submit an initial report to the County Executive and County Council by February 1, 2015 which summarizes the energy baseline, energy unit savings plan, and energy cost savings plan for each County building; and</paragraph>
      <paragraph indent="2">(3)   submit an annual report to the County Executive and County Council by February 1 of each year that summarizes the steps taken in the preceding fiscal year to implement the energy unit savings plan and energy cost savings plan for each County building.</paragraph>
      <paragraph indent="1">(c)   Energy performance contracts.  Each energy unit savings plan and energy cost savings plan that the Office prepares under subsection (b) must include a plan to use an energy performance contract unless the Office finds that the cost of using an energy performance contract outweighs the benefit.</paragraph>
    </section>
    <section heading="Sec. 8-14C.Lactation Rooms in County Buildings.">
      <paragraph indent="1">(a)   Definitions.  In this Section, the following terms have the meanings indicated.</paragraph>
      <paragraph indent="2">County building means a building, whether existing or newly constructed, that is owned or leased by the County where County employees work.</paragraph>
      <paragraph indent="2">County employee has the meaning stated in Section 33-6.</paragraph>
      <paragraph indent="2">Department means the Department of General Services.</paragraph>
      <paragraph indent="2">Director means the Director of General Services or the Director’s designee.</paragraph>
      <paragraph indent="2">Lactation room means a designated sanitary room, other than a bathroom, made available for expressing breast milk, that:</paragraph>
      <paragraph indent="2">(1)   is shielded from view;</paragraph>
      <paragraph indent="2">(2)   is free from public or coworker intrusion;</paragraph>
      <paragraph indent="2">(3)   displays appropriate signage that indicates “lactation room” or “nursing room;” and</paragraph>
      <paragraph indent="2">(4)   contains the following:</paragraph>
      <paragraph indent="3">(A)   a chair;</paragraph>
      <paragraph indent="3">(B)   a flat surface to place a breast pump;</paragraph>
      <paragraph indent="3">(C)   can be locked or secured from the inside;</paragraph>
      <paragraph indent="3">(D)   a small refrigerator;</paragraph>
      <paragraph indent="3">(E)   a microwave;</paragraph>
      <paragraph indent="3">(F)   at least one or more electrical outlets; and</paragraph>
      <paragraph indent="3">(G)   any other related supplies as provided in regulations.</paragraph>
      <paragraph indent="1">(b)   Lactation room – required.</paragraph>
      <paragraph indent="2">(1)   New Construction.  The Department must provide at least one lactation room that includes a sink with running water in each newly constructed County building that is available for use by any County employee to express breast milk.</paragraph>
      <paragraph indent="2">(2)   Existing Buildings.  Except as provided in subsection (c) or (d), the Department must provide at least one lactation room in an existing County building that includes a sink with running water and plumbing systems. If a sink with running water and plumbing systems cannot be provided, the lactation room must have nearby access to running water.</paragraph>
      <paragraph indent="1">(c)   Alternative Accommodation.  If the Director determines that a County building does not have a room that could be repurposed as a lactation room, at a reasonable cost, the Department must consider alternative accommodations. Alternative accommodation includes installing or creating a space for a portable lactation room or station.</paragraph>
      <paragraph indent="2">(1)   The Executive may enter into a memorandum of understanding between the Department and an owner that offers, for sale or lease, a portable lactation room or station to meet the requirement for subsection (c).</paragraph>
      <paragraph indent="1">(d)   Exceptions.  A County building may be excluded from the requirement under subsection (b), if the building:</paragraph>
      <paragraph indent="2">(1)   is solely a warehouse;</paragraph>
      <paragraph indent="2">(2)   is primarily used for archives; or</paragraph>
      <paragraph indent="2">(3)   would require new construction to create a lactation room and the cost of such construction is unfeasible.</paragraph>
      <paragraph indent="1">(e)   Regulations.  The Director may promulgate Method (2) regulations to implement the requirements of this Section.</paragraph>
      <paragraph indent="1">(f)   Assessment.  The Department must complete, or cause to be completed, an assessment and survey of all applicable County buildings for the inclusion of a lactation room.</paragraph>
      <paragraph indent="1">(g)   Reporting.  The Department must report to the County Council any findings, outcomes, and progress of the assessment required under subsection (f).</paragraph>
    </section>
    <section heading="Sec. 8-14D. Comprehensive Building Decarbonization.">
      <paragraph indent="1">(a)   Definitions. In this section, the following words have the meanings indicated:</paragraph>
      <paragraph indent="2">All-electric building means a public or private building that contains no combustion equipment, or plumbing for combustion equipment, installed within the building or building site.</paragraph>
      <paragraph indent="2">Combustion equipment means any equipment or appliance used for space heating, service water heating, cooking, clothes drying and/or lighting that uses fuel gas or fuel oil.</paragraph>
      <paragraph indent="2">New construction means the construction of any new stand-alone building, with no remnants of any prior structure or physical connection to existing structures or outbuildings on the property.</paragraph>
      <paragraph indent="1">(b)   Standards. The County Executive must issue Method (1) regulations to establish all-electric building standards for all new construction as part of the building code.</paragraph>
      <paragraph indent="2">(1)   The regulations must include a code modification process. A code modification must only be granted if the resulting building is carbon-neutral or net-zero.</paragraph>
      <paragraph indent="2">(2)   The regulations may include additional exemptions not listed in section 8-14D(c) if all-electric building standards cannot be applied to the system or use due to practical difficulty or undue hardship.</paragraph>
      <paragraph indent="1">(c)   Exemptions. All-electric building standards do not apply to:</paragraph>
      <paragraph indent="2">(1)   the emergency backup systems of buildings that require an emergency system and hence backup power;</paragraph>
      <paragraph indent="2">(2)   buildings primarily used by a utility regulated by the Maryland Public Service Commission for the generation of electric power or steam;</paragraph>
      <paragraph indent="2">(3)   buildings used to treat sewage or food waste;</paragraph>
      <paragraph indent="2">(4)   commercial kitchen equipment in an eating and drinking establishment that satisfies the requirements of Chapter 15;</paragraph>
      <paragraph indent="2">(5)   gas-powered fireplaces and gas-fired outdoor grills;</paragraph>
      <paragraph indent="2">(6)   applications for building permits submitted to the Department prior to the effective date of the regulation;</paragraph>
      <paragraph indent="2">(7)   district combined heat and powers facilities; and</paragraph>
      <paragraph indent="2">(8)   buildings used for the following uses, as defined in Chapter 59:</paragraph>
      <paragraph indent="3">(A)   Manufacturing and Production uses;</paragraph>
      <paragraph indent="3">(B)   Crematory;</paragraph>
      <paragraph indent="3">(C)   Life Sciences;</paragraph>
      <paragraph indent="3">(D)   Hospital; and</paragraph>
      <paragraph indent="3">(E)   Farming and Farm Alcohol Production.</paragraph>
      <paragraph indent="1">(d)   Reports.</paragraph>
      <paragraph indent="2">(1)   The County Executive must submit a report to the County Council regarding the system capacity needs and investments required for an all-electric building code standard no later than September 30, 2024, and not before December 1, 2023. This report must include a review of any studies issued by the Public Service Commission and should include information provided by the utility companies that service Montgomery County.</paragraph>
      <paragraph indent="2">(2)   The Department of Permitting Services must arrange for an annual audit that assesses a representative sample of new construction that complies with this section. The audit must include the number of applications submitted for new construction, the number of waivers granted, current electric rates for consumers, and an analysis of any alternative energy sources used. A complete copy of the audit findings must be submitted to the County Council on June 1 each year, beginning June 1, 2028.</paragraph>
      <paragraph indent="1">Sec. 3.  All-Electric Transition. Section 8-14D(b) of this Act must not apply to building permit applications submitted before December 31, 2027, for: (1) housing development projects where 50 percent or more of the dwelling units are moderately priced dwelling units as defined by Chapter 25A, or a similar instrument with a federal, state, or local government for the creation or preservation of income-restricted or market-rate affordable housing; (2) public or private schools; or (3) residential buildings with four or more stories.</paragraph>
    </section>
    <section heading="Sec. 8-15. Modifications.">
      <paragraph indent="1">(a)   Variances. When there are practical difficulties and undue hardship involved in carrying out structural or mechanical provisions of this chapter, the director may vary or modify such provision upon application of the owner or his representative; provided, that the spirit and intent of the law shall be observed and public welfare and safety be assured.</paragraph>
      <paragraph indent="1">(b)   Written application. The application for modification and the final decision of the director shall be in writing on a form approved by the department, shall include the names and address of the owners of all property contiguous or opposite to the property described on said application and shall be officially recorded with the application for the permit in the permanent records of the department.</paragraph>
      <paragraph indent="1">(c)   Notice of hearing. Within seven (7) days of the filing of the application provided for herein, the director shall cause to be mailed to the owners of any property contiguous or opposite to the property described in said application and, in his discretion, to other interested parties, organizations or agencies a copy of such application and the date, time and place fixed for the hearing.</paragraph>
      <paragraph indent="1">(d)   Record of hearing. In all contested cases, the department shall prepare an official record, which shall include testimony and exhibits, but it shall not be necessary to transcribe the stenographic record unless requested for purposes of appeal.</paragraph>
    </section>
    <section heading="Sec. 8-16. Controlled materials procedure.">
      <paragraph indent="1">(a)   When plans for the erection or alteration of a building are prepared by a licensed professional engineer or registered architect, which contemplate structural work or structural changes involving public safety or health and such plans are accompanied by an affidavit of the applicant that he has supervised the preparation of the architectural, structural and mechanical design plans and that he will supervise or check all working drawings and shop details for the construction and that the structure will be built under his field supervision and in accordance with the approved plans and that such plans conform to all the provisions of this chapter and the regulations adopted pursuant to its provisions and that all the material used in the construction will be controlled materials as defined herein, the director may waive examination of the plans and field inspection of the construction and may issue a permit for the performance of the work.</paragraph>
      <paragraph indent="1">(b)   The licensed or registered professional engineer or architect shall be qualified by experience and training in the particular field of construction involved in the building project under consideration.</paragraph>
