      <paragraph indent="2">These regulations identify the steps that an applicant must take to comply with Chapter 22A of the County Code.  These regulations were adopted by the Planning Board and approved as regulations by the County Council under Chapter 22A.</paragraph>
    </subsection>
    <subsection heading="22A.00.01.02Authority">
      <paragraph indent="2">In accordance with Chapter 22A, sometimes referred to in these regulations as the “Forest Conservation Law,” the following Planning Board Regulations shall pertain to all development applications, mandatory referrals, conditional uses, sediment control permits, or park development applications. In addition, the Trees Technical Manual is a guidance document, adopted by the Planning Board, which provides further clarification of the requirements of Chapter 22A of the Montgomery County Code and these regulations.</paragraph>
    </subsection>
    <subsection heading="22A.00.01.03 Definitions">
      <paragraph indent="2">(1)   “Afforestation” means the creation, on a tract that is not presently in forest cover, of a biological community dominated by trees and other woody plants (including plant communities, the understory, and forest floor), which is at least 10,000 square feet in area and 50 feet wide, and containing at least 100 trees per acre, with at least 50 of those trees having the potential of growing to a 2 inch or greater diameter at 4.5 feet above the ground within 7 years.  In some instances, afforestation includes creation of tree cover by landscaping areas under an approved landscaping plan.</paragraph>
      <paragraph indent="2">(2)   “Afforestation threshold” means the afforestation required for a site per Sections 22A-12(a), (d), and (f) of the Forest Conservation Law.</paragraph>
      <paragraph indent="2">(3)   “Applicant” means the person who is applying for a development plan, diagrammatic plan, subdivision, floating zone plan, sketch plan, site plan, project plan, expedited approval plan, preliminary plan of subdivision, administrative subdivision, minor subdivision, sediment control permit, special exception/conditional use, mandatory referral, or park development plan.</paragraph>
      <paragraph indent="2">(4)   “Break-even point” means an exact level of forest retention that precludes the need for reforestation.</paragraph>
      <paragraph indent="2">(5)   “Champion tree” means the largest tree of its species within the United States, the State, county or municipality, as appropriate.</paragraph>
      <paragraph indent="2">(6)   “Conservation easement” means a restriction on the land and the natural features on this land.  This easement must be shown on the record plat, if applicable, and its terms and conditions are recorded in the county’s land records.  If no plat is required, the easement is recorded in the County’s land records only.</paragraph>
      <paragraph indent="3">(a)   “Category I Conservation Easement” means a restriction on the land to permanently protect existing forest, planted forest, or forested or unforested environmental buffers.</paragraph>
      <paragraph indent="3">(b)   Category II Conservation Easement” means a restriction on the land that permanently protects large trees, landscape areas, and any tree planted outside of forest that receives forest conservation plan credit.</paragraph>
      <paragraph indent="2">(7)   “Conservation threshold” means a specific percentage of a tract that is used in determining reforestation requirements per Sections 22A-12(a) and (f) of the Forest Conservation Law.</paragraph>
      <paragraph indent="2">(8)   “Critical habitat area” means a critical habitat for an endangered species and its surrounding protection area.  A critical habitat area:</paragraph>
      <paragraph indent="3">(a)   is likely to contribute to the long-term survival of the species;</paragraph>
      <paragraph indent="3">(b)   is likely to be occupied by the species for the foreseeable future; and</paragraph>
      <paragraph indent="3">(c)   constitutes habitat of the species which is considered critical under the Annotated Code of Maryland Natural Resources Article.</paragraph>
      <paragraph indent="2">(9)   “Critical habitat for endangered species” means a habitat occupied by an endangered species as determined or listed under the Annotated Code of Maryland Natural Resources Article.</paragraph>
      <paragraph indent="2">(10)   “Critical root zone” means the zone in which the roots of a tree are located, as defined in the latest version of the Trees Technical Manual.  It is also the area around a tree that should be undisturbed unless protection measures are provided to protect the long-term viability of the tree.</paragraph>
      <paragraph indent="2">(11)   “Development application” means an application made to the Planning Board, Board of Appeals, Department of Permitting Services, or the Planning Director for approval of a regulated activity.</paragraph>
      <paragraph indent="2">(12)   “Declaration of intent” means a signed and notarized statement by a landowner that the cutting of trees on the landowner’s property:</paragraph>
      <paragraph indent="3">(a)   is for purposes exempted under Chapter 22A of the Montgomery County Code; and</paragraph>
      <paragraph indent="3">(b)   will not circumvent the requirements of the Chapter.</paragraph>
      <paragraph indent="2">(13)   “Development program” means a sequence of construction events and timing for submittal of the major forest conservation program elements.</paragraph>
      <paragraph indent="2">(14)   “Development project” means grading or construction activities occurring on a specific tract.  This includes redevelopment projects.</paragraph>
      <paragraph indent="2">(15)   “Environmental buffer” means perennial, intermittent, or ephemeral streams/channels and their associated buffers; wetlands and their associated buffers; and, hydraulically connected steep slopes according to the latest version of the environmental guidelines, or an appropriate master plan; and floodplains.</paragraph>
      <paragraph indent="2">16)   “Environmental guidelines” means the Guidelines for the Environmental Management of Development in Montgomery County, Maryland (M-NCPPC), as amended.</paragraph>
      <paragraph indent="2">(17)   “Ephemeral channel/stream” means a channel defined as ephemeral per the latest version of the environmental guidelines.</paragraph>
      <paragraph indent="2">(18)   “Extenuating circumstances” means conditions requiring extension of a set time limit to process an application, render a decision, or conduct a public hearing.</paragraph>
      <paragraph indent="2">19)   “Equity focus areas” means geographic areas of Montgomery County characterized by high concentrations of lower-income households, people of color, and individuals who may speak English less than very well. Boundaries are determined by Planning Department staff and are mapped on the Planning Department website.</paragraph>
      <paragraph indent="2">(20)   “Field survey” means a field investigation of the environmental characteristics of a site, including existing forest.</paragraph>
      <paragraph indent="2">(21)   “Flood, One Hundred-Year” means a flood which has a 1 percent statistical probability of being equaled or exceeded in any given year.  Unless otherwise stated, this calculation is based on the contributing watershed under existing zoning.</paragraph>
      <paragraph indent="2">(22)   “Floodplain, One Hundred-Year” means the area along or adjacent to a stream or body of water, except tidal waters, that is capable of storing or conveying floodwaters during a 100-year frequency storm event, or 100-year flood, based on ultimate development of the watershed under existing zoning.</paragraph>
      <paragraph indent="2">(23)   “Forest clearing” means the cutting or destruction of any trees or understory which are part of an existing forest even if the resulting community continues to meet the definition of forest, except if it is done as part of an approved forest management plan or timber harvest permit.  Forest loss will be based on a measure of the aerial extent of forest cover which includes the outer perimeter of individual trees.</paragraph>
      <paragraph indent="2">(24)   “Forest conservation plan” means a plan which outlines the strategies and specific plan proposed for retaining, protecting, and reforesting or afforesting areas on a site.</paragraph>
      <paragraph indent="2">(25)   “Forest conservation worksheet” means a step-by-step form for determining compliance with the requirements of the forest conservation law.</paragraph>
      <paragraph indent="2">(26)   “Forest management plan” means a plan establishing conservation and management practices for a landowner after assessment of the resource values of forested properties.  This plan is approved by the county, or by the MD Department of Natural Resources forester assigned to the county after coordination with the county, and by the Planning Director if located within a conservation easement.</paragraph>
      <paragraph indent="2">(27)   “Forest mitigation bank plan” means a plan that a property owner submits to document the acreage of forest mitigation bank credits and shows the credits based on the amount of existing forest permanently protected, forest planted and protected, and a planting plan.</paragraph>
