<section article="gpu" article_name="Public Utilities" number="7-207.4" title_number="7" title_name="Gas, Electric, and Water Companies" subtitle_number="2" subtitle_name="Electric Generation Facility Planning">
  <level label="a">
    <level label="1">
      <text>In this section the following words have the meanings indicated.</text>
    </level>
    <level label="2">
      <text>“Distributed generation certificate of public convenience and necessity” or “DGCPCN” means a certificate issued by the Commission under this section that authorizes the construction and operation of a distributed solar energy generating system.</text>
    </level>
    <level label="3">
      <text>“Distributed solar energy generating system” means a community solar energy generating system, as defined in § 7–306.2 of this title, that:</text>
      <level label="i">
        <text>would be required to obtain a certificate of public convenience and necessity under § 7–207 of this subtitle if the system does not obtain a DGCPCN under this section;</text>
      </level>
      <level label="ii">
        <text>has a capacity to produce more than 2 megawatts but not more than 5 megawatts of alternating current as measured by the alternating current rating of the system’s inverter; and</text>
      </level>
      <level label="iii">
        <text>is not located within a municipal corporation.</text>
      </level>
    </level>
    <level label="4">
      <text>“Forest” has the meaning stated in § 5–1601 of the Natural Resources Article.</text>
    </level>
    <level label="5">
      <text>“Power Plant Research Program” means the program within the Department of Natural Resources under Title 3, Subtitle 3 of the Natural Resources Article.</text>
    </level>
    <level label="6">
      <text>“Standard licensing conditions” means the predetermined licensing conditions adopted by the Commission under this section for the construction and operation of a distributed solar energy generating system that has been issued a DGCPCN under this section.</text>
    </level>
    <level label="7">
      <text>“Standard siting and design requirements” means the predetermined objective requirements adopted by the Commission under this section for the siting and design of a distributed solar energy generating system that has been issued a DGCPCN under this section.</text>
    </level>
  </level>
  <level label="b">
    <level label="1">
      <text>On or before July 1, 2026, the Power Plant Research Program, after giving notice and opportunity for public comment, shall develop and submit to the Commission proposed standard siting and design requirements and proposed standard licensing conditions for the issuance of a DGCPCN.</text>
    </level>
    <level label="2">
      <text>In developing the proposed standard siting and design requirements and the proposed standard licensing conditions, the Power Plant Research Program shall:</text>
      <level label="i">
        <text>consider achievement of the State’s climate and renewable energy commitments;</text>
      </level>
      <level label="ii">
        <text>consider reasonable setbacks and landscape screening requirements;</text>
      </level>
      <level label="iii">
        <text>consider environmental preservation, including prohibitions on forest clearance except where necessary to:</text>
        <level label="1">
          <text>reduce solar panel shading near the perimeter of the project site;</text>
        </level>
        <level label="2">
          <text>facilitate interconnection infrastructure; and</text>
        </level>
        <level label="3">
          <text>ensure adequate site access;</text>
        </level>
      </level>
      <level label="iv">
        <text>consider stormwater management, erosion and sediment control, and site stabilization, accounting for:</text>
        <level label="1">
          <text>the effects on runoff from solar panels and associated equipment;</text>
        </level>
        <level label="2">
          <text>the effects of soil characteristics and compaction on runoff; and</text>
        </level>
        <level label="3">
          <text>the effects of the ground cover under and between the solar panels on runoff;</text>
        </level>
      </level>
      <level label="v">
        <text>consider minimization and mitigation of the effects of a distributed solar energy generating system on historic sites;</text>
      </level>
      <level label="vi">
        <text>consider public safety;</text>
      </level>
      <level label="vii">
        <text>consider industry best practices;</text>
      </level>
      <level label="viii">
        <text>consider ensuring the stability and reliability of the electric system by requiring the applicant to submit a signed interconnection agreement with the electric company before the start of construction;</text>
      </level>
      <level label="ix">
        <text>consider licensing conditions previously adopted by the Commission for solar energy generating systems, including requirements related to decommissioning;</text>
      </level>
      <level label="x">
        <text>ensure the standard siting and design requirements are consistent with § 7–218 of this subtitle; and</text>
      </level>
      <level label="xi">
        <text>consider any other requirements determined necessary by the Power Plant Research Program.</text>
      </level>
    </level>
  </level>
  <level label="c">
    <level label="1">
      <text>Subject to paragraph (2) of this subsection, on or before July 1, 2027, the Commission shall adopt regulations to:</text>
      <level label="i">
        <text>implement standard siting and design requirements and standard licensing conditions for a DGCPCN;</text>
      </level>
      <level label="ii">
        <text>specify the form of the application for a distributed solar energy generating system to receive a DGCPCN and any application fee;</text>
      </level>
      <level label="iii">
        <text>specify the Commission’s procedure for processing an application for a DGCPCN; and</text>
      </level>
      <level label="iv">
        <text>establish the time period within which the Power Plant Research Program must make the determination under subsection (f) of this section.</text>
      </level>
    </level>
    <level label="2">
      <text>The Commission shall:</text>
      <level label="i">
        <text>consider the proposed standard siting and design requirements and the proposed standard licensing conditions developed by the Power Plant Research Program in adopting the regulations under this subsection; and</text>
      </level>
      <level label="ii">
        <text>ensure regulations adopted to implement standard siting and design requirements are consistent with § 7–218 of this subtitle.</text>