      <paragraph indent="1">(c)   Before the issuance of the certificate of use and occupancy for such building, the licensed professional engineer or architect who prepared and filed the original plans and who supervised the erection of the building shall file a verified report that the structure has been erected in accordance with the approved plans; and as erected, the building complies in all respects with this chapter and all other laws governing building construction except as to the specific variations legally authorized under the provisions of this chapter and as specifically noted in the verified report and cited in the certificate of use and occupancy.</paragraph>
      <paragraph indent="1">(d)   When applications for unusual designs or magnitude of construction are filed, the director may refer such plans and specifications to the plan review service of the Building Officials Conference of America for advice and recommendations as to their safety of design and compliance with this chapter; or he may, in his discretion, retain a properly qualified licensed engineer or registered architect to examine such application for a specific building operation with respect to safety and conformance to statutory requirements. Such employed licensed engineer or registered architect shall supervise the construction in the field to secure compliance with the approved plans and permit; and upon completion of the work, he and the builder shall file with the director a verified report to the effect that the building has been erected in accordance with accepted engineering practice and in conformity to all the statutory provisions governing building construction for the designated use group classification of the building or structure in respect to use, fire grading, floor and occupancy loads.</paragraph>
    </section>
    <section heading="Sec. 8-17. Inspection.">
      <paragraph indent="1">(a)   Preliminary inspection. Before issuing a permit, the director may examine or cause to be examined all buildings, structures and sites for which an application has been filed for a permit to construct, enlarge, alter, repair, remove, demolish or change the use thereof; and he may conduct such inspections from time to time during and upon completion of the work for which he has issued a permit; and he shall maintain a record of all such examinations and inspections and of all violations of this chapter.</paragraph>
      <paragraph indent="1">(b)   Accredited inspection services. The director may accept reports of his own inspectors or of approved inspection services which satisfy his requirements as to qualifications and reliability.</paragraph>
      <paragraph indent="1">(c)   Plan inspection. When required by the provisions of this chapter materials or assemblies shall be inspected at the point of manufacture or fabrication.</paragraph>
      <paragraph indent="1">(d)   Inspection reports. All inspection reports shall be in writing and shall be certified by the approved inspection service, or responsible officer of the service or the individual when expert inspection services are accepted. A label or mark of approval permanently fixed to the product indicating that factory inspection has been made shall be accepted in lieu of the aforesaid report in writing.</paragraph>
      <paragraph indent="1">(e)   Final inspection. Upon completion of the building or structure and before issuance of the certificate of use and occupancy as required by this chapter, a final inspection shall be made and all violations of the approved plans and permit shall be noted and the holder of the permit shall be notified of the violations.</paragraph>
    </section>
    <section heading="Sec. 8-18. Right of entry.">
      <paragraph indent="1">(a)   Generally. In the discharge of his duties, the director or his authorized representative shall have the authority to enter at any reasonable hour any building, structure or premises in the county for which a permit has been issued to enforce the provisions of this chapter.</paragraph>
      <paragraph indent="1">(b)   Municipal cooperation. The assistance and cooperation of police, fire, and health departments and all other county officials shall be available to him as required in the performance of his duties.</paragraph>
    </section>
    <section heading="Sec. 8-19. Emergency measures.">
      <paragraph indent="1">(a)   Vacating buildings. When, in the opinion of the director there is actual and immediate danger of failure or collapse of a building or structure or any part thereof which would endanger life or when any structure or part of a structure has fallen and life is endangered by the occupation of the building, the director is hereby authorized and empowered to order and require occupants to vacate the same forthwith. He shall cause to be posted at each entrance to such building a notice reading as follows:</paragraph>
      <paragraph indent="0">"THIS BUILDING IS UNSAFE AND ITS USE OR OCCUPANCY HAS BEEN PROHIBITED BY MONTGOMERY COUNTY"</paragraph>
      <paragraph indent="0">and it shall be unlawful for any person to enter such building or structure except for the purpose of making the required repairs or of demolishing the same.</paragraph>
      <paragraph indent="1">(b)   Temporary safeguards. When, in the opinion of the director there is actual and immediate danger of collapse or failure of a building or structure or any part thereof which would endanger life, he shall cause the necessary work to be done to render such building or structure or part thereof temporarily safe, whether or not the legal procedure herein described has been instituted.</paragraph>
      <paragraph indent="1">(c)   Closing streets. When necessary for the public safety, the director may temporarily close sidewalks, streets, buildings and structures and places adjacent to such unsafe buildings and prohibit the same from being used.</paragraph>
      <paragraph indent="1">(d)   Emergency repairs. For the purposes of this section the director shall employ the necessary labor and materials to perform the required work as expeditiously as possible.</paragraph>
      <paragraph indent="1">(e)   Costs of emergency repairs. Costs incurred in the performance of emergency work shall be charged to the owner of the property in the manner of taxes and such cost shall constitute a lien on the property.</paragraph>
    </section>
    <section heading="Sec. 8-20. Stop work order.">
      <paragraph indent="1">(a)   In addition to the other provisions set forth in this chapter, whenever the director determines that work on a building or structure is being prosecuted in violation of the provisions of this chapter or chapter 31B, "Noise Control," including those conditions upon which the permit has been issued or in a manner which threatens the safety, health and welfare of the public, the director may order the work to be immediately stopped.</paragraph>
      <paragraph indent="1">(b)   The stop work order described herein shall be issued by the director in writing and served upon the owner of the property involved or his agent or to the person doing the work.</paragraph>
      <paragraph indent="1">(c)   It shall be unlawful for any person to continue or permit the continuance of work in or about a building after having been served with a stop work order, except such work as he is directed to perform to remove a violation or unsafe condition.</paragraph>
    </section>
    <section heading="Sec. 8-21. Revocation of permit.">
      <paragraph indent="1">The director may revoke a permit or approval issued under the provisions of this chapter in case of any false statement or misrepresentation of fact in the application or on the plans on which the permit or approval was based or in case of any violation of the conditions upon which such permit was issued.</paragraph>
    </section>
    <section heading="Sec. 8-22. Violations.">
      <paragraph indent="1">A person has committed a class A violation if the person violates any provision of this Chapter or another applicable federal, state, or County law regulating an aspect of building construction which the Department enforces, including:</paragraph>
      <paragraph indent="1">(a)   building, altering, or repairing a building or structure in violation of an approved plan; or</paragraph>
      <paragraph indent="1">(b)   violating an order of the Director or any condition of an approved plan, permit, or certificate issued under this Chapter.</paragraph>
      <paragraph indent="1">Sec. 2. Transition.  This Act does not apply to any appeal to the Board of Appeals that was filed before this Act took effect.</paragraph>
      <paragraph indent="1">Sec. 3. Regulations. Regulations 6-06AM and 7-06AM remain in effect, notwithstanding any amendment to the County Code in Section 1 of this Act, except for any provision of the National Fire Code that authorizes or refers to an appeal to the Board of Appeals.</paragraph>
    </section>
    <section heading="Sec. 8-23. Appeals.">
      <paragraph indent="1">(a)   Any person aggrieved by the issuance, denial, renewal, amendment, suspension, or revocation of a permit, or the issuance or revocation of a stop work order, under this Chapter may appeal to the County Board of Appeals within 30 days after the permit is issued, denied, renewed, amended, suspended, or revoked or the stop work order is issued or revoked.  A person may not appeal any other order of the Department, and may not appeal an amendment of a permit if the amendment does not make a material change to the original permit.  A person must not contest the validity of the original permit in an appeal of an amendment or a stop work order.</paragraph>
      <paragraph indent="1">(b)   After notice and hearing, the Board may affirm, remand, modify, or reverse the action of the Department.</paragraph>
      <paragraph indent="1">(c)   Any party may seek judicial review of a decision of the Board under Section 2-114.</paragraph>
      <paragraph indent="1">Sec. 2. Transition.  This Act does not apply to any appeal to the Board of Appeals that was filed before this Act took effect.</paragraph>
      <paragraph indent="1">Sec. 3. Regulations. Regulations 6-06AM and 7-06AM remain in effect, notwithstanding any amendment to the County Code in Section 1 of this Act, except for any provision of the National Fire Code that authorizes or refers to an appeal to the Board of Appeals.</paragraph>
    </section>
  </article>
  <article heading="Article III. Permits.">
    <section heading="Sec. 8-24. Application for permit.">
      <paragraph indent="1">(a)   When required. It is unlawful to construct, enlarge, alter, remove or demolish a building or change the occupancy of a building from one use group to another requiring greater strength, exitway or sanitary provisions; or to change to a prohibited use; or create or alter any ownership unit when a use under an occupancy certificate or a structure exists on the parent lot; or to install or alter any equipment for which provision is made or the installation of which is regulated by this chapter, without first filing an application with the department in writing and obtaining the required permit therefor; except, that ordinary repairs as defined in Section 8-3 which do not involve any violation of this Chapter are exempt from this provision.</paragraph>
      <paragraph indent="1">(b)   Form. Application for a permit shall be submitted on forms prescribed by the director and shall be accompanied by the required fee as prescribed by this chapter.</paragraph>
      <paragraph indent="1">(c)   Qualified applicants. Application for a permit shall be made by the owner or lessee of the building or structure, or agent of either or by the licensed engineer or architect employed in connection with the proposed work. If the application is made by a person other than the owner in fee, it shall be accompanied by a duly verified affidavit of the owner or the qualified person making the application that the proposed work is authorized by the owner in fee and that the applicant is authorized to make such application. The full names and addresses of the owner, lessee, applicant and of the responsible officer, if the owner or lessee is a corporate body, shall be stated in the application.</paragraph>
      <paragraph indent="1">(d)   Description of work. The application must contain a general description of the proposed work, its location, the use and occupancy of all parts of the building or structure and of all portions of the site or lot not covered by the building, the location of any ownership units on the lot, and such additional information as may be required by the director.</paragraph>
      <paragraph indent="1">(e)   Projects not requiring site plan or conditional use approval. For projects that do not require site plan approval or conditional use approval and include more than 10 parking spaces, an application for building permit must include a plan showing:</paragraph>
      <paragraph indent="2">(1)   the location and design of entrances and exits to public roads;</paragraph>
      <paragraph indent="2">(2)   the location and size of all buildings and structures;</paragraph>