      <paragraph indent="2">(28)   “Forest mitigation bank credits” means the credits available for sale at a forest mitigation bank, where 1 acre of mitigation bank credit equals 2 acres of existing forest or 1 acre of planted forest.</paragraph>
      <paragraph indent="2">(29)   “Forest retention” means the forest shown on a forest conservation plan that will be saved, counted as forest retained on the worksheet, and included in a long-term protective agreement.</paragraph>
      <paragraph indent="2">(30)   “Forest stand delineation” or “FSD” means the evaluation of existing vegetation in relation to the natural resources on a site proposed for development or land disturbing activity. The FSD is submitted as part of the Natural Resources Inventory/Forest Stand Delineation (NRI/FSD).</paragraph>
      <paragraph indent="2">(31)   “Growing season” means a period of consecutive frost-free days as stated in the current soil survey for the county.  In an average year, a period commencing on April 1st and ending on October 31st.</paragraph>
      <paragraph indent="2">(32)   “Intermittent stream” means a stream defined as intermittent in the latest version of the environmental guidelines.</paragraph>
      <paragraph indent="2">(33)   “Landscaping credit” means areas shown on a forest conservation plan, that are not forest, but will receive credit toward a site’s reforestation or afforestation requirements, so long as the plantings are not required to meet zoning or other requirements.  The forest conservation plan must show the dimensions and details for tree planting and landscaping areas.  Any planting for landscaping credit to meet the forest conservation plan requirements must use native plants or cultivars of native plants.</paragraph>
      <paragraph indent="2">(34)   “Limits of disturbance” means a clearly designated area within which land disturbance may occur.</paragraph>
      <paragraph indent="2">(35)   “Maintenance and management agreement” means the short-term management agreement associated with a forest conservation plan, and may include the control of non-native and invasive plants.</paragraph>
      <paragraph indent="2">(36)   “Major amendment to a Forest Conservation Plan” means an amendment that results in more than a total of 5,000 square feet of additional forest clearing and/or the removal or partial removal of any conservation easement.</paragraph>
      <paragraph indent="2">(37)   “Minor amendment to a Forest Conservation Plan” means an amendment that does not result in more than a total of 5,000 square feet of additional forest clearing or the removal or partial removal of any conservation easement.</paragraph>
      <paragraph indent="2">(38)   “Native” means a plant or animal species whose geographic range during precolonial time included the Piedmont Region of Maryland.  Information of native plants can be found in Woody Plants of Maryland (Brown and Brown, 1972) and Herbaceous Plants of Maryland (Brown and Brown, 1984), as well as other literature sources.</paragraph>
      <paragraph indent="2">(39)   “Natural regeneration” means the natural establishment of native trees and other native vegetation.</paragraph>
      <paragraph indent="2">(40)   “Natural resources inventory” or “NRI” means the collection and presentation of environmental information for a property according to the guidelines specified in these regulations and in the latest version of the environmental guidelines. The NRI is submitted as part of the Natural Resources Inventory/Forest Stand Delineation (NRI/FSD).</paragraph>
      <paragraph indent="2">(41)   “Offsite” means outside the limits of the areas encompassed by a tract.</paragraph>
      <paragraph indent="2">(42)   “Onsite” means within the limits of an area encompassed by a tract.</paragraph>
      <paragraph indent="2">(43)   “Perennial stream” means a stream defined as perennial in the latest version of the environmental guidelines.</paragraph>
      <paragraph indent="2">(44)   “Planting plan” means a plan showing how areas to be reforested or afforested will be planted.</paragraph>
      <paragraph indent="2">(45)   “Priority planting area” means areas in which planting must occur when present.</paragraph>
      <paragraph indent="2">(46)   “Priority retention area” means areas, identified in Section 22A-12(b) of the Forest Conservation Law that are ranked as the highest priority for retention as part of a forest conservation plan.</paragraph>
      <paragraph indent="2">(47)   “Qualified professional” means a Maryland licensed forester, Maryland licensed landscape architect, or other qualified professional approved by the State.</paragraph>
      <paragraph indent="2">(48)   “Regulated activity” means any of the following activities:</paragraph>
      <paragraph indent="3">(a)   Subdivision;</paragraph>
      <paragraph indent="3">(b)   Expedited approval plan;</paragraph>
      <paragraph indent="3">(c)   Site plan;</paragraph>
      <paragraph indent="3">(d)   Project plan;</paragraph>
      <paragraph indent="3">(e)   Sketch plan;</paragraph>
      <paragraph indent="3">(f)   Floating zone plan;</paragraph>
      <paragraph indent="3">(g)   Development plan;</paragraph>
      <paragraph indent="3">(h)   Special exception/conditional use on a tract of land greater than 40,000 square feet;</paragraph>
      <paragraph indent="3">(i)   Clearing of more than 5,000 square feet of forest;</paragraph>
      <paragraph indent="3">(j)   Park development project on a tract of land greater than 40,000 square feet;</paragraph>
      <paragraph indent="3">(k)   An activity that requires a sediment control permit on a tract of land, individually or cumulatively that is greater then 40,000 square feet; or</paragraph>
      <paragraph indent="3">(j)   Mandatory referral on a tract of land greater than 40,000 square feet.</paragraph>
      <paragraph indent="2">(49)   “Retention area” means forested areas, tree stands and the critical root zone of individual trees that will be retained on a site.</paragraph>
      <paragraph indent="2">(50)   “Selective clearing” means the careful and planned removal of trees, shrubs, and plants using specific standards and protection measures under an approved forest conservation plan.</paragraph>
      <paragraph indent="2">(51)   “Specimen tree” means a tree that is a particularly impressive or unusual example of a species due to its size, shape, age, or any other trait that epitomizes the character of the species as further described in the most recent version of the Trees Technical Manual.</paragraph>
      <paragraph indent="2">(52)   “Stream buffer” means a strip of land contiguous with and parallel to the bank of a perennial or intermittent stream, the width of which must be determined according to the latest version of the environmental guidelines.</paragraph>
      <paragraph indent="2">(53)   “Subdivision” means the definition of subdivision in Chapter 50 of the Montgomery County Code.</paragraph>
      <paragraph indent="2">(54)   “Tract” means:</paragraph>
      <paragraph indent="3">(a)   The property, or adjacent properties, subject to a development application, the boundaries of which are described by deed or record plat; or</paragraph>
      <paragraph indent="3">(b)   The length and width of the right-of-way or the limits of disturbance, whichever is greater, for a linear project.</paragraph>
      <paragraph indent="2">(55)   “Tree save area” means an area designating trees, or stands of trees outside existing forest cover which are to be retained.</paragraph>
      <paragraph indent="2">(56)   “Tree save plan” means a plan approved by the Planning Board, or Planning Director, under Chapter 22A or Chapter 50 of the County Code which covers individual trees or stands of trees to be saved as part of, or instead of a forest conservation plan.</paragraph>
      <paragraph indent="2">57)   “Tree stand” means an area where trees are concentrated at too low a density, or that is too small in size or area to meet the definition of “forest.”</paragraph>
    </subsection>
    <subsection heading="22A.00.01.04 Reserved" />
    <subsection heading="22A.00.01.05 Application">
      <paragraph indent="2">A.   Except as provided in Sections 22A-5, 22A-6, 22A-7, 22A-8, 22A-9 and the Variance provisions in Section 22A-21 of the Forest Conservation Law, these regulations apply to the following plans or regulated activities:</paragraph>
      <paragraph indent="3">(1)   a development plan approved or amended under Division 59-D-1 of Chapter 59 of the County Code that was in effect prior to October 30, 2014;</paragraph>
      <paragraph indent="3">(2)   a project plan approved or amended under Division 59-D-1 of Chapter 59 of the County Code that was in effect prior to October 30, 2014;</paragraph>
      <paragraph indent="3">(3)   a preliminary plan of subdivision, administrative subdivision, or minor subdivision approved by the Planning Board, or Planning Director, under Chapter 50 of the County Code;</paragraph>
      <paragraph indent="3">(4)   a  site plan approved or amended under Division 59-D-3 of Chapter 59 of the County Code that was in effect prior to October 30, 2014;</paragraph>
      <paragraph indent="3">(5)   a site plan approved or amendment under Section 59.7.3.4 of Chapter 59 of the County Code;</paragraph>
