<?xml version='1.0' encoding='utf-8'?>
<section article="gpu" article_name="Public Utilities" number="23-201" title_number="23" title_name="Water, Sewers, and Drainage" subtitle_number="2" subtitle_name="Subdivision Lines and Service Connections">
  <level label="a">
    <level label="1">
      <text>In this section the following words have the meanings indicated.</text>
    </level>
    <level label="2">
      <text>“Authorization for service” means an application by a property owner or developer to the Commission for water or sewer service that requires the construction of subdivision lines.</text>
    </level>
    <level label="3">
      <text>“Development” means a project for the construction of:</text>
      <level label="i">
        <text>two or more residential dwelling units; or</text>
      </level>
      <level label="ii">
        <text>a commercial or industrial structure.</text>
      </level>
    </level>
    <level label="4">
      <text>“Health hazard” means an owner–occupied residential property with a failing well or septic system as certified by the State or a local health department.</text>
    </level>
    <level label="5">
      <text>“Payment security” means security to guarantee payment to the utility contractor, subcontractors, and suppliers that provide labor, materials, or construction equipment for the construction of subdivision lines.</text>
    </level>
    <level label="6">
      <text>“Performance security” means security to guarantee completion of the construction of subdivision lines.</text>
    </level>
    <level label="7">
      <level label="i">
        <text>“Subdivision lines” means the water and sewer pipelines or facilities necessary to provide service to a development, including service connections to individual lots or properties in a development.</text>
      </level>
      <level label="ii">
        <text>“Subdivision lines” does not include pipelines or facilities that constitute major projects as defined in § 23–301 of this title.</text>
      </level>
    </level>
  </level>
  <level label="b">
    <level label="1">
      <text>Subject to paragraph (2) of this subsection, this section does not apply to:</text>
      <level label="i">
        <text>authorizations for service for which:</text>
        <level label="1">
          <text>application was made with the Commission on or before June 30, 1999; and</text>
        </level>
        <level label="2">
          <text>the Commission entered into a contract for construction of subdivision lines with notice to proceed issued by the Commission to its contractor on or before June 30, 2001; or</text>
        </level>
      </level>
      <level label="ii">
        <text>authorizations for service for the relief of health hazards.</text>
      </level>
    </level>
    <level label="2">
      <text>Each part of a multipart authorization for service shall be considered a separate authorization under paragraph (1) of this subsection.</text>
    </level>
  </level>
  <level label="c">
    <text>Notwithstanding any other provision of law and except as provided in subsection (b) of this section, the owner or developer of a development in the sanitary district shall construct all subdivision lines for the development at the expense of the owner or developer.</text>
  </level>
  <level label="d">
    <text>Before constructing subdivision lines, the owner or developer of a development shall enter into an agreement with the Commission that:</text>
    <level label="1">
      <text>requires the subdivision lines to be constructed under plans and specifications submitted to and approved by the Commission;</text>
    </level>
    <level label="2">
      <text>requires the owner or developer to comply with all applicable laws and requirements for the construction of the subdivision lines;</text>
    </level>
    <level label="3">
      <text>provides for the inspection of the subdivision lines by the Commission before the line is placed in service;</text>
    </level>
    <level label="4">
      <text>requires the property owner or developer to provide:</text>
      <level label="i">
        <text>performance security payable to the Commission in an amount acceptable to the Commission, taking into account potential cost escalation; and</text>
      </level>
      <level label="ii">
        <text>payment security payable to the Commission in an amount equal to the amount of the performance security; and</text>
      </level>
    </level>
    <level label="5">
      <text>provides that before the subdivision lines are placed in service, the property owner or developer shall provide the Commission with a release of liens, on a form acceptable to the Commission, signed by the utility contractor and notarized, stating that the utility contractor, subcontractors, and suppliers have been paid.</text>
    </level>
  </level>
  <level label="e">
    <text>Acceptable forms of performance security and payment security under subsection (d) of this section are:</text>
    <level label="1">
      <text>a certified check;</text>
    </level>
    <level label="2">
      <text>a cash deposit;</text>
    </level>
    <level label="3">
      <text>a certificate of deposit;</text>
    </level>
    <level label="4">
      <text>an irrevocable letter of credit from a financial institution acceptable to the Commission and in a form acceptable to the Commission;</text>
    </level>
    <level label="5">
      <text>a bond executed by a surety company authorized to do business in the State; or</text>
    </level>
    <level label="6">
      <text>any other form of security acceptable to the Commission.</text>
    </level>
  </level>
  <level label="f">
    <level label="1">
      <level label="i">
        <text>A utility contractor, subcontractor, or supplier providing labor, materials, or equipment for the construction of the subdivision lines that has not been paid may file a claim against the payment security within 180 days after completion of construction of the subdivision lines under the procedure required in the payment security.</text>
      </level>
      <level label="ii">
        <text>If a procedure is not specified in the payment security, the procedure shall be as established by regulations adopted by the Commission.</text>
      </level>
    </level>
    <level label="2">
      <text>The Commission may not release or reduce the amount of the payment security until:</text>
      <level label="i">
        <text>all claimants have been paid; or</text>
      </level>
      <level label="ii">
        <text>180 days have passed since completion of construction and no claims have been made.</text>
      </level>
    </level>
  </level>
</section>