      <paragraph indent="2">(3)   the location of parking spaces, directional markings, traffic-control devices and signs; and</paragraph>
      <paragraph indent="2">(4)   that it satisfies Division 59-6.2 of Chapter 59.</paragraph>
      <paragraph indent="1">(f)   Plans and specifications. The application for the permit shall be accompanied by not less than two (2) copies of specifications and of plans drawn to scale, with sufficient clarity and detailed dimensions to show the nature and character of the work to be performed. When quality of materials is essential for conformity to this chapter, specific information shall be given to establish such quality; and in no case shall this chapter be cited or the term “legal” or its equivalent be used as a substitute for specific information. The director may waive the requirement for filing plans when the work involved is of a minor nature.</paragraph>
      <paragraph indent="1">(g)   Plot diagram. Each applicant for a building or occupancy permit must file 2 copies of a plot plan drawn to scale, showing:</paragraph>
      <paragraph indent="2">(1)   The lot upon which the proposed building is to be erected, lot dimensions, lot and block numbers and subdivision name, if any;</paragraph>
      <paragraph indent="2">(2)   Name and width of abutting streets;</paragraph>
      <paragraph indent="2">(3)   Location, dimensions and use of existing buildings and other structures on the same lot;</paragraph>
      <paragraph indent="2">(4)   The location, dimensions and proposed use of buildings and other structures for which a permit is requested;</paragraph>
      <paragraph indent="2">(5)   Front and rear yard widths;</paragraph>
      <paragraph indent="2">(6)   North point and scale of plan; and</paragraph>
      <paragraph indent="2">(7)   If the permit is for a new residential building or accessory structure or an addition to an existing residential building, and a storm water management plan has not already been approved for that construction, the location of any existing and proposed drainage structure, including any swale, and the general flow of water, indicated by arrows, to and from each structure.</paragraph>
      <paragraph indent="1">(h)   Engineering details. The director may require adequate details of structural, mechanical and electrical work including computations, stress diagrams and other essential technical data to be filed. All engineering plans and computations shall bear the signature of the engineer or architect responsible for the design.</paragraph>
      <paragraph indent="1">(i)   Amendments to application. Subject to subsection (i), an amendment to a plan, application, or other document may be filed at any time before the work for which the permit is sought or issued is completed. Each timely filed amendment must be treated as part of the original application and filed with it.</paragraph>
      <paragraph indent="1">(j)   Time limit. An application for a permit for any proposed work must be treated as abandoned 6 months after the application was filed, unless the application has been diligently prosecuted or a permit was issued.  However, for reasonable cause, the Director may extend the time for the Department to consider an application for one or more additional periods which do not exceed 90 days each.</paragraph>
    </section>
    <section heading="Sec. 8-24A. Child day care facility.">
      <paragraph indent="1">A building in which a day care provider lives and provides child day care services for 12 or fewer children in accordance with all applicable State and County laws and regulations, including the requirement for a use and occupancy permit under Chapter 59, is a residential use for purposes of this Chapter.</paragraph>
      <paragraph indent="1">Section 2. Registration Fees.  The Council intends that registration fees collected under this Act [section] be used to defray administrative costs associated with it by both the planning board and executive agencies. To that end, the planning board and the executive should execute an agreement to allocate those revenues.</paragraph>
    </section>
    <section heading="Sec. 8-24B. Permits for property within homeowners' associations, municipal corporations, or special taxing districts.">
      <paragraph indent="1">(a)   Homeowners' association registration.</paragraph>
      <paragraph indent="2">(1)   If a homeowners' association, as defined in section 24B-1 of this Code, wants the county to assist it in exercising its right to approve a proposed project that requires a permit under section 8-24 of this chapter, the homeowners' association must register with the department and pay a fee determined by the director, based on the cost of services provided to the association under this section.</paragraph>
      <paragraph indent="2">(2)   A homeowners' association registers with the department by providing the department with:</paragraph>
      <paragraph indent="3">a.    A statement made under penalty of perjury that it has the authority under its bylaws, declarations, documents, rules, or regulations to approve a proposed project that requires a building permit;</paragraph>
      <paragraph indent="3">b.   The boundaries of the area covered by the homeowners' association's covenants, by premises address;</paragraph>
      <paragraph indent="3">c.   The name, address, and telephone number of the individual to contact for obtaining approval; and</paragraph>
      <paragraph indent="3">d.   Other information the director requires.</paragraph>
      <paragraph indent="2">(3)   A registration of a homeowners' association under this section expires after two (2) years and may be renewed as provided by executive regulation.</paragraph>
      <paragraph indent="1">(b)   Municipal corporation and special taxing district registration.</paragraph>
      <paragraph indent="2">(1)   If a municipal corporation or special taxing district wants the county to assist it in exercising its right to approve a proposed project that requires a permit under section 8-24 of this chapter, the municipal corporation or special taxing district must register with the department and pay a fee determined by the director, based on the cost of services provided to the municipality or district under this section.</paragraph>
      <paragraph indent="2">(2)   A municipal corporation or special taxing district registers with the department by providing the department with:</paragraph>
      <paragraph indent="3">a.   A copy of the municipal corporation's or special taxing district's law, rule, or regulation authorizing it to approve a proposed project that requires a building permit;</paragraph>
      <paragraph indent="3">b.   The boundaries of the municipal corporation or special taxing district, by premises address;</paragraph>
      <paragraph indent="3">c.   The address and telephone number of the office to contact for obtaining approval; and</paragraph>
      <paragraph indent="3">d.   Other information the director requires.</paragraph>
      <paragraph indent="1">(c)   Changes in authority and boundaries. A homeowners' association, municipal corporation, or special taxing district that registers under this section must re-register with the department within thirty (30) days after the effective date of a change in:</paragraph>
      <paragraph indent="2">(1)   Its authority to approve a proposed project; or</paragraph>
      <paragraph indent="2">(2)   Its boundaries.</paragraph>
      <paragraph indent="1">(d)   Registration list. The director must maintain and make available to the public a list of:</paragraph>
      <paragraph indent="2">(1)   The homeowners' associations registered under subsection (a) of this section; and</paragraph>
      <paragraph indent="2">(2)   The municipal corporations and special taxing districts registered under subsection (b) of this section.</paragraph>
      <paragraph indent="1">(e)   Permit application process.</paragraph>
      <paragraph indent="2">(1)   When a person applies for a permit under section 8-24 of this chapter, the director must ask the applicant if the site of the proposed project is within:</paragraph>
      <paragraph indent="3">a.   An area covered by covenants of a homeowners' association;</paragraph>
      <paragraph indent="3">b.   A municipal corporation; or</paragraph>
      <paragraph indent="3">c.   A special taxing district.</paragraph>
      <paragraph indent="2">(2)   The applicant must provide the director with a statement made under penalty of perjury whether the site of the proposed project is within an area covered by covenants of a homeowners' association, a municipal corporation, or a special taxing district.</paragraph>
      <paragraph indent="2">(3)   If the applicant indicates that the site of the proposed project is within an area covered by covenants of a homeowners' association, a municipal corporation, or a special taxing district, the director must ask the applicant for:</paragraph>
      <paragraph indent="3">a.   An approval form signed by an authorized representative of the homeowners' association indicating that the work described in the application meets the requirements of all bylaws, declarations, documents, rules, and regulations of the homeowners' association; or</paragraph>
      <paragraph indent="3">b.   A permit from the municipal corporation or special taxing district.</paragraph>
      <paragraph indent="2">(4)   If the applicant does not provide the director with the approval form from the homeowners' association or permit from the municipal corporation or special taxing district when required, the director must send notice promptly to the representative or office listed in the homeowners' association's, municipal corporation's, or special taxing district's registration that the form or permit has not been provided.</paragraph>
      <paragraph indent="2">(5)   The applicant's failure to obtain a signed approval form from a representative of the homeowners' association or a permit from the municipal corporation or special taxing district does not prevent the director from approving the application for a permit under section 8-24 of this chapter. The permit may not take effect earlier than ten (10) days after its issuance.</paragraph>
      <paragraph indent="1">(f)   Regulations. The county executive must adopt regulations under method (2) of section 2A-15 of this Code to implement this section.</paragraph>
      <paragraph indent="1">(g)   Penalty. Section 8-22 of this chapter, establishing criminal penalties for violation of this chapter, does not apply to this section.</paragraph>
      <paragraph indent="1">(h)   Liability. The county is not liable for any act or failure to act by the department in carrying out the provisions of this section.</paragraph>
    </section>
    <section heading="Sec. 8-24C. Expedited review process for a solar photovoltaic system.">
      <paragraph indent="1">The Department must adopt a fast track review process for each permit to install a rooftop solar photovoltaic system for a single family detached home that meets standardized requirements adopted by the Department.  The Department must set the application fee by Executive Regulation adopted under Method 2 for each permit to install a rooftop solar photovoltaic system for a single family detached home that meets standardized requirements adopted by the Department.</paragraph>
    </section>
    <section heading="Sec. 8-24D. Expedited review process for an electric vehicle charging station.">
      <paragraph indent="1">The Department must adopt a fast track review process for each permit to install an electric vehicle charging station at a single family detached home that meets standardized requirements adopted by the Department.  The Department must set the application fee by Executive Regulation adopted under Method 2 for each permit to install an electric vehicle charging station at a single family detached home that meets standardized requirements adopted by the Department.</paragraph>
    </section>
    <section heading="Sec. 8-25. Permits.">
      <paragraph indent="1">(a)    Action on application. The Director must examine or cause to be examined each application for a building permit or an amendment to a permit within a reasonable time after the application is filed. If the application or the plans do not conform to all requirements of this Chapter, the Director must reject the application in writing and specify the reasons for rejecting it. If the proposed work conforms to all requirements of this Chapter and all other applicable laws and regulations, the Director must issue a permit for the work as soon as practicable.</paragraph>
      <paragraph indent="1">(b)    Time limit.</paragraph>
      <paragraph indent="2">(1)   A building permit is invalid if:</paragraph>
