<?xml version='1.0' encoding='utf-8'?>
<section article="gpu" article_name="Public Utilities" number="23-309" title_number="23" title_name="Water, Sewers, and Drainage" subtitle_number="3" subtitle_name="Capital Improvements Program">
  <level label="a">
    <text>If the Commission becomes legally liable to a third party as a direct result of a modification of a previous approval of a major project by Montgomery County or Prince George’s County, the county directing the change is responsible for the liability that results from the change.</text>
  </level>
  <level label="b">
    <text>The County Executive or County Council of Montgomery County or the County Executive of Prince George’s County shall settle or release a claim for liability under subsection (a) of this section by:</text>
    <level label="1">
      <text>negotiating with the claimant; or</text>
    </level>
    <level label="2">
      <text>paying the final judgment of a court award.</text>
    </level>
  </level>
  <level label="c">
    <text>In litigation resulting from a claim for liability under subsection (a) of this section, the County Executive or County Council of Montgomery County and the County Executive of Prince George’s County may:</text>
    <level label="1">
      <text>intervene in a court proceeding before judgment; and</text>
    </level>
    <level label="2">
      <text>interpose defenses available to the county or the Commission.</text>
    </level>
  </level>