<?xml version='1.0' encoding='utf-8'?>
<subtitle article="gpu" title_number="7" subtitle_number="13" title_name="Gas, Electric, and Water Companies">
  <section article="gpu" article_name="Public Utilities" number="7-1301" title_number="7" title_name="Gas, Electric, and Water Companies" subtitle_number="13">
    <level label="a">
      <text>In this subtitle the following words have the meanings indicated.</text>
    </level>
    <level label="b">
      <text>“Director” means the Director of the Strategic Energy Planning Office.</text>
    </level>
    <level label="c">
      <text>“Office” means the Strategic Energy Planning Office.</text>
    </level>
    <level label="d">
      <text>“PJM region” has the meaning stated in § 7–701 of this title.</text>
    </level>
    <level label="e">
      <text>“Risk Report” means the Comprehensive Wholesale Energy Markets and Bulk Power System Risk Report developed under § 7–1303 of this subtitle.</text>
    </level>
  </section>
  <section article="gpu" article_name="Public Utilities" number="7-1302" title_number="7" title_name="Gas, Electric, and Water Companies" subtitle_number="13">
    <level label="a">
      <text>There is a Strategic Energy Planning Office.</text>
    </level>
    <level label="b">
      <level label="1">
        <text>The head of the Office is the Director.</text>
      </level>
      <level label="2">
        <level label="i">
          <text>The Director shall be appointed by the Governor with the advice and consent of the Senate.</text>
        </level>
        <level label="ii">
          <level label="1">
            <text>The term of the Director is 5 years and begins on July 1.</text>
          </level>
          <level label="2">
            <text>The first term of the Director shall begin on July 1, 2026.</text>
          </level>
        </level>
        <level label="iii">
          <text>At the end of a term, the Director continues to serve until a successor is appointed and qualifies.</text>
        </level>
        <level label="iv">
          <text>A Director who is appointed after a term has begun serves for the rest of the term and until a successor is appointed and qualifies.</text>
        </level>
        <level label="v">
          <text>A Director may serve more than one term.</text>
        </level>
      </level>
      <level label="3">
        <text>The Governor may remove the Director for incompetence or misconduct in accordance with § 3–307 of the State Government Article.</text>
      </level>
      <level label="4">
        <text>The Director is entitled to a salary as provided in the State budget.</text>
      </level>
    </level>
    <level label="c">
      <level label="1">
        <text>The Office shall have the staff provided for in the State budget.</text>
      </level>
      <level label="2">
        <text>The Office may hire private consultants if necessary to carry out the requirements of this subtitle.</text>
      </level>
    </level>
    <level label="d">
      <text>In order to carry out the requirements of this subtitle, the Office shall collaborate with:</text>
      <level label="1">
        <text>the Maryland Energy Administration;</text>
      </level>
      <level label="2">
        <text>the Commission;</text>
      </level>
      <level label="3">
        <text>the Power Plant Research Program;</text>
      </level>
      <level label="4">
        <text>the Maryland Clean Energy Center; and</text>
      </level>
      <level label="5">
        <text>the Department of the Environment.</text>
      </level>
    </level>
    <level label="e">
      <text>The Office shall coordinate with the Commission to establish procedures and rules to obtain information from electric companies and gas companies necessary to accomplish the Office’s duties under this subtitle.</text>
    </level>
  </section>
  <section article="gpu" article_name="Public Utilities" number="7-1303" title_number="7" title_name="Gas, Electric, and Water Companies" subtitle_number="13">
    <level label="a">
      <level label="1">
        <text>Every 3 years, the Office shall develop a Comprehensive Wholesale Energy Markets and Bulk Power System Risk Report.</text>
      </level>
      <level label="2">
        <text>The purpose of the Risk Report is to:</text>
        <level label="i">
          <text>assess wholesale energy market financial, resource adequacy, and reliability risks associated with serving the State’s long–term energy needs; and</text>
        </level>
        <level label="ii">
          <text>identify any necessary cost–effective solutions that ensure electric system reliability while meeting the State’s energy policy goals.</text>
        </level>
      </level>
      <level label="3">
        <text>The solutions identified in the Risk Report shall seek to:</text>
        <level label="i">
          <text>minimize the growth of the cost of electricity or lower the cost of electricity; and</text>
        </level>
        <level label="ii">
          <text>minimize energy resource reliability risks.</text>
        </level>
      </level>
    </level>
    <level label="b">
      <level label="1">
        <text>The Risk Report shall include energy and demand forecasts that contain:</text>
        <level label="i">