      <paragraph indent="3">(A)   an approved inspection, as required by this Chapter, is not recorded in the Department's inspection history file within 12 months after the permit is issued and a second approved inspection is not recorded in the Department's inspection history file within 14 months after the permit is issued; or</paragraph>
      <paragraph indent="3">(B)   the authorized work is suspended or abandoned for a period of 6 months.</paragraph>
      <paragraph indent="2">(2)   The Director must extend a permit for 6 months if the permit holder, before the permit expires, files a written request for an extension and pays an extension fee equivalent to the minimum fee then applicable to the original permit.  Except as provided in paragraph (3), the Director must not grant more than one extension per permit under this subsection.</paragraph>
      <paragraph indent="2">(3)   For any building located in an enterprise zone, the Director may extend a permit for additional 6-month periods if the permit holder:</paragraph>
      <paragraph indent="3">(A)   shows good cause for each extension;</paragraph>
      <paragraph indent="3">(B)   requests an extension in writing before the permit expires; and</paragraph>
      <paragraph indent="3">(C)   pays the fee specified in paragraph (2).</paragraph>
      <paragraph indent="1">(c)    Reserved.</paragraph>
      <paragraph indent="1">(d)    Signature to permit. The director or his authorized representative shall attach his signature to each permit issued.</paragraph>
      <paragraph indent="1">(e)    Approved plans. The director shall stamp or endorse in writing both sets of corrected plans "approved" and one set of such approved plans shall be retained by him and the other set shall be kept at the building site, open to inspection of the director or his authorized representative at all reasonable times.</paragraph>
      <paragraph indent="1">(f)    Approval in part. The director may issue a permit for the construction of foundations or any other part of a building or structure before the entire plans and specifications for the whole building have been submitted; provided, that adequate information and detailed statements have been filed complying with all the pertinent requirements of this chapter. The holder of such permit for the foundations or other part of a building or structure shall proceed at his own risk with the building operation and without assurance that a permit for the entire structure will be granted.</paragraph>
      <paragraph indent="1">(g)    Posting of permit and site plans. The building permit or a true copy thereof and a copy of the building or other plans covered by the permit shall be kept on the site of operations open to inspection by the department, fire or police officials, in the course of their duties, during the entire time the work is in progress and until its completion.</paragraph>
      <paragraph indent="1">(h)    Notice of start and other inspections. At least twenty-four (24) hours' notice of start of work under a building permit shall be given to the department unless this requirement is waived in the building permit.</paragraph>
      <paragraph indent="1">At least twenty-four (24) hours' notice shall be given the department for inspection of footings, concrete reinforcement, fire stopping and similar details before they are covered up.</paragraph>
      <paragraph indent="1">The provision of § 8-25(b) invalidating a building permit which is not used for 6 months is mentioned in connection with a discussion of Montgomery County's growth policy in P. J. Tierney, Maryland's Growing Pains: The Need for State Regulation, 16 U. of Balt. L. Rev. 201 (1987), at p. 236.</paragraph>
    </section>
    <section heading="Sec. 8-25A. Permits affecting certain residential properties; public notice.">
      <paragraph indent="1">(a)   If a permit is issued under Section 8-25 for new construction on vacant residentially or agriculturally zoned land, or construction of a building or structure that would affect the footprint or height of any existing structure located on residentially or agriculturally zoned land or that is exempt from and exceeds any applicable building height limit, the Director must promptly require the recipient to post on the lot a conspicuous sign describing the proposed construction, specifying the time limit to appeal the issuance of the permit to the Board of Appeals, and including any other information the Director requires. The sign must conform to design, content, size, and location requirements set by regulation under Section 8-13(a).</paragraph>
      <paragraph indent="1">(b)   The regulations adopted under subsection (a) may allow a central sign to be posted, or otherwise vary the design, content, size, or location requirements, for any subdivision that consists of more than 5 new dwellings at a single site.</paragraph>
      <paragraph indent="1">(c)   The recipient must post the required sign within 3 days after the Department releases the permit to the recipient, and must maintain the sign until 30 days after the permit was released.</paragraph>
      <paragraph indent="1">(d)   If the recipient of a permit does not post a sign as required by this Section, the permit is automatically suspended until the recipient has posted the proper sign.  If the recipient begins work under the permit without having posted the sign as required, the Director must immediately issue a stop work order. During the 30-day period after the sign is properly posted, any person may appeal the issuance of the permit as if the permit had been released to the recipient on the day the sign was posted.</paragraph>
    </section>
    <section heading="Sec. 8-25B. Immigration Detention Facility – prohibited.">
      <paragraph indent="1">(a)   Definitions. In this Section, the following term(s) have the meanings indicated:</paragraph>
      <paragraph indent="2">Detention facility means any building, facility, or structure used, in whole or in part, to house or detain individuals for civil or criminal violations. Detention facility includes an immigration detention facility.</paragraph>
      <paragraph indent="1">(b)   Prohibition. The Department must not issue a building permit or a use-and-occupancy permit for a privately-owned detention facility.</paragraph>
    </section>
    <section heading="Sec. 8-26. Conditions of permit.">
      <paragraph indent="1">(a)    Generally. A permit to begin work for new construction, alteration, removal, demolition, or other building operation must not be issued until the fees authorized in this Section are paid to the Department.  An amendment to a permit that requires an additional fee because of an increase in the estimated cost of the work involved must not be approved until the additional fee is paid. The Department must not issue any building permit for a residence, except a building designed to be used as a residence for the person's own or immediate family use, under Section 31C-1, to any person except a licensed building contractor or an authorized agent of the licensed building contractor.</paragraph>
      <paragraph indent="1">(b)   Compliance with code. The permit shall be a license to proceed with the work and shall not be construed as authority to violate, cancel or set aside any of the provisions of this chapter except as specifically stipulated by legally granted waivers or modifications as described in the application. The issuance of a permit shall not prevent the department from thereafter requiring a correction of errors in plans or in construction or of violations of this chapter and all other applicable laws or ordinances specifically referring thereto. Certification by a certified engineer that the plans and specifications are in compliance with this chapter shall be accepted by the director as prima facie evidence that all the requirements of this chapter have been met unless he discovers otherwise.</paragraph>
      <paragraph indent="1">(c)    Compliance with permit. All work must conform to the approved application and plans for which the permit has been issued  and any approved amendments to the permit.</paragraph>
      <paragraph indent="1">(d)   Compliance with plot plan. All new work shall be located strictly in accordance with the approved plot plan.</paragraph>
      <paragraph indent="1">(e)   Change in plot plan. No lot or plot shall be changed, increased or diminished in area from that shown on the official plot plan, unless a revised diagram showing such changes accompanied by the necessary affidavit of owner or applicant shall have been filed and approved; except, that such revised plot plan will not be required if the change is caused by reason of an official street opening, street widening or other public improvement.</paragraph>
      <paragraph indent="1">(f)   Compliance with plumbing and gas fitting regulations. Permits for the erection, enlargement or alteration of buildings will not be issued until evidence has been presented that the plans of the proposed building comply with all applicable regulations relating to water supply, sewerage, drainage, plumbing and gas fitting.</paragraph>
      <paragraph indent="1">(g)   Compliance with zoning regulations. The building or structure must comply with all applicable zoning regulations, including all conditions and development standards attached to a site plan approved under Chapter 59. The issuance of a permit by the Department for the building or structure does not affect an otherwise applicable zoning regulation.</paragraph>
      <paragraph indent="1">(h)   Compliance with location certificate. Before any first floor construction of a building or structure is placed upon the foundation walls thereof, the owner of such building or structure shall provide the department with two (2) copies of a location plat, certified by a land surveyor entitled by law to practice property line surveying in the state; except, that a professional engineer entitled by law to practice in this state may provide such certification only where property lines and corners are already existing and determined on the ground. This plat shall be drawn accurately to an appropriate scale and shall show the actual location of the building or structure walls with respect to property lines and existing buildings or structures on the same lot, parcel or tract.</paragraph>
      <paragraph indent="1">(i)   Compliance with excavation, grading and sediment control regulations.</paragraph>
      <paragraph indent="2">(1)   Unless the construction is exempted by Chapter 19, an applicant for a building permit must obtain a sediment control permit before the building permit is issued.</paragraph>
      <paragraph indent="2">(2)   If a sediment control permit is suspended or revoked, the building permit for construction within the area subject to the sediment control permit may be suspended or revoked.</paragraph>
      <paragraph indent="2">(3)   All work shall conform to plans approved and/or permits issued in accordance with Chapter 19 of this Code.</paragraph>
      <paragraph indent="1">(j)    Compliance with performance bond for construction of streets before issuance of permit. As used in this subsection, the phrase “such streets” means streets abutting the building site and those extensions of streets necessary to meet the minimum requirements of Chapter 49.</paragraph>
      <paragraph indent="2">(1)   A permit must not be issued for the erection of any building or structure unless the applicant delivers to the County a performance bond for the construction of streets in all rights-of-way abutting the property on which the building or structure will be erected and those extensions of streets necessary to meet the minimum requirements of Chapter 49.  However, a performance bond for the construction of streets is not required when:</paragraph>
      <paragraph indent="3">(A)   all streets are paved with a hard surface and have been accepted for maintenance or are being maintained by the County; or</paragraph>
      <paragraph indent="3">(B)   the County Council authorized construction of each street on a front foot assessment basis.</paragraph>
      <paragraph indent="2">(2)   The performance bond to be delivered shall be that bond required by Section 49-40 of this Code, and such bond shall be in an amount to cover the entire cost of construction of such streets.</paragraph>
      <paragraph indent="2">(3)   If the applicant owns, or is obligated by contract to develop, all or substantially all of the property abutting the streets, a bond in an amount to cover the cost of grading of the streets is sufficient to obtain a building permit. When the applicant does not own, and is not obligated by contract to develop, all or substantially all of the property abutting the streets, the applicant may demand that the Director of Transportation present to the County Council the applicant's proposal to construct the streets on a front-foot-assessment basis. If the County Council refuses to authorize the construction of the streets on a front-foot- assessment basis, the Department must not require the applicant to post a performance bond.</paragraph>
