<chapter heading="Chapter 50. Subdivision of Land - Regulations">
  <section heading="COMCOR 50.10.01 Administrative Procedures for Development Review">
    <regulation heading="COMCOR 50.10.01 Administrative Procedures for Development Review">
      <subsection heading="50.10.01.01 Purpose and Applicability">
        <paragraph indent="2">A.   Purpose. These regulations define administrative procedures for the submission and review of all plans submitted to the Montgomery County Planning Department, under the Subdivision Regulations and the Zoning Ordinance of the Montgomery County Code. In addition, these regulations define the noticing procedures for forest conservation plans submitted to the Montgomery County Planning Department in compliance with the Forest Conservation Law. These procedures are designed to provide accurate and complete information and to ensure a thorough and timely review process as a basis for decisions. These regulations were adopted by the Planning Board and approved as regulations by the County Council under Chapter 50, Section 10.1 and as contemplated by Chapter 59, Section 7.6.3.D..</paragraph>
        <paragraph indent="3">1.   These regulations:</paragraph>
        <paragraph indent="4">(a)   define a process that is comprehensive, clear, transparent, and understandable to citizens, developers, applicants, review agencies, staff, and other interested parties;</paragraph>
        <paragraph indent="4">(b)   clarify standards and procedures for submission of timely and relevant information by applicants;</paragraph>
        <paragraph indent="4">(c)   provide procedures for timely participation by government agencies in the review of applications; and</paragraph>
        <paragraph indent="4">(d)   provide procedures for participation by interested parties, such as owners of properties adjoining the project site, so that their issues and concerns can be submitted to staff and the Board for consideration during the review process before the Board decides and acts on the proposed land development project.</paragraph>
        <paragraph indent="3">2.   These regulations are intended to identify the steps that an applicant must take to apply for the review and approval of specific types of development approvals that are acted upon by either the Board or Director, and to provide a comprehensive explanation of what is involved in processing a development application, including the steps to ensure a thorough and timely review.</paragraph>
        <paragraph indent="2">B.   Applicability. The development review process covered in these regulations applies to all development applications submitted to the Montgomery County Planning Department and acted upon by the Board or Director under Chapter 50 and Chapter 59 of the County Code. In addition, the noticing procedures covered in these regulations also apply to forest conservation plans not associated with preliminary plans, administrative subdivision plans, sketch plans, site plans, signature business headquarters plans or biohealth priority campus plans.</paragraph>
        <paragraph indent="2">C.   Definitions. All terms used in these regulations that are defined in Chapter 22A, Chapter 50, or Chapter 59 have the same meanings as the definitions in those Chapters.</paragraph>
        <paragraph indent="2">D.   Rules of interpretation. The rules of interpretation contained in Chapter 22A, Chapter 50, and Chapter 59 apply to these regulations. Footnotes used in these regulations are a part of the requirements.</paragraph>
      </subsection>
      <subsection heading="50.10.01.02 Basic Planning Department Policies for the Development Review Process">
        <paragraph indent="2">A.   In processing and reviewing the application, the Planning Department staff must:</paragraph>
        <paragraph indent="3">1.   Appoint a lead reviewer to coordinate the review of the application and the receipt of inquiries related to the application or the regulatory process.</paragraph>
        <paragraph indent="3">2.   Review the application carefully, fairly, and in a timely manner.</paragraph>
        <paragraph indent="3">3.   Apply the applicable laws, regulations, and guidelines consistently.</paragraph>
        <paragraph indent="3">4.   Work with all parties to present a recommendation to the Board that complies with the applicable standards of review.</paragraph>
        <paragraph indent="3">5.   Attempt to identify issues early in the process and strive to resolve them as early as possible.</paragraph>
        <paragraph indent="3">6.   Cooperate with other agency and utility company staffs, the applicant, and the public to seek a mutually satisfactory resolution when issues arise.</paragraph>
        <paragraph indent="3">7.   Collaborate with other review agencies and other parties, actively seeking solutions that achieve the County’s planning and community-building goals.</paragraph>
        <paragraph indent="3">8.   Carry out County and Planning Board policies, with special attention to:</paragraph>
        <paragraph indent="4">(a)   adopted Master Plans;</paragraph>
        <paragraph indent="4">(b)   applicable land use, transportation, and environmental laws, regulations, and guidelines;</paragraph>
        <paragraph indent="4">(c)   the Growth and Infrastructure Policy, as amended;</paragraph>
        <paragraph indent="4">(d)   standards of professional responsibility; and</paragraph>
        <paragraph indent="4">(e)   promotion of design excellence.</paragraph>
        <paragraph indent="2">B.   Planning Department staff and other government agency and utility company staff who participate in the review of development applications must:</paragraph>
        <paragraph indent="3">1.   Review each application carefully, fairly, and in a timely manner.</paragraph>
        <paragraph indent="3">2.   Participate in scheduled Development Review Committee (DRC) meetings, either in person or by transmitting written comments to the DRC chair.</paragraph>
        <paragraph indent="3">3.   Make reasonable efforts to participate, when necessary, in supplemental meetings on specific cases, as requested by either the lead reviewer or the applicant.</paragraph>
        <paragraph indent="3">4.   Work collaboratively to identify and seek mutually satisfactory resolutions, using the lead-agency protocol for conflicting recommendations created though a Memorandum of Understanding between the Planning Department and several of the agency members of the DRC to involve appropriate managers or chiefs from the conflicting agencies.</paragraph>
        <paragraph indent="3">5.   Report recommendations to the Board that are contrary to Planning staff’s in the rare event that agencies with conflicting comments are unable to timely reach a mutually satisfactory recommendation on issues related to a development application after following the protocol referenced above.</paragraph>
        <paragraph indent="2">C.   Applicants must:</paragraph>
        <paragraph indent="3">1.   Select a development team, consultants, and representatives appropriate for the project.</paragraph>
        <paragraph indent="3">2.   Follow Planning Board and County policies, procedures, and regulations related to the proposed development project.</paragraph>
        <paragraph indent="3">3.   Submit complete and accurate applications.</paragraph>
        <paragraph indent="3">4.   Refer questions, issues, and all revisions concerning the filed application to the lead reviewer.</paragraph>
        <paragraph indent="3">5.   Notify the lead reviewer promptly if there is a major change to the development project under review.</paragraph>
        <paragraph indent="3">6.   Work with review staffs and the public in a cooperative manner to seek a mutually satisfactory resolution when issues arise.</paragraph>
      </subsection>
      <subsection heading="50.10.01.03 Overview of the Application Types">
        <paragraph indent="0">These regulations specify the submission, notice, review and approval procedures that must be followed for all development applications and associated requests that are submitted to the Montgomery County Planning Department and acted upon by the Board or Director. The types of applications that may be required before an applicant can apply for permits to disturb land and build structures are dependent on many factors, such as, the zoning on the subject site, the legal status (i.e., recorded lot, unplatted parcel, etc.) of the site, and the type of land use proposed for the project. This section includes an overview of the various application types.</paragraph>
        <paragraph indent="2">A.   Land Development Plan Applications. The land development plan applications covered by these regulations include: pre-preliminary submissions, sketch or project plans, preliminary and administrative subdivision plans, site plans, signature business headquarters plans, biohealth priority campus plans, and record plats.</paragraph>
        <paragraph indent="2">B.   Plan Amendments. Proposed changes to a land development plan that has been approved and certified by the Board or Director must be approved as a plan amendment. A plan amendment may be filed to request changes to features of an approved plan drawing, or to specific conditions of the Board’s or Director’s approval for the plan.1</paragraph>
        <paragraph indent="3">1.   Classification of Preliminary and Site Plan Amendments. An amendment to a preliminary plan or site plan may be classified as major or minor depending on the purpose of the proposed amendment and as specified by the Subdivision Regulations (Section 50.4.2.F) or the Zoning Ordinance (Section 59.7.3.4.J).</paragraph>
        <paragraph indent="4">(a)   Major amendments to a site plan or a preliminary plan must be acted on by the Board.</paragraph>
        <paragraph indent="4">(b)   Minor amendments to a preliminary plan must be acted on by the Board; except that, if the amendment is to change the validity period of the approved plan’s phasing schedule, the Director may act on the proposed amendment.</paragraph>
        <paragraph indent="4">(c)   Minor site plan amendments may be acted upon by the Director under certain circumstances as set forth in Section 59.7.3.4.J of the Zoning Ordinance.</paragraph>
        <paragraph indent="4">(d)   A new preliminary plan or administrative subdivision plan is required to resubdivide previously approved and recorded lots, or to resubmit a revised version of a previous application that was denied.</paragraph>
        <paragraph indent="3">2.   Amendment to a Preliminary or Site Plan to change an associated Forest Conservation Plan. Preliminary or site plan amendments that involve amendments to associated forest conservation plans may be filed as minor amendments.</paragraph>
        <paragraph indent="4">(a)   Per the Forest Conservation regulations (COMCOR 22A.00.01, Section 22A.00.01.13.A(1)), a forest conservation plan amendment that proposes no more than 5000 square feet of additional forest clearing may be acted on by the Director.</paragraph>
        <paragraph indent="4">(b)   A forest conservation plan amendment that proposes more than 5000 square feet of additional forest clearing must be acted on by the Board. Corresponding amendments to the associated preliminary or site plan to reflect these changes must also be acted on by the Board.</paragraph>
        <paragraph indent="4">(c)   A proposed forest conservation plan amendment that involves changes to recorded conservation easements approved by the Board must be acted on by the Board. Corresponding amendments to the associated preliminary or site plan to reflect any easement changes must also be acted on by the Board.</paragraph>
        <paragraph indent="3">3.   Amendments to Sketch Plans. Sketch Plans can be amended by filing a separate amendment application, or as part of a subsequent site plan application pursuant to Section 59.7.3.3.I of the Zoning Ordinance. A site plan must be submitted within 36 months after the date of the resolution for the sketch plan, and any request to amend the sketch plan to extend this period must be filed prior to the expiration of the 36-month period.</paragraph>
        <paragraph indent="3">4.   Changes to Site Plan-approved structures. A structure located on property covered by an approved site plan may be replaced without applying for a site plan amendment if the replacement conforms to the specifications approved as part of the site plan; for instance, replacing an existing fence or retaining wall, in kind. Changes that do not conform to approved specifications must be filed as a minor or major site plan amendment, as appropriate, except for those changes allowed under 59-7.3.4.G.2.</paragraph>
        <paragraph indent="4">(a)   Playground areas and equipment. Many approved site plans that have residential uses include details for playground areas and equipment. For the purposes of site plan review, the term “playground equipment” includes benches, picnic tables, and trash receptacles, in addition to structures that are used for outdoor recreation activities by children, such as swing sets and slides. Over time, playground equipment may become old and outdated and need to be replaced; or a resident association may want to change its location or configuration, or remove it entirely.</paragraph>
        <paragraph indent="5">i.   Installation of a new playground or removal of an existing one requires review and action under the minor site plan amendment process.</paragraph>
        <paragraph indent="5">ii.   Replacing playground equipment requires review and approval by Planning Department staff. Such a change is not classified as a site plan amendment. The following rules apply to the substitution of playground equipment, for a site that has an approved site plan and specific playground equipment requirements:</paragraph>
        <paragraph indent="6">a.   A request for a playground equipment substitution must be made by submitting a complete Recreational Equipment Substitution Request Form.</paragraph>
        <paragraph indent="6">b.   The form may be filled out by the provider of the proposed playground equipment, but the project developer must also submit a cover letter confirming that the current site plan applicant supports the proposed substitution.</paragraph>
        <paragraph indent="6">c.   Staff must review the substitution request to determine if the proposed equipment is equal in capacity, features, age group served, and quality2 (including conformance with CPSC and ASTM3 safety standards.)</paragraph>
        <paragraph indent="6">d.   If staff does not render a decision as to whether the proposed substitution meets the “or approved equal” standard within 45 calendar days after the applicant’s complete submission of a Recreational Equipment Substitution Request Form, the substitution is automatically approved.</paragraph>
