<section article="gpu" article_name="Public Utilities" number="7-207.5" effective_note="EFFECTIVE UNTIL JUNE 30, 2030 PER CHAPTERS 625 AND 626 OF 2025" title_number="7" title_name="Gas, Electric, and Water Companies" subtitle_number="2" subtitle_name="Electric Generation Facility Planning">
  <level label="a">
    <level label="1">
      <text>In this section the following words have the meanings indicated.</text>
    </level>
    <level label="2">
      <text>“Construction” has the meaning stated in § 7–207 of this subtitle.</text>
    </level>
    <level label="3">
      <level label="i">
        <text>“Dispatchable energy generation project” means a generating station or energy storage device that is part of a proposal approved by the Commission under § 7–1206 of this title.</text>
      </level>
      <level label="ii">
        <text>“Dispatchable energy generation project” includes any associated infrastructure necessary to interconnect the generating station to the electric distribution system.</text>
      </level>
    </level>
    <level label="4">
      <text>“Energy storage device” has the meaning stated in § 7–216 of this subtitle.</text>
    </level>
    <level label="5">
      <text>“Generating station” has the meaning stated in § 7–207 of this subtitle.</text>
    </level>
    <level label="6">
      <text>“Large capacity energy resource” means a generating station that:</text>
      <level label="i">
        <text>on or before January 1, 2025:</text>
        <level label="1">
          <text>has applied to PJM for interconnection approval; or</text>
        </level>
        <level label="2">
          <text>has been approved by PJM for interconnection;</text>
        </level>
      </level>
      <level label="ii">
        <text>has a capacity rating equal to or greater than 20 megawatts after accounting for the effective load carrying capability; and</text>
      </level>
      <level label="iii">
        <text>is part of a proposal approved by the Commission under § 7–1206 of this title.</text>
      </level>
    </level>
    <level label="7">
      <text>“Qualifying project” means a dispatchable energy generation project or large capacity energy resource project that has been approved by the Commission under § 7–1208 of this title.</text>
    </level>
  </level>
  <level label="b">
    <text>This section applies only to an application for a certificate of public convenience and necessity for the construction of a qualifying project.</text>
  </level>
  <level label="c">
    <text>Unless a certificate of public convenience and necessity is first obtained from the Commission in accordance with this section or § 7–207 of this subtitle, a person may not construct a qualifying project.</text>
  </level>
  <level label="d">
    <text>A certificate of public convenience and necessity issued under this section bestows the same rights as a certificate of public convenience and necessity issued under § 7–207 of this subtitle.</text>
  </level>
  <level label="e">
    <text>A person applying for a certificate of public convenience and necessity under this section shall:</text>
    <level label="1">
      <text>at least 45 days before submitting an application under this section, notify the Commission and the Power Plant Research Program; and</text>
    </level>
    <level label="2">
      <text>unless otherwise specified under this section, complete all pre–application requirements before submitting an application.</text>
    </level>
  </level>
  <level label="f">
    <level label="1">
      <text>Except as provided in paragraph (2) of this subsection, the timelines associated with the normal pre–application requirements under § 7–207 of this subtitle, including the requirements under COMAR 20.79.01.04 and COMAR 20.79.01.05, shall be shortened to 45 days for applications submitted under this section.</text>
    </level>
    <level label="2">
      <text>If the proposed location of a qualifying project is in an overburdened community or underserved community, as defined in § 1–701 of the Environment Article, the timeline for the pre–application requirements under COMAR 20.79.01.04 and COMAR 20.79.01.05 shall remain at 90 days.</text>
    </level>
  </level>
  <level label="g">
    <text>Once five applications have been received under this section within a 2–month period, the Commission may delay processing any subsequent applications submitted under this section without impacting the timelines specified in this section.</text>
  </level>
  <level label="h">
    <level label="1">
      <text>The Commission shall:</text>
      <level label="i">
        <text>expedite all proceedings for the review and approval of a certificate of public convenience and necessity for a qualifying project; and</text>
      </level>
      <level label="ii">
        <text>take final action on a certificate of public convenience and necessity for a qualifying project not later than 295 days after the Power Plant Research Program determines that the application is complete in accordance with COMAR 20.79.01.10.</text>
      </level>
    </level>
    <level label="2">
      <text>The Commission may extend the time to take final action on a certificate of public convenience and necessity under this section if an applicant fails to comply with the law, regulatory requirements, or Commission orders associated with obtaining a certificate of public convenience and necessity.</text>
    </level>
    <level label="3">
      <text>Notwithstanding any other law or regulation, in order to meet the required timelines for the issuance of a certificate of public convenience and necessity under this section, the Commission may review and determine whether to approve decommissioning plans for a qualifying project after the certificate of public convenience and necessity has been issued.</text>
    </level>
  </level>
  <level label="i">
    <text>In evaluating an application for a certificate of public convenience and necessity under this section, the Commission may contract for the services of independent consultants and experts.</text>
  </level>
</section>