<?xml version='1.0' encoding='utf-8'?>
<section article="gpu" article_name="Public Utilities" number="7-202" title_number="7" title_name="Gas, Electric, and Water Companies" subtitle_number="2" subtitle_name="Electric Generation Facility Planning">
  <level label="a">
    <text>If the Commission determines that a site is needed, the Commission, on its own motion, may request the Secretary of Natural Resources to purchase a power plant site as provided in Title 3, Subtitle 3 of the Natural Resources Article.</text>
  </level>
  <level label="b">
    <text>In determining whether a need exists for the State to purchase a power plant site, the Commission shall consider:</text>
    <level label="1">
      <text>the suitability of sites owned by an electric company, both within and outside the State;</text>
    </level>
    <level label="2">
      <text>the anticipated growth of electric power demand and the alternative means and locations for meeting that demand, both within and outside the State; and</text>
    </level>
    <level label="3">
      <text>any other factors required by law.</text>
    </level>
  </level>
  <level label="c">
    <level label="1">
      <text>The Commission may determine that a power plant site is needed only after the Commission gives public notice and holds a public hearing.</text>
    </level>
    <level label="2">
      <text>The hearing shall be held in the legislative district in which the site under consideration is located.</text>
    </level>
  </level>
</section>