        <paragraph indent="6">e.   After deciding, staff must reply, in writing, to the current site plan applicant. If the request is denied, the staff must specify, in writing, each reason for the denial. Staff must place a copy of the reply letter in the site plan file. The site plan applicant may appeal a denial to the Board.</paragraph>
        <paragraph indent="2">C.   Other Application Types. An application must also be submitted to the Planning Department for the following:</paragraph>
        <paragraph indent="3">1.   Subdivision Waiver Request. A request for a waiver from the requirement to submit a preliminary plan or administrative subdivision plan under Division 50.9 of Chapter 50.</paragraph>
        <paragraph indent="3">2     Adequate Public Facilities (APF) Review at Building Permit. A request for Planning Board APF review and finding required under Chapter 8 before issuance of a building permit for development on an existing recorded lot that is not subject to a previous preliminary plan approval, and does not require a site plan under Chapter 59, Section 7.3.4.; a signature business headquarters plan under Chapter 59, Section 7.3.5.; or a biohealth priority campus plan under Chapter 59, Section 7.3.6.</paragraph>
        <paragraph indent="3">3    Request to Extend a Hearing Date. A request for extension of a Board hearing date pursuant to Chapter 59, Sections 7.3.3.C or 7.3.4.C, and Chapter 50, Section 4.1.E.</paragraph>
        <paragraph indent="0">----------</paragraph>
        <paragraph indent="0">1  A plan amendment is different than a plan revision.  A plan revision is a change to a submitted application that an applicant chooses to make prior to action. Significant revisions may, on a case-by-case basis, require re-notice of the application.</paragraph>
        <paragraph indent="0">2  The equipment proposed must also be able to fit in the space shown on the site plan.  If the proposed substitution becomes so big that it no longer fits in the “play area” shown on the site plan, a site plan amendment is required.</paragraph>
        <paragraph indent="0">3  If there is a conflict between Consumer Product Safety Commission (CPSC) and American Society for Testing and Materials (ASTM) standards, ASTM standards will govern.</paragraph>
      </subsection>
      <subsection heading="50.10.01.04 Notice">
        <paragraph indent="0">Certain types of notice must be provided by both the applicant and Planning Department staff at specific steps during the regulatory review process. The individuals receiving these notices vary depending upon the notice type, but include: owners of adjoining and confronting properties; nearby civic and homeowners’ associations; “interested parties” who request notice during the process; and the general public.</paragraph>
        <paragraph indent="0">Individuals, groups, and interested parties receive notice in writing, by mail. The general public receives notice from signs that are posted on a project site, and for applications that are acted upon by the Board, from the weekly Planning Board agenda on the Board’s website.</paragraph>
        <paragraph indent="2">A.   Notice Standards</paragraph>
        <paragraph indent="3">1.   Notice Required. Notice is required for each application per the following table, or as otherwise specified in the Code:</paragraph>
        <paragraph indent="0">APPLICATI ON TYPE | Pre- submittal Community Mtg. | Site Posting | Written Notice from Applicant | Written Hearing Notice from Planning Departme nt | Planning Department Website Posting
Pre- submittal Communi ty Mtg. | Applicati on | Pre- submittal Communi ty Mtg. | Applicati on | DRC Agenda | Planning Board Agenda</paragraph>
        <paragraph indent="0">1 Notice shown in this table is per Section 7.5.1 of Chapter 59.</paragraph>
        <paragraph indent="0">2 Forest conservation plan amendments are subject to noticing if a Planning Board hearing is required, if there is a change to an approved tree variance, or if a new tree variance is required.</paragraph>
        <paragraph indent="3">2.   Notice List. Applicants must create and submit a notice list as part of applications that require written notices to be sent. The notice list must be:</paragraph>
        <paragraph indent="4">•   compiled using the latest available records;</paragraph>
        <paragraph indent="4">•   compiled no more than 30 calendar days before the pre-submittal community meeting, if applicable; and</paragraph>
        <paragraph indent="4">•   updated no more than 30 calendar days before the date the Application is accepted by the Planning Department, Intake and Regulatory Coordination (IRC) Division, Intake Section staff.</paragraph>
        <paragraph indent="4">(a)   Individuals and groups included. Individuals and groups that must be on the notice list are defined as follows:</paragraph>
        <paragraph indent="5">i.   Abutting and Confronting Property Owners. The applicant must compile the names and addresses of the owners of properties that are adjacent to the project site or directly across a right-of-way, of a width of less than 80 feet, from the project site. This list must be based on tax assessment ownership records from the Maryland Department of Assessments and Taxation (SDAT), Real Property Database. If an abutting or confronting property includes a multi-unit building (residential, non-residential, or mixed use), the notice list must include the property owner, the building management company, and the condominium association, if any. The list must also include any individual unit owner or renter in the building who has registered to receive notices on the MNCPPC website. If an abutting or confronting property is a recorded open space parcel for a subdivision, the applicant’s notice list must include the homeowners’ association, condominium association, or renters’ association and any individual owner of a property in that subdivision that is located within 300 feet of the subject property.</paragraph>
        <paragraph indent="5">ii.   Civic, Community, Condominium Associations, Homeowners’ and Renters’ Associations, and Municipalities.</paragraph>
        <paragraph indent="6">a.   The civic, community, condominium and homeowner’s associations that have registered with M-NCPPC4 and are either: a) located within a half-mile radius of the center point of the subject property; or b) an association that has requested to receive notices for all development applications. At staff’s discretion, this list may be expanded for large or unusually shaped properties to include associations within a half-mile radius from a point or points along the property boundary, or to include a larger radius from the center point.</paragraph>
        <paragraph indent="6">b.   For a project that proposes to amend only a part of a site which is covered by an approved preliminary and/or site plan, and the site has been partially constructed, sold, and occupied, the project’s notice list is generated from the boundary of the amendment area. Property owners, including any individual unit owner or renter in a multi-unit building within the area being amended who has registered to receive notices on the MNCPPC website, must be included in the notice list. Residents who are not property owners within the constructed part of the site must be notified of the proposed project through their HOA or Community Association.</paragraph>
        <paragraph indent="6">c.   Planning staff may require the applicant to add to the applicant’s notice list any common ownership association or civic association listed in the Planning Department’s records that abuts or confronts a public facility not adjacent or close to the project site, but which may require construction or improvement because of the proposed project. If required during plan review, as opposed to initial application, this notice must be directed to each designated association no later than 30 calendar days before the Board’s hearing on the application.</paragraph>
        <paragraph indent="5">iii.   Pre-Submittal Community Meeting Participants. An applicant for certain plan types is required to hold a community meeting before the application is submitted to the Planning Department. Only meeting participants who have asked to receive future notices are required to be on the notice list.</paragraph>
        <paragraph indent="5">iv.   Parties of Record from Previous Applications. If a project site has an approved plan, and an applicant applies for a plan amendment, individuals or groups that were identified as Parties of Record in the earlier application must be added to the notice list of the current application. For example, a notice list for a preliminary plan amendment would include all individuals and groups who were identified as Parties of Record for the original preliminary plan application, in addition to those who meet the criteria covered above.</paragraph>
        <paragraph indent="5">v.   Others. The IRC Division – Intake Section must be included on the applicant’s notification list. The applicant and members of the applicant’s team who wish to receive notices should also be included.</paragraph>
        <paragraph indent="4">(b)   Updates Required. The applicant must update the notice list of adjoining and confronting property owners if the application is pending for more than 6 months after the final application is accepted, and provide the new list to the IRC Division for use in sending hearing notices.</paragraph>
        <paragraph indent="2">B.   Pre-submittal Community Meetings. For a sketch plan, preliminary plan, site plan, signature business headquarters plan, or biohealth priority campus plan, the applicant must hold at least one public pre-submittal community meeting no more than 90 calendar days before the initial application date. The purpose of the meeting is to explain the proposed project, address concerns about its impact on the community, and notify those attending of their right to participate in the review process. The applicant must expressly invite all individuals on the notice list and must also post one or more signs that are visible from the street on the property. The meeting must be held on an evening or a weekend, in a location convenient to the proposed development site. The applicant must provide a sign-in sheet at the meeting so that attendees can identify themselves and provide their mailing address, if they wish to receive future notices.</paragraph>
        <paragraph indent="2">C.   Site Posting. In addition to site posting required for notice of the pre-submittal community meeting, the applicant must post one or more signs at the development site for the plans noted in the table in subsection A.1 above, indicating that an application has been filed. The applicant must:</paragraph>
        <paragraph indent="3">1.   pay all costs associated with the sign posting requirements;</paragraph>
        <paragraph indent="3">2.   monitor the signs and replace any damaged or illegible signs; and</paragraph>
        <paragraph indent="3">3.   maintain posted pre-submittal community meeting signs until the date the meeting is held, and application signs throughout the review of the application.5</paragraph>
        <paragraph indent="4">(a)   Timing.</paragraph>
        <paragraph indent="5">i.   Pre-Submittal Community Meeting signs must be posted at least 15 days before the meeting is held.</paragraph>
        <paragraph indent="5">ii.   Signs to advertise the filing of the application must be posted before the application is accepted.</paragraph>
        <paragraph indent="4">(b)   Sign Specifications. The applicant and its sign vendor, if any, must follow the Sign Template for sign content and lettering specifications. The Planning Department may modify these requirements in special circumstances to assure that all signs will be visible to the public.</paragraph>
        <paragraph indent="4">(c)   Posting specifications. The required number and location of posted signs are as follows:</paragraph>
        <paragraph indent="5">i.   A minimum of one sign must be placed parallel to each public or private street that is adjacent to the property.</paragraph>
        <paragraph indent="5">ii.   If the frontage for a street adjacent to the project site is more than 500 feet long, an additional sign must be posted adjacent to the street for every 500 feet of frontage.</paragraph>
        <paragraph indent="5">iii.   Signs are not required to be placed along and adjacent to a freeway.</paragraph>
        <paragraph indent="5">iv.   Signs must be placed on the property in the most visible location available in such a manner that landscaping or other features do not impair or obstruct the visibility of the signs from the street.</paragraph>
        <paragraph indent="5">v.   Signs must be posted within the project site, no more than 10 feet behind the property line adjacent to a street right-of-way or the access easement covering a private street.</paragraph>
        <paragraph indent="5">vi.   Signs must not be placed within a street right-of-way or private street access easement.</paragraph>
        <paragraph indent="5">vii.   For a large site or one with unusual constraints, the requirements listed above may be modified by Planning Department staff to provide good visibility of posted signs.</paragraph>
        <paragraph indent="4">(d)   Posting information. Posted signs must contain the following information.</paragraph>
        <paragraph indent="5">i.   Signs advertising a Pre-Submittal Community Meeting must include:</paragraph>
        <paragraph indent="6">a.   meeting date, time, and place;</paragraph>
        <paragraph indent="6">b.   purpose of the meeting; and</paragraph>
        <paragraph indent="6">c.   applicant’s contact information.</paragraph>
        <paragraph indent="5">ii.   Signs advertising the submission of the application must include:</paragraph>
        <paragraph indent="6">a.   project name as it appears on the accepted application;</paragraph>
        <paragraph indent="6">b.   project number, as assigned by the Planning Department at the time of the application submission;</paragraph>
        <paragraph indent="6">c.   type of plan (i.e., preliminary plan, site plan, etc.);</paragraph>
        <paragraph indent="6">d.   size and zoning of the site;</paragraph>
        <paragraph indent="6">e.   each proposed use, and its associated proposed number of dwelling units, if residential use is proposed, and/or square footage of all non-residential buildings identified by type (i.e., office, retail, etc.); and</paragraph>
        <paragraph indent="6">f.   Planning Department contact information.</paragraph>
        <paragraph indent="2">D.   Written Notice.</paragraph>
        <paragraph indent="3">1.   Timing. Required written notice must be sent per the following table:</paragraph>
        <paragraph indent="0">Requirements | Pre-submittal Community Meeting 1 | Application Notice | Hearing Notice