      <paragraph indent="2">(4)   Whenever the applicant must post a performance bond to cover the entire cost of construction, the applicant simultaneously must apply to the Department of Permitting Services for a permit to construct the streets. If the bond covers only grading, the applicant simultaneously must apply for a permit to grade the streets.</paragraph>
      <paragraph indent="2">(5)   If the construction or grading guaranteed by such bond is not begun and completed within a period of one (1) year after the delivery of such bond, the County may proceed to cause such work to be done, in accordance with the provisions of Chapter 49 of this Code and hold the principal or surety on such bond or both liable for the cost thereof.</paragraph>
      <paragraph indent="1">(k)   Location of underground utilities. On all work calling for excavation exceeding twelve (12) inches in depth, the applicant shall provide evidence of the location of all utility lines within the area of the proposed excavation.</paragraph>
      <paragraph indent="1">(l)    Compliance with stop work orders. The issuance of a permit shall be expressly conditioned upon the applicant's prompt compliance with all stop work orders issued by the Director.</paragraph>
      <paragraph indent="1">(m)   County line.  Every building or other structure for which a permit is issued must be located completely in the County.</paragraph>
      <paragraph indent="1">(n)   Tree protection.  If any clearing, construction, or development allowed by any permit issued under this Chapter would result in the trimming, cutting, removal, or injury of any roadside tree (as defined in Section 49-35) or any tree located in a State right-of-way in the County, the Director must not issue that permit until:</paragraph>
      <paragraph indent="2">(1)   the applicant obtains a roadside tree care permit as necessary from the State Department of Natural Resources; and</paragraph>
      <paragraph indent="2">(2)   the applicant has submitted, in connection with the permit applied for under this Chapter, and the Director has approved, a site-specific tree protection plan that meets the requirements of Section 49-36A(d).</paragraph>
      <paragraph indent="2">The Department must approve or reject each proposed plan within 30 days after receiving it. If the Department does not act on a proposed plan within 30 days, the plan is approved by default. The Department may require further information after a proposed plan is submitted, and may extend this deadline once for an additional 15 days to receive any needed information. The Department also may extend this deadline at the request of the applicant.</paragraph>
      <paragraph indent="1">(o)   Regulations.   The Director may recommend, and the Executive may adopt, regulations under Method (2) to specify standards and practices needed to protect and maintain roadside trees, including construction practices needed to prevent or minimize damage to roadside trees, under subsection (n)  These regulations must be at least as stringent as applicable state roadside tree care standards and requirements.</paragraph>
    </section>
    <section heading="Sec. 8-27. Demolition or removal of buildings.">
      <paragraph indent="1">(a)    Notice.  The Director must mail written notice, at least 10 days before the Director issues a permit to remove or demolish a building or structure, to the owner of each adjacent and confronting lot.  The applicant must give the Department the name and address of the owner of each adjacent and confronting lot.  The notice must identify the building or structure to be demolished or removed, specify the process for issuing the permit and the time limit to appeal the issuance of a permit to the Board of Appeals, and include any other information the Director finds useful.  The Director need not deliver this notice if unsafe conditions require immediate demolition or removal of the building or structure.</paragraph>
      <paragraph indent="1">(b)   Signage.  The Director need not deliver the notice required by subsection (a) if, at least 10 days before the Director issues a permit to remove or demolish a building or structure, the applicant posts at a conspicuous location on the lot a sign describing the proposed demolition or removal, specifying the process for issuing the permit and the time limit to appeal the issuance of a permit to the Board of Appeals, and including any other information the Director requires.  The sign must conform to design, content, size, and location requirements set by regulation under Section 8-13(a).</paragraph>
      <paragraph indent="1">(c)   Special notice for older buildings.  At least 30 days before the Director issues a permit to demolish or remove a building, other than a single-family dwelling, that will be more than 25 years old when it is demolished or removed, the Director must list the address of the property on a properly designated website or other widely available form of electronic notice.</paragraph>
      <paragraph indent="1">(d)   Notice to utilities.  Before the Director may issue a demolition or removal permit, the applicant must notify each connected public utility and obtain a written release confirming that all service connections and appurtenant equipment, such as meters and regulators, have been safely disconnected and sealed.</paragraph>
      <paragraph indent="1">(e)   Permit requirement; conditions.  A person must not demolish or remove a building or structure unless the Director has issued a permit to do so under this Section.  Each demolition or removal permit must require the applicant to:</paragraph>
      <paragraph indent="2">(1)   before demolishing or removing a building or structure, exterminate any rodents or other pests in it;</paragraph>
      <paragraph indent="2">(2)   after demolition or removal, clear all construction and demolition debris;</paragraph>
      <paragraph indent="2">(3)   restore the established grade of the surrounding land, unless a sediment control permit is otherwise required; and</paragraph>
      <paragraph indent="2">(4)   at all times keep the site free from any unsafe condition.</paragraph>
      <paragraph indent="1">(f)    Bond or surety.  Each applicant for a demolition or removal permit must file a performance bond, cash, certificate of guarantee, or surety with the Department, in an amount equal to the cost of demolition or removal, to assure the safe and expedient demolition or  removal of the building or structure and clearing of the site. If the building or structure is not demolished or removed and the site is not cleared of all debris within the time specified in the permit, but not sooner than 60 days after the permit is issued, the Director may enter the property, demolish or remove the building or structure, clear the site of debris, and take action to forfeit the performance bond, enforce the guarantee, or otherwise reimburse the Department for its cost.</paragraph>
      <paragraph indent="1">(g)   Definitions.  As used in this Section:</paragraph>
      <paragraph indent="2">(1)   Demolish means to tear down or destroy an entire building or structure, or sixty-seven (67) percent or more of first story exterior walls of a one-family or two-family dwelling unit. Demolish includes the conversion of an exterior wall into an interior wall. Basement and cellar walls are not considered exterior walls; and</paragraph>
      <paragraph indent="2">(2)   Remove means to move a building or structure substantially intact from or within a site.</paragraph>
    </section>
    <section heading="Sec. 8-28. Certificate of use and occupancy.">
      <paragraph indent="1">(a)   Applicability.</paragraph>
      <paragraph indent="2">(1)   A use-and-occupancy permit is required before any building, structure, or land can be used or can be converted, wholly or in part, from one use to another.</paragraph>
      <paragraph indent="2">(2)   Exemptions from use-and-occupancy permit requirement:</paragraph>
      <paragraph indent="3">(A)   land or buildings used exclusively for agricultural purposes;</paragraph>
      <paragraph indent="3">(B)   a use for which a valid occupancy permit was issued and not revoked before June 1, 1958; and</paragraph>
      <paragraph indent="3">(C)   a Transitory Use.</paragraph>
      <paragraph indent="1">(b)   Application Requirements. Each application for a use-and-occupancy permit must be accompanied by 2 copies of a plan drawn to scale showing:</paragraph>
      <paragraph indent="2">(1)   the lot on which a use is proposed, lot dimensions, lot and block numbers and subdivision name, if any;</paragraph>
      <paragraph indent="2">(2)   the location, extent, and layout for the proposed use and any other pertinent information; and</paragraph>
      <paragraph indent="2">(3)   north point, date and scale of plan.</paragraph>
      <paragraph indent="1">(c)   New buildings. It is unlawful for any person to use or occupy a building hereafter erected in whole or in part until the certificate of use and occupancy is issued by the Director in satisfaction of this Chapter.</paragraph>
      <paragraph indent="1">(d)   Buildings hereafter altered. It is unlawful for any person to use or occupy a building hereafter enlarged, extended or altered to change from one use group to another, in whole or in part until a certificate of use and occupancy is issued by the director certifying that the work was completed in satisfaction of the approved permit. Any use or occupancy that was continued during the work of alteration, must be discontinued within 30 days after the completion of the alteration unless the required certificate is secured from the Director.</paragraph>
      <paragraph indent="1">(e)   Existing buildings. Upon written request from the owner of an existing building, the Director must issue a certificate of use and occupancy if there are no violations of law or orders of the Director pending. In addition, the Director must establish that the alleged use of the building has heretofore existed. Nothing in this Chapter requires the removal, alteration, or abandonment of the use and occupancy of a lawfully existing building, unless such use is deemed to endanger public safety and welfare.</paragraph>
      <paragraph indent="1">(f)   Changes in use and occupancy. After a change of use is made in a building, a person is prohibited from reestablishing a prior use that is not lawful for a new building of the same type of construction unless the owner complies with all the applicable provisions of this Chapter.</paragraph>
      <paragraph indent="1">(g)   Temporary occupancy. Upon the request of the holder of a permit, the Director may issue a temporary certificate of occupancy for a building or structure or part thereof before the entire work covered by the permit shall have been completed if that such portion or portions may be occupied safely before full completion of the building without endangering life or public welfare.</paragraph>
      <paragraph indent="1">(h)   Necessary Findings.</paragraph>
      <paragraph indent="2">(1)   The Department must find the building complies with Chapter 59.</paragraph>
      <paragraph indent="2">(2)   Any building, structure, or land on a site with any previous development approval must satisfy the requirements, representations, plans, and conditions contained in the decision or resolution of the deciding body.</paragraph>
      <paragraph indent="2">(3)   The Department must inspect construction or alteration for completion under the applicable decision or resolution.</paragraph>
      <paragraph indent="1">(i)   Contents of certificate. When a building or structure is entitled to a certificate of use and occupancy, the Director must issue a certificate 10 days after written applications. The certificate certifies compliance with this Chapter and the purpose for which the building or structure may be used. The certificate of use and occupancy must specify the use group, the fire grading, the allowable live load on all floors, the occupancy load in the building and all parts of the building and any special stipulations and conditions of the building permit.</paragraph>
    </section>
    <section heading="Sec. 8-29. Building within floodplain areas and on unsafe land.">
      <paragraph indent="1">(a)   A building permit must not be issued for any structure or any alteration of an existing structure:</paragraph>
      <paragraph indent="2">(1)   On land which lies within the floodplain covered by the 100-year flood, as defined in Section 19-36, of any stream or drainage course, or on land which the Director finds to be unsafe for development use because it is subject to flooding, erosion, unstabilized slope or fill within the danger reach of a high hazard dam, or otherwise located in a situation that causes unsafe building conditions; or</paragraph>
