<section article="gen" article_name="Environment" number="15-815" title_number="15" title_name="Mines and Mining" subtitle_number="8" subtitle_name="Surface Mining">
  <level label="a">
    <level label="1">
      <text>Any permittee engaged in surface mining under a surface mining permit may apply at any time for modification of the permit.</text>
    </level>
    <level label="2">
      <text>The application shall be in writing on forms furnished by the Department and fully state the information called for.</text>
    </level>
    <level label="3">
      <text>The applicant may be required to furnish additional information that the Department reasonably deems necessary to enforce this subtitle.</text>
    </level>
    <level label="4">
      <text>If an applicant states in writing that information has not changed since the original application, the applicant is not required to resubmit that information.</text>
    </level>
  </level>
  <level label="b">
    <level label="1">
      <text>A modification under this section may affect:</text>
      <level label="i">
        <text>The land area covered by the permit;</text>
      </level>
      <level label="ii">
        <text>The approved mining and reclamation plan coupled with the permit; or</text>
      </level>
      <level label="iii">
        <text>Other terms and conditions of the permit.</text>
      </level>
    </level>
    <level label="2">
      <level label="i">
        <text>A permit may be modified to include land contiguous to the existing affected land, but not other lands.</text>
      </level>
      <level label="ii">
        <text>The mining and reclamation plan may be modified in any manner, if the Department determines that the modified plan fully meets the standards set forth in § 15–822 of this subtitle and that the modifications would be generally consistent with the bases for the issuance of the original permit.</text>
      </level>
      <level label="iii">
        <text>Other terms and conditions may be modified only if the Department determines that the permit as modified would meet the requirements of §§ 15–808 and 15–810 of this subtitle.</text>
      </level>
      <level label="iv">
        <text>A modification may not extend the expiration date of any permit issued under this subtitle.</text>
      </level>
    </level>
  </level>
  <level label="c">
    <text>Except as otherwise provided in subsection (d) of this section, a $150 fee shall be charged for a permit modification.</text>
  </level>
  <level label="d">
    <level label="1">
      <text>In addition to the fee required in subsection (c) of this section, a fee shall be charged equal to:</text>
      <level label="i">
        <text>$18.50 for each additional acre of affected land over and above the amount of land covered in the original permit for each year of operation, not to exceed $3,000; and</text>
      </level>
      <level label="ii">
        <text>Except as provided in paragraph (2) of this subsection, 0.50 cent per ton of mined material sold per year.</text>
      </level>
    </level>
    <level label="2">
      <text>The per ton of material sold fee in paragraph (1) of this subsection shall be increased by 0.13 cent per ton in fiscal year 2028 and every 2 fiscal years thereafter.</text>
    </level>
  </level>
  <level label="e">
    <text>The Department shall approve and grant the permit modification requested as expeditiously as possible but not later than 30 days after the application forms or any supplemental information required are filed with the Department.</text>
  </level>
  <level label="f">
    <text>The Department may deny the permit modification on finding:</text>
    <level label="1">
      <text>An uncorrected violation of the type listed in § 15–810(b)(7) of this subtitle;</text>
    </level>
    <level label="2">
      <text>Failure to submit an adequate mining and reclamation plan in light of conditions existing at the time of the modification; or</text>
    </level>
    <level label="3">
      <text>Failure or refusal to pay the modification fee.</text>
    </level>
  </level>
  <level label="g">
    <text>If the Department denies an application to modify a permit, the Department shall give the permittee written notice of:</text>
    <level label="1">
      <text>The Department’s determination;</text>
    </level>
    <level label="2">
      <text>Any changes in the application which would make it acceptable; and</text>
    </level>
    <level label="3">
      <text>The permittee’s right to a hearing at a stated time and place.</text>
    </level>
  </level>
  <level label="h">
    <text>The date for the hearing may not be less than 15 days nor more than 30 days after the date of the notice unless the Department and the permittee mutually agree on another date.</text>
  </level>
</section>