§ 12–605

Statutes in effect as of October 1, 2026.

Md. Code Ann., Pub. Safety § 12-605 (2026)
Title 12. Building and Material Codes; Other Safety Provisions
Subtitle 6. Electrical Code

§ 12–605Copy Citation

(a)
Before a utility authorizes electrical current to be turned on for a premise or structure, the utility must receive a cut–in certificate from a certified nongovernmental electrical inspector or governmental unit that is qualified to issue electrical inspection certificates.
(b)
Within 15 days after completion, each electrical installation shall be certified by a certified nongovernmental electrical inspector or a governmental unit that is qualified to issue electrical inspection certificates.