    <text>A decision and order of the Commission in a contested proceeding shall:</text>
    <level label="1">
      <text>be based on consideration of the record;</text>
    </level>
    <level label="2">
      <text>be in writing;</text>
    </level>
    <level label="3">
      <text>state the grounds for the conclusions of the Commission; and</text>
    </level>
    <level label="4">
      <text>in the case of a complaint proceeding between two public service companies, be issued within 180 days after the close of the record.</text>
    </level>
  </level>
  <level label="b">
    <text>An order of the Commission shall take effect within a reasonable time that the Commission prescribes, and shall continue in force according to the terms of the order unless vacated, suspended, modified, or superseded by further order of the Commission or by a court of competent jurisdiction.</text>
  </level>
  <level label="c">
    <level label="1">
      <text>A person served with an order of the Commission shall promptly notify the Commission in writing of receipt of service.</text>
    </level>
    <level label="2">
      <text>For notification by a corporation under paragraph (1) of this subsection, a person authorized to accept service for the corporation shall sign the notice.</text>
    </level>
    <level label="3">
      <text>The Commission may require in an order that notice be provided to the Commission:</text>
      <level label="i">
        <text>within the time specified in the order;</text>
      </level>
      <level label="ii">
        <text>in the same manner as notice provided in paragraph (1) of this subsection; and</text>
      </level>
      <level label="iii">
        <text>describing if, and to what extent, the order is accepted and will be obeyed.</text>
      </level>
    </level>
  </level>
  <level label="d">
    <level label="1">
      <text>An order of a panel constituted under § 3–104(a) of this subtitle is final.</text>
    </level>
    <level label="2">
      <level label="i">
        <text>A proposed order of a commissioner or public utility law judge under § 3–104(d) of this subtitle becomes final unless a party to the proceeding notes an appeal with the Commission within the time period for appeal designated in the proposed order.</text>
      </level>
      <level label="ii">
        <text>The time period for appeal designated in the proposed order is 30 days unless the order specifies a shorter period of at least 7 days.</text>
      </level>
    </level>
    <level label="3">
      <text>On appeal, the Commission promptly shall:</text>
      <level label="i">
        <text>consider the matter on the record before the commissioner or public utility law judge;</text>
      </level>
      <level label="ii">
        <text>conduct any further proceedings that it considers necessary including requiring the filing of briefs and the holding of oral argument; and</text>
      </level>
      <level label="iii">
        <text>issue a final order.</text>
      </level>
    </level>
  </level>
  <level label="e">
    <text>Notwithstanding the Administrative Procedure Act, unless a provision of this article specifically requires the Commission to act through regulation, the Commission may implement any provision of this article by either order or regulation as the Commission deems necessary and proper.</text>