  <level label="a">
    <text>This section applies only in Prince George’s County.</text>
  </level>
  <level label="b">
    <level label="1">
      <text>The county planning board shall approve or disapprove a preliminary subdivision plan within 70 days after the complete plan application is submitted to the county planning board.</text>
    </level>
    <level label="2">
      <text>If the county planning board does not take action in accordance with paragraph (1) of this subsection:</text>
      <level label="i">
        <text>the plan shall be considered approved; and</text>
      </level>
      <level label="ii">
        <text>the county planning board shall issue a certificate of approval on demand.</text>
      </level>
    </level>
    <level label="3">
      <text>The 70–day time period under paragraph (1) of this subsection does not include:</text>
      <level label="i">
        <text>the month of August; or</text>
      </level>
      <level label="ii">
        <text>December 20 through January 3.</text>
      </level>
    </level>
  </level>
  <level label="c">
    <level label="1">
      <text>Each office to which the county planning board refers a preliminary subdivision plan shall return to the county planning board one copy of the plan and any comments noted on it within 30 days after the referral.</text>
    </level>
    <level label="2">
      <text>If an office does not reply in accordance with paragraph (1) of this subsection, the plan shall be considered to be approved by the office.</text>
    </level>
  </level>
  <level label="d">
    <text>An applicant may consent to an extension not greater than 70 days.</text>