Sign Posting | At least 15 days before meeting | Before application is accepted | 
Written Notice Sent 2 | At least 15 days before meeting | No more than 5 days after application is accepted | At least 10 days before hearing date
Posting on Planning Board Agenda |  |  | At least 10 days before hearing date 3
Responsible Party | Applicant | Applicant | Planning Department Staff</paragraph>
        <paragraph indent="0">1 Must occur no more than 90 days before an application is filed.</paragraph>
        <paragraph indent="0">2 By First-Class Mail</paragraph>
        <paragraph indent="0">3 At least 7 calendar days before the Board meeting for an application that will be reviewed by the Board but acted on by another agency.</paragraph>
        <paragraph indent="3">2.   Standards. Written notice sent by the applicant and Planning Department staff must meet the following standards:</paragraph>
        <paragraph indent="4">(a)   Pre-submittal Community Meeting. The notice letter must be sent to everyone on the notice list and must contain:</paragraph>
        <paragraph indent="5">i.   date, time, and place for the meeting;</paragraph>
        <paragraph indent="5">ii.   date that the notice is sent;</paragraph>
        <paragraph indent="5">iii.   name and contact information of applicant or applicant’s representative. The listed individual must be available to provide further information about the proposed project and respond to any reasonable public request;</paragraph>
        <paragraph indent="5">iv.   proposed project name;</paragraph>
        <paragraph indent="5">v.   type of application that will be filed;</paragraph>
        <paragraph indent="5">vi.   property street address or other easily understood geographical reference to the location of the project site;</paragraph>
        <paragraph indent="5">vii.   property size and zoning;</paragraph>
        <paragraph indent="5">viii.   proposed use and density of development; and</paragraph>
        <paragraph indent="5">ix.   website and phone number for the  IRC Division.</paragraph>
        <paragraph indent="4">(b)   Application Notice.</paragraph>
        <paragraph indent="5">i.   Notice letter. The notice letter must be sent to everyone on the notice list and any individuals who requested notice at the pre-submittal community meeting and must contain:</paragraph>
        <paragraph indent="6">a.   application number, as assigned by the Planning Department;</paragraph>
        <paragraph indent="6">b.   date that the notice was sent;</paragraph>
        <paragraph indent="6">c.   project name;</paragraph>
        <paragraph indent="6">d.   plan type;</paragraph>
        <paragraph indent="6">e.   property street address or other easily understood geographical reference to the location of the project site;</paragraph>
        <paragraph indent="6">f.   property size and zoning;</paragraph>
        <paragraph indent="6">g.   proposed use and density of development, if applicable, and if the application is an amendment to an approved plan, the changes that are proposed;</paragraph>
        <paragraph indent="6">h.   tentative Board hearing date scheduled by the Planning Department, if applicable;</paragraph>
        <paragraph indent="6">i.   deadline date for receiving comments on the application, if applicable; and</paragraph>
        <paragraph indent="6">j.   contact address and phone number for the IRC Division.</paragraph>
        <paragraph indent="5">ii.   Notice letters for applications submitted for Director approval. The applicant must expand the notice list under subsection 50.10.01.04.A.2 above, to include all other parties of record noted in any previous files related to the current amendment, and mail the notice to all parties. In addition to the items in subsection 50.10.01.04.D.2(b)i above, the notice letter must include a deadline (at least 15 days after the mailing date of the notice) for the submission of comments regarding the application.</paragraph>
        <paragraph indent="5">iii.   Additional items. The following attachments must be included with the notice letter:</paragraph>
        <paragraph indent="6">a.   Separate, legible 11" x 17" copy of the applicant’s proposed plan drawing for the project.</paragraph>
        <paragraph indent="6">b.   Latest version of the Planning Department’s brochure, entitled ”Development Applications in Montgomery County”.</paragraph>
        <paragraph indent="4">(c)   Hearing Notice.</paragraph>
        <paragraph indent="5">i.   Written notice. The notice must be sent to everyone on the notice list, anyone who requested notice and provided a mailing address at the pre-submittal community meeting or any other time during application review, and any individuals who submitted written comments and included a mailing address regarding the application. The notice must contain:</paragraph>
        <paragraph indent="6">a.   date and location of the meeting;</paragraph>
        <paragraph indent="6">b.   project name;</paragraph>
        <paragraph indent="6">c.   application number;</paragraph>
        <paragraph indent="6">d.   plan type;</paragraph>
        <paragraph indent="6">e.   property size and zoning;</paragraph>
        <paragraph indent="6">f.   project location; and</paragraph>
        <paragraph indent="6">g.   description of the proposed development or application.</paragraph>
        <paragraph indent="5">ii.   Website posting. The Board’s Weekly Agenda provides a notice for the general public of items to be reviewed by the Board, and public access to a staff report for each item where one is required. Information that can be found for each item on the agenda includes:</paragraph>
        <paragraph indent="6">a.   project name and plan number;</paragraph>
        <paragraph indent="6">b.   brief description of the application and project site;</paragraph>
        <paragraph indent="6">c.   area team lead review staff name;</paragraph>
        <paragraph indent="6">d.   staff recommendation and link to the staff technical report, if required; and</paragraph>
        <paragraph indent="6">e.   item number on the agenda and approximate time of day that the Board will take up the item.</paragraph>
        <paragraph indent="0">----------</paragraph>
        <paragraph indent="0">4  Applicants may use the Association Finder Interactive Map tool, a GIS-based map created and maintained by the Planning Department for convenience.</paragraph>
        <paragraph indent="0">5  If an applicant does not maintain a properly posted sign on the project site, the Board may postpone a hearing on the application until the applicant has demonstrated that the site has been properly posted for at least 30 consecutive calendar days. Signs may be removed from the property after Board or Director action, as required, has been taken on the application.</paragraph>
      </subsection>
      <subsection heading="50.10.01.05 Requirements for Application Submittal">
        <paragraph indent="2">A.   Pre-submittal.</paragraph>
        <paragraph indent="3">1.   Required Meeting with the Community. The applicant must hold at least one pre-submittal community meeting before submitting a project plan, sketch plan, preliminary plan, site plan, signature business headquarters plan, or biohealth priority campus plan.</paragraph>
        <paragraph indent="4">(a)   Requirements of the meeting.</paragraph>
        <paragraph indent="5">i.   The applicant must schedule the meeting no more than 90 calendar days before the initial application date, on an evening or weekend, at a location that is convenient to the proposed project site.</paragraph>
        <paragraph indent="5">ii.   The purpose of the meeting is to present information about the proposed project and allow members of the community and the larger public to ask questions.</paragraph>
        <paragraph indent="5">iii.   The applicant must provide a sign-in sheet at the meeting so that attendees can identify themselves, provide a mailing address, and indicate whether they want to be added to the notice list.</paragraph>
        <paragraph indent="5">iv.   The applicant must take meeting minutes that include a summary of any issues or concerns raised by attendees.</paragraph>
        <paragraph indent="3">2.   Optional Meeting(s) with Staff. If site constraints or other issues related to the proposed development of a property raise questions about a future development application, an applicant may request one or more pre-submittal meetings with staff.</paragraph>
        <paragraph indent="2">B.   Application. All applications covered by this manual must be filed with the IRC Intake Section staff. The applicant or its representative must fill out and sign the application form and checklist certifying that application and checklist are complete and ready for processing.</paragraph>
        <paragraph indent="3">1.   Applicant’s Responsibility.</paragraph>
        <paragraph indent="4">(a)   Required submittal items. Applications for review and action by either the Board or Director are typically submitted and processed electronically through Montgomery Planning ePlans.6 Filing an application includes submittal of an application form, followed by uploading electronic copies of required drawings and documents. The application must include all information required in the application checklist.</paragraph>
        <paragraph indent="4">(b)   Meeting required before plan amendment application. The required items for a plan amendment vary depending upon the specifics of the case. For each plan amendment, the applicant must contact the appropriate area team supervisor to determine the exact submission requirements. The amendment must clearly identify the items or areas of the approved plan proposed for revision.</paragraph>
        <paragraph indent="3">2.   Staff’s Responsibility.</paragraph>
        <paragraph indent="4">(a)   Intake Review. Staff must review the application and, within 10 days, either accept the application, or provide initial comments containing all revisions or additional materials required to make the application consistent with the submission requirements. Staff’s review consists of a pre-screen step to make any necessary corrections on the application form and compute the appropriate application fee, and then intake review of the initial application materials to determine if the information submitted is complete and meets the requirements of the application checklist. Intake review is not a review of the merits of the application. Applicants should strive to ensure that each application is complete and correct at the time of initial submission. Staff must not accept an incomplete application for review.</paragraph>
        <paragraph indent="3">3.   Items Required for all Applications. Applications filed with the Planning Department must contain:</paragraph>
        <paragraph indent="4">(a)   plan drawings, documents, and other items as required by the application checklist;</paragraph>
        <paragraph indent="4">(b)   a certificate of compliance;</paragraph>
        <paragraph indent="4">(c)   a statement of justification; and</paragraph>
        <paragraph indent="4">(d)   documentation of notice, including pre-submittal community meeting and site posting.</paragraph>
        <paragraph indent="0">The following are also required before an application is accepted:</paragraph>
        <paragraph indent="4">(e)   a copy of the application form signed and dated by the property owner or applicant; and</paragraph>
        <paragraph indent="4">(f)   payment of the appropriate fee.7</paragraph>
        <paragraph indent="3">4.   Plan drawings and documents. A digital copy of all submittal items required by the application checklist for each application type must be provided with the application in the appropriate file format, with the appropriate file name, and prepared following the submittal requirements on the Planning Department Webpage. Plan drawings must be legible and include appropriate notes and specifications and proper certification by a licensed professional or other qualified preparer.</paragraph>
        <paragraph indent="3">5.   Certificates of Compliance. The Certificate of Compliance8, signed and dated by the Applicant, attests that, to the best of the applicant’s knowledge, information, and belief after reasonable investigation, the application conforms to all applicable Federal, State, and County laws and regulations, including standards of the applicable zone. The certification also confirms that the plans and documents in the application package provide complete and correct information on boundary, ownership, and other information on properties, topography, historic resources, etc.</paragraph>
        <paragraph indent="3">6.   Statements of Justification. The Statement of Justification is a written statement listing the facts and reasons that the applicant believes would support Board or Director approval of the application. The statement must address each finding that is required in either Chapter 50 or Chapter 59, depending on the type of application.</paragraph>
        <paragraph indent="4">(a)   Waiver requests. If the application includes a request for any waiver of any law or regulation, the statement must specifically identify the applicable code section and provide details of the facts and legal basis that support the granting of the requested waiver. If a waiver is requested for environmental reasons, the applicant should refer to the latest approved Environmental Guidelines: Guidelines for the Environmental Management of Development in Montgomery County, Maryland. If a proposed development application requires approval of a variance of a zoning standard by the Montgomery County Board of Appeals, Planning Board staff will not process the application until the Board of Appeals acts.</paragraph>
        <paragraph indent="4">(b)   Supporting information. The applicant must attach any diagrammatic or illustrative materials that support the facts asserted in the statement of justification. The Applicant, or the Applicant’s representative, must certify that the information set forth in each statement of justification is true, complete, and correct to the best of their knowledge, information, and belief.</paragraph>
        <paragraph indent="3">7.   Documentation of Notice.</paragraph>
        <paragraph indent="4">(a)   Notice List. The submitted application documents must include a copy of the notice list, satisfying the requirements above. After mailing written notice, the applicant must retain each item of mail returned undelivered and produce any item retained for inspection by the staff or the Board upon request. If IRC Division staff has not received a copy of the required written notice, the Development Review Committee meeting on the application must be postponed until the applicant demonstrates that each required notice was mailed. If an application is pending for more than one year, the applicant must update the notice list and re-send notice (with the latest plan drawings) to each party on the updated list before the plan is scheduled for Board action.</paragraph>