      <paragraph indent="2">(2)   In violation of a residential building restriction line placed on a recorded subdivision plat under the subdivision law, except that a building permit may be issued for fences, public utilities, recreation and agricultural uses, and for reconstruction, repair, or improvement of single family dwellings located within any floodplain covered by the 100-year flood as defined in Section 19-36.</paragraph>
      <paragraph indent="1">(b)   No part of any on-site sewage disposal system may be located within the floodplain covered by the 100-year flood as defined in section 19-36.</paragraph>
    </section>
    <section heading="Sec. 8-29A. Residential fire sprinklers.">
      <paragraph indent="1">(a)    In this Section, fire sprinkler system means equipment that includes 1 or more devices that:</paragraph>
      <paragraph indent="2">1.   open automatically by operation of a heat-responsive releasing mechanism;</paragraph>
      <paragraph indent="2">2.   discharge water in a specific pattern over a designated area to extinguish or control fire;</paragraph>
      <paragraph indent="2">3.   use the same service water supply pipe to the building that the domestic water system uses;</paragraph>
      <paragraph indent="2">4.   meet the requirements of current National Fire Protection Association standards as modified by the Director of Fire and Rescue Services; and</paragraph>
      <paragraph indent="2">5.   are approved by the Director of Fire and Rescue Services.</paragraph>
      <paragraph indent="1">(b)    The County must not issue a building permit for the construction or reconstruction of any residential building unless the plans include the installation in each dwelling unit and any attached accessory structure of a fire sprinkler system.</paragraph>
      <paragraph indent="1">(c)    The County Executive must issue regulations to implement this Section.  The regulations may authorize the Director to approve the use of specific construction alternatives that provide equivalent or greater protection of the public in residential buildings in which fire sprinkler systems will be installed.</paragraph>
      <paragraph indent="1">(d)   After inspection and final approval of a fire sprinkler system required under this Section, the inspector must provide to the initial occupant of the dwelling unit written information approved by the Fire Administrator about the proper care and maintenance of a residential fire sprinkler system.  If the dwelling unit has never been occupied, the builder or other current owner must not accept payment or rent for the unit until the inspector has transmitted this fire sprinkler information to the initial occupant.  The Fire Administrator must make the information widely available to residents who purchase or lease a previously occupied unit with an installed fire sprinkler system, and other County residents.</paragraph>
      <paragraph indent="1">(a) § 8-29A(d), as added by Section 1, applies to any detached single-family dwelling unit for which an application for a building permit is filed on or after July 1, 1990.</paragraph>
      <paragraph indent="1">(b) § 8-29A(b), as amended by Section 1, applies to any group home for which an application for a building permit is filed on or after July 1, 1990.</paragraph>
      <paragraph indent="1">(c) The builder must install a fire sprinkler system that complies with § 8-29A(e), as added by Section 1, in any primary sales model detached single-family dwelling unit which is shown to prospective buyers for sales purposes on or after July 1, 1990.</paragraph>
    </section>
    <section heading="Sec. 8-29B. Control of water runoff on small lots.">
      <paragraph indent="1">(a)   The Director must not issue a building permit for any detached one- or two-family residential building located on a recorded lot smaller than 15,000 square feet, or a permit for any addition to such a residential building that would increase the building lot coverage by more than 400 square feet, unless the plans provide for safe conveyance or control of any increased water runoff, resulting from additional impervious area or any other topographic alteration, that would drain onto any adjacent or nearly private property.</paragraph>
      <paragraph indent="1">(b)   In this Section, approved drainage system means any method of safe conveyance from the property or storage on the property of on-site water runoff at the design rate specified in subsection (c), using one or more of the following methods or devices or any other method or device approved by the Director that would provide equivalent or greater protection of adjacent and nearby properties:</paragraph>
      <paragraph indent="2">(1)   on-site absorption or drainage device, such as rain barrel, cistern with slow release or controlled pump discharge, underground percolation and storage system, rain garden, rooftop garden or detention device, bioretention filter, or vegetation buffer;</paragraph>
      <paragraph indent="2">(2)   existing or new drainage facility, such as drainage interceptor, inlet, trench, permeable paved area, or similar feature;</paragraph>
      <paragraph indent="2">(3)   drainage line, inlet or pipe, or other engineered feature such as a swale or ditch; or</paragraph>
      <paragraph indent="2">(4)   natural topography or buffer area that successfully absorbs water drainage.</paragraph>
      <paragraph indent="1">(c)   Each approved drainage system must be designed to convey or control at least 1.5 inches of rainfall during a 24-hour period.</paragraph>
      <paragraph indent="1">(d)   After the approved drainage system is installed, the permittee must certify to the Director that the system:</paragraph>
      <paragraph indent="2">(1)   has been installed as provided in the plans approved by the Director; and</paragraph>
      <paragraph indent="2">(2)   will convey or control the water runoff specified in subsection (c) without impacting adjacent or nearby private properties.</paragraph>
      <paragraph indent="1">(e)   The permittee and the permittee’s successors in interest must preserve and maintain each approved drainage system to the extent necessary to provide the same level of protection for adjacent and nearby properties.  The permittee and the permittee’s successors in interest must obtain the Director’s approval before materially modifying any element of an approved drainage system.  The Director may require a permittee to record an easement in the County land records for any approved drainage system to assure the continued preservation and maintenance of that system.</paragraph>
    </section>
  </article>
  <article heading="Article IV. Timely Adequate Public Facilities Determination.">
    <section heading="Sec. 8-30. Purpose; definitions.">
      <paragraph indent="1">(a)    Purpose. The purpose of this article is to avoid the premature development of land where public facilities, including transportation, are inadequate. It is intended to promote better timing of development with the provision of adequate public facilities.</paragraph>
      <paragraph indent="1">(b)    Definitions. In this article, the following words and phrases have the meanings stated, unless the context clearly indicates otherwise.</paragraph>
      <paragraph indent="2">(1)   Development means proposed work to construct, enlarge, or alter a building for which a building permit is required. Development does not include an addition to, or renovation or replacement of, an existing building if, as measured under guidelines adopted by the Planning Board for calculating numbers of vehicle trips and students:</paragraph>
      <paragraph indent="3">(A)   occupants of the building would generate fewer than 30 total peak hour vehicle trips; or, if they would generate more than 30 trips, the total number of trips would not increase by more than 5 over the number of trips generated by the building at full occupancy; and</paragraph>
      <paragraph indent="3">(B)   the number of public school students who will live in the building would not increase by more than 5 over the number of students generated by the building at full occupancy.</paragraph>
      <paragraph indent="2">(2)   Non-residential development means any development that does not contain only any type of dwelling or dwelling unit (including a multiple-family building, mobile home or townhouse) as defined in Section 59-A-2, and any extension, addition, or accessory building.</paragraph>
      <paragraph indent="2">(3)   Existing building means a building that is substantially intact when an application for a building permit for renovation, replacement, or reconstruction is filed.</paragraph>
      <paragraph indent="2">(4)   Renovation means an interior or exterior alteration that does not affect a building’s footprint.</paragraph>
      <paragraph indent="2">(5)   Replacement means demolition or partial demolition of an existing building and rebuilding that building.  A replacement building may exceed the footprint of the previous building.</paragraph>
      <paragraph indent="2">(6)   Recorded lot means any parcel, lot, or other tract of land recorded as developable property among the County land records.</paragraph>
      <paragraph indent="2">(7)   Timely adequate public facilities determination means an adequate public facilities determination by the Planning Board that is required before a building permit is issued, or is within the time limits prescribed by law for the validity of an adequate public facilities determination, or both.</paragraph>
    </section>
    <section heading="Sec. 8-31. Requirement for timely adequate public facilities determination; applicability.">
      <paragraph indent="1">(a)    As provided in subsection (b), the Director may issue a building permit only if the Planning Board has made a timely determination that public facilities will be adequate to serve the proposed development encompassed by the permit application under:</paragraph>
      <paragraph indent="2">(1)   Chapter 50, if required;</paragraph>
      <paragraph indent="2">(2)   Chapter 59 for project plans or site plans, if required; or</paragraph>
      <paragraph indent="2">(3)   Section 8-32 for development if the Planning Board or its designee finds that a new adequate public facilities determination is required under this Article, Section 50-20, or other applicable law.</paragraph>
      <paragraph indent="1">The work performed after the permit is issued must conform to the uses and amount of development for which the adequacy of public facilities was reviewed.</paragraph>
      <paragraph indent="1">(b)   Applicability.  This Article applies to each applicant for a building permit on a recorded lot for which no valid finding of adequate public facilities has been made, including any recorded lot for which an original finding of adequate public facilities has expired.</paragraph>
    </section>
    <section heading="Sec. 8-32. Administrative procedures.">
      <paragraph indent="1">(a)    Initial referral of applications. The Director must refer each building permit application to which this Article applies to the designee of the Planning Board to conduct an adequate public facilities analysis for the Board’s review.</paragraph>
      <paragraph indent="1">(b)   Review by other agencies.  The Director must also refer each application to which this Article applies for comments on the adequacy of public facilities to:</paragraph>
      <paragraph indent="2">(1)   the Department of Transportation;</paragraph>
      <paragraph indent="2">(2)   the Superintendent of the Montgomery County Public School System;</paragraph>
      <paragraph indent="2">(3)   the County Fire and Rescue Service; and</paragraph>
      <paragraph indent="2">(4)   the Department of Police.</paragraph>
      <paragraph indent="0">Each recipient must submit any comments on the application to the Planning Board within 30 days after receiving the application from the Director.</paragraph>
      <paragraph indent="1">(c)    Review and finding by Planning Board.</paragraph>
      <paragraph indent="2">(1)   Standards and Conditions. The Planning Board may consider an application for timely adequate public facilities determination as part of a site plan review under Division 59-D-3 if site plan review is otherwise required. The Board may condition its adequacy finding on the execution of appropriate agreements with an applicant to the extent permitted for adequate public facilities determinations under subdivision or site plan approval procedures.</paragraph>
      <paragraph indent="2">(2)   Hearing Requirement. An applicant for a building permit or other interested person must be given the opportunity for a hearing before the Board acts under this Section. The Planning Board finding is final agency action for purposes of judicial review.</paragraph>
