# Public Utilities (GPU)

## Title 23. Water, Sewers, and Drainage

### Subtitle 3. Capital Improvements Program

#### Section 23-313

(a) The Commission shall submit a final report, including construction cost figures, on completed major projects to the county executive and county council of Montgomery County or Prince George's County.

(b)

  (1) When the Commission submits a Program under Sec. 23-304 of this subtitle, the Commission shall include a status report of all approved major projects that have not been completed as of the date that the Program is submitted.

  (2) The report shall:

    (i) identify the major project;

    (ii) specify the dates of approval of the major project;

    (iii) indicate the current status of the major project, including an estimate of the date of completion of construction;

    (iv) indicate if the major project is the subject of a material change and any amendment that is required under Sec. 23-312 of this subtitle; and

    (v) for an approved major project in Montgomery County, indicate a change in the last estimated construction costs and a modification in location, size, and length of a construction item.

---

Md. Code Ann., Pub. Util. (as displayed at mgaleg.maryland.gov, October 16, 2026)