<?xml version='1.0' encoding='utf-8'?>
<section number="32-153" name="Contents, Review and Approval of the Erosion and Sediment Control Plan" law="code" slug="sec-32-153" node_id="PTIITI17PULOLAPRGECOMA_SUBTITLE_32WAREPRGRCO_DIV2GRDRERSECO_S32-153COREAPERSECOPL">
  <level label="a">
    <text>No grading permit shall be issued for areas to be disturbed in excess of five thousand (5,000) square feet or one hundred (100) cubic yards of earth moved without an approved erosion and sediment control plan which meets the requirements of the Prince George's Soil Conservation District, this Division, the State Sediment Control Regulations, COMAR 26.17.01, and the Standards and Specifications. The plan shall include sufficient information to evaluate the environmental characteristics of the affected areas, the potential impacts of the proposed grading on water resources, and the effectiveness and acceptability of measures proposed to minimize soil erosion and off-site sedimentation. This plan shall serve as a basis for all subsequent grading and stabilization. The applicant shall certify on the plan that all clearing, grading, drainage, construction and development shall be conducted in strict accordance with the plan.</text>
  </level>
  <level label="b">
    <text>At a minimum, applicants shall submit the following information to the Prince George's Soil Conservation District:</text>
    <level label="1">
      <text>A letter of transmittal and/or application known as a site analysis;</text>
    </level>
    <level label="2">
      <text>A vicinity sketch indicating north arrow, scale and other information necessary to easily locate the property;</text>
    </level>
    <level label="3">
      <text>Drainage area map(s) showing existing, interim, and proposed topography, proposed improvements, standard symbols for proposed sediment control features, and pertinent drainage information including provisions to protect downstream areas from erosion for a minimum of 200 feet downstream or to the next conveyance system;</text>
    </level>
    <level label="4">
      <text>The location of natural resources, wetlands, floodplains, highly erodible soils, slopes 15 percent and steeper, and any other sensitive areas;</text>
    </level>
    <level label="5">
      <text>A general description of the predominant soil types on the site, as described by the appropriate soil survey information available through the Prince George's Soil Conservation District or the USDA Natural Resources Soils Conservation Service;</text>
    </level>
    <level label="6">
      <text>Proposed stormwater management practices;</text>
    </level>
    <level label="7">
      <text>An Erosion and sediment control plan at an appropriate scale, including at least:</text>
      <level label="A">
        <text>Name, address and telephone number of:</text>
        <level label="i">
          <text>The owner of the property where the grading is proposed;</text>
        </level>
        <level label="ii">
          <text>The applicant; and</text>
        </level>
        <level label="iii">
          <text>The developer.</text>
        </level>
      </level>
      <level label="B">
        <text>The existing topography and improvements as well as proposed topography and improvements at a scale between 1" = 10' and 1" = 50' with 2 foot contours or other approved contour interval;</text>
      </level>
      <level label="C">
        <text>Scale, project and sheet title, and north arrow on each plan sheet;</text>
      </level>
      <level label="D">
        <text>The proposed grading and earth disturbance including:</text>
        <level label="i">
          <text>Total disturbed area;</text>
        </level>
        <level label="ii">
          <text>Volume of cut and fill quantities;</text>
        </level>
        <level label="iii">
          <text>Volume of borrow and spoil quantities;</text>
        </level>
        <level label="iv">
          <text>Specific limits of disturbance consistent to that shown on an approved Type 2 Tree Conservation Plan; and</text>
        </level>
        <level label="v">
          <text>A clear and definite delineation of all woodland conservation areas and areas to remain undisturbed consistent with the approved Type 2 Tree Conservation Plan;</text>
        </level>
      </level>
      <level label="E">
        <text>Scale, project and sheet title, and north arrow on each plan sheet;</text>
      </level>
      <level label="F">
        <text>The limit of disturbance (LOD) including:</text>
        <level label="i">
          <text>Limit of grading (grading units, if applicable); and</text>
        </level>
        <level label="ii">
          <text>Initial, interim, and final phases;</text>
        </level>
      </level>
      <level label="G">
        <text>Storm drainage features, including:</text>
        <level label="i">
          <text>Existing and proposed bridges, storm drains, culverts, outfalls, etc.;</text>