        <paragraph indent="4">(b)   Pre-submittal community meeting. The applicant must provide the following pre-submittal community meeting documentation with the application:</paragraph>
        <paragraph indent="5">i.   a signed and notarized affidavit attesting to the date, time, and location of the meeting;</paragraph>
        <paragraph indent="5">ii.   a dated copy of the invitation notice letter;</paragraph>
        <paragraph indent="5">iii.   a copy of the sign-in sheet, and a typed summary list that identifies each attendee, the attendee’s contact information, and identification of each attendee who provided a mailing address and wants to receive all future notifications concerning the proposed application; and</paragraph>
        <paragraph indent="5">iv.   meeting minutes that include a summary of issues or concerns raised by attendees.</paragraph>
        <paragraph indent="3">8.   Documentation of Site Posting. The applicant must provide the following documentation of site posting:</paragraph>
        <paragraph indent="4">(a)   Initial application. When an application is initially submitted, the applicant must include a template of the proposed sign and a drawing showing the proposed posting locations on the development site.</paragraph>
        <paragraph indent="4">(b)   Before application acceptance. A document file containing the following items must be submitted before application acceptance to demonstrate that site posting requirements have been met:</paragraph>
        <paragraph indent="5">i.   a signed and notarized affidavit attesting to the date and location of the posted signs;</paragraph>
        <paragraph indent="5">ii.   date-stamped photographs of each posted sign;</paragraph>
        <paragraph indent="5">iii.   the staff-approved sign layout plan drawing; and</paragraph>
        <paragraph indent="5">iv.   a photograph of one of the actual signs.</paragraph>
        <paragraph indent="2">C.   Acceptance of an Application.</paragraph>
        <paragraph indent="3">1.   Terms of acceptance. A final application must be complete and comply with all filing procedures to be accepted for review. IRC Intake staff must give the applicant written confirmation when acceptance occurs. The acceptance of an application means that it is complete for purposes of filing. Acceptance for filing does not constitute approval of the submitted plan; it allows the application to move forward to evaluation by the participating review agencies and others.</paragraph>
        <paragraph indent="3">2.   Regulatory clocks. After application acceptance, Code-required review clocks for the application are started and tentative Board hearing dates are assigned, as applicable. If the application is going to be discussed at a Development Review Committee (DRC) meeting, it is added to the next available meeting agenda.</paragraph>
        <paragraph indent="3">3.   Public record.9 All information contained in the accepted application, or added during application review is part of the public record. In addition, all supporting materials presented to the Board or Director or otherwise incorporated into the plan as part of the action taken on an application, become part of the public record. By submitting an application, the applicant agrees to complete the checklist of standard plan requirements included with each application form.</paragraph>
        <paragraph indent="2">D.   Rejection of an Application.</paragraph>
        <paragraph indent="3">1.   Inaccurate, misleading or false certifications. At any point in the review process, if staff finds that information certified by an applicant or a licensed professional10 is materially inaccurate, misleading, or false, staff must report the matter in writing to the Director. The Director must review the report, give the applicant or professional an opportunity to respond in writing, and consider any other relevant information. If the Director finds that the applicant or professional submitted materially inaccurate, false, or misleading information, the Director must reject the application and take appropriate action, which may include reporting the facts to the appropriate licensing board.</paragraph>
        <paragraph indent="3">2.   New application needed. Any plan rejected for these reasons must be returned to the applicant without any refund of the initial application fee. The application must be dropped from the queue of pending plans, and the applicant must submit a new application with associated fees to be considered further.</paragraph>
        <paragraph indent="2">E.   Filing of Concurrent Applications. Many types of land development projects require the filing, review, and Board approval of more than one type of plan. With the agreement of Planning staff, some of these plans may be filed concurrently. Depending upon the application types, concurrent filing may require extensions of the mandatory review timeframes required by law to facilitate concurrent action on the applications.</paragraph>
        <paragraph indent="0">----------</paragraph>
        <paragraph indent="0">6  Complete instructions for making an application, including application forms and checklists are available on the Planning Department’s website at http://montgomeryplanning.org/development/.</paragraph>
        <paragraph indent="0">7  Fees paid by check must be made out to the Maryland-National Capital Park and Planning Commission (MNCPPC) or to the Montgomery County Planning Department</paragraph>
        <paragraph indent="0">8 Standard Certificate of Compliance template available at:  https://montgomeryplanning.org/development/development-applications/ under the section for each plan type</paragraph>
      </subsection>
      <subsection heading="50.10.01.06 Evaluation of Applications">
        <paragraph indent="0">After a final application is accepted, it must be reviewed to determine if it meets the requirements of the County Code and other applicable laws and adopted guidelines. Individual reviewers must provide their recommendations regarding the approval of the application. These recommendations are part of the basis for the eventual Board or Director action on the plan.</paragraph>
        <paragraph indent="2">A.   Referral and Inter-Agency Consultation. When a final application is accepted, the planning staff must:</paragraph>
        <paragraph indent="3">•   provide a copy of the plan and necessary supporting information to designated offices of the Commission, other government or public agencies, and utility companies for comment or approval, as required by applicable law; and</paragraph>
        <paragraph indent="3">•   if applicable, schedule a discussion of the application before the Development Review Committee (DRC).</paragraph>
        <paragraph indent="3">1.   Lead Reviewer. For each plan application, the appropriate chief or supervisor must assign a Planning Department lead reviewer. The lead reviewer ensures that the following steps are coordinated and occur in a timely manner.</paragraph>
        <paragraph indent="4">(a)   Comments and recommendations from the reviewers are included in the application file and conveyed to the applicant team.</paragraph>
        <paragraph indent="4">(b)   Documentation is added to the application file noting assigned reviewers that do not participate or provide any substantive comments.</paragraph>
        <paragraph indent="4">(c)   Potential conflicting comments are identified.</paragraph>
        <paragraph indent="4">(d)   Plan revisions and information from the applicant in response to comments are provided to reviewers.</paragraph>
        <paragraph indent="4">(e)   The adopted protocol for resolving any agency conflicts is applied when necessary.</paragraph>
        <paragraph indent="3">2.   Responsibility of all reviewers. Comments from any reviewers must be made in writing before the end of each designated review period. A reviewer who is unable to meet this timeframe must complete their review by stating their need for additional time and providing an estimate of when their review will be provided.</paragraph>
        <paragraph indent="3">3.   Review Steps. Chapter 50 and Chapter 59 establish review periods for the different applications, but these may be extended depending upon the number of issues identified as part of the review and the need for plan revisions. The typical review for most applications consists of the following steps:</paragraph>
        <paragraph indent="4">(a)   Agency review before DRC meeting</paragraph>
        <paragraph indent="4">(b)   DRC meeting</paragraph>
        <paragraph indent="4">(c)   Applicant revisions after DRC meeting</paragraph>
        <paragraph indent="4">(d)   Agency review and approval of each final revised plan</paragraph>
        <paragraph indent="4">(e)   Planning Staff prepares a written report</paragraph>
        <paragraph indent="4">(f)   Staff report is posted 10 days before a Board hearing</paragraph>
        <paragraph indent="4">(g)   Board or Director Action</paragraph>
        <paragraph indent="3">4.   Extended review. Review and action on the application types covered in these regulations involves approval of certain required plan components by other agencies, such as, fire access and road grade plans; and concurrent review of related applications, such as, stormwater management concept and Special Protection Area (SPA) water quality plans, water and sewer category change requests, well and septic permits, or conditional use applications. Obtaining these related approvals may require extension of the review timeframes specified above. Delays may also result if an applicant does not submit adequate revisions under section 50.10.01.06.B.</paragraph>
        <paragraph indent="3">5.   Extension of a Board hearing date or Director decision date. Review deadlines may be extended for sketch, site, preliminary, and administrative subdivision plans under Chapter 59, Sections 7.3.3.C and 7.3.4.C, and Chapter 50, Sections 4.1.E and 6.3.b.4, respectively, by rescheduling the required decision date. A request must be made in writing to the Planning Department for such extension. Per Chapter 50 and Chapter 59, the Director may postpone the decision date by up to 30 days one time without Board approval. The Board may act to grant extensions of more than 30 days upon request from the Director or applicant. Any extension of a hearing date acted upon by the Board must be noticed on the hearing agenda. The new hearing date must be noticed on the appropriate agenda for the new date and identified on the notice list as part of the written hearing notice.</paragraph>
        <paragraph indent="3">6.   Extension of plat review. An applicant may consent to waive the 90-day review period required under Chapter 50, Section 8.2.B to gain time to obtain the necessary approvals from the reviewing agencies; otherwise, staff must base their required recommendation on the latest version of the plat. When staff’s final recommendation on a plat is denial, the applicant must be permitted to submit a final plat and staff must prepare a staff report and schedule a Board hearing on the next available agenda.</paragraph>
        <paragraph indent="3">7.   Application lapse deemed withdrawal. An application that has not yet been accepted that has been inactive for 180 days or an application that has been accepted that has been inactive for 365 days with no substantive response to review comments, or that has not been properly extended under Chapter 50 or 59, must be treated as withdrawn unless the applicant can demonstrate good cause to extend the application. The staff must send written notice to an applicant whose plan has been inactive indicating that the applicant has 30 calendar days to request an extension of the staff review. Any request for an extension must:</paragraph>
        <paragraph indent="4">(a)   be in writing;</paragraph>
        <paragraph indent="4">(b)   show good cause to grant an extension; and</paragraph>
        <paragraph indent="4">(c)   propose a timeframe to finalize the application.</paragraph>
        <paragraph indent="0">If the applicant does not request an extension by the due date, staff must send the applicant written notice that the application has been withdrawn by default. A new application and fee must be submitted to re-file any plan that is withdrawn by default.</paragraph>
        <paragraph indent="2">B.   Plan Revision.11 Each applicant is responsible for timely response to reviewer comments. The response may be by resubmitting plans and other documents with revisions, requesting a meeting with reviewers to discuss the comments, or indicating the desire to proceed to Board or Director action without any revision. Resubmitted materials should be submitted within 14 days after the comments are received, unless staff and the applicant agree on an extended deadline. Depending on the size and complexity of the 
									proposed project, a plan may be revised multiple times during the application review. Any final revised plan for an application that is scheduled for Board action must be submitted not less than 65 days before the scheduled Board meeting date.</paragraph>
        <paragraph indent="3">1.   Major revision. If the lead reviewer determines that an applicant’s revised plan or any other related revised document constitutes a major change12 from the original submission, the applicant must:</paragraph>
        <paragraph indent="4">(a)   re-send written notices to all parties on the notice list; and</paragraph>
        <paragraph indent="4">(b)   revise and resubmit an application form if the revision involves a change in:</paragraph>
        <paragraph indent="5">i.   acreage of the application site;</paragraph>
        <paragraph indent="5">ii.   type of use or units proposed;</paragraph>
        <paragraph indent="5">iii.   proposed density of any use;</paragraph>
        <paragraph indent="5">iv.   proposed method of development; or</paragraph>
        <paragraph indent="5">v.   ownership, applicant, or engineer.</paragraph>
        <paragraph indent="0">The submittal of a major application revision should be discussed with the assigned lead reviewer before they are submitted, and will require extension of any minimum review timeframe specified by law. The lead reviewer must decide how the revised plan will be reviewed after submittal, and may schedule another DRC meeting.</paragraph>
        <paragraph indent="2">C.   Public Participation. Any individual or organization with an interest in or concern about a proposed development or specific application may participate in the review and approval process by:</paragraph>
        <paragraph indent="3">•   attending the pre-submittal community meeting organized and held by the applicant before an application is submitted to the Planning Department.</paragraph>
