COMCOR 8-14. Standards Applicable - Regulations
COMCOR 08.14.01 Schedule of Fees for Permits, Licenses and Certifications - Method 2Link
Montgomery County, Md., COMCOR § 08.14.01.01Building (2026)
08.14.01.01Building PermitsLinkCopy Citation
A. General
1. All fees required by this section must be paid before release of the permit. Construction, including excavation, must not begin until all fees are paid.
2. A filing fee must be paid when the application is submitted. Filing fees are included in the permit fee.
3. Permit fees are calculated and collected for each permit application. When an application includes multiple buildings, a separate fee will be assessed to each building or for each mailing address.
4. For the purpose of calculating the permit fee for commercial buildings, the following shall apply:
Each portion of a building separated by one or more fire walls, or horizontal assemblies (3 hours) shall be considered as a separate building. Two or more buildings on the same lot shall be treated as separate buildings.
5. For the purposes of calculating the permit fee residential is defined as detached one- and two-family dwellings and townhouses not more than three stories above grade plane in height with a separate means of egress.
6. Plan revision fees are in addition to the original fees.
7. Plan revisions are considered changes made by the applicant to the approved construction documents.
8. Permit fees are calculated on gross square footage of construction or area affected or created by construction (except commercial alteration).
B. One- and Two-Family Dwellings and Related Accessory Structures
1. Application filing fee for new building construction 50% of permit fee or $700 whichever is greater
2. Application filing fee for addition, alteration or repair 50% of permit fee or $265 whichever is greater
3. Application filing fee for residential rooftop solar panel meeting standard requirements $133
4. One- and Two-family detached dwelling unit
a. up to 5000 SF of construction area $0.71 per SF
b. 5001 SF of construction area and above $0.71 per SF for first 5000SF + $0.30 per SF of area exceeding 5000 SF
5. One- and two-family attached dwelling unit per dwelling unit $1,400
6. One- and Two-Family attached dwelling unit constructed under the MPDU program $1,000
7. Additions $0.71 per SF
8. Alterations or repairs $0.63 per SF
9. Private in-ground swimming pool (including fence) $290
10. Private above-ground swimming pool (including fence) $215
11. Decks (opened unenclosed) 500 SF or less in area $180
12. Decks (opened unenclosed) more than 500 SF in area $0.71 per SF
13. Retaining Walls $180
14. Accessory Buildings 200 SF or less $110
15. Accessory Buildings more than 200 SF $0.71 per SF
16. Solar Panels $210
17. Rooftop Solar Panels $210
18. Rooftop Solar Panels Refer-backs $105
C. Residential Plan revisions: $0.71 per SF of new construction or the application filing fee per occurrence, whichever is greater; $0.63 per SF of alteration or repair or the application filing fee per occurrence, whichever is greater. Each revision occurrence may include revision to one or more disciplines. Revisions submitted on different dates are considered separate occurrences.
D. Demolition Permit $145
E. Fence Permit $72
F. Commercial Buildings and Structures and Ownership Units
1. Application filing fee for new building construction, addition, alteration or repair 50% or permit fee or $670 whichever is greater
2. New construction and additions
a. Up to 500,000 SF of construction area $1.19 per SF
b. 500,001 SF of construction area and above $1.19 per SF for first 500,000SF + $0.60 per SF of area exceeding 500,000 SF
3. Commercial dwelling unit (reviewed under the IBC) constructed under the MPDU program $1.14 per SF
4. Repairs, alterations and accessory structures: Permit fee is based on the cost of construction as provided by the applicant multiplied by 0.024, the local permit fee multiplier. However, the department may verify and recalculate the cost estimation submitted by the applicant. The applicant may be required to provide construction bid documents. The Director will provide a worksheet and a formula that includes the latest numerical values of the valuation data to be used in determining the fee. An applicant must provide building dimensions, square footage, use group, construction type, and numbers of floors including basements, in order for the fee to be calculated.
5. Ownership Units $1,400 per unit created
G. Commercial Plan revisions: $670 or calculated under sections F.2. or F.3. above per occurrence, whichever is greater. Each revision occurrence may include revision to one or more disciplines. Revisions submitted on different dates are considered separate occurrences.
