(a)
A person that submits an application for approval of the construction of a solar energy generating station in accordance with § 7–207, § 7–207.1, or § 7–207.4 of this subtitle shall:
(1)
request, within 90 days before beginning construction, the Commissioner of Labor and Industry to determine the prevailing wage rate for each classification of worker required to perform work on the project;
(2)
require that any contractor or subcontractor on the project pay its employees not less than the prevailing wage rate as determined by the Commissioner of Labor and Industry under item (1) of this subsection and Title 17, Subtitle 2 of the State Finance and Procurement Article; and
(3)
include in the application an attestation that the person shall comply with the provisions of this section and any additional requirements imposed by the Commissioner of Labor and Industry.
(b)
In accordance with Title 3, Subtitle 5 of the Labor and Employment Article, the Maryland Department of Labor shall enforce the requirement under subsection (a)(2) of this section for contractors and subcontractors to pay employees not less than the prevailing wage rate determined by the Commissioner of Labor and Industry.