<?xml version='1.0' encoding='utf-8'?>
<section article="gpu" article_name="Public Utilities" number="7-205" title_number="7" title_name="Gas, Electric, and Water Companies" subtitle_number="2" subtitle_name="Electric Generation Facility Planning">
  <level label="a">
    <level label="1">
      <text>In this section, “modification” means a physical alteration of, replacement of, or other change to the facilities at a power plant, or a change in the fuel used by the plant, that could result in a change of the air emissions from the plant or from a generating unit of the plant.</text>
    </level>
    <level label="2">
      <text>“Modification” does not include:</text>
      <level label="i">
        <text>routine maintenance or repairs of the facilities of a power plant; or</text>
      </level>
      <level label="ii">
        <text>a change that the Commission determines will not result in an increase in air emissions from the plant or from a generating unit of the plant.</text>
      </level>
    </level>
  </level>
  <level label="b">
    <text>Subject to subsections (c) through (e) of this section, a person may not commence a modification without the prior approval of the Commission under this title.</text>
  </level>
  <level label="c">
    <level label="1">
      <text>Unless the Commission orders otherwise, an application for a modification to a power plant shall be filed with the Commission at least 180 days before the date on which the modification is to commence.</text>
    </level>
    <level label="2">
      <text>The applicant for the modification shall submit to the Commission and to the Department of the Environment all information relating to the modification, including:</text>
      <level label="i">
        <text>detailed plans and specifications; and</text>
      </level>
      <level label="ii">
        <text>the impact of the modification on air quality.</text>
      </level>
    </level>
  </level>
  <level label="d">
    <text>The Commission shall render its decision within 150 days after the day the application is filed.</text>
  </level>
  <level label="e">
    <text>Notwithstanding the provisions of this section, a modification to a power plant that involves the short-term inability to obtain the type of fuel normally used by the plant is subject to Title 2, Subtitle 5 of the Environment Article.</text>
  </level>
</section>