H. Use and Occupancy Certificates
1. The fee for any Use-and-Occupancy Certificate must be paid when the application is submitted.
2. Residential Use-and Occupancy Certificate $94
3. The fee for any commercial Use-and-Occupancy Certificate for each building or portion of a building or use is per square foot of area, as follows:
0 – 5000 SF $355
5,001 – 10,000 SF $520
10,001 – 20,000 SF $795
20,001 SF and up $1,240 +$.024 per SF of area exceeding 20,000 SF
4. The fee for Use-and Occupancy Certificate for lots or parcels without buildings/structures on them $575
I. Mechanical Permit
1. A minimum fee of $65 applies to all Mechanical permits issued to one- and two-family attached and detached dwellings. This fee is in addition to the equipment fee listed in this section.
2. A minimum fee of $105 applies to all other Mechanical permits. This fee is in addition to the equipment fee listed in this section.
3. Except for one-and two-family attached and detached dwellings, the base mechanical fee is 1.59% of the cost difference between the contract value and the value of listed equipment. The Department may require evidence of the contract value and equipment value. The fee is in addition to the equipment fees listed in this section. The following fee schedule applies to each piece of equipment.
New or replacement equipment:
a. Heating equipment (includes, but is not limited to, heat pump auxiliary heat, heating capacity of packaged units, duct heaters, VAV box heating elements, gas-fired fireplaces, geo-thermal units, etc.): Each 100 MBH or fraction $23
b. Cooling equipment (includes but is not limited to, cooling capacity of heat pumps, packaged units, cooling boxes, cooling equipment with compressors, etc.): Each five ton capacity or fraction $23
c. Fuel Tanks: Each 500 water gallons $52
d. Expansion Tanks: Each 50 water gallons $52
e. Pre-fabricated fireplace $26
f. Pre-fabricated chimney $14
4. Commercial Consultation inspection (per hour or fraction) $135
Montgomery County, Md., COMCOR § 08.14.01.02 (2026)
08.14.01.02 Electrical Permits and License FeesLinkCopy Citation
A. General
1. All fees required by this section must be paid before any permit is released, before any electrical work may begin, and before any inspection may be made.
2. A minimum fee of $90 applies to all electrical permits issued to one- and two-family attached and detached dwellings. This fee is in addition to the equipment fee listed in this section.
3. A minimum fee of $150 applies to all other electrical permits. This fee is in addition to the equipment fee listed in this section.
B. Electrical Permits
1. Air conditioners: (see motor schedule, item 18)
2. Appliance, small* $ 9
*Such as air filters, automatic-vent amperes, clothes washers or dryers, cooking appliances (stoves, ranges, built-ins), dishwashers, disposals, fans (exhaust, attic), humidifiers, sump pumps, trash compactors, water heaters or other water-treatment appliances
3. Arc-vapor lamps, rectifiers, rheostat chargers for storage batteries (each) $13 each
4. Battery packs (each) $ 9
5. Commercial new construction: This includes all branch circuit wiring, temporaries-pending-final, equipment/appliances within the structure. These fees are applicable to alternative power sources - such as, but not limited to: photovoltaic, wind turbine and generators.
Not over 100 Amps $600
101 – 200 Amps $745
201 – 300 Amps $895
301 – 400 Amps $1,055
Over 400 Amps $1,055
PLUS $140 for each additional 100 Amps or fraction
6. Commercial tenant fit-ups, alterations, additions (includes all branch circuit wiring, temporaries-pending-final and equipment/appliances within the space)
For low voltage or up to 20 devices $155
For single story up to 5,000 SF $230
For single story 5001 – 10,000 SF $380
For single story 10,001 – 20,000 SF $450
Over 20,001 SF or multi-story $520 per story
7. Control wiring for heating, air conditioning, duct heaters, air handlers, and motor-control centers $21
8. Dental chairs $13
9. Electrical heating equipment (see motor schedule, item 18)
10. Fire/security alarm systems $38
11. Single-station smoke detectors (each) installed separately $ 4
12. First 20 Fixtures $13
Each additional 10 (or fraction thereof) $ 9
13. Gasoline pumps (each) $ 9
14. Heating equipment (other than strictly electrical)
Residential or commercial: oil burners and gas burners, including controls (each) $13
15. Modular/mobile home $90
16. Motion-picture booths and equipment (each) $90
17. Meter stacks - replacements (each meter) $31