      <paragraph indent="2">(3)   Planning Board Finding. When the Planning Board receives all necessary information from the applicant and reviews any comments received from other public agencies and any other person, the Board must find, consistent with the adopted Growth Policy, whether all applicable public facilities will be adequate to support the proposed development.</paragraph>
      <paragraph indent="2">(4)   The Planning Board may establish procedures to carry out its responsibilities under this Section, including procedures to delegate the review of certain applications to a designee of the Board.</paragraph>
      <paragraph indent="1">(d)    Decision by Director.</paragraph>
      <paragraph indent="2">(1)   Administrative Decision. After receiving the adequacy finding of the Planning Board, the Director may issue, deny, or condition any permit, as appropriate, including requiring the applicant to execute binding agreements with the Planning Board.</paragraph>
      <paragraph indent="2">(2)   Appeal. An applicant or other interested person may appeal the decision of the Director as provided in Section 8-23. The Planning Board must receive notice of each decision of the Director under this Section and any appeal to the Board of Appeals. The Planning Board may intervene, request a hearing, and otherwise participate fully in a proceeding before the Director, the Board of Appeals, or any court with respect to the adequacy of public facilities.</paragraph>
      <paragraph indent="1">(e)    Time limit. An adequate public facilities determination made under this section remains valid for not less than 5 or more than 12 years, using the standards in Section 50-20.</paragraph>
    </section>
    <section heading="Sec. 8-33. Reserved." />
    <section heading="Sec. 8-34. Reserved." />
    <section heading="Sec. 8-35. Reserved." />
    <section heading="Sec. 8-36. Reserved." />
  </article>
  <article heading="Article V. Development Approval Payments.">
    <section heading="Sec. 8-37. Payment.">
      <paragraph indent="1">(a)    Any person who receives approval of a preliminary plan of subdivision under any Alternative Review Procedure for Transportation Facilities adopted in the Growth Policy which requires a Development Approval Payment must pay a development approval payment to the Director of Finance.</paragraph>
      <paragraph indent="1">(b)    If the applicant has received approval under the Alternative Review Procedure for limited residential development, the applicant must pay the applicable development approval payment before a building permit is released for any building in the area covered by the subdivision plan.</paragraph>
      <paragraph indent="1">(c)    If the applicant has applied under the Alternative Review Procedure for Metro Station Policy Areas, the applicant must agree, in a contract with the Planning Board and the Department of Transportation, as a condition of plan approval to pay the first installment of the development approval payment, as provided in Section 8-41, for each building in the area covered by the subdivision plan before the Department releases a building permit for that building. In addition, the applicant, and the owner of the property if the owner is not the applicant, must expressly accept in the same contract:</paragraph>
      <paragraph indent="2">(1)   the applicant's liability for the entire development approval payment, and</paragraph>
      <paragraph indent="2">(2)   the attachment to all real property in the subdivision of the lien imposed under Section 8-42(e).</paragraph>
    </section>
    <section heading="Sec. 8-38. Rates.">
      <paragraph indent="1">(a)   The rate of the payment required under Section 8-37 is:</paragraph>
      <paragraph indent="2">(1)   $1 per square foot of gross floor area in any building or part of a building that is:</paragraph>
      <paragraph indent="3">(A)   owned by a nonprofit organization that is exempt from federal income taxes under Section 501(c)(3) of the Internal Revenue Code;</paragraph>
      <paragraph indent="3">(B)   intended to be used primarily for the direct provision of charitable services; and</paragraph>
      <paragraph indent="3">(C)   not intended to be used as a permanent residence;</paragraph>
      <paragraph indent="2">(2)   $2.40 per square foot of gross floor area in any building or part of a building that is intended to be used primarily:</paragraph>
      <paragraph indent="3">(A)   for storage, industrial or manufacturing, or research and development purposes, or</paragraph>
      <paragraph indent="3">(B)   for offices by a nonprofit organization that is exempt from federal income taxes under Section 501(c)(3) of the Internal Revenue Code;</paragraph>
      <paragraph indent="3">(3)   $4 per square foot of gross floor area in any other nonresidential building or part of a building;</paragraph>
      <paragraph indent="3">(4)   $3 per square foot of gross floor area in any multi-family residential building or any addition to a multi-family residential building; and</paragraph>
      <paragraph indent="3">(5)   $3.75 per square foot of gross floor area in any single-family residential building, including any townhouse, or any addition to a single-family residential building.</paragraph>
      <paragraph indent="1">(b)   However, notwithstanding subsection 8-39(c), the minimum rate that must be charged for each single-family dwelling unit (including each townhouse) is $1500, and the minimum rate that must be charged for each multi-family dwelling unit is $1200.</paragraph>
      <paragraph indent="1">(c)   If, within 5 years after a use and occupancy permit is issued, any person changes the use of all or part of a building to a use for which a higher payment would have been due under this Section when the building permit was issued (including a change from a status, use, or ownership that is exempt under Section 8-39 to a status, use, or ownership that is not so exempt), the owner of the building must within 10 days after the change in status, use, or ownership pay all additional payments that would have been due if the building or part of the building had originally been used as it is later used.  If the building owner does not pay any additional payment when due, each later owner is liable for the payment, and any interest or penalty due under Section 8-42, until all payments, interest, and penalties are paid.</paragraph>
      <paragraph indent="1">(d)   Each year the County Council by resolution, after a public hearing advertised at least 15 days in advance, may increase or decrease the payment rates set in this Section.</paragraph>
      <paragraph indent="1">(e)</paragraph>
      <paragraph indent="2">(1)   "Gross floor area," as used in this Article, means the sum of the gross horizontal areas of the several floors of a building measured from the exterior faces of the exterior walls or from the center line of a party wall.</paragraph>
      <paragraph indent="2">(2)   "Gross floor" area does not include any:</paragraph>
      <paragraph indent="3">(A)   unfinished basement or attic area with a clear height less than 7 feet 6 inches;</paragraph>
      <paragraph indent="3">(B)   interior amenity space required to obtain approval of a site plan;</paragraph>
      <paragraph indent="3">(C)   area occupied by an atrium or other multi-story space other than the first floor of the space;</paragraph>
      <paragraph indent="3">(D)   area occupied by unenclosed mechanical, heating, air conditioning, or ventilating equipment;</paragraph>
      <paragraph indent="3">(E)   parking garage or area; or</paragraph>
      <paragraph indent="3">(F)   other accessory structure that is not a separate building.</paragraph>
      <paragraph indent="2">(3)   In any single-family residential building, "gross floor area" also does not include 50% of any finished or unfinished basement or attic area with a clear height of 7 feet 6 inches or more.</paragraph>
    </section>
    <section heading="Sec. 8-39. Exemptions.">
      <paragraph indent="1">The payment required under Section 8-37 does not apply to:</paragraph>
      <paragraph indent="1">(a)</paragraph>
      <paragraph indent="2">(1)   any reconstruction or alteration of an existing building or part of a building that does not increase the gross floor area of the building; and</paragraph>
      <paragraph indent="2">(2)   any building that replaces an existing building on the same site to the extent of the gross floor area of the previous building, if construction begins within one year after demolition or destruction of the previous building was substantially completed;</paragraph>
      <paragraph indent="1">(b)   the first 1200 square feet of gross floor area of:</paragraph>
      <paragraph indent="2">(1)   a new nonresidential building, or</paragraph>
      <paragraph indent="2">(2)   an addition to an existing nonresidential building;</paragraph>
      <paragraph indent="1">(c)   the first 1200 square feet of gross floor area in any  dwelling unit or addition to an existing dwelling unit;</paragraph>
      <paragraph indent="1">(d)</paragraph>
      <paragraph indent="2">(1)   any Moderately Priced Dwelling Unit built under Chapter 25A,</paragraph>
      <paragraph indent="2">(2)   any Productivity Housing Unit, as defined in Section 25B-17(m), and</paragraph>
      <paragraph indent="2">(3)   any other dwelling unit built under a government regulation or binding agreement that limits for at least 15 years the price or rent charged for the unit in order to make the unit affordable to households earning less than the income levels set by regulation for Moderately Priced Dwelling Units, adjusted for family size;</paragraph>
      <paragraph indent="1">(e)   a nonresidential building owned, and used primarily, by any agency or instrumentality of federal, state, County or municipal government;</paragraph>
      <paragraph indent="1">(f)   a building or part of a building owned by an accredited college or university and used exclusively for instruction, instruction-related research, and administration of higher education programs;</paragraph>
      <paragraph indent="1">(g)   a building owned by a nonprofit organization that is exempt from federal income taxes under Section 501(c)(3) of the Internal Revenue Code, used primarily for educational or religious activities, and not used for any substantial commercial activity.</paragraph>
    </section>
    <section heading="Sec. 8-40. Credits.">
      <paragraph indent="1">Any person who makes a development approval payment under Section 8-37 may reduce that payment by:</paragraph>
      <paragraph indent="1">(a)   any amount the person paid under Chapter 52 Article IV (development impact tax for transportation improvements) or Chapter 52 Article VI (expedited development approval excise tax) for the building that is the subject of this payment; and</paragraph>
      <paragraph indent="1">(b)   any amount the person paid or is required to pay for any development district tax levied under County law on account of the building which is the subject of this payment, to the extent that the development district tax is in addition to (and not a part of or substitute for) the ad valorem real property tax applicable to the property.</paragraph>
    </section>
    <section heading="Sec. 8-41. Payments; installment payments.">
      <paragraph indent="1">(a)   Before the Department of Permitting Services releases a building permit for all or any part of a building subject to this Article, the applicant must show that all payments due under Section 8-38 have been paid.</paragraph>
      <paragraph indent="1">(b)   When a person applies to a city or town in the County for a building permit for a building or dwelling unit, the applicant must show that all payments due under Section 8-38 with respect to the building or unit have been paid.  The Director of Finance must promptly refund any payment made for any building or part of a building for which a building permit is not issued by the city or town.</paragraph>
      <paragraph indent="1">(c)</paragraph>
      <paragraph indent="2">(1)</paragraph>
      <paragraph indent="3">(c)   Any payment due under Section 8-37(c) may be paid in not more than 6 equal annual installments.  The first installment must be paid before the building permit for any building subject to the subdivision plan is released, and each succeeding installment must be paid not later than the next December 31.</paragraph>
      <paragraph indent="2">(2)   In addition, the person making the payment must pay interest on the amount of each installment except the first at a rate set each year by the Director of Finance not less than the annual nationwide rate of inflation in construction costs since the first installment was paid.  The payer may pay any installment in advance at any time, with interest calculated to the end of the month of payment.</paragraph>