        <paragraph indent="3">•   reviewing information about the submitted application in person at the Planning Department offices or online at the Planning Department website; and</paragraph>
        <paragraph indent="3">•   attending the DRC meeting scheduled for the application13, if applicable. The DRC meeting is not open to public participation; but members of the public may attend and listen to the discussion. Groups should notify IRC staff about their interest in attending the DRC meeting before the scheduled date so that space accommodations can be made. Details of the DRC meetings are on the Planning Department’s website.</paragraph>
        <paragraph indent="3">1.   Public comment. Members of the public who have questions or concerns may contact the Planning Department’s lead reviewer at any time during the review process. Any public comments must be submitted in writing by letter or email, and will become part of the public record of the application. The Planning staff must make reasonable efforts to address issues raised by the public during the plan review and address the issues that are not resolved in their recommendations on the plan. Public comments may also be presented directly to the Board if a public hearing is scheduled, pursuant to the Board’s Rules of Procedure.</paragraph>
        <paragraph indent="3">2.   Community meetings during review. Meetings with members of the public may be scheduled for a case upon request to the lead reviewer, or for particularly complex or controversial cases, staff may initiate a community meeting. These meetings may include other agency representatives and the applicant, as appropriate.</paragraph>
        <paragraph indent="2">D.   Staff Reports. The lead reviewer, after completing the application review and receiving all required agency recommendations or approvals, must prepare a report summarizing the proposed findings of fact and conclusions of law that the Board or Director must make and recommend approval, approval subject to conditions, or denial of the application.</paragraph>
        <paragraph indent="3">1.   Contents of the staff report. A staff report should include the following elements:</paragraph>
        <paragraph indent="4">(a)   a site description, including a vicinity map and aerial photograph of the site;</paragraph>
        <paragraph indent="4">(b)   an overview of the project, and a plan drawing;</paragraph>
        <paragraph indent="4">(c)   a summary of previous approvals, if any;</paragraph>
        <paragraph indent="4">(d)   a summary of the major issues and concerns related to the application and staff’s proposed resolution;</paragraph>
        <paragraph indent="4">(e)   staff’s recommended action, including for an approval, any recommended conditions; and</paragraph>
        <paragraph indent="4">(f)   staff’s findings of fact and conclusions regarding each applicable requirement of law related to the plan under the applicable sections of Chapter 50 and Chapter 59; and the basis for each finding and conclusion.</paragraph>
        <paragraph indent="3">2.   Staff Reports for Board action. The staff report for a plan or major plan amendment application under Chapter 50 or 59 must be published on the Board’s website as part of the meeting agenda at least 10 days before the date of the scheduled meeting.</paragraph>
        <paragraph indent="3">3.   Staff Reports for a minor plan amendment. A staff report for a minor plan amendment involving limited aspects of the original plan must include the applicable elements listed above and details on each item that is proposed to be changed.</paragraph>
        <paragraph indent="3">4.   Objections to a staff report scheduled for Board action. The applicant or other individuals may submit objections to any finding or conclusion in a staff report that is scheduled for Board action no later than noon on the business day prior to the scheduled Board meeting that includes the application or as set forth in the Board’s Rules of Procedure. Each objection must be made in writing to the Board Chair and must clearly identify and fully explain the basis for each disagreement. The applicant or any other party may also object to any finding or conclusion in the staff report during the scheduled public hearing on the application.</paragraph>
        <paragraph indent="0">----------</paragraph>
        <paragraph indent="0">9  The public record is not the same as the legal record that the Board bases its decision upon for purposes of a petition for judicial review.</paragraph>
        <paragraph indent="0">10  Licensed professionals include engineers, surveyors, landscape architects, attorneys, and any other profession licensed by the State of Maryland.</paragraph>
        <paragraph indent="0">11  A plan revision is distinct and separate from a plan amendment.  A plan revision incorporates changes that are made as part of the plan review process (i.e., before a plan is approved by a regulatory body).  An amended plan incorporates changes made to a certified or approved plan.</paragraph>
        <paragraph indent="0">12  A major revision includes any increase or significant decrease in density or number of units, an increase in the limits of disturbance, a significant change in lot layout, or an increase in building height or scale.  The lead reviewer determines if an applicant’s proposed plan revision is a major or minor revision.</paragraph>
        <paragraph indent="0">13   The DRC meeting is generally held every 2 weeks. A DRC Agenda containing items and the times they will be discussed, is posted on the MNCPPC website.</paragraph>
      </subsection>
      <subsection heading="50.10.01.07 Action on a Plan">
        <paragraph indent="0">An application is acted on by the Board or Director, depending on the application type. The Chapter 50 and Chapter 59 requirements for action on a plan are as follows:</paragraph>
        <paragraph indent="0">Application Type | Approval Authority</paragraph>
        <paragraph indent="2">A.   Board Action. Board action as part of their regularly scheduled meetings is required for sketch plans, preliminary plans, site plans, signature business headquarters plans, biohealth priority campus plans, record plats, waivers under Chapter 50, and APF determinations; and may be required for pre-preliminary applications administrative subdivision plans, and amendments to land development plan applications.</paragraph>
        <paragraph indent="3">1.   Board Meeting Agenda. The Board votes to act on an application during its meetings pursuant to its Rules of Procedure and applicable law.</paragraph>
        <paragraph indent="3">2.   Scheduling. Board action on an application must be scheduled per the requirements of Chapter 50 and Chapter 59. Depending on the plan type, the hearing dates must be scheduled either 90 or 120 days after a complete application is accepted by IRC Intake staff. The following table contains the scheduling requirements for the applicable plans.</paragraph>
        <paragraph indent="0">Application Type | Maximum Days Between Application Acceptance and Decision 1 | Reference to County Code
Pre-preliminary Submission | 90 (if applicant requests a Board hearing) | Ch. 50, Sec. 5.2
Sketch Plan and Amendments | 90 | Ch. 59, Sec. 7.3.3.C
Administrative Subdivision Plan and Amendments | 90 (if a Board hearing is necessary) | Ch. 50, Sec. 6.3
Preliminary Plan and Amendments | 120 | Ch. 50, Secs. 4.1.E and 4.2.F
Site Plan and Amendments | 120 | Ch. 59, Secs. 7.3.4.C and 7.3.4.J
Record Plat | 30 (this timeframe is measured from submittal of final plat) | Ch. 50, Sec. 8.2.F</paragraph>
        <paragraph indent="0">1 This column does not include hearing date extensions that may be granted under Chapter 50 and Chapter 59.</paragraph>
        <paragraph indent="4">(a)   Start of clock. For a pre-preliminary submission, sketch, preliminary, site plan, signature business headquarters plan, or biohealth priority campus plan application, the plan action date must be scheduled at the time of application acceptance, and noted in the Application Notice letter sent by the applicant. If the Director determines that an administrative subdivision plan requires a Board hearing and action, the hearing must be scheduled on the next available agenda date.</paragraph>
        <paragraph indent="4">(b)   Possible extension. Depending on the complexity of the plan and the degree of controversy, Board hearing dates may need to be extended, as discussed above, to have sufficient time to identify and understand the issues of the proposed project and sufficiently explore and incorporate features to address these issues.</paragraph>
        <paragraph indent="4">(c)   Minimum requirements for scheduling a Board hearing. Action on an application must not be scheduled until the lead reviewer determines that:</paragraph>
        <paragraph indent="5">i.   a final plan has been submitted by the applicant and date stamped by the lead reviewer to identify it as the official plan for Board consideration;</paragraph>
        <paragraph indent="5">ii.   all agency reviews are completed and written recommendations have been received; and</paragraph>
        <paragraph indent="5">iii.   all relevant issues and concerns have either been resolved or will be presented to the Board for resolution.</paragraph>
        <paragraph indent="4">(d)   Request to postpone a public hearing agenda item. The applicant or any other party may request postponement of a scheduled public hearing after the staff report has been published. The request must be made in writing to the Chair of the Planning Board no later than 12:00 p.m. on the day prior to the scheduled hearing. Each request for postponement must clearly identify and fully explain the basis for postponement. The staff must notify the applicant of each postponement request, and the applicant must be given an opportunity to respond. A decision to postpone a public hearing may only be made by the Planning Board Chair or the Planning Board.</paragraph>
        <paragraph indent="3">3.   Visual exhibits. Applicants must submit digital copies of any exhibits to the lead reviewer for use in the Board hearing, at least 3 business days before the scheduled date of the hearing:</paragraph>
        <paragraph indent="4">(a)   a rendered copy of the applicable land development plan (pre-preliminary, sketch, preliminary, administrative subdivision, and site);</paragraph>
        <paragraph indent="4">(b)   a rendered forest conservation plan and landscape plan, if applicable; and</paragraph>
        <paragraph indent="4">(c)   other exhibits, depending upon the issues of the plan, as requested by the lead reviewer.</paragraph>
        <paragraph indent="0">Anyone wishing to present visual exhibits to the Board must submit them to the Chair’s office by 12:00 p.m. on the day prior to the hearing. Any exhibits submitted will become part of the hearing record15.</paragraph>
        <paragraph indent="3">4.   Testimony. Any interested party may present testimony for consideration as part of the Board’s hearing by signing up in accordance with the Board’s Rules of Procedure.</paragraph>
        <paragraph indent="3">5.   Action on a record plat. Staff must schedule action for a record plat immediately after the final plat is accepted. Action is generally taken by the Board without discussion. A staff memorandum that includes a summary of staff’s review and recommendations and a copy of the proposed plat must be posted on the Commission’s website at least 10 days before the scheduled Board action date. Staff may add record plats to the Board’s agenda not later than 5 days before the scheduled action date in limited circumstances. Plats may be listed as part of the same agenda item and approved by the Board in one vote without discussion or individual motions.</paragraph>
        <paragraph indent="2">B.   Director Action. Action on administrative subdivision plans and certain minor amendments to preliminary plans and site plans may be taken by the Director instead of the Board. A public hearing is not required before the Director acts, but the Director may determine that a hearing is warranted in some cases. When such a determination is made, the Director must cede their authority to act on the application to the Board and schedule the public hearing on the next available Board meeting agenda.</paragraph>
        <paragraph indent="3">1.   Public participation for a Director action. The required written application notice for an application that will be acted upon by the Director must include the fact that a public hearing will not be scheduled. The notice must also state that comments concerning the application must be submitted to the Director, and specify the time within which the comments must be received to be considered as part of the Director’s decision. Any comment period must be a minimum of 15 days from the date the written application notice is sent.</paragraph>
        <paragraph indent="3">2.   Timing. The timing of a Director action is subject to the scheduling requirements of subsection 50.10.01.07.A.2, above.</paragraph>
        <paragraph indent="2">C.   Documentation of action. Written documentation of a Board or Director action is required.</paragraph>
        <paragraph indent="3">1.   Resolutions. Resolutions documenting a Board action required under Chapter 50 and Chapter 59 must be adopted per the Board’s Rules of Procedure. The resolution mailing date is the basis for calculation of the plan validity periods specified in Chapter 50 and Chapter 59.</paragraph>
        <paragraph indent="4">(a)   Resolution notice. A copy of the resolution must be sent by staff to the applicant, the applicant’s engineer and attorney, if applicable, and all parties of record who provided a mailing address for the hearing16, and included in any certified plan drawing set.</paragraph>
        <paragraph indent="3">2.   Written Director action. The Director’s action on an application may be by letter or memorandum, or as part of the staff report. When the Director accepts all findings in the staff report and staff’s recommendation, the Director’s counter-signature and action date on the staff report is sufficient documentation of the action. The Director’s action date is the start of the plan validity period of the approved plan.</paragraph>
        <paragraph indent="4">(a)   Notice of Director action. A copy of the Director’s approval must be sent to the applicant, placed in the public record of the application, and included in any certified plan drawing set.</paragraph>
        <paragraph indent="0">----------</paragraph>
        <paragraph indent="0">15  With advanced notice before the day of the scheduled hearing, IRC Division staff will scan paper copies of visual exhibits and create digital copies for use in the meeting.</paragraph>