      <paragraph indent="3">(6)   a sketch plan approved under Section 59.7.3.3 of Chapter 59 of the County Code;</paragraph>
      <paragraph indent="3">(7)   a sediment control permit required under Chapter 19 of the County Code;</paragraph>
      <paragraph indent="3">(8)   clearing or grading conducted on two or more platted contiguous lots that are part of the same project, that collectively total 40,000 square feet or larger, that are graded at the same time, and where sediment control is required under Chapter 19 of the County Code.</paragraph>
      <paragraph indent="3">(9)   a special exception approved under Article 59-G of Chapter 59 of the County Code that was in effect prior to October 30, 2014;</paragraph>
      <paragraph indent="3">(10)   a conditional use approved under Section 59.7.3.1 of Chapter 59 of the County Code;</paragraph>
      <paragraph indent="3">(11)   a mandatory referral;</paragraph>
      <paragraph indent="3">(12)   a park development plan, and.</paragraph>
      <paragraph indent="4">an expedited approval plan.</paragraph>
      <paragraph indent="2">B.   The general procedure for meeting the requirements of Chapter 22A for these plans is:</paragraph>
      <paragraph indent="3">(1)   Preparation by a qualified professional, of a natural resources inventory which may include a forest stand delineation, as described in Section 22A.00.01.06 and in the latest versions of the environmental guidelines and the Trees Technical Manual (MNCPPC).  To be reviewed and approved by the Planning Director.</paragraph>
      <paragraph indent="3">(2)   Identification by a qualified professional, of forest and tree retention areas per subsection 22A-12(b) of the Forest Conservation Law, Sections 22A.00.01.06 and 22A.00.01.07, and the criteria for area to be cleared in the Trees Technical Manual.</paragraph>
      <paragraph indent="3">(3)   Preparation by a qualified professional, of a forest conservation plan to be approved by the Planning Board or Planning Director, as applicable, which includes:</paragraph>
      <paragraph indent="4">(a)   lot lines, building, and proposed infrastructure, located to maximize retention areas and avoid environmentally sensitive areas such as environmental buffers and critical habitats wherever practical;</paragraph>
      <paragraph indent="4">(b)   areas of existing forest, areas of forest to be removed, and areas of forest to be retained;</paragraph>
      <paragraph indent="4">(c)   afforestation and reforestation areas and planting plan, as required;</paragraph>
      <paragraph indent="4">(d)   appropriate protection and maintenance measures; and</paragraph>
      <paragraph indent="4">(e)   a timetable for construction and planting.</paragraph>
    </subsection>
    <subsection heading="22A.00.01.06 Natural Resource Inventory and Forest Stand Delineation (NRI/FSD) Requirements">
      <paragraph indent="2">A.   A Natural Resource Inventory (NRI) application must be considered complete if it contains a complete analysis of existing natural resources and man-made features on a property which is verified by field survey and contains the following information to cover the development site and first 100 feet of adjoining land around the perimeter or the width of adjoining properties, whichever is less:</paragraph>
      <paragraph indent="3">(1)   property boundaries;</paragraph>
      <paragraph indent="3">(2)   topography at a minimum scale of 1" = 200' with contour intervals not more than 5 feet (larger scale may be required by the Planning Director on a case-by-case basis, if necessary to determine the accuracy of the plan);</paragraph>
      <paragraph indent="3">(3)   slopes 25% and greater, and slopes between 15% and 25% that are associated with erodible soils;</paragraph>
      <paragraph indent="3">(4)   perennial and intermittent streams and stream buffers per the latest version of the environmental guidelines;</paragraph>
      <paragraph indent="3">(5)   ephemeral channels/streams and buffers for those locations where such buffers are required per the latest version of the environmental guidelines or appropriate master plan;</paragraph>
      <paragraph indent="3">(6)   existing one-hundred year floodplains and associated 25' building restriction lines;</paragraph>
      <paragraph indent="3">(7)   wetlands and their buffers per the latest version of the environmental guidelines;</paragraph>
      <paragraph indent="3">(8)   soils and geologic conditions including, soil type, structural limitations, soils that are hydric or have hydric inclusions, and erodible soils per the list in Appendix C of the environmental guidelines, and known serpentinite soils in Montgomery County;</paragraph>
      <paragraph indent="3">(9)   rare, threatened or endangered plants or animals observed in the field;</paragraph>
      <paragraph indent="3">(10)   critical habitat areas observed or documented by the Maryland Department of Natural Resources;</paragraph>
      <paragraph indent="3">(11)   aerial extent of forest and tree cover which includes the outside perimeter of the canopy of individual trees;</paragraph>
      <paragraph indent="3">(12)   champion trees and trees that have a diameter at 4.5 feet above the ground (DBH) that is 75% or more of the diameter of the current state champion for that species;</paragraph>
      <paragraph indent="3">(13)   specimen trees;</paragraph>
      <paragraph indent="3">(14)   a table that identifies individual trees that have a diameter at 4.5 feet above the ground (DBH) of 24" or greater by size and species and the health of those trees;</paragraph>
      <paragraph indent="3">(15)   cultural features and historic sites;</paragraph>
      <paragraph indent="3">(16)   a site vicinity map at 1" = 2000' which shows the location of the site within a square mile and indicates major roads;</paragraph>
      <paragraph indent="3">(17)   a table containing acreage of wetlands, 100-year floodplains, stream buffers, and environmental buffers; and</paragraph>
      <paragraph indent="3">(18)   a completed NRI/FSD application form, fee schedule worksheet, and review fee.</paragraph>
      <paragraph indent="2">B.   A Forest Stand Delineation (FSD) application must be considered complete if it contains a detailed summary of existing forest and trees on a tract, or forest stand delineation which is verified by field survey and contains the following information to cover the development site and first 100 feet of adjoining land around the perimeter or the width of adjoining properties, whichever is less:</paragraph>
      <paragraph indent="3">(1)   forest stands and field verified boundaries;</paragraph>
      <paragraph indent="3">(2)   a description of each stand including:</paragraph>
      <paragraph indent="4">(a)   acreage;</paragraph>
      <paragraph indent="4">(b)   dominant and codominant tree species;</paragraph>
      <paragraph indent="4">(c)   size class by species;</paragraph>
      <paragraph indent="4">(d)   percent canopy closure;</paragraph>
      <paragraph indent="4">(e)   number of canopy layers (vertical structure);</paragraph>
      <paragraph indent="4">(f)   percent of forest floor covered by herbaceous plants (native species), downed woody material, and alien or invasive species; and</paragraph>
      <paragraph indent="4">(g)   a stand condition narrative for each stand including, priority for retention, information on condition classes, structure, function, retention potential, transplant and regenerative potential, and comments on evidence of past management; and</paragraph>
      <paragraph indent="3">(3)   specimen trees by size and species;</paragraph>
      <paragraph indent="3">(4)   champion trees and trees that have a diameter at 4.5 feet above the ground (DBH) that is 75% or more of the diameter of the current state champion for that species, which must also be clearly numbered with corresponding tags in the field;</paragraph>
      <paragraph indent="3">(5)   a table that identifies individual trees that have a diameter at 4.5 feet above the ground (DBH) of 24" or greater by size and species and the health of those trees, which must also be clearly numbered with corresponding tags in the field;</paragraph>
      <paragraph indent="3">(6)   field survey reference points demarked on a plan drawing and in the field;</paragraph>
      <paragraph indent="3">(7)   a table containing total acreage of forest, forest in priority retention areas, forest not in priority retention areas, forest within existing wetlands, forest within 100-year floodplains, and forest within stream buffers;</paragraph>
      <paragraph indent="3">(8)   a summary map, which in addition to the information in subsections (1) and (2), shows the priority of forest stands for retention as described in Section 22A.00.01.07; and</paragraph>
      <paragraph indent="3">(9)   a completed NRI/FSD application form, fee schedule worksheet and review fee.</paragraph>
      <paragraph indent="2">C.   A simplified forest stand delineation may be used per subsection 22A-10(b)(2) of the Forest Conservation Law.  The simplified plan must also include:</paragraph>
      <paragraph indent="3">(1)   forest stands as determined by dominant species types and priority for retention;</paragraph>
      <paragraph indent="3">(2)   stand condition narrative as described in subsection (B)(2).</paragraph>
