<?xml version='1.0' encoding='utf-8'?>
<section article="gpu" article_name="Public Utilities" number="7-306" title_number="7" title_name="Gas, Electric, and Water Companies" subtitle_number="3" subtitle_name="Consumer Relations">
  <level label="a">
    <level label="1">
      <text>In this section the following words have the meanings indicated.</text>
    </level>
    <level label="2">
      <text>“Biomass” means “qualified biomass” as defined in § 7–701 of this title.</text>
    </level>
    <level label="3">
      <text>“Closed conduit hydro” means a hydroelectric generating facility that:</text>
      <level label="i">
        <text>generates electricity within existing piping or limited adjacent piping of a potable water supply system;</text>
      </level>
      <level label="ii">
        <text>is owned or operated by a municipal corporation or public water authority; and</text>
      </level>
      <level label="iii">
        <text>is designed to produce less energy than is consumed to operate the water supply system.</text>
      </level>
    </level>
    <level label="4">
      <text>“Community solar energy generating system” has the meaning stated in § 7–306.2 of this subtitle.</text>
    </level>
    <level label="5">
      <text>“Community solar energy generating system program” means a program administered by an electric company in accordance with § 7–306.2 of this subtitle.</text>
    </level>
    <level label="6">
      <text>“Eligible customer–generator” means a customer that owns and operates, leases and operates, or contracts with a third party that owns and operates a biomass, micro combined heat and power, solar, fuel cell, wind, or closed conduit hydro electric generating facility that:</text>
      <level label="i">
        <text>is located on the customer’s premises or contiguous property;</text>
      </level>
      <level label="ii">
        <text>is interconnected and operated in parallel with an electric company’s transmission and distribution facilities; and</text>
      </level>
      <level label="iii">
        <text>is intended primarily to offset all or part of the customer’s own electricity requirements.</text>
      </level>
    </level>
    <level label="7">
      <text>“Fuel cell” means an electric generating facility that:</text>
      <level label="i">
        <text>includes integrated power plant systems containing a stack, tubular array, or other functionally similar configuration used to electrochemically convert fuel to electric energy; and</text>
      </level>
      <level label="ii">
        <text>may include:</text>
        <level label="1">
          <text>an inverter and fuel processing system; and</text>
        </level>
        <level label="2">
          <text>other plant equipment to support the plant’s operation or its energy conversion, including heat recovery equipment.</text>
        </level>
      </level>
    </level>
    <level label="8">
      <text>“Micro combined heat and power” means the simultaneous or sequential production of useful thermal energy and electrical or mechanical power not exceeding 30 kilowatts.</text>
    </level>
    <level label="9">
      <text>“Net energy metering” means measurement of the difference between the electricity that is supplied by an electric company and the electricity that is generated by an eligible customer–generator and fed back to the electric grid over the eligible customer–generator’s billing period.</text>
    </level>
    <level label="10">
      <text>“Net excess generation” means the amount of the electricity generated by an eligible customer–generator that is in excess of the electricity consumed by the eligible customer–generator and that results in a negative kilowatt–hour reading at the end of the eligible customer–generator’s billing cycle.</text>
    </level>
    <level label="11">
      <level label="i">
        <text>“Repowered” means a solar energy generating system owned by an eligible customer–generator or a community solar energy generating system that, through a single action or a series of actions, has had replaced more than 80% of the direct current nameplate capacity of the photovoltaic modules at the system as of the date the system was originally placed in service under this section.</text>
      </level>
      <level label="ii">
        <text>“Repowered” does not include:</text>
        <level label="1">
          <text>routine equipment repair and maintenance, including the replacement of equipment during routine repair and maintenance with equipment that has similar or improved ratings, impedances, efficiencies, or capabilities;</text>
        </level>
        <level label="2">
          <text>roof replacement or other project site maintenance;</text>
        </level>
        <level label="3">
          <text>the remediation of equipment defects;</text>
        </level>
        <level label="4">
          <text>the remediation of damage caused by a natural disaster, an act of God, fire, vandalism, theft, or another casualty event; or</text>
        </level>
        <level label="5">
          <text>replacements required by a governmental authority or electric company.</text>
        </level>
      </level>
    </level>
  </level>
  <level label="b">
    <text>The General Assembly finds and declares that a program to provide net energy metering for eligible customer–generators is a means to encourage private investment in renewable energy resources, stimulate in–State economic growth, enhance continued diversification of the State’s energy resource mix, and reduce costs of interconnection and administration.</text>
  </level>
  <level label="c">
    <text>An electric company serving an eligible customer–generator shall ensure that the meter installed for net energy metering is capable of measuring the flow of electricity in two directions.</text>
