<?xml version='1.0' encoding='utf-8'?>
<section number="21-131" name="License application; plans; bond; fee" law="code" slug="sec-21-131" node_id="PTIITI17PULOLAPRGECOMA_SUBTITLE_21RE_DIV2COMOFI_S21-131LIAPPLBOFE">
  <level label="a">
    <text>Applications for licenses to engage in the disposal of construction of demolition materials or both by the rubble fill method shall be made on forms provided by the Director of the Department of Environmental Resources.</text>
  </level>
  <level label="b">
    <text>Such applications shall be submitted to the Permit Division of the Department of Environmental Resources, accompanied by the following:</text>
    <level label="1">
      <text>Engineering report of proposed site survey.</text>
    </level>
    <level label="2">
      <text>Design and development plans and specifications.</text>
    </level>
    <level label="3">
      <text>Completion maintenance bond, either cash or negotiable paper acceptable to the Director of the Department of Environmental Resources in the amount of One Thousand Dollars ($1,000.00) per acre, based on the number of acres planned or intended to be employed in the rubble fill operation during the license period. Completion maintenance bond is to guarantee completion and maintenance of the rubble fill, as specified in this Division, in the event of default on the part of the licensee. In the event of the default by the licensee, the unsuitable conditions at the fill site, or an adjacent road or street may be corrected by the County forces or by a County contract, with all costs to be reimbursed from the completion maintenance bond. After default is established, the licensee shall be notified at least one (1) week in advance of County operations. In cases where the applicant plans to operate on leased land, legally acceptable documented assurances from the property owner shall be furnished the County as follows:</text>
      <level label="A">
        <text>The owner accepts the fact, that after construction and completion of the landfill, no building permit shall be issued for building construction on such land at any time in the future; and</text>
      </level>
      <level label="B">
        <text>The owner gives the right of entry to the property by the County for the purpose of completion and maintenance of the fill as specified in this Division in the event of default on the part of the operator.</text>
      </level>
    </level>
    <level label="4">
      <text>License fee, in the amount of Twenty-five Dollars ($25.00).</text>
    </level>
  </level>
</section>