<section article="ged" article_name="Education" number="5-312" title_number="5" title_name="Financing" subtitle_number="3" subtitle_name="State Aid for School Construction">
  <level label="a">
    <text>In this section, “high performance building” has the meaning stated in § 3–602.1 of the State Finance and Procurement Article.</text>
  </level>
  <level label="b">
    <text>This section applies to the construction of new schools that have not initiated a Request For Proposal for the selection of an architectural and engineering consultant on or before July 1, 2009.</text>
  </level>
  <level label="c">
    <text>Except as provided in subsection (d) of this section, a new school that receives State public school construction funds shall be constructed to be a high performance building.</text>
  </level>
  <level label="d">
    <level label="1">
      <text>The Interagency Commission shall establish a process to allow a school system to obtain a waiver from complying with subsection (c) of this section.</text>
    </level>
    <level label="2">
      <text>The waiver process shall:</text>
      <level label="i">
        <text>Include a review by the Interagency Commission to determine if the construction of a high performance building is not practicable; and</text>
      </level>
      <level label="ii">
        <text>Require the approval of a waiver by the Interagency Commission.</text>
      </level>
    </level>
  </level>
  <level label="e">
    <text>For fiscal years 2010 through 2014 only, the State shall pay 50% of the local share of the extra costs, identified and approved by the Interagency Commission, that are incurred in constructing a new school to meet the high performance building requirements of this section.</text>
  </level>
  <level label="f">
    <text>The Interagency Commission shall adopt regulations to implement the requirements of this section.</text>
  </level>