        <paragraph indent="0">16  The parties of record for a hearing include the applicant, the applicant’s engineer, the applicant’s attorney, any individual or group that testifies at the hearing and provides a mailing address, and any individual or group that submits written testimony and provides a mailing address.</paragraph>
      </subsection>
      <subsection heading="50.10.01.08 Plan Certification">
        <paragraph indent="0">Certification of plan drawings is required for preliminary plans, administrative subdivision plans, site plans, signature business headquarters plans, and biohealth priority campus plans (and any amendment thereto) that have been approved. The certified plan set must include all plans associated with these approvals, including, but not limited to forest conservation or tree save plans, landscape and lighting plans, architectural plans, and impervious surface plans.</paragraph>
        <paragraph indent="2">A.   Steps for certification. After the Board or Director, as appropriate, approves an application that requires a certified plan to confirm the approval, the following steps must be taken:</paragraph>
        <paragraph indent="3">1.   The applicant must make any modifications to the application drawings that were required by the conditions of the approval, add a copy of the signed Board Resolution or Director approval, and submit the plan drawing set to the Planning Department.</paragraph>
        <paragraph indent="3">2.   Staff should review the submitted application drawing set within 15 days and either accept the plans or provide review comments to the applicant outlining necessary corrections.</paragraph>
        <paragraph indent="3">3.   Accepted drawings must be stamped approved, signed, and dated by the Director or designee.</paragraph>
        <paragraph indent="3">4.   A copy of the fully executed certified plan will be added to the electronic files for the application on the Planning Department’s website.</paragraph>
        <paragraph indent="2">B.   Separate exhibit required for ownership units. Ownership units may not be included on a certified preliminary plan, or site plan, signature business headquarters plan, or biohealth priority campus plan drawing set. When an applicant intends to create ownership units within a lot included on such plans, a separate ownership unit drawing must be submitted for certification along with the preliminary plan, site plan, signature business headquarters plan, or biohealth priority campus plan.</paragraph>
      </subsection>
      <subsection heading="50.10.01.09 Post-Approval Requirements">
        <paragraph indent="2">A.   Inspections. The applicant must schedule all Planning Department inspections that are required by conditions of any approval with a Planning Department inspector per the approved inspection schedule. The inspection must confirm that land development activities occurring on a project site will conform to all requirements of the approved plans. Required pre-construction inspections must be coordinated with the DPS inspector and an applicant’s representative to ensure that requirements for sediment and erosion control and stormwater management do not conflict with approved requirements for forest conservation and protection of environmentally-sensitive areas.</paragraph>
        <paragraph indent="2">B.   Surety and bonds. The applicant must enter into a Surety and Maintenance Agreement with the Board as required by any approved application, submit a cost estimate of the materials and facilities that are required to establish the surety amount, and provide a performance bond or other form of surety.</paragraph>
        <paragraph indent="3">1.   Timing and elements included.</paragraph>
        <paragraph indent="4">(a)   Subdivision and site plan surety. Surety and bonding for the required elements of a preliminary plan, administrative subdivision plan, site plan, signature business headquarters plan, or biohealth priority campus plan must be provided per the timing specified in the conditions of approval; generally, before the issuance of building permits, use and occupancy permits, or sediment control permits. The elements include but are not limited to: landscape plant material, on-site lighting, indoor and outdoor recreational facilities, site furniture, mailbox pad sites, trash enclosures, retaining walls, fences, railings, private utilities, private roads and associated improvements, including sidewalks, bikeways, storm drainage facilities, street trees and street lights.</paragraph>
        <paragraph indent="4">(b)   Forest conservation and tree save plan surety. Surety and bonding for the required elements of a forest conservation plan or tree save plan must be provided before the Planning Department inspector authorizes any clearing or grading of the development site. The elements include but are not limited to plant materials, tree protection measures, mitigation plantings, invasive species control measures, planting site preparation, fencing, boundary signage, and maintenance costs.</paragraph>
        <paragraph indent="3">2.   Review and approval. The required surety and bonds must be submitted to the IRC Division for distribution to the appropriate review staff.</paragraph>
        <paragraph indent="2">C.   Other.</paragraph>
        <paragraph indent="3">1.   Before submittal of a Record Plat. An application for a record plat will not be accepted without verification that the following requirements have been met.</paragraph>
        <paragraph indent="4">(a)   Certified plans. The applicant must submit a copy of the certified preliminary plan and associated forest conservation plan, and the Board’s resolution on the preliminary plan, with the record plat application. The applicant must also submit a copy of the certified site plan, signature business headquarters plan, or biohealth priority campus plan and associated forest conservation plan, and site plan, signature business headquarters plan, or biohealth priority campus plan resolution for any property that is subject to site plan, signature business headquarters plan, or biohealth priority campus plan approval.</paragraph>
        <paragraph indent="4">(b)   Road improvements. The applicant must comply with Chapter 50, Sections 4.3.E.2.b, 4.3.E.3.b, 4.3.E.4.e, and 4.3.E.5.d by:</paragraph>
        <paragraph indent="5">i.   Public roads. Applying to DPS for right-of-way permit(s) or satisfying any alternative requirements of DPS to ensure proper design of public roads.</paragraph>
        <paragraph indent="5">ii.   Private roads. Obtaining the certification of an engineer that each private road has been designed to meet the requirements of Chapter 50, Section 4.3.4.</paragraph>
        <paragraph indent="4">(c)   Conservation easements. Documentation needed to create all conservation easements must be prepared in at least draft form.</paragraph>
        <paragraph indent="4">(d)   treet naming and address plan. The applicant must request an Address Plan or Address Verification from IRC Division staff before the initial submission of the Record Plat application. Staff will work with the applicant to assign addresses for newly created lots and verify addresses for existing properties that are to remain in their original configuration. If the approved subdivision includes new streets, the applicant must submit a list of proposed street names for staff review and approval to ensure that: new streets are not assigned names that are already in use in the County; the assigned names do not cause confusion in locating addresses for properties or structures; and they meet other Board guidelines for street names17.</paragraph>
        <paragraph indent="4">(e)   Other necessary covenants or agreements. All covenants, agreements and easements required by Board conditions of approval must be prepared in at least draft form.</paragraph>
        <paragraph indent="4">(e)   Required agency approvals. Regulatory approvals that are conditioned as part of the Board’s approval of an application, such as, a DPS well and septic permit or stormwater management concept, must be obtained before a plat is submitted.</paragraph>
        <paragraph indent="3">2.   Before issuance of Building Permit. The applicant must verify for IRC Division staff that all conditions of a Board approval that were required to be met before the issuance of a building permit have been satisfied.</paragraph>
        <paragraph indent="0">----------</paragraph>
        <paragraph indent="0">17   Rules and guidelines for assigning addresses and street names in the County are provided in the latest version of the Addressing and Street Naming Guidelines and Procedures Manual for Montgomery County, Maryland (IRC Division, Montgomery County Planning Department, M-NCPPC).</paragraph>
      </subsection>
      <subsection heading="50.10.01.10 Alternative Procedures and Additional Requirements">
        <paragraph indent="0">Certain types of applications have additional requirements not covered by Chapter 50 or the sections above, or are subject to alternative procedures for submission and review. These alternative requirements and procedures are described below.</paragraph>
        <paragraph indent="2">A.   Administrative Subdivision Plan.</paragraph>
        <paragraph indent="3">1.   Board action required. The Director must cede their authority to act on an administrative subdivision plan application and schedule action by the Board if:</paragraph>
        <paragraph indent="4">(a)   an objection to the application is received during the review, and the Director determines the objection is relevant;</paragraph>
        <paragraph indent="4">(b)   the project site is within a Special Protection Area and required to submit a Water Quality Plan;</paragraph>
        <paragraph indent="4">(c)   the application includes a request for a waiver under Section 50.9 of Chapter 50;</paragraph>
        <paragraph indent="4">(d)   the application includes a request for abandonment of land dedicated for public use under Section 50.8.4.A.2 of Chapter 50;</paragraph>
        <paragraph indent="4">(e)   the application includes a change to a recorded conservation easement on the project site;</paragraph>
        <paragraph indent="4">(f)   the application includes flag lots and/or lots without frontage on a public road; and</paragraph>
        <paragraph indent="4">(g)   the application includes a reservation of land for public use.</paragraph>
        <paragraph indent="3">2.   Director participation in application review. The Director may not participate in the DRC meeting or any other meetings that occur on an application before acting on the plan.</paragraph>
        <paragraph indent="3">3.   Effect of an appeal to an Administrative Subdivision Plan. An appeal of an administrative subdivision plan filed under Section 6.3.C of Chapter 50 stays the Director’s action on the plan until the Board acts on the appeal after a public hearing.</paragraph>
        <paragraph indent="2">B.   Validity Period Extension Requests. The date when the Planning Board’s resolution for a preliminary plan is mailed establishes both the plan validity period and the validity period for the associated adequate public facilities review. The Board may extend these validity periods under Chapter 50, Sections 4.2.H and 4.3.J.7.</paragraph>
        <paragraph indent="3">1.   Application. An application filed for extension of a validity period must include a letter from the applicant, or the applicant’s representative, which identifies the facts, conditions, and provisions of law relied upon by the applicant to justify an extension.</paragraph>
        <paragraph indent="3">2.   Review and Action. Planning Department staff may review an application filed for extension of a validity period without referring it to other government or public agencies, and utility companies. A DRC meeting on the application is not required. Staff must prepare a staff report for the application as noted above, and schedule action per the timing required for the plan under which the validity period was established.</paragraph>
        <paragraph indent="2">C.   Subdivision Regulations Waiver Requests. Chapter 50, Division 50.9 specifies waivers that the Planning Board may grant. Waivers are generally reviewed as part of an application for a preliminary plan of subdivision. However, a waiver of the requirement to submit a preliminary plan of subdivision may be requested. In that case, a separate subdivision waiver application is required.</paragraph>
        <paragraph indent="3">1.   Application. Each application for waiver must include a letter from the applicant or the applicant’s representative which specifies the facts, conditions, and provisions of law on which the applicant relies to justify a waiver.</paragraph>
        <paragraph indent="3">2.   Review and Action. An application for a subdivision regulations waiver must be reviewed per the requirements of Chapter 50, Section 9.5.A and acted upon by the Board.</paragraph>
        <paragraph indent="2">D.   Adequate Public Facilities (APF) Review at Building Permit. Per Chapter 8, Section 8-31, a building permit must not be issued for lots that do not have a valid APF approval from the Board. If such approval is not granted by the conditions of an approved preliminary plan, administrative subdivision plan, site plan, signature business headquarters plan, or biohealth priority campus plan, the Department of Permitting Services refers the building permit application to the Board for a determination that public facilities will be adequate to serve the proposed development. In these cases, an application for APF review should be filed under these procedures.</paragraph>
        <paragraph indent="3">1.   Application. Each application for a building permit APFO APF review must include an application form, and applicable fee, and sufficient information to demonstrate the expected impact on and use of public facilities by the development.</paragraph>
        <paragraph indent="3">2.   Referral of the application. Immediately after accepting the application, the Director must send a copy to DOT, MCPS, DPS Fire Department Access and Water Supply, and any other applicable reviewing agencies for their comments concerning the plan. Per Chapter 8, each recipient must respond to the Board within 30 days after receiving the application from the Director.</paragraph>
        <paragraph indent="3">3.   Review. After receiving the recommendations of the participating reviewers, staff must prepare a staff report for the application as noted above.</paragraph>
        <paragraph indent="3">4.   Action. Action on an application for APF review at building permit may be taken by either the Director or Board, depending upon the circumstances of the request.</paragraph>
        <paragraph indent="4">(a)   If a complete and adequate traffic statement is submitted and the proposed development generates less than 50 total peak hour person trips, the APF determination may be approved administratively by the Planning Department Director or designee.</paragraph>