18. Motors, rotating machinery, transformers, switch boards, electrical heaters, air conditioners, manually operated generators (assumes 1kwor 1kva 1hp):
Under ½ HP charge d as fixture s
½ HP – 10 HP (each) $16
11 HP – 20 HP (each) $21
21 HP – 30 HP (each) $31
31 HP – 50 HP (each) $38
51 HP – 75 HP (each) $46
75 HP (each) $52
19. Outlets and rough wiring (1 – 20 lights, switches or receptacles) $16
Each additional 10 outlets (or fraction thereof) $ 7
20. Radio, television, telephone (towers, dishes, microwave, relay systems, etc.) $97
21. Service equipment, heavy-up, replacement, sub-panel, or relocation (Residential only)
0 – 400 Amps $38
Over 400 Amps $76
22. Signs (each sign) $90
23. New Multi-family buildings (apartments, condominium dwelling units)
Each dwelling unit $230
(Common areas such as stairwells, laundry, and storage rooms are charged as individual units for each panel or sub-panel required)
24. Existing Multi-family buildings (apartments, condominium dwelling units)
Each dwelling unit $150
(Common areas such as stairwells, laundry, and storage rooms are charged as individual units for each panel or sub-panel required)
25. One- and two-family dwellings and townhouses: This includes all branch circuit wiring, temporaries-pending-final and equipment/appliances within the structure. These fees are also applicable to alternative power sources (such as but not limited to: photovoltaic, wind turbine and generators switched with an automatic transfer switch). The flat fees for all wiring, fixtures, appliances, etc., including temporaries-pending-final are as follows:
Up to 200 Amps $230
201 – 400 Amps $335
Over 400 Amps $450
26. Special deck inspections, slab concealment (each) $46
27. Sub-panels (Commercial)
0 – 400 Amps $38
Over 400 Amps $76
28. Swimming pools, hot tubs, and spas (including circulating pumps, fixtures and receptacles) $76
Bonding $21
29. Temporary wiring - carnivals, fairs, holiday decorations and tree lots, etc. (includes panels and fixtures) $110
30. Temporary for construction (Residential only) $76
31. Transformers (see motor schedule, item 18)
32. Transformer vaults, duct banks
(outdoor transformer, enclosure substation, or a switch-and-meter vault on private property including wiring) $97
33. X-ray machines (each) $16
34. Any low-voltage work not previously specified
1 – 10 devices $33
Each additional 10 or fraction thereof $ 7
35. Rooftop Solar Photovoltaic (up to 200 amps) $115
36. Electrical Charging Station $50
C. Electrical License Fees
1. Electrical Examinations
a. Master Electrician and Master Limited $75
b. Journeyman Electrician $75
c. Homeowner’s Electrical Examination Fee $75
d. Homeowner’s Electrical Re-Examination Fee $75
2. License and License Renewal Fees (per year)
a. Electrical Contractor $88
b. Master Electrician $88
c. Master Electrician (Limited) $88
d. Journeyman Electrician $88
e. Apprentice Electrician (identification card) $88
3. Duplicate license or identification card $31
4. Re-examination fee $31
5. Late renewal fee $59
6. Electrical contractor change of business name or status $59
7. Electrician Good Standing Letter $31
Montgomery County, Md., COMCOR § 08.14.01.03Fire (2026)
08.14.01.03Fire Code FeesLinkCopy Citation
A. General
1. All fees required by this section must be paid before any permit is released and construction is started.
2. The minimum application filing fee for new installation or revision is $155.
3. Plan revisions are considered changes made by the applicant to the approved construction documents. Revision fees are in addition to the original or maximum permit fees. Revisions submitted on different dates are considered separate occurrences.
B. Fire-Protection-Systems Fees
1. Fire-alarm and -detection systems (devices, main control panels, or household devices and control panels (per device) $31
2. CO2 or Clean Agent systems (per system) $760
3. Sprinkler systems (per sprinkler head) $ 7
4. Fire pumps (per pump) $600
5. Added hose valves on existing standpipe (per hose) $355
6. Dry or Wet Chemical Extinguishing systems (per system) $465
7. Standpipe systems (per riser) $525
C. Plan Revisions
1. Fire Alarm (per device) $31
2. Sprinkler Systems (per sprinkler head) $ 7
3. Other - per device (includes CO2 and Clean Agent systems, Fire pumps, added hose valves on existing standpipe, Dry or Wet Chemical extinguishing systems) $155
Montgomery County, Md., COMCOR § 08.14.01.04Certificate (2026)
08.14.01.04Certificate FeesLinkCopy Citation
Capacity Certificate fee is $115 per assembly room; $5.00 for each duplicated certificate.