      <paragraph indent="2">D.   When necessary the items described in A and B, or A and C, above must be combined into one plan drawing and is called a Natural Resources Inventory/Forest Stand Delineation.</paragraph>
      <paragraph indent="2">E.   The Natural Resources Inventory and Forest Stand Delineation must be prepared by a licensed forester, licensed landscape architect or other qualified professional; and must exhibit a stamp or certification of the preparer.  The Natural Resources Inventory/Forest Stand Delineation must be used to determine areas of forest to be saved or planted.</paragraph>
      <paragraph indent="2">F.   A Natural Resources Inventory and Forest Stand Delineation is valid for two years from the date it is approved. If a forest conservation plan or a plan under Section 22A-9 has not been accepted as complete during the two-year validity period, an approved Natural Resources Inventory and Forest Stand Delineation expires at the end of its validity period. An expired Natural Resources Inventory and Forest Stand Delineation may be recertified within one year after the expiration date, if the original plan preparer attests that there are no changes to the size and shape of the application tract, existing conditions, forest acreage, tree canopy, or any other detail of the originally approved Natural Resources Inventory and Forest Stand Delineation. A Natural Resources Inventory and Forest Stand Delineation may only be recertified one time. A new Natural Resources Inventory and Forest Stand Delineation may be required if there are changes to site conditions, applications, plan preparer, or applicant.</paragraph>
    </subsection>
    <subsection heading="22A.00.01.07 Priorities for Retention">
      <paragraph indent="2">A.   The following areas are considered the highest priority retention areas for protection and must be left in an undisturbed condition unless the Planning Director or Planning Board find that the provisions of subsection 22A-12(b)(1) of the Forest Conservation Law, have been met and the development proposal cannot reasonably be altered:</paragraph>
      <paragraph indent="3">(1)   trees, shrubs, and other plants located in sensitive areas including environmental buffers, slopes over 25 percent (not man-made), erodible soils on slopes of 15% or more, and critical habitats;</paragraph>
      <paragraph indent="3">(2)   a contiguous forest that connects the largest undeveloped or most vegetated tracts of land within and adjacent to the site;</paragraph>
      <paragraph indent="3">(3)   trees, shrubs, or plants identified on the Maryland Department of Natural Resources list of rare, threatened, and endangered species;</paragraph>
      <paragraph indent="3">(4)   a forest area which has been designated as priority for retention in master plans or functional plans, or in the absence of such plans, a forest which exhibits all of the following characteristics as further described in the most recent version of the Trees Technical Manual:</paragraph>
      <paragraph indent="4">(a)   high structural and species diversity;</paragraph>
      <paragraph indent="4">(b)   few alien or invasive species present;</paragraph>
      <paragraph indent="4">(c)   very good overall stand health; and</paragraph>
      <paragraph indent="4">(d)   high potential to provide a significant amount of habitat for forest interior dwelling plant, animal, and bird species; and</paragraph>
      <paragraph indent="3">(5)   an individual tree, and its critical root zone, with one or more of the following characteristics:</paragraph>
      <paragraph indent="4">(a)   a tree that is 1" caliper or larger and part of a historic site or associated with a historic structure;</paragraph>
      <paragraph indent="4">(b)   a tree designated as a national, state, or County champion tree;</paragraph>
      <paragraph indent="4">(c)   a tree having a diameter, measured at 4.5 feet above the ground, of 75 percent or more of the diameter of the designated state or County champion tree; and</paragraph>
      <paragraph indent="4">(d)   trees which have a diameter, measured at 4.5 feet above the ground with a diameter of 30 inches or greater; and</paragraph>
      <paragraph indent="4">(e)   a tree which is a specimen of a species.;</paragraph>
      <paragraph indent="4">a forest area located in a Tier II or Tier III high quality watershed as identified by the Maryland Department of Environment;</paragraph>
      <paragraph indent="4">a forest area located in a water resource protection zone, a reservoir watershed or a wellhead protection area;</paragraph>
      <paragraph indent="3">(8)   forests in urban areas as defined in Section 5-1607(c)(i) of the Natural Resources Article of the Maryland Code.</paragraph>
      <paragraph indent="2">B.   The following areas are not subject to the retention provisions in subsection 22A-12(b)(1) of the Forest Conservation Law, but should be given consideration for preservation where feasible:</paragraph>
      <paragraph indent="3">(1)   a forested area which provides a corridor 300 feet or more of primarily native vegetation between two larger forested tracts;</paragraph>
      <paragraph indent="3">(2)   a forested stream buffer up to 300 feet on either side of a stream channel;</paragraph>
      <paragraph indent="3">(3)   trees which act as a buffer between incompatible land uses and between dwellings and roads;</paragraph>
      <paragraph indent="3">(4)   a forest stand, or portions of a stand, with good forest structural diversity; and</paragraph>
      <paragraph indent="3">(5)   an individual tree with a diameter, measured at 4.5 feet above the ground, of 24 inches or greater which will significantly enhance the site through preservation.</paragraph>
    </subsection>
    <subsection heading="22A.00.01.08 General Forest Conservation Plan Provisions">
      <paragraph indent="2">A.   In developing a forest conservation plan, the applicant must give priority to techniques for maximizing retention of existing forest on the site.  The Forest Conservation Law specifies percentages of all forested sites which, at a minimum, should be preserved.  Applicants must strive to maximize forest retention whenever practical.</paragraph>
      <paragraph indent="2">B.   If existing forest on the site subject to a forest conservation plan cannot be retained, the applicant must demonstrate, to the satisfaction of the Planning Board or Planning Director, as applicable:</paragraph>
      <paragraph indent="3">(1)   how techniques for retention have been exhausted;</paragraph>
      <paragraph indent="3">(2)   why the forests in priority retention areas specified in Section 22A.00.01.07 are not being retained;</paragraph>
      <paragraph indent="3">(3)   if forests in priority retention areas cannot be left undisturbed, how the sequence for afforestation or reforestation will be followed in compliance with subsection 22A-12(e)(1)(A) of the Forest Conservation Law;</paragraph>
      <paragraph indent="3">(4)   where on site in priority planting areas the afforestation or reforestation will occur in compliance with subsection 22A-12(e)(3) of the Forest Conservation Law; and</paragraph>
      <paragraph indent="3">(5)   how the standards for afforestation and reforestation requirements in subsection 22A-12(e)(4) of the Forest Conservation Law will be met.</paragraph>
      <paragraph indent="2">C.   Wetlands.  A regulated activity within the net tract area that occurs wholly or partly in areas regulated as nontidal wetlands under Environment Article, Title 9, Annotated Code of Maryland, is subjected to the reforestation requirements of both the nontidal wetlands regulations and this subtitle, subject to the following:</paragraph>
      <paragraph indent="3">(1)   forested nontidal wetlands which are retained, must be counted toward the forest conservation requirements of this subtitle;</paragraph>
      <paragraph indent="3">(2)   forested wetlands which are permitted to be cleared must be replaced as required under the provisions of Environment Article, Title 9, Annotated Code of Maryland;</paragraph>
      <paragraph indent="3">(3)   clearing within forested wetlands must be shown on the forest conservation plan; and</paragraph>
      <paragraph indent="3">(4)   wetlands are priority retention areas.</paragraph>
      <paragraph indent="2">D.   Retention Areas.</paragraph>
      <paragraph indent="3">(1)   Forest retention areas must be at least 10,000 square feet in size and 50 feet wide, or be a part of a larger forest area which extends off-site and is protected.</paragraph>
      <paragraph indent="3">(2)   Individual trees described as highest priority for retention in subsection 22A.00.01.07A may receive retention credit equal to the area of their critical root zone protected when at least two thirds of the entire critical root zone is permanently protected by an easement.</paragraph>
      <paragraph indent="3">(3)   Individual trees which are not the highest priority for retention and tree stands less than 10,000 square feet and 50 feet wide may be credited toward afforestation and reforestation requirements as part of landscaping credit.</paragraph>
      <paragraph indent="3">(4)   Retention area boundaries must be determined by a measure of the aerial extent of remaining forest cover which includes the outer perimeter of the canopy of individual trees, or the critical root zones that are protected, whichever is greater.</paragraph>