        <paragraph indent="4">(b)   If a complete and adequate traffic study is submitted and the proposed development generates 50 or more total peak hour person trips, the APF determination must be approved by the Planning Board following a public hearing.</paragraph>
        <paragraph indent="2">E.   Request for an Exemption to Platting. When DPS requires verification from the Planning Department that a property is exempt from the requirement to be recorded by a plat per Chapter 50, Section 3.3, a written request must be submitted to the IRC Division. The request must include copies of all information needed to support the exemption as outlined in Section 3.3.</paragraph>
        <paragraph indent="2">F.   Concept Plan. A concept plan is an optional, voluntary application that may be filed before a sketch, preliminary, site plan, signature business headquarters plan, or biohealth priority campus plan application to obtain advice concerning a proposed development project from the Development Review Committee (DRC).</paragraph>
        <paragraph indent="3">1.   Application. Each application for a concept plan must include an application form, a narrative statement from the applicant, or the applicant’s representative, that identifies the aspects of the proposed development on which advice is being sought, and sufficient information on accompanying plan drawings to show existing conditions and the extent of proposed development.</paragraph>
        <paragraph indent="3">2.   Referral of the application. Immediately after accepting the application, the Director must send a copy to the DRC reviewing agencies for their comments concerning the plan.</paragraph>
        <paragraph indent="3">3.   Review. The application must be scheduled for discussion at the next available DRC meeting after acceptance. Planning Department staff must prepare a summary of the DRC comments and provide it to the applicant within two weeks from the DRC meeting.</paragraph>
        <paragraph indent="0">(Legislative History:  Council Res. No. 20-112; Supersedes: Council Res. No. 18-879)</paragraph>
      </subsection>
    </regulation>
  </section>
  <section heading="COMCOR 50.35.01 Schedule of Fees for Transportation-related Reviews of Subdivision Plans and Documents">
    <regulation heading="COMCOR 50.35.01 Schedule of Fees for Transportation-related Reviews of Subdivision Plans and Documents">
      <subsection heading="50.35.01.01 The following fees are proposed:">
        <paragraph indent="1">A.    Preliminary Plans</paragraph>
        <paragraph indent="2">(1)   Residential component (includes all types of dwellings)</paragraph>
        <paragraph indent="3">(a)   1 - 100 dwelling units      =   $1000/application + ($50/Dwelling Unit)</paragraph>
        <paragraph indent="3">(b)   101 - 750 dwelling units   =   (a) + ($25/dwelling unit, for units 101 - 750)</paragraph>
        <paragraph indent="3">(c)   more than 750 dwelling units   =   (a) + (b) + ($5/dwelling unit, for each unit beyond 750)</paragraph>
        <paragraph indent="2">(2)   Commercial component (building gross floor area for all commercial uses)</paragraph>
        <paragraph indent="3">(a)   1 - 200,000 square feet      =   $1000/application + ($0.10/SF - for first 200,000 square feet)</paragraph>
        <paragraph indent="3">(b)   200,001 - 500,000 square feet      =   (a) + ($0.05/SF - for 200,001 to 500,000 SF)</paragraph>
        <paragraph indent="3">(c)   more than 500,000 square feet   =   (a) + (b) + ($0.025/SF, for each SF beyond 500,000 SF)</paragraph>
        <paragraph indent="2">(3)   Institutional/Religious*          =   $1000/application</paragraph>
        <paragraph indent="0">(*NOTE: for the purposes of this Regulation, “Institutional/Religious” is intended to address facilities for private, tax-exempt organizations whose primary function is to provide either health, social, recreational, religious, or benevolent services, or research or educational activities in areas of benefit to the public such as health, medicine, or conservation of natural resources.  Applicable facilities include charitable or philanthropic institutions, places of worship, private educational institutions, libraries, museums, community buildings, private clubs or service organizations, hospice care facilities, hospitals, nursing homes, domiciliary care homes, group homes, or housing and related facilities for senior adults or persons with disabilities.</paragraph>
        <paragraph indent="0">If a preliminary plan is submitted which includes an Institutional/Religious facility in addition to other for-profit residential and/or commercial space, the fee for that plan shall be $1000 (for the Institutional/Religious facility) plus the applicable plan review fee for the remaining residential and/or commercial space.)</paragraph>
        <paragraph indent="3">(4)   Storm drain capacity and post-   =   $500/application</paragraph>
        <paragraph indent="4">development impact studies for</paragraph>
        <paragraph indent="4">projects located within the Special</paragraph>
        <paragraph indent="4">Taxing Districts which pay a Storm</paragraph>
        <paragraph indent="4">Drain Tax to Montgomery County</paragraph>
        <paragraph indent="4">(for County maintenance of their</paragraph>
        <paragraph indent="4">storm drain systems)</paragraph>
        <paragraph indent="2">B.    Local Area Traffic Impact Studies      =   $2000/study*</paragraph>
        <paragraph indent="1">*NOTE: This fee is in addition to the base fees for the review of preliminary plan packages.</paragraph>
      </subsection>
      <subsection heading="50.35.01.02 General">
        <paragraph indent="2">1.   These fees apply to all preliminary plans for property within the Regional District, as defined in Article 28 of the Maryland Annotated Code, located in Montgomery County with the exception of those municipalities which have their own planning authority and those Special Taxing Districts which maintain their own roads and storm drainage systems.</paragraph>
        <paragraph indent="0">For those Special Taxing Districts in which the storm drain system is maintained by Montgomery County (and the Special Taxing District pays a Storm Drain Tax to Montgomery County), the DPWT review will be limited to the storm drain capacity and post-development impact analyses (see fee no. A.4 above)</paragraph>
        <paragraph indent="2">2.   Applicants must pay the plan review fee or the minimum fee as specified at or before the time the package is submitted for review or the submittal package will be deemed incomplete and returned to the applicant.</paragraph>
        <paragraph indent="2">3.   Fees for revisions to previously reviewed applications are 35% of the fees in parts (A) and (B).  Minor revisions to previously reviewed applications do not require an additional plan-review fee.  The decision of when to require an additional plan-review fee shall be made by the Department of Public Works and Transportation.</paragraph>
        <paragraph indent="2">4.   Application fees are based on the rates in effect on the date the application was filed with the Department of Public Works and Transportation.  Revision fees are based on the rates in effect at the time the revision was requested.</paragraph>
        <paragraph indent="2">5.   If any part of this Regulation is found to be invalid by a Court of competent jurisdiction and a final non-applicable judgment to that effect is entered by the Court, then those parts of the Regulation not deemed invalid will remain in full force and effect.</paragraph>
      </subsection>
      <subsection heading="50.35.01.03 Indexing of Fees to Labor Cost Increases">
        <paragraph indent="0">The Director of Public Works and Transportation must adjust each fee set in or under this regulation on July 1 of each year.  The Department of Public Works and Transportation may raise this fee annually by regulation by a percentage that does not exceed the rate of the increase (if any) in the department’s approved personnel costs for the then-current fiscal year compared to the approved personnel costs for the preceding fiscal year.  For fees of $100 or more, the Director must calculate the revised fee to the nearest five dollars.  For fees under $100, the Director must calculate the revised fee to the nearest dollar.</paragraph>
      </subsection>
    </regulation>
  </section>
  <section heading="COMCOR 50.35.02 Implementing the Subdivision Staging Policy’s White Flint Alternative Review Procedure">
    <regulation heading="COMCOR 50.35.02 Implementing the Subdivision Staging Policy’s White Flint Alternative Review Procedure">
      <subsection heading="50.35.02.01 Transportation Approval Mechanism">
        <paragraph indent="2">A.   Staging Allocation Request Process</paragraph>
        <paragraph indent="3">1.   General</paragraph>
        <paragraph indent="4">Within the White Flint Sector Plan boundary, the Planning Board must allocate staging capacity based on the order in which requests for capacity are received and in a manner that is consistent with these regulations.</paragraph>
        <paragraph indent="3">2.   Staging Allocation Request</paragraph>
        <paragraph indent="4">A Staging Allocation Request is a request for staging capacity under the Approved and Adopted 2010 White Flint Sector Plan. The contents of a Staging Allocation Request and the effect of submitting a completed Staging Allocation Request will be governed by these regulations.</paragraph>
        <paragraph indent="3">3.   Contents of Staging Allocation Request</paragraph>
        <paragraph indent="4">A Staging Allocation Request must include a statement by the applicant that the applicant has received any necessary sketch plan approvals, preliminary plan approvals, or site plan approvals. The request must indicate the number of buildings proposed as well as the amount of residential and non-residential staging capacity requested, the gross amount of new development, and the net amount of new development if there will be demolition of existing structures. An applicant that demolished space after the adoption of the White Flint Sector Plan must provide, as part of any Staging Allocation Request, evidence of the date of demolition and the number of square feet or residential units demolished. Each Staging Allocation Request must include any Staging Allocation Request Form required by the Planning Board.</paragraph>
        <paragraph indent="3">4.   Planning Board Review of Staging Allocation Request</paragraph>
        <paragraph indent="4">The Planning Board must approve the Staging Allocation Request if sufficient staging capacity remains available, under the White Flint Sector Plan, to accommodate the applicant’s entire request. If sufficient capacity is not available to accommodate the applicant’s entire request, the Planning Department staff must place the Staging Allocation Request in a queue, and the Planning Board must schedule the Request on the Planning Board’s agenda when capacity becomes available.</paragraph>
        <paragraph indent="3">5.   Effect of Staging Allocation Request</paragraph>
        <paragraph indent="4">In order to be deemed complete by Planning Department staff, a Staging Allocation Request must contain any information required under the Subdivision Staging Policy (Section TA6, Alternative Review Procedure for the White Flint Policy Area), and must comply with these regulations. Once a Staging Allocation Request has been deemed complete by Planning Department staff, the staff must place the capacity requested in reserve. The Planning Board must not allocate the reserved capacity to any other applicant unless the Staging Allocation Request is rejected due to insufficient capacity or withdrawn by the applicant or the Staging Allocation Approval becomes void or expires under these regulations.</paragraph>
        <paragraph indent="3">6.   Joint Staging Allocation Requests</paragraph>
        <paragraph indent="4">Multiple property owners may submit a Joint Staging Allocation Request if those property owners also submitted a joint sketch plan application, which was approved by the Planning Board, and which included conditions establishing a phasing schedule for demolition and construction on all subject properties.</paragraph>
        <paragraph indent="2">B.   Staging Allocation Approval Process</paragraph>
        <paragraph indent="3">1.   Contents of Staging Allocation Approval</paragraph>
        <paragraph indent="4">In a Staging Allocation Approval, the Planning Board must incorporate all information included in the Staging Allocation Request. The Staging Allocation Approval must also specify, as established in these regulations, the deadline for completion and acceptance of a building permit application under B.2, and the Staging Allocation Approval expiration date under B.5.</paragraph>
        <paragraph indent="3">2.   Requirement to obtain timely acceptance of building permit applications</paragraph>
        <paragraph indent="4">a.   Applicants with a Staging Allocation Approval for a single building</paragraph>
        <paragraph indent="5">An applicant who has received a Staging Allocation Approval for a single building must have building permit applications accepted by the Department of Permitting Services for at least core and shell by close of business on the 90th day after the date of the Planning Board’s resolution granting the Staging Allocation Approval.</paragraph>
        <paragraph indent="4">b.   Applicants with a Staging Allocation Approval for multiple buildings</paragraph>
        <paragraph indent="5">An applicant who has received a Staging Allocation Approval for multiple buildings must have all building permit applications accepted by the Department of Permitting Services for at least core and shell by close of business on the 180th day after the date of the Planning Board’s resolution granting the Staging Allocation Approval.</paragraph>
        <paragraph indent="3">3.   Reporting Requirement</paragraph>
        <paragraph indent="4">The applicant must present evidence of acceptance to the Planning Board within 15 business days after the Department of Permitting Services accepts a building permit application.</paragraph>
        <paragraph indent="3">4.   Effect of failure to obtain timely acceptance</paragraph>
        <paragraph indent="4">An applicant who fails to obtain timely acceptance of a building permit application loses any staging capacity allocated for which no building permit application has been accepted. The portion of the Staging Allocation Approval that is not perfected by obtaining timely acceptance by the Department of Permitting Services is thereafter void.</paragraph>
        <paragraph indent="3">5.   Validity</paragraph>
        <paragraph indent="4">a.   Applicants with a Staging Allocation Approval for a single building</paragraph>
