      <text>In this subtitle the following words have the meanings indicated.</text>
    </level>
    <level label="b">
      <text>“Payment date” means the date of the Commission’s check.</text>
    </level>
    <level label="c">
      <text>“Proper invoice” means an invoice that:</text>
      <level label="1">
        <text>contains:</text>
        <level label="i">
          <text>the contractor’s federal employer identification number or Social Security number; and</text>
        </level>
        <level label="ii">
          <text>the contract or purchase order number or other description of the contract; and</text>
        </level>
      </level>
      <level label="2">
        <text>contains or is accompanied by substantiating information and documentation as required by regulation or contract.</text>
      </level>
    </level>
    <level label="d">
      <text>“Receipt date” means the date that a proper invoice is received by the Commission.</text>
    </level>
  </section>
  <section article="glu" article_name="Land Use" number="18-502" title_number="18" title_name="Finances" subtitle_number="5" subtitle_name="Payment of Obligations">
    <text>It is the policy of the Commission that payment under an authorized, written procurement contract shall be made by the Commission to the contractor within 30 days after the receipt date of a proper invoice.</text>
  </section>
  <section article="glu" article_name="Land Use" number="18-503" title_number="18" title_name="Finances" subtitle_number="5" subtitle_name="Payment of Obligations">
    <text>An amount due and payable under an authorized, written procurement contract and in accordance with law that remains unpaid for more than 45 days after the receipt date shall accrue interest:</text>
    <level label="1">
      <text>for the period that begins 31 days after the receipt date; and</text>
    </level>
    <level label="2">
      <text>at the rate specified in § 11–107(a) of the Courts Article.</text>
    </level>
  </section>
  <section article="glu" article_name="Land Use" number="18-504" title_number="18" title_name="Finances" subtitle_number="5" subtitle_name="Payment of Obligations">
    <text>The Commission is not liable for the payment of interest under this subtitle:</text>
    <level label="1">
      <text>if a proper invoice for accrued interest is not submitted within 30 days after the payment date of the amount on which the interest accrued;</text>
    </level>
    <level label="2">
      <text>for more than 1 year and 31 days after the receipt date;</text>
    </level>
    <level label="3">
      <text>on amounts representing unpaid interest; or</text>
    </level>
    <level label="4">
      <text>if the Commission determines there is a dispute regarding any material factor in the contract or purchase order.</text>
    </level>