      <paragraph indent="2">E.   Afforestation and Reforestation.</paragraph>
      <paragraph indent="3">(1)   Afforestation and reforestation areas must be at least 10,000 square feet in size and 50 feet wide, or be adjacent to an existing forest area (either on-site or off-site) which is protected.</paragraph>
      <paragraph indent="3">(2)   The following must be considered as highest priority planting areas for forest conservation plans with required afforestation and reforestation:</paragraph>
      <paragraph indent="4">(a)   environmental buffers;</paragraph>
      <paragraph indent="4">(b)   establish or enhance forest in buffers adjacent to ephemeral streams, when such streams are required to have buffers as recommended in an applicable Master Plan or in the latest version of the environmental guidelines;</paragraph>
      <paragraph indent="4">(c)   establish or enhance forested areas on 100-year floodplains, when appropriate;</paragraph>
      <paragraph indent="4">(d)   establish or increase existing forested corridors to connect existing forest within or adjacent to the site.  Where practical forested corridors should be a minimum of 300 feet in width to facilitate wildlife movement;</paragraph>
      <paragraph indent="4">(e)   establish or enhance forest buffers adjacent to critical habitats where appropriate;</paragraph>
      <paragraph indent="4">(f)   establish planting to stabilize natural slopes of 25% or greater and 15% or greater with erodible soils including slopes of ravines or other natural depressions;</paragraph>
      <paragraph indent="4">(g)   establish buffers adjacent to areas of differing land use where appropriate, or adjacent to highways or utility rights-of-way;</paragraph>
      <paragraph indent="4">(h)   establish forest areas adjacent to existing forests to increase the overall area of contiguous forest cover, when appropriate; and</paragraph>
      <paragraph indent="4">(i)   non-forested wetlands are priority planting areas; however, these areas may be left in their existing condition when appropriate.</paragraph>
      <paragraph indent="3">(3)   Planting plans for afforestation and reforestation must include the following:</paragraph>
      <paragraph indent="4">(a)   a minimum of 5 native tree species (unless the site is to be actively managed under an approved forest management plan) and 2 species of native understory shrubs;</paragraph>
      <paragraph indent="4">(b)   appropriate site preparation, protection and/or maintenance measures as described in the latest version of the Trees Technical Manual; and</paragraph>
      <paragraph indent="4">(c)   a stocking rate for trees and shrubs and survival requirements, as shown in the following chart:</paragraph>
      <paragraph indent="2">F.   Tree Save Plans.</paragraph>
      <paragraph indent="3">(1)   Development applications on tracts which impact specimen or champion trees, including those on adjoining properties, are required to submit a tree save plan.</paragraph>
      <paragraph indent="3">(2)   Preserving specimen or champion trees, and stands of trees which are valuable for compatibility reasons, must be included in these plans.  If the loss of these trees is shown to be unavoidable, replacement must be required.</paragraph>
      <paragraph indent="3">(3)   The replacement ratio must be determined in the following manner:</paragraph>
      <paragraph indent="4">(a)   specimen and champion trees must be replaced by a planting plan at a ratio of 1caliper inch replaced for every 4 inches of trunk diameter removed, measured at 4.5 feet above the ground, which may be required to include planting or transplanting of large trees;</paragraph>
      <paragraph indent="4">(b)   tree stands in an existing recorded scenic buffer must be replaced to replace the function of the stand; for instance, trees which provide screening must be replaced in sufficient kind and number to perform the same function.</paragraph>
      <paragraph indent="3">(4)   The tree save plans must show on-site or off-site trees 6" DBH or greater located along the limits of disturbance if the proposed activity would impact the critical root zone of those trees, and must identify methods to preserve and protect those trees.</paragraph>
      <paragraph indent="2">G.   Credit Toward Afforestation and Reforestation for Landscaping and Tree Save.</paragraph>
      <paragraph indent="3">(1)   The Planning Board or Planning Director, as applicable, must find that all opportunities for establishing forest have been incorporated into on-site afforestation and reforestation plans before any credit for landscaping or tree save area is applied.</paragraph>
      <paragraph indent="3">(2)   Trees receiving credit towards forest conservation requirements must not also be credited towards landscaping requirements, including planting and screening required by zoning or other regulatory requirements.</paragraph>
      <paragraph indent="3">(3)   Newly planted landscape trees, within landscape areas must be 3" minimum caliper stock to be counted toward requirements.</paragraph>
      <paragraph indent="3">(4)   Newly planted trees outside of forest, or designated landscape areas, must be 3" minimum caliper stock to be counted toward requirements.</paragraph>
      <paragraph indent="3">(5)   The area(s) where trees are planted must have adequate soil conditions, volume, and surface area to sustain plantings;</paragraph>
      <paragraph indent="3">(6)   Afforestation areas may be established as tree cover if the Planning Board or Planning Director, as applicable, find that tree cover is appropriate.  Instances where it may be appropriate to satisfy afforestation requirements using tree cover include:</paragraph>
      <paragraph indent="4">(i)   developments in urban areas;</paragraph>
      <paragraph indent="4">(ii)   redevelopments;</paragraph>
      <paragraph indent="4">(iii)   high-density residential developments;</paragraph>
      <paragraph indent="4">(iv)   commercial and industrial developments;</paragraph>
      <paragraph indent="4">(v)   high density mixed-use developments; and</paragraph>
      <paragraph indent="4">(vi)   some institutional areas.</paragraph>
      <paragraph indent="3">(7)   Landscaping, retention of tree stands, and retention of individual trees may be credited toward a sites’ reforestation requirements only for projects located within an equity focus area as follows:</paragraph>
      <paragraph indent="4">(a)   landscaping areas or retained tree stands which are at least 2,500 square feet in size and 35 feet wide may receive full credit for their area;</paragraph>
      <paragraph indent="4">(b)   landscaping areas and retained tree stands which are less than 2,500 square feet in size or 35 feet wide may receive one quarter credit for their area;</paragraph>
      <paragraph indent="4">(c)   individual landscape trees may receive one quarter credit for the projected area of their canopy at 20-years;</paragraph>
      <paragraph indent="4">(d)   individual non-priority trees which are retained may receive one quarter credit for the protected area of their critical root zone when at least two thirds of the entire critical root zone is protected; and</paragraph>
      <paragraph indent="4">(e)   the total credit from these areas must not exceed twenty percent of the overall reforestation requirement for a site.</paragraph>
      <paragraph indent="3">(8)   Landscaping, retention of tree stands, and retention of individual trees may be credited toward a sites’ afforestation requirements as follows:</paragraph>
      <paragraph indent="4">(a)   sites with tree cover requirements per subsection (3):</paragraph>
      <paragraph indent="5">(i)   landscaping areas or retained tree stands of any size may receive full credit for their area; and</paragraph>
      <paragraph indent="5">(ii)   individual landscape trees which are retained may receive full credit for the projected area of canopy at 20-years;</paragraph>
      <paragraph indent="4">(b)   sites with special provisions for meeting minimum afforestation requirements per Section 22A-12(f) of the Forest Conservation Law:</paragraph>
      <paragraph indent="5">(i)   landscaping areas or retained tree stands which are at least 2,500 square feet in size and 35 feet wide may receive full credit for their area;</paragraph>
      <paragraph indent="5">(ii)   landscaping areas or retained tree stands which are less than 2,500 square feet in size or less than 35 feet wide may receive one quarter credit for their area;</paragraph>
      <paragraph indent="5">(iii)   individual non-priority landscape trees may receive one quarter credit for the projected area of their canopy at 20-years;</paragraph>
      <paragraph indent="5">(iv)   individual trees which are retained may receive one quarter credit for the protected area of their critical root zone when at least two thirds of the entire critical root zone is protected; and</paragraph>
      <paragraph indent="5">(v)   the total credit from these areas must not exceed twenty percent of the overall afforestation requirement for a site.</paragraph>
    </subsection>
    <subsection heading="22A.00.01.09 Forest Conservation Plan Requirements">
      <paragraph indent="2">A.   Preliminary Forest Conservation Plans.</paragraph>