          <text>reasonable, 20–year projections for electricity load and energy demands for:</text>
          <level label="1">
            <text>transmission zones; and</text>
          </level>
          <level label="2">
            <text>electric service territories; and</text>
          </level>
        </level>
        <level label="ii">
          <text>projections for meeting State energy needs and clean energy goals and load forecasts in the PJM region, including:</text>
          <level label="1">
            <text>low, average, and high projections of energy demand based on State policies and other reasonable assumptions that impact the provision of electricity in the State; and</text>
          </level>
          <level label="2">
            <text>other projections as necessary.</text>
          </level>
        </level>
      </level>
      <level label="2">
        <text>In collecting the data for the forecasts under paragraph (1) of this subsection, the Office should, but is not required to, use:</text>
        <level label="i">
          <text>historical and projected information from electric companies;</text>
        </level>
        <level label="ii">
          <text>load forecasts for the PJM region;</text>
        </level>
        <level label="iii">
          <text>appropriate econometric data for the State; and</text>
        </level>
        <level label="iv">
          <text>any other information the Office considers appropriate.</text>
        </level>
      </level>
    </level>
    <level label="c">
      <level label="1">
        <text>The Office shall examine different wholesale energy market and bulk power system scenarios to serve the forecasts under subsection (b) of this section.</text>
      </level>
      <level label="2">
        <text>Each scenario examined shall:</text>
        <level label="i">
          <text>identify the resulting wholesale energy market and bulk power system financial and resource adequacy impacts of serving the forecasts with the existing electric system, known additions to the electric system, and electric system resource retirements; and</text>
        </level>
        <level label="ii">
          <text>identify resource and demand–side management solutions that may resolve potential resource adequacy issues at the least cost.</text>
        </level>
      </level>
      <level label="3">
        <text>For a subset of scenarios that are primarily relied on within the Risk Report, the Office shall, in addition to the requirements of paragraph (2) of this subsection:</text>
        <level label="i">
          <text>identify the resulting wholesale market and bulk power system reliability impacts of serving the forecasts with the existing electric system, known additions to the electric system, and electric system resource retirements; and</text>
        </level>
        <level label="ii">
          <text>identify resource and demand–side management solutions that may resolve potential reliability constraints at the least cost.</text>
        </level>
      </level>
      <level label="4">
        <text>Each scenario shall also examine:</text>
        <level label="i">
          <text>different energy resource mixes to meet the State’s energy needs, including the use of demand–side management;</text>
        </level>
        <level label="ii">
          <text>different approaches for meeting the State’s clean energy goals;</text>
        </level>
        <level label="iii">
          <text>improvements to existing energy resources as opposed to the deployment of new energy resources;</text>
        </level>
        <level label="iv">
          <text>balancing the use of electricity imported from outside the State with the development of new energy resources in the State;</text>
        </level>
        <level label="v">
          <text>financial and other risks associated with retiring energy generation resources;</text>
        </level>
        <level label="vi">
          <text>directional assessing of cost risks to ratepayers; and</text>
        </level>
        <level label="vii">
          <text>impacts to the wholesale energy market and bulk power system in meeting the State’s policy goals related to electricity.</text>
        </level>
      </level>
      <level label="5">
        <text>The scenarios required under paragraph (1) of this subsection shall include:</text>
        <level label="i">
          <text>at least one scenario that examines the achievement of the State’s clean energy goals;</text>
        </level>
        <level label="ii">
          <text>at least one scenario that examines a least–cost approach to meeting the State’s projected energy needs; and</text>
        </level>
        <level label="iii">
          <text>at least one scenario that assumes no changes in State energy and climate policies.</text>
        </level>
      </level>
    </level>
    <level label="d">
      <level label="1">
        <text>The Risk Report shall:</text>
        <level label="i">
          <text>be informed by the forecasts and scenarios required under this section;</text>
        </level>
        <level label="ii">
          <text>provide information on the risks associated with serving the identified energy forecasts and achievement of the State’s clean energy goals;</text>
