<section article="gpu" article_name="Public Utilities" number="7-1209" title_number="7" title_name="Gas, Electric, and Water Companies" subtitle_number="12" subtitle_name="Energy Solicitation and Procurement">
  <level label="a">
    <level label="1">
      <text>Except as provided in paragraph (2) of this subsection and subject to paragraph (3) of this subsection, the Commission may approve up to 10 proposals to be eligible to undergo the expedited certificate of public convenience and necessity process under § 7–207.4 of this title.</text>
    </level>
    <level label="2">
      <text>The Commission may approve more than 10 proposals to be eligible to undergo the expedited certificate of public convenience and necessity process under § 7–207.4 of this title only if the Commission determines that:</text>
      <level label="i">
        <text>the Commission has sufficient resources to complete that number of expedited reviews of applications for a certificate of public convenience and necessity under § 7–207.4 of this title; and</text>
      </level>
      <level label="ii">
        <text>the number of expedited reviews of applications for a certificate of public convenience and necessity under § 7–207.4 of this title is in the public interest.</text>
      </level>
    </level>
    <level label="3">
      <text>If not more than 10 projects respond to a solicitation issued under § 7–1206 of this subtitle, the Commission shall approve, subject to § 7–1208(d)(2) of this subtitle, all projects that apply for the solicitation.</text>
    </level>
  </level>
  <level label="b">
    <level label="1">
      <text>For the purpose of this subsection, a transmission energy storage device shall be considered a non–emissions–emitting project.</text>
    </level>
    <level label="2">
      <text>Subject to paragraph (3) of this subsection, the Commission shall approve 4 non–emissions–emitting projects to every 1 emissions–emitting project.</text>
    </level>
    <level label="3">
      <text>The Commission may waive the requirement under paragraph (2) of this subsection if a sufficient number of applications for projects that meet the requirement are not received.</text>
    </level>
  </level>
  <level label="c">
    <level label="1">
      <text>In determining which proposals to approve, the Commission shall prioritize dispatchable energy generation projects over large capacity energy resources.</text>
    </level>
    <level label="2">
      <text>In addition to the prioritization in paragraph (1) of this subsection, if the Commission receives more than 10 proposals or determines that more than 10 proposals may be approved under § 7–1208 of this subtitle, the Commission shall base the approvals on:</text>
      <level label="i">
        <text>which projects will provide the highest capacity value to the State;</text>
      </level>
      <level label="ii">
        <text>the timeliness of a project to begin construction;</text>
      </level>
      <level label="iii">
        <text>the timeliness of a project to begin operation; and</text>
      </level>
      <level label="iv">
        <text>which projects have the lowest emissions intensity.</text>
      </level>
    </level>
  </level>
  <level label="d">
    <text>The Commission shall determine when the proceedings for a certificate of public convenience and necessity under § 7–207.4 of this title will begin for a proposal approved under this part.</text>
  </level>
  <level label="e">
    <text>The Commission may contract for the services of independent consultants and experts in evaluating and comparing whether a proposal shall be approved to be eligible to undergo an expedited certificate of public convenience and necessity process under § 7–207.4 of this title.</text>
  </level>
  <level label="f">
    <text>A proposal that is not approved to be eligible to undergo an expedited certificate of public convenience and necessity process under § 7–207.4 of this title may apply for a certificate of public convenience and necessity under § 7–207 of this title.</text>
  </level>
</section>