<section article="glg" article_name="Local Government" number="27-701" title_number="27" title_name="Drainage Districts" subtitle_number="7" subtitle_name="Financing">
  <level label="a">
    <text>The board of drainage commissioners shall ascertain the total cost of the drainage project, including the payment of damages awarded to the landowners, after:</text>
    <level label="1">
      <text>the classification of lands and the ratio of assessment of the different classes of lands has been confirmed by the county commissioners or county council at the time of the final hearing; and</text>
    </level>
    <level label="2">
      <text>any appeal made to the circuit court has been adjudicated.</text>
    </level>
  </level>
  <level label="b">
    <text>The total cost of the drainage project may include:</text>
    <level label="1">
      <text>all costs and incidental expenses;</text>
    </level>
    <level label="2">
      <text>the compensation of members of the board of viewers and assistants and the superintendent of construction;</text>
    </level>
    <level label="3">
      <text>the expenses of the board of drainage commissioners;</text>
    </level>
    <level label="4">
      <text>the necessary expenses of maintaining the drainage project for a period of 3 years after the completion of the construction work; and</text>
    </level>
    <level label="5">
      <text>the payment of interest on drainage bonds for a period of 3 years.</text>
    </level>
  </level>
  <level label="c">
    <level label="1">
      <text>The board of drainage commissioners, under the direction of the chair and secretary of the board, shall certify to the designated officer the total estimated cost of the drainage project.</text>
    </level>
    <level label="2">
      <text>The certification shall be recorded in the drainage record and open to inspection by any landowner.</text>
    </level>
  </level>
  <level label="d">
    <text>If the total estimated cost of the proposed drainage project constructed under this title is less than an average of 25 cents per acre of the total area, the board of drainage commissioners may issue bonds and shall collect the assessment from the landowners.</text>
  </level>