        <paragraph indent="5">Any Staging Allocation Approval for a single building that has not become void due to failure to obtain timely acceptance of a building permit application remains valid for 2 years from the date of the Planning Board’s Resolution granting the Staging Allocation Approval. All core and shell building permits necessary to construct the capacity allocated by the Planning Board must be issued within that 2-year validity period. Any applicant whose building permits are not issued within the 2-year validity period loses any allocated but unused capacity.</paragraph>
        <paragraph indent="4">b.   Applicants with a Staging Allocation Approval for multiple buildings</paragraph>
        <paragraph indent="5">A Staging Allocation Approval for multiple buildings that has not become void due to failure to obtain timely acceptance of a building permit application remains valid for 3 years from the date of the Planning Board’s Resolution granting the Staging Allocation Approval. All core and shell building permits necessary to construct the capacity allocated by the Planning Board must be issued within that 3-year validity period. Any applicant whose building permits are not issued within the 3-year validity period loses any allocated but unused capacity.</paragraph>
        <paragraph indent="3">6.   Staff approval of Staging Allocation Requests for zero net staging capacity</paragraph>
        <paragraph indent="4">a.   No net draw on capacity</paragraph>
        <paragraph indent="5">A Staging Allocation Request must always be approved, regardless of available staging capacity, if the Request is for an amount equal to or less than any development being removed. In that case, Planning Department staff may grant the Staging Allocation Approval.</paragraph>
        <paragraph indent="4">b.   Development approvals that pre-date the approval of the Sector Plan</paragraph>
        <paragraph indent="5">A Staging Allocation Request must always be approved, regardless of available staging capacity, for any project that has a valid Adequate Public Facilities approval or development plan approval that predates the approval of the White Flint Sector Plan. In that case, Planning Department staff may grant the Staging Allocation Approval.</paragraph>
        <paragraph indent="4">c.   Procedures for staff approval of Staging Allocation Requests</paragraph>
        <paragraph indent="5">Any Staging Allocation Request that can be approved by Planning Department staff under subsection (a) or subsection (b) must be approved by the Planning Director or designee. Each staff approval must be included in the Biennial Monitoring Report.</paragraph>
        <paragraph indent="4">d.   Projects approved by staff under this section not subject to certain provisions of these regulations</paragraph>
        <paragraph indent="5">A Staging Allocation Approval that can be issued by staff under section 6 is not subject to the requirements of the following sections: B.1 (Contents of Staging Allocation Approval); B.2 (Requirement to obtain timely acceptance of building permit applications); B.3 (Reporting requirement); B.4 (Effect of failure to obtain timely acceptance); and B.5 (Validity).</paragraph>
        <paragraph indent="2">C.   Staging queue management</paragraph>
        <paragraph indent="3">The Planning Department must maintain a White Flint Sector Plan staging queue.</paragraph>
        <paragraph indent="4">Any Staging Allocation Request for which there is not sufficient capacity must be placed in the queue.</paragraph>
        <paragraph indent="4">For each Staging Allocation Request placed in the queue, the Planning Department must track the submission date and the date on which the Staging Allocation Request is deemed complete by Planning Department staff.</paragraph>
        <paragraph indent="4">Queue position is based on the order in which projects are placed in the queue. The Planning Department must place the oldest eligible application(s) in the queue on the Planning Board’s consent agenda calendar when staging capacity exists for the full development proposed in the application, both residential and commercial.</paragraph>
        <paragraph indent="4">Adjustments to queue position may be granted by the Planning Board upon receipt of a proposal jointly submitted by all applicants whose positions in the queue would be affected. The Planning Board is not a party to any negotiations between applicants who agree to change queue positions.</paragraph>
        <paragraph indent="2">D.   Exemptions from Staging Allocation Request Process</paragraph>
        <paragraph indent="3">1.   Development approvals predating approval of the Sector Plan</paragraph>
        <paragraph indent="4">The White Flint Sector Plan states:</paragraph>
        <paragraph indent="4">“Any development approvals that predate the approval of this Sector Plan are considered to be in conformance with this Plan. For such approvals, only the difference between the amount of the prior approval and any requested increase would be subject to the phasing caps.”</paragraph>
        <paragraph indent="4">Projects with development approvals that predate the approval of this Sector Plan are not subject to either the phasing caps specifically or to the staging capacity allocation process generally. Staff approval of a Staging Allocation Request remains an option for such property owners, however, such approvals are not subject to the other requirements or limitations set forth in these Regulations.</paragraph>
        <paragraph indent="4">On December 9, 2010 the Planning Board confirmed its intent that four specific projects should not be subject to the phasing caps up to the amount of development approval that predated the adoption of the Sector Plan.</paragraph>
        <paragraph indent="4">1)   North Bethesda Center (LCOR)</paragraph>
        <paragraph indent="5">1,350 dwelling units</paragraph>
        <paragraph indent="5">1.14 million square feet of office</paragraph>
        <paragraph indent="5">202,037 square feet of commercial</paragraph>
        <paragraph indent="5">Zone: TSM</paragraph>
        <paragraph indent="4">2)   North Bethesda Market (JBG)</paragraph>
        <paragraph indent="5">440 dwelling units</paragraph>
        <paragraph indent="5">223,000 square feet of non-residential</paragraph>
        <paragraph indent="5">Zone: TSM</paragraph>
        <paragraph indent="4">3)   White Flint View (Quantum/Noland Plumbing)</paragraph>
        <paragraph indent="5">183 dwelling units</paragraph>
        <paragraph indent="5">29,500 square feet of non-residential</paragraph>
        <paragraph indent="5">Zone: C-2</paragraph>
        <paragraph indent="4">4)   Metro Pike (BF Saul)</paragraph>
        <paragraph indent="5">247 dwelling units</paragraph>
        <paragraph indent="5">201,822 square feet of non-residential</paragraph>
        <paragraph indent="5">Zone: TSM</paragraph>
        <paragraph indent="3">2.   Affordable housing units</paragraph>
        <paragraph indent="4">Affordable housing units that are in addition to those required by Chapter 25A, and which are provided under the CR Zone incentives, must not be counted against the total available capacity as established under the White Flint Sector Plan.</paragraph>
        <paragraph indent="3">3.   Public facilities and staging</paragraph>
        <paragraph indent="4">A public facility is one that is owned or operated by a governmental body or an instrumentality of a governmental body and which serves a public purpose.</paragraph>
        <paragraph indent="4">a.   Public facilities subject to mandatory referral are exempt from staging</paragraph>
        <paragraph indent="5">A public facility that is subject to the mandatory referral provisions of Article 28, section 7-112 is not subject to these regulations.</paragraph>
        <paragraph indent="4">b.   Public facilities provided as a proffer are exempt from staging</paragraph>
        <paragraph indent="5">A public facility that is to be owned or operated by a public entity and that is provided in a private project as a proffer (e.g. in exchange for a density award) is not subject to these regulations, if the public facility will be conveyed to the public entity in fee simple, by perpetual exclusive easement, or by a long-term lease in excess of fifty years. The terms and method of any conveyance must be accepted by the public entity that will own or lease the facility before the Planning Board approves the Staging Allocation Request for the private elements of the project. The private elements of a project that includes a public facility are subject to the staging allocation requirements.</paragraph>
      </subsection>
      <subsection heading="50.35.02.02 Relationship of Transportation Approval Mechanism to other transportation related processes and requirements">
        <paragraph indent="2">A.   General</paragraph>
        <paragraph indent="3">The Subdivision Staging Policy exempts properties in the White Flint Special Taxing District from the requirements of Local Area Transportation Review and Policy Area Mobility Review. Consequently, individual applicants need not prepare transportation studies to satisfy the requirements of the LATR and PAMR Guidelines.</paragraph>
        <paragraph indent="2">B.   Comprehensive Local Area Transportation Review</paragraph>
        <paragraph indent="3">1.   General</paragraph>
        <paragraph indent="4">The Planning Department must perform a biennial Comprehensive Local Area Transportation Review (CLATR) to review and assess transportation capacity in White Flint. CLATR must analyze traffic conditions throughout the policy area and at individual intersections. The Planning Board must use CLATR to identify specific capital projects and services necessary to promote adequate transportation service.</paragraph>
        <paragraph indent="3">2.   Effect of CLATR</paragraph>
        <paragraph indent="4">The Planning Board must provide guidance on trip generation and distribution assumptions as part of the CLATR. Applicants outside the White Flint Special Taxing District who must submit transportation studies in order to satisfy the requirements of the LATR and PAMR Guidelines must use the trip generation and distribution assumptions established as part of CLATR when accounting for trips generated within the White Flint Special Taxing District.</paragraph>
        <paragraph indent="2">C.   Transportation information required from applicants inside the Special Taxing District</paragraph>
        <paragraph indent="3">Individual applicants exempted from LATR and PAMR under the Subdivision Staging Policy need not submit transportation studies to satisfy requirements of the LATR and PAMR Guidelines.</paragraph>
        <paragraph indent="3">Applicants must still provide information to State or County agencies as needed to fulfill other legal requirements. This information may include, but is not limited to:</paragraph>
        <paragraph indent="4">Parking space requirements; and</paragraph>
        <paragraph indent="4">Sight distance evaluations.</paragraph>
        <paragraph indent="2">D.   Development outside the special taxing district</paragraph>
        <paragraph indent="3">1.   Generally</paragraph>
        <paragraph indent="4">Applicants whose property is located inside and outside of the White Flint Special Taxing District are responsible only for improvements on their side of the Special Taxing District boundary. Applicants whose property is located outside of the White Flint Special Taxing District must be tested for APF compliance, if applicable, and required to provide intersection improvements as appropriate outside of the Special Taxing District boundary.</paragraph>
        <paragraph indent="3">2.   Trips generated in the White Flint Special Taxing District</paragraph>
        <paragraph indent="4">Applicants whose property is located outside the Special Taxing District who must submit transportation studies to satisfy the requirements of the LATR and PAMR Guidelines must include traffic attributable to development in the White Flint Special Taxing District as part of their background traffic, but only if the approved development in the White Flint Special Taxing District has a valid Staging Allocation Approval.</paragraph>
        <paragraph indent="3">3.   Trips generated by public facilities in the White Flint Special Taxing District</paragraph>
        <paragraph indent="4">Applicants whose property is located outside the White Flint Special Taxing District who must submit transportation studies to satisfy requirements of the LATR and PAMR Guidelines must include as background traffic any traffic attributable to public facilities in the White Flint Special Taxing District.</paragraph>
        <paragraph indent="3">4.   Traffic assignment consistent with CLATR</paragraph>
        <paragraph indent="4">Applicants whose property is located outside the White Flint Special Taxing District who must submit transportation studies to satisfy the requirements of the LATR and PAMR Guidelines must conduct traffic assignment consistent with the CLATR.</paragraph>
        <paragraph indent="3">5.   Improvements and mitigation</paragraph>
        <paragraph indent="4">Applicants whose property is located outside the White Flint Special Taxing District must be responsible only for transportation improvements outside the White Flint Special Taxing District.</paragraph>
        <paragraph indent="2">E.   Conditions attached to development inside the Special Taxing District</paragraph>
        <paragraph indent="3">1.   General</paragraph>
        <paragraph indent="4">Individual applicants in the White Flint Special Taxing District must be responsible only for improvements required by County Code Section 50-24, such as streets interior or adjacent to the site, making any additional improvements necessary for safe access and circulation, and providing the funds for shared projects identified through the White Flint Special Taxing District and any District implementing resolution.</paragraph>
        <paragraph indent="3">2.   Privatization of traffic-carrying streets</paragraph>
        <paragraph indent="4">The White Flint Sector Plan (page 51) identifies four specific business street segments that are required to be open to general vehicular use as part of the robust street grid needed to disperse traffic. Each of these four specific streets may be implemented as private streets only if eight conditions have been satisfied. Those eight conditions are listed in the White Flint Sector Plan (page 52). All eight conditions must be incorporated within the Planning Board’s subdivision approval opinion for any project that proposes such a private street.</paragraph>
        <paragraph indent="1">(Legislative History:  Council Res. No. 17-213)</paragraph>
      </subsection>
    </regulation>
  </section>
</chapter>