      <paragraph indent="3">(1)   Development applications that need more than one approval must submit a preliminary forest conservation plan in conjunction with the first approval, unless multiple applications are submitted for simultaneous review and only a final forest conservation plan is required.. The The preliminary forest conservation plan may be based on conceptual analysis if the basic parameters are met and any assumptions are realistic.</paragraph>
      <paragraph indent="3">(2)   A preliminary forest conservation plan must contain the following:</paragraph>
      <paragraph indent="4">(a)   the shape and dimensions of lots, showing locations of any existing structures and improvements, including paved areas;</paragraph>
      <paragraph indent="4">(b)   locations and dimensions of all existing and proposed rights-of-way, setbacks, easements, stockpile areas, and stormwater management facilities (road and utility rights-of-way which will not be improved as part of the development application must be identified);</paragraph>
      <paragraph indent="4">(c)   location of building restriction lines and areas to be conserved including environmental buffers;</paragraph>
      <paragraph indent="4">(d)   conceptual locations of proposed structures and improvements, drainage systems, and sediment control measures;</paragraph>
      <paragraph indent="4">(e)   preliminary limits of disturbance of the natural terrain, and location of forest and tree retention areas, including acreage, with appropriate justification and proposed long-term protection methods (a conceptual grading plan and/or a more detailed tree survey may be required to determine the feasibility of proposed retention areas);</paragraph>
      <paragraph indent="4">(f)   proposed locations of afforestation and reforestation areas, including acreage, and mitigation trees, if required;</paragraph>
      <paragraph indent="4">(g)   a table containing the following information:</paragraph>
      <paragraph indent="5">(i)   acreage of tract;</paragraph>
      <paragraph indent="5">(ii)   acreage of the tract remaining part of an agricultural use;</paragraph>
      <paragraph indent="5">(iii)   acreage of road and utility rights-of-way which will not be improved as part of the development application;</paragraph>
      <paragraph indent="5">(iv)   acreage of total existing forest;</paragraph>
      <paragraph indent="5">(v)   acreage of total forest retention;</paragraph>
      <paragraph indent="5">(vi)   acreage of forest in priority retention areas;</paragraph>
      <paragraph indent="5">(vii)   acreage of total forest retention in priority retention areas;</paragraph>
      <paragraph indent="5">(viii)   acreage of total forest retention not in priority retention areas;</paragraph>
      <paragraph indent="5">(ix)   acreage of total forest cleared in priority retention areas;</paragraph>
      <paragraph indent="5">(x)   acreage of forest cleared not in priority retention areas;</paragraph>
      <paragraph indent="5">(xi)   land use category and conservation and afforestation thresholds from subsection 22A-12(a) of the Forest Conservation Law;</paragraph>
      <paragraph indent="5">(xii)   acreage of forest retained, cleared, and planted within wetlands;</paragraph>
      <paragraph indent="5">(xiii)   acreage of forest retained, cleared, and planted within 100-year floodplains;</paragraph>
      <paragraph indent="5">(xiv)   acreage of forest retained, cleared, and planted within stream buffers;</paragraph>
      <paragraph indent="5">(xv)   total acreage of forest retained, cleared, and planted within priority planting areas; and</paragraph>
      <paragraph indent="5">(xvi)   linear feet and average width of stream buffer provided; and</paragraph>
      <paragraph indent="4">(h)   a forest conservation worksheet showing calculation of forest conservation requirements.</paragraph>
      <paragraph indent="2">B.   Final Forest Conservation Plans.</paragraph>
      <paragraph indent="3">(1)   A final forest conservation plan must be based on final site grading, if known, and must be submitted in conjunction with the final approval needed as part of a development application.  However, if the development project requires the approval of one development application, the final forest conservation plan must be submitted with that development application.</paragraph>
      <paragraph indent="3">(2)   In addition to the items listed in subsection A(2)(a-c), (f), (g) and (h), a final forest conservation plan must include:</paragraph>
      <paragraph indent="4">(a)   conceptual or final grading plans which include building locations and footprints, retaining walls, road and parking layout, sidewalks and pathways, and location of recreation facilities;</paragraph>
      <paragraph indent="4">(b)   a limits of disturbance line which reflects the limits of all clearing and grading on the tract, and the proposed location of sediment and erosion control devices and staging areas;</paragraph>
      <paragraph indent="4">(c)   a survey of trees with a diameter of 24 inches and greater at 4.5 feet above the ground (or trees of other sizes if requested by Planning Department staff to determine the feasibility of proposed retention areas), within 50' on either side of the limits of disturbance, with critical root zones delineated, and with the distance from the tree face to the limits of disturbance shown on the plan or in an associated table;</paragraph>
      <paragraph indent="4">(d)   retention areas including forest, tree stands and other individual trees to be saved, including acreage;</paragraph>
      <paragraph indent="4">(e)   a note describing whether on site downed woody material is to be retained and incorporated into retention, afforestation, or reforestation areas to build habitat.</paragraph>
      <paragraph indent="4">(f)   an afforestation and/or reforestation planting plan, if required, which contains:</paragraph>
      <paragraph indent="5">(i)   a note indicating whether soil restoration techniques will be implemented;</paragraph>
      <paragraph indent="5">(ii)   location and acreage of areas to be planted;</paragraph>
      <paragraph indent="5">(iii)   an analysis of the suitability of the site for planting and a description of necessary methods;</paragraph>
      <paragraph indent="5">(iv)   a list of target tree and shrub species, chosen based on analysis of site conditions, which can be used for site planting;</paragraph>
      <paragraph indent="5">(v)   a plant materials table including size of plants to be installed and quantities;</paragraph>
      <paragraph indent="5">(vi)   planting and inspection schedule which is tied to the construction sequence for the project;</paragraph>
      <paragraph indent="5">(vii)   a maintenance plan which includes provisions for necessary watering, control of competing vegetation, protection from disease, pests, and mechanical injury, removal of protective measures such as deer caging, and reinforcement planting if plant survival falls below the requirements of subsection 22A.00.01.08E(3)(c); and</paragraph>
      <paragraph indent="5">(viii)   a maintenance and management agreement; and</paragraph>
      <paragraph indent="4">(f)   permanent protection area boundaries and long-term protection agreement, where appropriate, and building restrictions lines;</paragraph>
      <paragraph indent="4">(g)   a protection plan which shows:</paragraph>
      <paragraph indent="5">(i)   location of temporary protection devices which must be installed if clearing, grading, or construction occurs within 50 feet of a retention area boundary;</paragraph>
      <paragraph indent="5">(ii)   stockpile areas and borrow pits;</paragraph>
      <paragraph indent="5">(iii)   specifications and details for the protection device;</paragraph>
      <paragraph indent="5">(iv)   a narrative of stress reduction or other measures which are needed for specific trees;</paragraph>
      <paragraph indent="5">(v)   a field inspection schedule pursuant to Section 22A.00.01.10;;</paragraph>
      <paragraph indent="5">(vi)   location of permanent protection devices;</paragraph>
      <paragraph indent="5">(vii)   an arborist report that shows the methods to be utilized to protect any tree, 24" dbh and greater, when 30% or more of the critical root zone is impacted; and</paragraph>
      <paragraph indent="5">(viii)   an arborist report may be required, on a case-by-case basis, for trees less than 24" dbh, when 30% or more of the critical root zone is impacted;</paragraph>
      <paragraph indent="4">(h)   identification of how the off-site planting requirements will be met either through a fee in lieu payment, by acquiring mitigation credits from an approved forest mitigation bank, or by planting offsite; and</paragraph>
      <paragraph indent="4">(i)   if off-site planting is going to occur, the forest conservation plan must include the items listed in subsection (e) plus a map of the proposed planting site showing location, soils, and environmental features which are priority planting areas as stated in subsection 22A.00.01.08E(2).</paragraph>
      <paragraph indent="2">C.   Noticing Requirements for Forest Conservation Plans.</paragraph>
      <paragraph indent="3">(1)   Applicants that require approval of a forest conservation plan must follow the noticing requirements identified in Chapter Administrative Procedures for Development Review in COMCOR 50/59.00.01.04.</paragraph>