Montgomery County, Md., COMCOR § 08.14.01.05Well-Location (2026)
08.14.01.05Well-Location PermitLinkCopy Citation
Well-Location Permit (Each well) $160
Montgomery County, Md., COMCOR § 08.14.01.06Vendor (2026)
08.14.01.06Vendor FeesLinkCopy Citation
A. Operator Permit fee
1. For Non-Certified Agricultural Producers and their operators $70
2. For Certified Agricultural Producers and their operators $56
B. Point-of-Sale License for Vendors Who are not Certified Agricultural Producers
1. Per site for Site-Specific $315
2. Door-to-Door $140
3. Regular Route $245
C. Temporary Sales License
1. 60 consecutive days $175
2. Daily Rate $175
D. Performance Bond for Future-Delivery Vendor $1,305
Montgomery County, Md., COMCOR § 08.14.01.07Benefit (2026)
08.14.01.07Benefit PerformancesLinkCopy Citation
A. A benefit performance may not be conducted without a permit and all fees required by this section must be paid before release of the permit for a benefit performance.
B. A bona fide non-profit organization must pay the following permit fee for a permit for a benefit performance.
Benefit Performance $175
Montgomery County, Md., COMCOR § 08.14.01.08Storage (2026)
08.14.01.08Storage of Vendor-Confiscated GoodsLinkCopy Citation
This regulation sets a fee for the storage of goods confiscated by the Department of Permitting Services enforcement staff from vendors illegally offering goods for sale.
Storage Fee $140
Montgomery County, Md., COMCOR § 08.14.01.09Miscellaneous (2026)
08.14.01.09MiscellaneousLinkCopy Citation
A. Filing fees and permit fees are based on fees in effect on the date the application was filed. All other fees are based on fees in effect at the time the service is requested (revision fee, extension fee, etc.).
B. All fees in this schedule are subject to the Automation Enhancement Fee per COMCOR 08.24B.02.
C. Refunds: Minimum permit filing and license fees are non-refundable, except in the case of an administrative error. In the case of an abandonment or discontinuance of a project under permit, the person who has paid the permit fee may return the permit for cancellation and, upon cancellation, may be refunded up to 50% of the fee paid, less the filing fee or minimum fee, as appropriate, provided: (1) No construction has occurred, and (2) the written request for a refund is made before the expiration date of the permit. Revoked, suspended, or invalid permits or licenses, or licenses or permits in litigation, are not eligible for refunds.
D. Application Extensions: The fee to extend an application (before the permit is issued) is 15% of the filing fee.
E. Permit Extensions: The fee to extend a permit, after written application and before expiration of the original permit, is 15% of the total permit fee.
F. Inspection Fees:
1. First or second approved inspection of the same item or stage of construction for permitted work: Included in permit fee.
2. Initial inspection of sites or property where work is proceeding without a permit $150
3. Applicant requested partial inspection for residential (each occurrence). Each re-inspection (residential or commercial) of the same item or stage of construction after two disapprovals $97
4. The re-inspection fee must be paid before an additional inspection is scheduled.
G. Permit Application Revisions: The fee for revisions to permit information after submission by the applicant $49
H. Plan revision, residential - room description name change $49
I. Construction codes modifications or interpretations $510
J. Permit Denials: All permit requests that are denied because the applicant must apply to the Board of Appeals for a variance must include a non-refundable $62 processing fee.
Montgomery County, Md., COMCOR § 08.14.01.10Indexing (2026)
08.14.01.10Indexing Of Fees To Labor and Operating Cost Changes and to Manage ReservesLinkCopy Citation
The Director of Permitting Services must calculate an enterprise fund stabilization factor (EFSF) each year to be applied to each fee set in or under this regulation on July 1 or each year. The EFSF is the factor by which the fee calculation is adjusted, up or down, to cover DPS labor and operating costs and to manage the DPS reserve policy in accordance with the 2002 Principles of the Fiscal Management of the Permitting Services Fund. The Director must publish the EFSF for each upcoming fiscal year not later than March 15 of the current fiscal year. For any year in which the EFSF will be less than .80 or greater than 1.20, the Department must review its fee rates and functional analysis behind the fee rates to determine if changes need to be made to the fee rates.
Montgomery County, Md., COMCOR § 08.14.01.11Severability (2026)
08.14.01.11SeverabilityLinkCopy Citation
The provisions of this regulation are severable. If a court of competent jurisdiction holds that a provision is invalid or inapplicable, the remainder of the regulation remains in effect.