      </level>
    </level>
    <level label="3">
      <level label="i">
        <text>The Commission, in consultation with the Power Plant Research Program, may periodically solicit public comments regarding improvements to the standard siting and design requirements and standard licensing conditions for a DGCPCN.</text>
      </level>
      <level label="ii">
        <text>The process for soliciting public comments under subparagraph (i) of this paragraph shall be the same as the process for soliciting public comment regarding the adoption of a regulation.</text>
      </level>
    </level>
    <level label="4">
      <level label="i">
        <text>The Commission and the Department of Natural Resources may jointly set an application fee for a DGCPCN application at an amount that the Commission and the Department of Natural Resources determine may offset the administrative costs of the DGCPCN approval process that are incurred by the Commission and the Department of Natural Resources.</text>
      </level>
      <level label="ii">
        <text>The administrative costs under subparagraph (i) of this paragraph shall be based on an estimate of the number of DGCPCN applications that will be filed with the Commission each year.</text>
      </level>
    </level>
  </level>
  <level label="d">
    <level label="1">
      <text>A person may not begin construction of a distributed solar energy generating system unless:</text>
      <level label="i">
        <text>a DGCPCN is first obtained from the Commission in accordance with this section; or</text>
      </level>
      <level label="ii">
        <text>a certificate of public convenience and necessity is first obtained from the Commission in accordance with § 7–207 of this subtitle.</text>
      </level>
    </level>
    <level label="2">
      <text>At least 30 days before submitting an application for a DGCPCN to the Commission, the applicant shall submit a copy of the application to the governing body of the county in which the distributed solar energy generating system is proposed to be located.</text>
    </level>
    <level label="3">
      <text>When a person submits an application for a DGCPCN to the Commission, the person shall submit a copy of the application to the Power Plant Research Program.</text>
    </level>
  </level>
  <level label="e">
    <level label="1">
      <text>After receiving an application for a DGCPCN but before a determination is made under subsection (f) of this section, the Commission shall provide an opportunity for public comment and hold a public hearing on an application for a DGCPCN in each county in which any portion of the construction of the distributed solar energy generating system is proposed to be located.</text>
    </level>
    <level label="2">
      <text>The Commission may hold the public hearing virtually rather than in person if the Commission provides a comparable opportunity for public comment and participation in the hearing.</text>
    </level>
  </level>
  <level label="f">
    <level label="1">
      <text>After an application for a DGCPCN is filed with the Commission and within the time period set by the Commission under subsection (c)(1)(iv) of this section, the Power Plant Research Program shall:</text>
      <level label="i">
        <text>determine whether the distributed solar energy generating system satisfies the standard siting and design requirements for the DGCPCN; and</text>
      </level>
      <level label="ii">
        <text>notify the Commission in writing as to the determination made under item (i) of this paragraph, including how an application that is determined not to satisfy the standard siting and design requirements can cure the deficiency.</text>
      </level>
    </level>
    <level label="2">
      <text>In making a determination under paragraph (1) of this subsection, the Power Plant Research Program shall consider public comments received by the Commission.</text>
    </level>
  </level>
  <level label="g">
    <level label="1">
      <text>Within 60 days after the Power Plant Research Program makes its determination under subsection (f)(1) of this section, the Commission shall schedule a hearing to consider the application for a DGCPCN.</text>
    </level>
    <level label="2">
      <level label="i">
        <text>At the hearing under paragraph (1) of this subsection, the Commission shall determine whether the proposed distributed solar energy generating system satisfies the standard siting and design requirements.</text>
      </level>
      <level label="ii">
        <text>The Commission shall issue a DGCPCN to an applicant to construct a proposed distributed solar energy generating system subject to the standard licensing conditions if the Commission determines that the proposed distributed solar energy generating system satisfies the standard siting and design requirements.</text>
      </level>
      <level label="iii">
        <text>The Commission may not issue a DGCPCN to an applicant if the proposed distributed solar energy generating system does not satisfy each of the standard siting and design requirements.</text>
      </level>
    </level>
    <level label="3">
      <text>In making a determination under this subsection, the Commission shall consider public comments received by the Commission under subsection (e) of this section.</text>
    </level>
  </level>
  <level label="h">
    <level label="1">
      <text>A DGCPCN issued by the Commission under this section shall require the person constructing the distributed solar energy generating system to obtain the following permits and approvals from the county, municipal corporation, or soil conservation district in which the system is to be constructed:</text>
      <level label="i">
        <text>site plan approval;</text>
      </level>
      <level label="ii">
        <text>stormwater management plan approval;</text>
      </level>
      <level label="iii">
        <text>erosion and sediment control plan approval;</text>
      </level>
      <level label="iv">
        <text>all applicable building and electrical permits; and</text>
      </level>
      <level label="v">
        <text>any additional local permit required by the standard licensing conditions.</text>
      </level>
    </level>
    <level label="2">
      <text>The provisions of § 7–207(h) of this subtitle shall apply to any permits and approvals required under paragraph (1) of this subsection.</text>
    </level>
  </level>
  <level label="i">
    <text>A DGCPCN issued by the Commission under this section has the same force and effect as a certificate of public convenience and necessity issued under § 7–207 of this subtitle.</text>
  </level>