        </level>
        <level label="ii">
          <text>Velocities and quantities of peak flow rates at outfalls for the two-year and ten-year frequency storm events; and</text>
        </level>
        <level label="iii">
          <text>Site conditions around points of all surface water discharge from the site;</text>
        </level>
      </level>
      <level label="H">
        <text>Erosion and sediment control practices to minimize on-site erosion and prevent off-site sedimentation including:</text>
        <level label="i">
          <text>The salvage and reuse of top soil;</text>
        </level>
        <level label="ii">
          <text>Phased construction and implementation of grading unit(s) to minimize disturbances, both in extent and duration, not to exceed 20 acres;</text>
        </level>
        <level label="iii">
          <text>Location and type of all proposed erosion and sediment control practices;</text>
        </level>
        <level label="iv">
          <text>Design details and data for all erosion and sediment control practices; and</text>
        </level>
        <level label="v">
          <text>Specifications for temporary and permanent stabilization measures including, at a minimum:</text>
          <level label="aa">
            <text>The "Standard Stabilization Note" on the plan stating: "Following initial soil disturbance or re-disturbance, permanent or temporary stabilization must be completed within:</text>
            <level label="I">
              <text>Three (3) calendar days as to the surface of all perimeter dikes, swales, ditches, perimeter slopes, and all slopes steeper than 3 horizontal to 1 vertical (3:1); and</text>
            </level>
            <level label="II">
              <text>Seven (7) calendar days as to all other disturbed or graded areas on the project site not under active grading."</text>
            </level>
          </level>
          <level label="bb">
            <text>Details for areas requiring accelerated stabilization; and</text>
          </level>
          <level label="cc">
            <text>Maintenance requirements as defined in the Standards and Specifications;</text>
          </level>
        </level>
      </level>
    </level>
    <level label="8">
      <text>Design details for structural controls;</text>
    </level>
    <level label="9">
      <text>Details of temporary and permanent stabilization measures including placement of the statement on the plan that following initial soil disturbance or redisturbance, permanent or temporary stabilization shall be completed within seven (7) calendar days for the surface of all perimeter dikes, swales, ditches, perimeter slopes and all slopes greater than 3 horizontal to 1 vertical (3:1), and for all embankments of ponds, basins and traps; and fourteen (14) days for all other disturbed or graded areas on the project site provided that the requirements of this Section do not apply to those areas which are shown on the plan and are currently being used for material storage or for those areas on which actual construction activities are currently being performed or to interior areas of a surface mine site where the stabilization material would contaminate the recoverable resource;</text>
    </level>
    <level label="10">
      <text>A sequence of construction describing the relationship between the implementation and maintenance of controls, including permanent and temporary stabilization and the various stages or phases of earth disturbance and construction. Any changes or revisions to the sequence of construction must be approved by the Prince George's Soil Conservation District prior to proceeding with construction. The sequence of construction shall, at a minimum, include a schedule and time frame for the following:</text>
      <level label="A">
        <text>Request for a pre-construction meeting with the Department;</text>
      </level>
      <level label="B">
        <text>Clearing and grubbing for those areas necessary for installation of perimeter controls;</text>
      </level>
      <level label="C">
        <text>Construction and stabilization of perimeter controls within installed perimeter controls;</text>
      </level>
      <level label="D">
        <text>Remaining clearing and grubbing;</text>
      </level>
      <level label="E">
        <text>Road grading;</text>
      </level>
      <level label="F">
        <text>Grading for the remainder of the site;</text>
      </level>
      <level label="G">
        <text>Utility installation and connections to existing structures;</text>
      </level>
      <level label="H">
        <text>Construction of buildings, roads, and other construction;</text>
      </level>
      <level label="I">
        <text>Final grading, landscaping and stabilization;</text>
      </level>
      <level label="J">
        <text>Construction of buildings, roads and other construction;</text>