    </subsection>
    <subsection heading="22A.00.01.10 Inspections">
      <paragraph indent="2">A.   The Planning Department must conduct field inspections of a site subject to an approved forest conservation plan, tree save plan or confirmed forest conservation exemption as follows:</paragraph>
      <paragraph indent="3">(1)   after the limits of disturbance have been staked and flagged, but before any clearing or grading begins (the purpose of the meeting should be to field verify the limits of clearing specified on the approved plan, authorize necessary adjustments, and to authorize necessary stress reduction measures and installation of protection devices);</paragraph>
      <paragraph indent="3">(2)   after necessary stress reduction measures have been completed and the protection measures have been installed, but before any clearing or grading begins (the purpose of the meeting should be to field verify that both measures have been done correctly and to authorize clearing and grading);</paragraph>
      <paragraph indent="3">(3)   after completion of all construction activities to determine the level of compliance with the approved plan;</paragraph>
      <paragraph indent="3">(4)   before the start of any required reforestation planting (the purpose of the meeting should be to determine whether necessary pre-planting measures have been completed and authorize any necessary adjustments to the planting specifications);</paragraph>
      <paragraph indent="3">(5)   after required reforestation and afforestation planting has been completed to verify that the planting is acceptable and to begin the required maintenance and management period;</paragraph>
      <paragraph indent="3">(6)   two years after reforestation and afforestation have been completed, to determine survival and assess necessary maintenance activities for the remaining duration of the maintenance and management period; and</paragraph>
      <paragraph indent="3">(7)   at the end of the maintenance and management period to determine the level of compliance with the provisions of the planting plan and, if appropriate, authorize release of any financial security.</paragraph>
      <paragraph indent="2">B.   The applicant must:</paragraph>
      <paragraph indent="3">(a)   request these inspections at the designated points; and</paragraph>
      <paragraph indent="3">(b)   submit to the Planning Department semi-annual reports and photographs showing compliance with the provisions of the forest conservation plan by October 31st and April 30th of each year for the duration of the maintenance and management period.</paragraph>
      <paragraph indent="2">C.   The Planning Department is authorized to conduct field inspections at any time other than those identified in Section 22A.00.01.10A.</paragraph>
      <paragraph indent="2">D.   For sites without any planting requirements the final inspection is for the Planning Department to authorize removal of any tree protection measure.  For sites with planting requirements, the final inspection occurs at the end of the maintenance and management period.</paragraph>
    </subsection>
    <subsection heading="22A.00.01.11 Exemptions">
      <paragraph indent="2">A.   A request for exemption from forest conservation plan requirements per Sections 22A-5, 22A-6, and 22A-7 of the Forest Conservation Law must be made in writing to the Planning Director.</paragraph>
      <paragraph indent="2">B.   The following information must be provided as part of an exemption request:</paragraph>
      <paragraph indent="3">(1)   an application form;</paragraph>
      <paragraph indent="3">(2)   a written request detailing how the exemption applies to the proposed plan;</paragraph>
      <paragraph indent="3">(3)   a Natural Resources Inventory, or Natural Resources Inventory/Forest Stand Delineation if forest is proposed to be removed, prepared per Section 22.00.01.06 and the environmental guidelines;</paragraph>
      <paragraph indent="3">(4)   an original copy of a declaration of intent, if required, signed by the applicant named on the development or sediment control application; and</paragraph>
      <paragraph indent="3">(5)   other appropriate information which supports the exemption request including a copy of the proposed plan for development, if applicable.</paragraph>
      <paragraph indent="2">C.   A waiver from the requirement to provide a Natural Resources Inventory with an exemption request may be granted for:</paragraph>
      <paragraph indent="3">(1)   single lot exemptions per subsection 22A-5(a) of the Forest Conservation Law if information is submitted, and the Planning Director affirms, that a natural resource inventory is not necessary but the information does show existing and proposed topography and forest boundaries;</paragraph>
      <paragraph indent="3">(2)   agricultural exemptions per subsection 22A-5(b) of the Forest Conservation Law if a diagram is submitted with the exemption request showing existing and future forest boundaries;</paragraph>
      <paragraph indent="3">(3)   commercial logging and timber harvesting exemptions per subsection 22A-5(d) of the Forest Conservation Law if a diagram is submitted with the exemption request showing existing and future forest boundaries, environmental buffers, harvest areas, and haul roads; and</paragraph>
      <paragraph indent="3">(4)   applications for other exemptions, if the site being developed does not contain any forest specimen or significant trees, existing conservation easements, or environmentally sensitive features, and a plan showing existing features and topography is submitted with the exemption request.</paragraph>
      <paragraph indent="2">D.   The Planning Director may require a person requesting an exemption from submitting a forest conservation plan to submit a tree save plan in conjunction with the exemption request.</paragraph>
      <paragraph indent="2">E.   The Planning Board, or Planning Director, may require a person failing to file an exemption request per section 22A-4 of the Forest Conservation Law, or found in noncompliance with an exemption or a declaration of intent to:</paragraph>
      <paragraph indent="3">(1)   submit a Forest Conservation Plan and meet the requirements in the Forest Conservation Law for a regulated activity;</paragraph>
      <paragraph indent="3">(2)   pay a noncompliance fee;</paragraph>
      <paragraph indent="3">(3)   be subject to other enforcement actions appropriate under Article III of the Forest Conservation Law; and/or</paragraph>
      <paragraph indent="3">(4)   submit a request to be exempt form submitting a forest conservation plan.</paragraph>
      <paragraph indent="2">F.   In its determination of appropriate enforcement action, the Planning Board may consider whether failure to file an exemption by a person required to file is a violation of this subtitle.</paragraph>
      <paragraph indent="2">G.   A confirmed exemption that has not started any authorized land disturbance within 5 years from the date of confirmation automatically expires without notice.</paragraph>
      <paragraph indent="2">H.   A confirmed exemption may not be amended. A new exemption must be submitted for review in order to make any changes.</paragraph>
    </subsection>
    <subsection heading="22A.00.01.12 Declaration of Intent">
      <paragraph indent="2">A.   A declaration of intent is an affirmation by an applicant that a property is subject to the following activities and limitations and therefore is eligible for an exemption from the Forest Conservation  A declaration of intent is required for the following exemptions from submitting a forest conservation plan;</paragraph>
      <paragraph indent="3">(1)   An activity conducted on an existing single lot that is required to construct a dwelling house or accessory structure intended for the use of the owner, if the activity complies with subsection 22A-5(a) of the Forest Conservation Law;</paragraph>
      <paragraph indent="3">(2)   A real estate transfer subject to subsection 22A-5(m) of the Forest Conservation Law.</paragraph>
      <paragraph indent="3">(3)   An agricultural activity that complies with subsection 22A-5(b) of the Forest Conservation Law;</paragraph>
      <paragraph indent="3">(4)   A commercial logging and timber harvesting operation that complies with subsection 22A-5(d) of the Forest Conservation Law;</paragraph>
      <paragraph indent="3">(5)   A minor subdivision that complies with subsection 22A-5(n) of the Forest Conservation Law;</paragraph>
      <paragraph indent="3">(6)   An activity involving the demolition of an existing structure that complies with subsection 22A-5(x) of the Forest Conservation Law.</paragraph>
      <paragraph indent="2">B.   The declaration of intent must provide Planning Department staff with access to the property to verify compliance with the declaration.</paragraph>
      <paragraph indent="2">C.   The declaration of intent is effective for 5 years after the date defined in the declaration of intent.</paragraph>
      <paragraph indent="2">D.   The filing of a declaration of intent does not preclude another exempted activity on the property subject to a declaration of intent, if the activity:</paragraph>
