  <level label="a">
    <text>Upon application for a permit under this subtitle, and except as otherwise provided in this section, the procedures in § 5–204 of this title shall apply.</text>
  </level>
  <level label="b">
    <text>Under the following conditions, the Department may waive the notice requirements and the holding of a public informational hearing on a permit application:</text>
    <level label="1">
      <text>If there is an emergency or a request to make minor repairs, the Department, upon written or oral application, may grant an application to repair any reservoir, dam, or waterway obstruction without notice or hearing. Repair necessary to save life or property may be made without an application, but notice shall be given promptly to the Department;</text>
    </level>
    <level label="2">
      <text>If plans of other projects which conform to water resources development plans accepted and adopted by the Department were subject to public hearing, and the Department’s review finds no changed conditions in them since the last public review and comment to justify another hearing;</text>
    </level>
    <level label="3">
      <text>If temporary structures constructed to provide access across streams during construction operations or to trap sediment or achieve another similar purpose meet minimum design standards the Department establishes, and are removed completely, in a manner acceptable to the Department, within 6 months after need for the structure is terminated;</text>
    </level>
    <level label="4">
      <text>If the requested waterway construction permit is for temporary excavation, filling, or grading for the installation of utilities which meet minimum design standards acceptable to the Department and preconstruction contours which are to be reestablished upon installation of the utility;</text>
    </level>
    <level label="5">
      <text>If the requested waterway construction permit is for clearing and grading activities disturbing less than 5,000 square feet of land area and disturbing less than 100 cubic yards of earth; or</text>
    </level>
    <level label="6">
      <text>If the requested waterway construction permit is for livestock crossing of a stream.</text>
    </level>
  </level>
  <level label="c">
    <text>If contiguous property owners and interested persons who receive periodic reports are notified under § 5–204 of this title, the Department may waive the notice requirements of this section and the holding of a public informational hearing on a permit application for roads, bridges, or culverts if they meet minimum design standards acceptable to the Department and construction does not adversely affect known water resources projects.</text>
  </level>
  <level label="d">
    <text>The Department shall waive notice requirements and the holding of a public hearing if the requested appropriation or use of waters of the State is for an agricultural use in effect prior to July 1, 1993.</text>
  </level>
  <level label="e">
    <text>Notwithstanding any other requirement of this section:</text>
    <level label="1">
      <text>The Department may waive the notice and hearing requirements of this section if the appropriation requested is for:</text>
      <level label="i">
        <text>An average annual water use of 10,000 gallons per day or less; or</text>
      </level>
      <level label="ii">
        <text>A construction dewatering project; and</text>
      </level>
    </level>
    <level label="2">
      <text>The Department may waive the holding of a public informational hearing if the requested appropriation or use of waters of the State is greater than an average annual water use of 10,000 gallons per day but less than an average annual water use of 50,000 gallons per day.</text>
    </level>
  </level>