      </level>
      <level label="K">
        <text>Installation of stormwater management measures;</text>
      </level>
      <level label="L">
        <text>Approval of the appropriate enforcement authority prior to removal of sediment controls; and</text>
      </level>
      <level label="M">
        <text>Removal of controls and stabilization of areas that are disturbed by removal of sediment controls.</text>
      </level>
    </level>
    <level label="11">
      <text>A statement placed on the plan indicating that the owner/developer or representative shall request that the Department of Permitting, Inspections, and Enforcement or its agent approve work completed in accordance with the approved erosion and sediment control plan, the grading or building permit, and this Division, and that the owner/developer or representative shall obtain written inspection approvals by the Director or his designee at the following stages in the development of the site, or of each subdivision thereof:</text>
      <level label="A">
        <text>Prior to the start of earth disturbance;</text>
      </level>
      <level label="B">
        <text>Upon completion of installation of tree protection devices, followed by the installation of perimeter erosion and sediment controls, prior to proceeding with any other earth disturbance or grading. Other building or grading inspection approvals may not be authorized until initial approval by the Department is made;</text>
      </level>
      <level label="C">
        <text>Upon completion of stripping, the stockpiling of top soil, the construction of temporary sediment and erosion control facilities, disposal of all waste material and preparation of the ground;</text>
      </level>
      <level label="D">
        <text>Upon completion of rough grading, but prior to placing top soil, permanent drainage or other site development improvements and ground covers;</text>
      </level>
      <level label="E">
        <text>Prior to the start of another phase of construction or opening of another grading unit;</text>
      </level>
      <level label="F">
        <text>Prior to the removal of sediment control practices; and</text>
      </level>
      <level label="G">
        <text>Upon completion of final grading, reforestation, permanent drainage, and erosion control facilities including established ground covers and planting, and all other work of the building permit;</text>
      </level>
    </level>
    <level label="12">
      <text>Certification by the owner/developer or permittee that any clearing, grading, construction or development, or all of these, will be done pursuant to the approved erosion and sediment control plan. The certification must also require that responsible personnel involved in the construction project will have a Certification of Training at a State of Maryland Department of the Environment approved training program (i.e. Green Card Certification) for the control of sediment and erosion before beginning the project. The Certification of Training for Responsible Personnel requirement may be waived by the Prince George's Soil Conservation District on any project involving four (4) or fewer residential units. Additionally, the owner/developer shall allow right of entry for periodic on-site evaluation by the Prince George's Soil Conservation District, the Department, and/or MDE;</text>
    </level>
    <level label="13">
      <text>Certification by a professional engineer, land surveyor, landscape architect (only for plans with no hydraulic and hydrologic calculations), or forester (for forest harvest operations only) registered in the State that the plans have been designed in accordance with erosion and sediment control laws, regulations, and standards, if required by the Prince George's Soil Conservation District or the Administration; and</text>
    </level>
    <level label="14">
      <text>In approving the plan, the Prince George's Soil Conservation District may require any additional information or data deemed appropriate and/or may impose such conditions thereto as may be deemed necessary to ensure compliance with the provisions of this Division, the State Sediment Control Regulations, COMAR 26.17.01, the Standards and Specifications, or the preservation of public health and safety.</text>
    </level>
  </level>
  <level label="c">
    <text>Review and Approval of Erosion and Sediment Control Plans.</text>
    <level label="1">
      <text>A person may not grade land without an erosion and sediment control plan approved by the Prince George's Soil Conservation District if the site is not exempt from these requirements.</text>
    </level>
    <level label="2">