        </level>
        <level label="iii">
          <text>discuss the potential financial impacts of the different scenarios examined under subsection (c) of this section on the State and ratepayers;</text>
        </level>
        <level label="iv">
          <text>identify the financial, resource adequacy, and reliability risks of the wholesale energy markets and bulk power system on ratepayers; and</text>
        </level>
        <level label="v">
          <text>specify the inputs and assumptions used in developing the Risk Report.</text>
        </level>
      </level>
      <level label="2">
        <level label="i">
          <text>The Risk Report shall also include any recommendations of the Office regarding short– and long–term solutions to minimize wholesale energy market and bulk power system financial, resource adequacy, and reliability risks, including strategies to implement any recommendations.</text>
        </level>
        <level label="ii">
          <text>The recommendations may include:</text>
          <level label="1">
            <text>energy generation, transmission, or distribution resource deployment or demand–side management solutions;</text>
          </level>
          <level label="2">
            <text>program development, including:</text>
          </level>
          <level label="A">
            <text>altering or adding to existing programs; or</text>
          </level>
          <level label="B">
            <text>proposing new programs;</text>
          </level>
          <level label="3">
            <text>statutory or regulatory changes; and</text>
          </level>
          <level label="4">
            <text>recommendations to the General Assembly to implement short– and long–term recommendations identified in subparagraph (i) of this paragraph, including:</text>
          </level>
          <level label="A">
            <text>utilizing existing or creating new market structures;</text>
          </level>
          <level label="B">
            <text>utilizing existing or creating new State programs;</text>
          </level>
          <level label="C">
            <text>State financing options, including State procurement and multistate procurement;</text>
          </level>
          <level label="D">
            <text>electric company procurement or programs;</text>
          </level>
          <level label="E">
            <text>examining the mix of in–State generation versus relying on imports and demand–side management; and</text>
          </level>
          <level label="F">
            <text>any other recommendations that the Office considers appropriate.</text>
          </level>
        </level>
        <level label="iii">
          <text>If the Office determines that the identified risks are acceptable or that existing market designs, processes, or policies will adequately address the risks identified in the Risk Report, the Office may recommend that no actions be taken.</text>
        </level>
        <level label="iv">
          <text>The Office shall support the recommendations by analyses that balance affordability, reliability, and greenhouse gas emissions reductions.</text>
        </level>
      </level>
    </level>
  </section>
  <section article="gpu" article_name="Public Utilities" number="7-1304" title_number="7" title_name="Gas, Electric, and Water Companies" subtitle_number="13">
    <level label="a">
      <level label="1">
        <text>The Office shall:</text>
        <level label="i">
          <text>develop and maintain the tools and resources necessary to complete the analyses required under this subtitle;</text>
        </level>
        <level label="ii">
          <text>coordinate with PJM Interconnection, LLC to develop and maintain the tools necessary to complete the analyses required under this subtitle;</text>
        </level>
        <level label="iii">
          <text>have the ability to conduct cost–benefit analyses of energy generation resources in wholesale energy markets; and</text>
        </level>
        <level label="iv">
          <text>provide an opportunity for stakeholder feedback on any reports developed by the Office.</text>
        </level>
      </level>
      <level label="2">
        <level label="i">
          <text>For the Risk Report required under § 7–1303 of this subtitle, the Office shall conduct a stakeholder process to solicit feedback regarding the development of data inputs that will inform the forecasts and scenarios for developing the Risk Report.</text>
        </level>
        <level label="ii">
          <text>The Office is not required to utilize the feedback received from the stakeholder process conducted under paragraph (1)(ii) of this subsection, but shall provide documentation of the stakeholder process in the Risk Report.</text>
        </level>
      </level>
      <level label="3">
        <level label="i">
          <text>In addition to the public hearing required in § 7–1306 of this subtitle, after the publication of the Risk Report or any update to the report, the Office shall conduct a stakeholder process to develop a report that assesses strategies to address the identified risks and recommendations in the Risk Report.</text>
