<?xml version='1.0' encoding='utf-8'?>
<section article="gpu" article_name="Public Utilities" number="7-216.1" title_number="7" title_name="Gas, Electric, and Water Companies" subtitle_number="2" subtitle_name="Electric Generation Facility Planning">
  <level label="a">
    <level label="1">
      <text>In this section the following words have the meanings indicated.</text>
    </level>
    <level label="2">
      <text>“Delivery year” has the meaning stated in the PJM Interconnection glossary.</text>
    </level>
    <level label="3">
      <text>“Energy storage device” has the meaning stated in § 7–216 of this subtitle.</text>
    </level>
    <level label="4">
      <text>“Investor–owned electric company” has the meaning stated in § 7–216 of this subtitle.</text>
    </level>
    <level label="5">
      <text>“Program” means the Maryland Energy Storage Program.</text>
    </level>
  </level>
  <level label="b">
    <level label="1">
      <text>The Commission shall establish targets for the cost–effective deployment of new energy storage devices in the State with a goal of achieving:</text>
      <level label="i">
        <text>750 megawatts of cumulative energy storage capacity by the end of delivery year 2027;</text>
      </level>
      <level label="ii">
        <text>1,500 megawatts of cumulative energy storage capacity by the end of delivery year 2030; and</text>
      </level>
      <level label="iii">
        <text>3,000 megawatts of cumulative energy storage capacity by the end of delivery year 2033.</text>
      </level>
    </level>
    <level label="2">
      <text>If a target specified in paragraph (1) of this subsection cannot be met cost effectively, the target shall be reduced to the maximum cost–effective amount of energy storage, measured in megawatts, that can be deployed by the end of the delivery year for the target.</text>
    </level>
  </level>
  <level label="c">
    <level label="1">
      <text>The Commission shall establish the Maryland Energy Storage Program.</text>
    </level>
    <level label="2">
      <text>The Program shall be implemented no later than July 1, 2025.</text>
    </level>
    <level label="3">
      <text>The Program shall include competitive procurement mechanisms to reach a minimum of 3,000 megawatts of energy storage, or the maximum cost–effective amount of energy storage that can be deployed, by the end of delivery year 2033.</text>
    </level>
    <level label="4">
      <text>The Program may include:</text>
      <level label="i">
        <text>a system of energy storage credits and market–based incentives designed to:</text>
        <level label="1">
          <text>develop a robust energy storage market in the State; and</text>
        </level>
        <level label="2">
          <text>deploy energy storage devices in a cost–effective manner;</text>
        </level>
      </level>
      <level label="ii">
        <text>a requirement that investor–owned electric companies:</text>
        <level label="1">
          <text>install or contract for energy storage devices; or</text>
        </level>
        <level label="2">
          <text>contract for credits from an energy storage project under § 7–216 of this subtitle;</text>
        </level>
      </level>
      <level label="iii">
        <text>a requirement that Program participants make reasonable efforts to apply for all applicable State and federal grants, rebates, tax credits, loan guarantees, and other similar benefits as the benefits become available; or</text>
      </level>
      <level label="iv">
        <text>any other mechanism or policy that the Commission determines is appropriate to achieve the goal of a robust, cost–effective energy storage system in the State.</text>
      </level>
    </level>
  </level>
  <level label="d">
    <text>On or before November 1 each year, the Commission shall report to the General Assembly, in accordance with § 2–1257 of the State Government Article, on the status of the Program, including:</text>
    <level label="1">
      <text>the capacity of operational energy storage devices in the State that is being counted toward the capacity goal established under subsection (c)(3) of this section, disaggregated by:</text>
      <level label="i">
        <text>electric company service territory;</text>
      </level>
      <level label="ii">
        <text>energy storage device capacity;</text>
      </level>
      <level label="iii">
        <text>front–of–meter transmission–level storage;</text>
      </level>
      <level label="iv">
        <text>front–of–meter distribution–level storage;</text>
      </level>
      <level label="v">
        <text>behind–the–meter storage; and</text>
      </level>
      <level label="vi">
        <text>any other relevant category, as determined by the Commission;</text>
      </level>
    </level>
    <level label="2">
      <text>whether the capacity goal established under subsection (c)(3) of this section should be altered;</text>
    </level>
    <level label="3">
      <text>barriers to achieving the goals identified under this section; and</text>
    </level>
    <level label="4">
      <text>any other information the Commission considers pertinent.</text>
    </level>
  </level>
</section>