      <text>The Prince George's Soil Conservation District shall review erosion and sediment control plans to determine compliance with this Ordinance and the Standards and Specifications prior to approval. In approving the plan, the Prince George's Soil Conservation District may impose such conditions that may be deemed necessary to ensure compliance with the provisions of this Ordinance, COMAR 26.17.01, the Standards and Specifications, and the preservation of public health and safety.</text>
    </level>
    <level label="3">
      <text>The review and approval process shall be in accordance with the comprehensive and integrated plan approval process described in the Standards and Specifications, Prince George's County Stormwater Ordinance, and the Act.</text>
    </level>
    <level label="4">
      <text>At a minimum, a concept plan must include the mapping of natural resources and sensitive areas including highly erodible soils and slopes greater than 15 percent as well as information required under Prince George's County Stormwater Ordinance. These areas are to remain undisturbed or an explanation must be included with either the concept or site development plan describing enhanced protection strategies for these areas during construction. Approved concept sediment control plans remain valid for three (3) years from the date of approval unless extended or renewed by the Prince George's Soil Conservation District.</text>
    </level>
    <level label="5">
      <text>A site development plan submittal must include all concept plan information and indicate how proposed erosion and sediment control practices will be integrated with proposed stormwater management practices. The latter is being done through a narrative and an overlay plan showing both ESD and erosion and sediment control practices. An initial sequence of construction and proposed project phasing to achieve the grading unit restriction should be submitted at this time. Approved site development sediment control plans remain valid for three (3) years from the date of approval unless extended or renewed by the Prince George's Soil Conservation District.</text>
    </level>
    <level label="6">
      <text>An applicant shall submit a final erosion and sediment control plan to the Prince George's Soil Conservation District for review and approval. The plan must include all of the information required by the concept and site development plans as well as any information in this Section.</text>
    </level>
    <level label="7">
      <text>A final erosion and sediment control plan shall not be considered approved without the inclusion of the signature and date of signature of the Prince George's Soil Conservation District on the plan.</text>
    </level>
    <level label="8">
      <text>Final erosion and sediment control plans remain valid for two (2) years from the date of approval unless extended or renewed by the Prince George's Soil Conservation District.</text>
    </level>
    <level label="9">
      <text>Grandfathering of Approved Plans:</text>
      <level label="A">
        <text>Any plans that receive final approval after January 9, 2013 must be in compliance with the erosion and sediment control requirements of this Ordinance and the Standards and Specifications.</text>
      </level>
      <level label="B">
        <text>A plan that receives final approval by January 9, 2013 may be reapproved under its existing conditions if grading activities have begun on the site by January 9, 2015, with the exception of stabilization requirements.</text>
      </level>
      <level label="C">
        <text>Stabilization practices on all sites must be in compliance with the erosion and sediment control requirements of this Ordinance and the Standards and Specifications by January 9, 2013, regardless of when an approved erosion and sediment control plan was approved.</text>
      </level>
    </level>
  </level>
  <level label="d">
    <text>The erosion and sediment control plan must be designed in concert with a site's stormwater management plan as required by the Stormwater Management Act of 2007 (Act). The Act requires an integrated review of erosion and sediment control plans and stormwater management plans via a comprehensive plan review process to ensure that environmental site design (ESD) is implemented to the maximum extent practicable (MEP) on all sites.</text>
  </level>
  <level label="e">
    <text>Standard Erosion and Sediment Control Plan.</text>
    <level label="1">
      <text>The Prince George's Soil Conservation District may adopt a standard erosion and sediment control plan for activities with minor earth disturbances, such as single-family residences, small commercial and other similar building sites, minor maintenance grading, and minor utility construction.</text>
    </level>
    <level label="2">
      <text>A standard erosion and sediment control plan must meet the requirements of this Ordinance and the Standards and Specifications.</text>
    </level>
    <level label="3">
      <text>MDE shall review and approve a standard plan prior to its adoption.</text>
    </level>
  </level>
</section>