        </level>
        <level label="ii">
          <text>When assessing strategies under subparagraph (i) of this paragraph, there shall be consideration of:</text>
          <level label="1">
            <text>new or existing programs;</text>
          </level>
          <level label="2">
            <text>leveraging technology enhancements;</text>
          </level>
          <level label="3">
            <text>revised regulatory structures;</text>
          </level>
          <level label="4">
            <text>State coordination of federal solutions;</text>
          </level>
          <level label="5">
            <text>utilizing market mechanisms; and</text>
          </level>
          <level label="6">
            <text>any other factors considered appropriate.</text>
          </level>
        </level>
      </level>
    </level>
    <level label="b">
      <text>The Office, in consultation with the Commission and the Maryland Energy Administration, shall complete energy modeling for the Risk Report.</text>
    </level>
    <level label="c">
      <level label="1">
        <text>On or before November 1 each year, the Senate Committee on Education, Energy, and the Environment and the House Environment and Transportation Committee may jointly request the Office to assess up to five policy scenarios.</text>
      </level>
      <level label="2">
        <text>Not later than 1 year after the date the Office receives a request under paragraph (1) of this subsection, the Office shall submit a report of the results of the requested policy scenarios to the Senate Committee on Education, Energy, and the Environment and the House Environment and Transportation Committee in accordance with § 2–1257 of the State Government Article.</text>
      </level>
    </level>
  </section>
  <section article="gpu" article_name="Public Utilities" number="7-1305" title_number="7" title_name="Gas, Electric, and Water Companies" subtitle_number="13">
    <level label="a">
      <text>On or before September 1, 2028, and every 3 years thereafter, the Office shall submit the Risk Report to the Governor and, in accordance with § 2–1257 of the State Government Article, the General Assembly.</text>
    </level>
    <level label="b">
      <level label="1">
        <text>The Office may submit to the Governor and, in accordance with § 2–1257 of the State Government Article, the General Assembly any additional updates to the Risk Report at any time.</text>
      </level>
      <level label="2">
        <text>The updates shall include:</text>
        <level label="i">
          <text>the status of and any changes to the forecasts and scenarios developed under § 7–1303 of this subtitle;</text>
        </level>
        <level label="ii">
          <text>information on any new forecasts and scenarios the Office has developed; and</text>
        </level>
        <level label="iii">
          <text>any other changes to the information or recommendations contained in the report or any preceding updates to the report.</text>
        </level>
      </level>
    </level>
    <level label="c">
      <text>On or before September 1, 2028, and every 3 years thereafter, the Office shall submit to the Governor and, in accordance with § 2–1257 of the State Government Article, the General Assembly the report required under § 7–1304(a)(3) of this subtitle.</text>
    </level>
  </section>
  <section article="gpu" article_name="Public Utilities" number="7-1306" title_number="7" title_name="Gas, Electric, and Water Companies" subtitle_number="13">
    <level label="a">
      <text>Beginning on or before September 1, 2030, and at least once every 3 years thereafter, after receiving a request by the Office, the Commission, in consultation with the Office, shall conduct a public proceeding to assess the results and recommendations contained in the Risk Report and any updates to the report.</text>
    </level>
    <level label="b">
      <text>The public proceeding shall include a public hearing and an opportunity for public comment on the recommendations of the Risk Report and any updates to the report.</text>
    </level>
    <level label="c">
      <text>The Office shall consider any feedback received through the public proceeding and determine if any further changes to the Risk Report are necessary.</text>
    </level>
    <level label="d">
      <text>The Commission shall consider any feedback received through the public proceeding and determine whether any action under its jurisdiction is warranted.</text>
    </level>
  </section>
  <section article="gpu" article_name="Public Utilities" number="7-1307" title_number="7" title_name="Gas, Electric, and Water Companies" subtitle_number="13">
    <level label="a">
      <text>This section does not apply to:</text>
      <level label="1">
        <text>the report required under § 7–1304(a)(3) of this subtitle; and</text>
      </level>
      <level label="2">
        <text>the report required under § 7–1304(c)(2) of this subtitle.</text>
      </level>
    </level>
    <level label="b">
      <text>Each report required under this subtitle shall include documentation of stakeholder engagement and any feedback received related to the development of that report.</text>
    </level>
  </section>
</subtitle>