<?xml version='1.0' encoding='utf-8'?>
<section article="glu" article_name="Land Use" number="12-201" title_number="12" subtitle_number="2">
  <level label="a">
    <level label="1">
      <text>Subject to the provisions of this subsection, the approval, conditional approval, or denial of a housing development project application by a local regulatory authority or the Commission shall be governed only by the duly adopted laws and regulations in effect at the time of submission of a complete application.</text>
    </level>
    <level label="2">
      <level label="i">
        <text>Within 30 days after receipt of a housing development project application, a local regulatory authority or the Commission shall make a determination as to whether the application is a complete application.</text>
      </level>
      <level label="ii">
        <text>After making a determination under this paragraph, the local regulatory authority or the Commission shall:</text>
        <level label="1">
          <text>promptly notify the applicant of the determination and the date of the determination; and</text>
        </level>
        <level label="2">
          <text>if the local regulatory authority or the Commission has determined that the application is not a complete application, provide the applicant with a list of deficiencies and a reasonable time frame for curing the deficiencies.</text>
        </level>
      </level>
    </level>
    <level label="3">
      <text>If a local regulatory authority or the Commission fails to notify an applicant of its determination regarding the completeness of a housing development application within 35 days after receipt of the application, the application is deemed to be a complete application for purposes of this section.</text>
    </level>
    <level label="4">
      <level label="i">
        <text>When a local regulatory authority or the Commission requires approval of multiple housing development project applications for the completion of a housing development project, the date of a complete application submission under paragraph (1) of this subsection shall be the date of the first complete application submission for any process that may culminate in the completion of a housing development project.</text>
      </level>
      <level label="ii">
        <text>A zoning text amendment, application for rezoning, or other local equivalent may not be considered as a process that may culminate in the completion of a housing development project.</text>
      </level>
    </level>
  </level>
  <level label="b">
    <text>After a housing development project has received all required approvals, the proponent of the project shall have a vested right to that authorized use and development for the longer of:</text>
    <level label="1">
      <text>5 years; or</text>
    </level>
    <level label="2">
      <text>a period determined by the local regulatory authority or the Commission.</text>
    </level>
  </level>
  <level label="c">
    <text>For purposes of this section, each phase of a housing development project subject to a phased development plan shall be considered a discrete housing development project.</text>
  </level>
  <level label="d">
    <text>This section may not be construed to:</text>
    <level label="1">
      <text>subject to the vesting period in subsection (b) of this section, prevent the expiration of an approval of a housing development project application in accordance with the laws or regulations governing a local regulatory authority or the Commission; or</text>
    </level>
    <level label="2">
      <text>limit the ability of a local regulatory authority or the Commission to:</text>
      <level label="i">
        <text>require approvals or permits for each phase of a housing development project subject to a phased development plan in accordance with the laws and regulations in effect at the time of submission of a complete application for each respective phase;</text>
      </level>
      <level label="ii">
        <text>enforce health and safety laws or regulations that are necessary to address immediate threats to public safety;</text>
      </level>
      <level label="iii">
        <text>execute a development rights and responsibilities agreement under Title 7, Subtitle 3 of this article; or</text>
      </level>
      <level label="iv">
        <text>approve a zoning text amendment, application for rezoning, or other local equivalent to increase the density of a housing development project beyond the maximum allowable amount at the time of complete application submission under subsection (a) of this section.</text>
      </level>
    </level>
  </level>
  <level label="e">
    <text>The requirements of this section apply to a local regulatory authority and the Commission only to the extent that the requirements do not conflict with other State or federal laws or regulations.</text>
  </level>
</section>