    </section>
    <section heading="Sec. 8-42. Collection and administration; interest and penalties; violation; lien.">
      <paragraph indent="1">(a)   If any person fails to pay the Director of Finance the full payment or any installment payment due under Section 8-37, that person is liable for:</paragraph>
      <paragraph indent="2">(1)   interest on the unpaid amount at the rate of  of one percent per month for each month or part of a month after the due date for payment under Section 8-41; and</paragraph>
      <paragraph indent="2">(2)   a penalty of 5 percent of the amount due and unpaid per month or part of a month after the due date for payment under Section 8-41, not to exceed 25 percent of the amount due and unpaid.</paragraph>
      <paragraph indent="1">The Director must collect any interest and penalty as a part of the payment.</paragraph>
      <paragraph indent="1">(b)   If any person fails to pay the payment when due, the Director must obtain information on which to calculate the payment due.  As soon as the Director obtains sufficient information to calculate any payment due, the Director must assess interest and penalties against the person.  The Director must notify the person by mail sent to the person's last known address of the total amount of all payments, interest, and penalties.  The total amount must be paid within 10 days after the notice is mailed.</paragraph>
      <paragraph indent="1">(c)   Every person liable for any payment under Section 8-37 must preserve for 6 years all records necessary to determine the amount of the payment.  The Director may inspect the records at any reasonable time.</paragraph>
      <paragraph indent="1">(d)   Any failure to pay the payment due under Section 8-37, and any other violation of this Article, is a Class A violation.  Each violation is a separate offense.  A conviction does not relieve any person from liability for any unpaid payments, interest, or penalties.</paragraph>
      <paragraph indent="1">(e)</paragraph>
      <paragraph indent="2">(1)</paragraph>
      <paragraph indent="3">(c)   Section 52-18D applies to this payment as if it were a tax. However, the lien under this Article attaches to all real property in the subdivision when the contract is signed under Section 8-37(c).  The lien imposed under this Article has the same priority and may be enforced in the same manner as a lien imposed in case of nonpayment of County real property taxes.</paragraph>
      <paragraph indent="2">(2)   A lien must not be attached to any real property owned by the Washington Metropolitan Area Transit Authority if the applicant for subdivision approval furnishes sufficient alternative security in a form and amount accepted by the County Attorney.</paragraph>
      <paragraph indent="1">(f)   The County Executive may adopt regulations under method (2) to implement this Article.</paragraph>
      <paragraph indent="1">(g)   As used in this Article, "person" includes any individual, corporation, association, firm, partnership, group of individuals acting as a unit, trustee, receiver, assignee or personal representative.  "Building" and "dwelling unit" have the same meaning as in Chapter 59.</paragraph>
      <paragraph indent="1">(h)   By September 1 of each year in which payments are received under this Article, the Director must report to the County Council for the preceding fiscal year:</paragraph>
      <paragraph indent="2">(1)   the amount collected under this Article, by policy area and building use type;</paragraph>
      <paragraph indent="2">(2)   the amount of property exempted from development approval payments under Section 8-39; and</paragraph>
      <paragraph indent="2">(3)   the amount of credits granted under Section 8-40.</paragraph>
      <paragraph indent="1">(i)   In each fiscal year the Director must transfer 20 percent of the revenue received under this Article to support the Montgomery Housing Initiative established under Section 25B-9.  The Council must appropriate the remaining revenue received under this Article to fund transportation projects in the annual capital improvements program and the expenses of any transportation management district established under Chapter 42A.  Unless the Council by resolution directs otherwise, revenue under this Article must not be appropriated to any project that is eligible for federal or state funding, except for the County's matching share of the project costs.</paragraph>
    </section>
  </article>
  <article heading="Article VI. Works of Art in Public Architecture.">
    <section heading="Sec. 8-43. Definitions.">
      <paragraph indent="1">In this Article, work of art means an object, objects or surface embellishment produced with skill and taste. A work of art should generally be an original creation, rather than a mass-produced item, generally expressing, but not limited to, a social, cultural or historical theme. Works of art include, but are not limited to, paintings, sculptures, engravings, carvings, frescos, mobiles, murals, collages, mosaics, statues, bas-reliefs, tapestries, photographs, drawings, stained glass, fountains, or other decoration, either exterior or interior. The term does not include temporarily hung works of art, landscaping, or the choice or use of materials in architecture.</paragraph>
    </section>
    <section heading="Sec. 8-44. Public arts trust.">
      <paragraph indent="1">(a)   There is a Public Arts Trust fund within County Government to:</paragraph>
      <paragraph indent="2">(1)   receive, hold, and pay out public and private funds to:</paragraph>
      <paragraph indent="3">(A)   buy and display works of art on public property in the County; and</paragraph>
      <paragraph indent="3">(B)   pay the cost of administering the fund; and</paragraph>
      <paragraph indent="2">(2)   sponsor privately-funded temporary or permanent displays of art on public property in the County.</paragraph>
      <paragraph indent="1">(b)   The Chief Administrative Officer or a designee must administer the trust in consultation with:</paragraph>
      <paragraph indent="2">(1)   Arts and Humanities Council;</paragraph>
      <paragraph indent="2">(2)   Montgomery County Public Schools;</paragraph>
      <paragraph indent="2">(3)   Montgomery College; and</paragraph>
      <paragraph indent="2">(4)   Montgomery County Parks Commission.</paragraph>
      <paragraph indent="1">(c)   The Chief Administrative Officer must report to the County Council:</paragraph>
      <paragraph indent="2">(1)    each quarter on:</paragraph>
      <paragraph indent="3">(A)   new locations selected for works of art to be funded by the Public Arts Trust; and</paragraph>
      <paragraph indent="3">(B)   works of art purchased or displayed with Public Arts Trust funds during the quarter; and</paragraph>
      <paragraph indent="2">(2)   each year by January 15 on all other uses of Public Arts Trust funds during the prior calendar year.</paragraph>
    </section>
    <section heading="Sec. 8-45. Appropriation for art.">
      <paragraph indent="1">Each year the County Council should consider appropriating funds for the next fiscal year to the Public Arts Trust in an amount equal to .05% of the combined total approved programmed capital expenditures for the then current fiscal year for County Government, Public Schools, Montgomery College, and Maryland-National Capital Park and Planning Commission.</paragraph>
    </section>
  </article>
  <article heading="ARTICLE VII. Reserved.">
    <section heading="Sec. 8-46. Reserved." />
    <section heading="Sec. 8-47. Reserved." />
    <section heading="Sec. 8-48. Reserved." />
    <section heading="Sec. 8-49. Reserved." />
    <section heading="Sec. 8-50. Reserved." />
    <section heading="Sec. 8-51. Reserved." />
    <section heading="Sec. 8-52. Reserved." />
    <section heading="Sec. 8-53. Reserved." />
  </article>
  <article heading="Article Viii. Clean Renewable Energy Technology.">
    <section heading="Sec. 8-54. Definitions.">
      <paragraph indent="1">In this Article, the following words have the meanings indicated:</paragraph>
      <paragraph indent="2">Clean energy portfolio target means a target, expressed in megawatt hour equivalents, for establishing an amount of clean energy to be installed on the County’s portfolio of facilities. The County’s portfolio includes any building, facility, or property in which the County has a financial interest. A financial interest includes any ownership, lease,  or public private partnership, and any facility where the County provides 30% of total funding.</paragraph>
      <paragraph indent="2">Clean renewable energy technology means a technology or system that uses geothermal heating and cooling, solar hot water heating, wind power, solar electricity generation, or solar thermal generation. Clean renewable energy technology includes passive solar energy generation that reduces energy use from other sources by at least 20%.</paragraph>
      <paragraph indent="2">Department means the Department of General Services.</paragraph>
      <paragraph indent="2">Director means the Director of the Department or the Director’s designee.</paragraph>
    </section>
    <section heading="Sec. 8-55. Clean renewable energy technology required.">
      <paragraph indent="1">(a)   By December 10, 2014, the County Executive must establish, by Method 1 Regulation, a Clean Energy Plan that includes a specific amount of on-site clean energy that must be installed on any new or existing County facility. This Plan must include:</paragraph>
      <paragraph indent="2">(1)   a clean energy portfolio target for total clean energy to be installed on County facilities, which must exceed 1 kilowatt per 1,000 square feet of facilities anticipated to be added to the County’s portfolio as documented in the Capital Improvement Program;</paragraph>
      <paragraph indent="2">(2)   a process for vetting any new facility for potential renewable energy installation during the design phase, including key criteria for evaluating opportunities for solar energy;</paragraph>
      <paragraph indent="2">(3)   a plan to ensure that appropriate facilities are solar ready, to the extent possible;</paragraph>
      <paragraph indent="2">(4)   criteria for responsible site selection to balance the County’s renewable energy goals with other environmental objectives;</paragraph>
      <paragraph indent="2">(5)   a process to coordinate with County agencies on any new facility built using at least 30% County funds; and</paragraph>
      <paragraph indent="2">(6)   required funding and staffing to achieve the target.</paragraph>
      <paragraph indent="1">(b)   The County may install a clean energy system in an alternate location in the County to meet this requirement, including:</paragraph>
      <paragraph indent="2">(1)   a vacant property;</paragraph>
      <paragraph indent="2">(2)   a land swap or lease agreement; or</paragraph>
      <paragraph indent="2">(3)   any other property or facility where the County has a contractual, budgetary, or other interest.</paragraph>
      <paragraph indent="1">(c)   The Executive must recommend to the Council whether funds to support solar energy should be incorporated in a energy specific capital improvement budget, utility Non Departmental Account, or other mechanism to overcome any funding gap to meet the renewable energy target.</paragraph>
    </section>
    <section heading="Sec. 8-56. Alternative financing.">
      <paragraph indent="1">(a)   An alternative financing arrangement which allows leveraging of federal, state, utility, and other incentives, including any grant, lease-purchase agreement, power purchase agreement, or energy savings performance contract, may meet the clean renewable energy technology requirement under this Article.</paragraph>
      <paragraph indent="1">(b)   The purchase of Renewable Energy Credits does not meet the clean renewable energy technology requirement under this Article.</paragraph>
    </section>
    <section heading="Sec. 8-57. Administration; reporting.">
      <paragraph indent="1">(a)   The Department must administer this Article using accepted principles of sound accounting and fiscal management.</paragraph>
      <paragraph indent="1">(b)   The Department must submit an annual report to the County Council and County Executive by April 1 each year describing:</paragraph>
      <paragraph indent="2">(1)   the added clean renewable energy technology generation by each project;</paragraph>
      <paragraph indent="2">(2)   the revenues and expenditures of each project;</paragraph>
      <paragraph indent="2">(3)   each project supported by the Program; and</paragraph>
      <paragraph indent="2">(4)   the cost and energy savings resulting from the program.</paragraph>
    </section>
  </article>
</chapter>