  </level>
  <level label="d">
    <level label="1">
      <text>The Commission shall require electric utilities to develop a standard contract or tariff for net energy metering and make it available to eligible customer–generators on a first–come, first–served basis until the earlier of:</text>
      <level label="i">
        <text>the date on which the rated generating capacity owned and operated by eligible customer–generators in the State reaches 3,000 megawatts; or</text>
      </level>
      <level label="ii">
        <text>July 1, 2027.</text>
      </level>
    </level>
    <level label="2">
      <text>Notwithstanding paragraph (1)(ii) of this subsection and except as provided in paragraph (3) of this subsection, if the 3,000–megawatt limit in paragraph (1)(i) of this subsection has not been met, a community solar energy generating system that is placed in service after July 1, 2027, shall be eligible for net energy metering under this section if:</text>
      <level label="i">
        <text>the system:</text>
        <level label="1">
          <text>on or before July 1, 2027, received a community solar program queue position under § 7–306.2 of this subtitle and paid a deposit to the electric company equal to at least 50% of the electric company’s estimate of all necessary interconnection fees; and</text>
        </level>
        <level label="2">
          <text>except as provided in paragraph (4) of this subsection, is placed in service on or before July 1, 2030; and</text>
        </level>
      </level>
      <level label="ii">
        <text>the electric company in whose service territory the community solar energy generating system is located has not met the net energy metering capacity limit under paragraph (3)(i) of this subsection.</text>
      </level>
    </level>
    <level label="3">
      <level label="i">
        <text>Subject to subparagraphs (ii) and (iii) of this paragraph, for an electric company with a 2025 annual peak demand of 2,500 megawatts or less, the net energy metering capacity limit for community solar energy generating systems that are placed in service in the electric company’s service territory on or after April 1, 2026, shall be 150% of the total combined rated generating capacity of community solar energy generating systems that had not been placed in service but hold queue positions in a community solar energy generating system program in the electric company’s service territory on April 1, 2026.</text>
      </level>
      <level label="ii">
        <text>If the 150% net energy metering capacity limit established under subparagraph (i) of this paragraph in an electric company’s service territory is reached, the electric company shall:</text>
        <level label="1">
          <text>close the net energy metering contract or tariff under this section to any community solar energy generating systems that do not already hold queue positions; and</text>
        </level>
        <level label="2">
          <text>notify the Commission.</text>
        </level>
      </level>
      <level label="iii">
        <text>A community solar energy generating system holding a queue position in a community solar energy generating system program in the electric company’s service territory that is placed in service on or after April 1, 2026, shall continue to count toward the 150% net energy metering capacity limit established under subparagraph (i) of this paragraph.</text>
      </level>
    </level>
    <level label="4">
      <level label="i">
        <text>If the Commission does not implement a successor program under § 7–306.4 of this subtitle by July 1, 2027, a community solar energy generating system that has not been placed in service by July 1, 2027, but meets the requirements of paragraph (2)(i)1 and (ii) of this subsection shall be eligible for net energy metering under this section if it is placed in service on or before 3 years after the date that the successor program is implemented.</text>
      </level>
      <level label="ii">
        <text>The Commission may grant an extension to the deadlines under paragraph (2)(i) of this subsection and subparagraph (i) of this paragraph if the community solar energy generating system was unable to meet the deadline, including inability to meet the deadline due to any of the following reasons:</text>
        <level label="1">
          <text>a force majeure event, as determined by the Commission;</text>
        </level>
        <level label="2">
          <text>failure by a government or municipal authority to timely complete an action necessary to authorize or enable any portion of the project construction;</text>
        </level>
        <level label="3">
          <text>failure of an electric company to comply with a Commission order, regulation, statute, or tariff; or</text>
        </level>
        <level label="4">
          <text>the system is ready to be placed in service and is waiting only on the electric company to grant the system permission to operate.</text>
        </level>
      </level>
    </level>
    <level label="5">
      <text>An eligible customer–generator that, on July 1, 2027, is under a net energy metering contract or tariff under this section or a community solar energy generating system that meets the requirements of paragraph (2) of this subsection shall remain eligible for net energy metering under this section until the earlier of when:</text>
      <level label="i">
        <text>the system is decommissioned in accordance with § 7–218(g) of this title;</text>
      </level>
      <level label="ii">
        <text>the system is modified to increase:</text>
        <level label="1">
          <text>the net power flow injection into the electric system due to the addition of more photovoltaic modules than were present as of the date the system was originally placed in service under this section; or</text>