      <paragraph indent="3">(1)   does not conflict with the purpose of any existing declaration of intent; and</paragraph>
      <paragraph indent="3">(2)   complies with the applicable requirements for an exempted activity.</paragraph>
      <paragraph indent="2">E.   If a regulated activity on the area covered by the declaration of intent occurs within 5 years of the effective date of the declaration of intent:</paragraph>
      <paragraph indent="3">(1)   the exemption immediately terminates without any action by the Planning Board;</paragraph>
      <paragraph indent="3">(2)   the Planning Director may require approval of a Forest Conservation Plan for the property; and</paragraph>
      <paragraph indent="3">(3)   the Planning Director, or Planning Board may take other enforcement actions, including those listed under Section 22A-17(a) of Article III of the Forest Conservation Law.</paragraph>
      <paragraph indent="2">F.   An applicant may apply for a regulated activity on the area of the property not covered under the declaration of intent if the requirements of Section 22A-5 are satisfied.</paragraph>
    </subsection>
    <subsection heading="22A.00.01.13 Amendment to Forest Conservation Plan">
      <paragraph indent="2">A.   Forest Conservation Plan Amendments.</paragraph>
      <paragraph indent="3">(1)   Minor amendments which do not result in more than a total of 5,000 square feet of additional forest clearing may be approved by the Planning Director on a case by case basis.  These minor amendments may include field modifications and substituting one area of forest, for retention of another of equal or greater size and value.</paragraph>
      <paragraph indent="3">(2)   Major amendments which entail:</paragraph>
      <paragraph indent="4">(a)   more than a total of 5,000 square feet of additional forest clearing must be approved by the Planning Board or Planning Director (depending on who approved the original plan), or</paragraph>
      <paragraph indent="4">(b)   removal of any conservation easement must be approved by the Planning Board.</paragraph>
      <paragraph indent="3">(3)   All Forest Conservation Plan amendment applications must conform to the requirements of the Forest Conservation Law and regulations in effect at the time of submission.</paragraph>
    </subsection>
    <subsection heading="22A.00.01.14 Forest Conservation Maintenance and Management Agreements">
      <paragraph indent="2">A.   Maintenance Agreements.</paragraph>
      <paragraph indent="3">(1)   A person required to conduct afforestation or reforestation under this regulation and the Forest Conservation Law must include in the forest conservation plan a binding maintenance agreement for a minimum length of 5 years unless reduced pursuant to Section 22A-12(h)(1) of the Forest Conservation Law.  The binding maintenance agreement for forest conservation plans within Special Protection Areas must have a minimum length of 5 years and cannot be reduced.</paragraph>
      <paragraph indent="3">(2)   The maintenance agreement must be submitted and approved by the Planning Director before the start of any land disturbing activities.</paragraph>
      <paragraph indent="3">(3)   The maintenance agreement must detail how the areas designated for afforestation or reforestation will be maintained to ensure protection and satisfactory establishment of forest.</paragraph>
      <paragraph indent="3">(4)   The “oblige,” or person required to conduct the afforestation or reforestation must present evidence of a legal right to implement the proposed maintenance agreement on a selected site by providing:</paragraph>
      <paragraph indent="4">(a)   an executed deed conveying title to a selected site to the obligee;</paragraph>
      <paragraph indent="4">(b)   an executed conservation easement agreement;</paragraph>
      <paragraph indent="4">(c)   written evidence of the landowner’s consent to the use of a selected property;</paragraph>
      <paragraph indent="4">(d)   a fully executed option agreement, long-term lease agreement, or contract of sale for a selected property; or</paragraph>
      <paragraph indent="4">(e)   other written evidence of a possessory or ownership interest in a selected property.</paragraph>
      <paragraph indent="3">(5)   The Planning Director must be a signatory to the maintenance agreement, or must be designated a third-party beneficiary of the agreement.</paragraph>
      <paragraph indent="3">(6)   The maintenance agreement must provide Planning Department staff with access to the property to verify compliance with the Forest Conservation Plan.</paragraph>
      <paragraph indent="3">(7)   If the plantings have not met the survival requirements established in section 22A.00.01.08 or required control of non-native and invasive vegetation, reinforcement plantings and/or additional non-native invasive control will be required, and the maintenance period may be extended.</paragraph>
      <paragraph indent="2">B.   Bonding.</paragraph>
      <paragraph indent="3">(1)   Financial security must be provided per subsection 22A-12(i) of the Forest Conservation Law.</paragraph>
      <paragraph indent="3">(2)   Financial security must be provided before authorization is granted to begin any clearing, grading, demolition, or land disturbing activities.</paragraph>
      <paragraph indent="3">(3)   The value of the financial security must equal the in-lieu fee applicable at the time of land disturbance, or be based on a cost estimate, approved by the Planning Director, for implementing the planting and maintenance of trees and shrubs (including mitigation trees) and control of non-native and invasive plants.</paragraph>
      <paragraph indent="3">(4)   The financial security must be in force until all measures for reforestation, afforestation, and maintenance requirements have been met to the satisfaction of the Planning Director.</paragraph>
      <paragraph indent="3">(5)   A surety bond or other alternative form of security must not be canceled by the surety, bank, or other issuing entity unless both of the following conditions are satisfied:</paragraph>
      <paragraph indent="4">(a)   the surety notifies the Planning Director and the applicant of its intent to cancel the bond, in writing, by registered mail, not less than 90 days before cancellation; and</paragraph>
      <paragraph indent="4">(b)   at least 45 days before the cancellation date indicated in the notice, the applicant files a commitment from a surety, bank, or other issuing entity to provide a substitute security which must take effect on the cancellation date indicated in the notice.</paragraph>
      <paragraph indent="3">(6)   Release of part of the financial security may be authorized by the Planning Department enforcement and monitoring staff after planting has been done.  Any remaining financial security must be at least 50 percent, or greater, than the in-lieu fee that was in effect at the time of the first land disturbance.</paragraph>
      <paragraph indent="3">(7)   An applicant must request an inspection of the planted areas by Planning Department enforcement and monitoring staff immediately after planting is complete.</paragraph>
      <paragraph indent="3">(8)   Planning Department enforcement and monitoring staff must determine whether a partial release should occur, after planting has occurred, and how much, based on the following factors:</paragraph>
      <paragraph indent="4">(a)   evidence of deer browse on existing trees and forest;</paragraph>
      <paragraph indent="4">(b)   adherence to the planting plan;</paragraph>
      <paragraph indent="4">(c)   condition of the planted material;</paragraph>
      <paragraph indent="4">(d)   time of year when the planting has occurred and whether or not watering will occur;</paragraph>
      <paragraph indent="4">(e)   size of planting stock; and</paragraph>
      <paragraph indent="4">(f)   provisions of the protection and maintenance plan, including required control of non-native invasive vegetation.</paragraph>
      <paragraph indent="3">(9)   Planning staff must release the financial security if the applicant requests a final inspection and the Planning staff determines that survival requirements have been met at the end of the maintenance period.</paragraph>
    </subsection>
    <subsection heading="22A.00.01.15 Long-Term Protective Agreements">
      <paragraph indent="2">An applicant must have in effect at all times, approved long-term protective measures as provided in subsection 22A-12(h)(2) of the Forest Conservation Law, to retain as forest, all land forested, afforested, or reforested and unforested lands left in an undisturbed condition per section 22A-12(b) of the Forest Conservation Law and limit the uses of those areas which are consistent with forest conservation.</paragraph>
      <paragraph indent="3">(1)   Long-term protective measures may include, but are not limited to:</paragraph>
      <paragraph indent="4">(a)   conservation easements or covenants;</paragraph>
      <paragraph indent="4">(b)   Deed restrictions; and</paragraph>
      <paragraph indent="4">(c)   dedication to M-NCPPC Parks as a conservation area.</paragraph>
      <paragraph indent="3">(2)   A forest management plan may be included as part of a long-term protective agreement if the Planning Director finds it is consistent with County forest conservation objectives.</paragraph>