        </level>
        <level label="2">
          <text>the alternating current output capacity to be more than when the system was originally placed into service under this section;</text>
        </level>
      </level>
      <level label="iii">
        <text>the system enters into a new interconnection agreement; or</text>
      </level>
      <level label="iv">
        <text>the system is repowered.</text>
      </level>
    </level>
  </level>
  <level label="e">
    <level label="1">
      <text>A net energy metering contract or tariff shall be identical, in energy rates, rate structure, and monthly charges, to the contract or tariff that the customer would be assigned if the customer were not an eligible customer–generator.</text>
    </level>
    <level label="2">
      <level label="i">
        <text>A net energy metering contract or tariff may not include charges that would raise the eligible customer–generator’s minimum monthly charge above that of customers of the rate class to which the eligible customer–generator would otherwise be assigned.</text>
      </level>
      <level label="ii">
        <text>Charges prohibited by this paragraph include new or additional demand charges, standby charges, customer charges, and minimum monthly charges.</text>
      </level>
    </level>
  </level>
  <level label="f">
    <level label="1">
      <text>The electric company shall calculate net energy metering in accordance with this subsection.</text>
    </level>
    <level label="2">
      <text>Net energy produced or consumed on a regular basis shall be measured in accordance with standard metering practices.</text>
    </level>
    <level label="3">
      <text>If electricity supplied by the grid exceeds electricity generated by the eligible customer–generator during a month, the eligible customer–generator shall be billed for the net energy supplied in accordance with subsection (e) of this section.</text>
    </level>
    <level label="4">
      <text>If electricity generated by the eligible customer–generator exceeds the electricity supplied by the grid, the eligible customer–generator shall be billed only customer charges for that month in accordance with subsection (e) of this section.</text>
    </level>
    <level label="5">
      <level label="i">
        <text>An eligible customer–generator under paragraph (4) of this subsection may:</text>
        <level label="1">
          <text>accrue net excess generation for a period:</text>
        </level>
        <level label="A">
          <text>not to exceed 12 months; and</text>
        </level>
        <level label="B">
          <text>that ends with the billing cycle that is complete immediately prior to the end of April of each year; or</text>
        </level>
        <level label="2">
          <text>except for an eligible customer–generator served by a municipal electric utility or an electric cooperative and subject to subparagraph (iv) of this paragraph, accrue net excess generation for an indefinite period regardless of whether the eligible customer–generator previously accrued net excess generation for a period authorized under item 1 of this subparagraph.</text>
        </level>
      </level>
      <level label="ii">
        <text>The electric company shall carry forward net excess generation until:</text>
        <level label="1">
          <text>the eligible customer–generator’s consumption of electricity from the grid eliminates the net excess generation;</text>
        </level>
        <level label="2">
          <text>the accrual period under subparagraph (i)1 of this paragraph expires; or</text>
        </level>
        <level label="3">
          <text>the account is closed.</text>
        </level>
      </level>
      <level label="iii">
        <level label="1">
          <text>If an eligible customer–generator elects to accrue net excess generation for a period not to exceed 12 months under subparagraph (i)1 of this paragraph, the dollar value of net excess generation shall be equal to the generation or commodity portion of the rate that the eligible customer–generator would have been charged by the electric company averaged over the previous 12–month period ending with the billing cycle that is complete immediately before the end of April multiplied by the number of kilowatt–hours of net excess generation.</text>
        </level>
        <level label="2">
          <text>For an eligible customer–generator that elects to accrue net excess generation under subparagraph (i)1 of this paragraph and is served by a community choice aggregator or an electricity supplier, the dollar value of the net excess generation shall be equal to the generation or commodity rate that the customer would have been charged by the community choice aggregator or electricity supplier multiplied by the number of kilowatt–hours of net excess generation.</text>
        </level>
      </level>
      <level label="iv">
        <text>If an eligible customer–generator elects to accrue net excess generation for an indefinite period under subparagraph (i)2 of this paragraph:</text>
        <level label="1">
          <text>the eligible customer–generator may not elect to switch to accruing net excess generation under subparagraph (i)1 of this paragraph unless the electric company approves the switch; and</text>
        </level>
        <level label="2">
          <text>the electric company shall, within 15 days after an eligible customer–generator’s account is closed, pay the eligible customer–generator, in accordance with subparagraph (v) of this paragraph, for any accrued net excess generation remaining at the time the account is closed.</text>
        </level>
      </level>
      <level label="v">
        <text>The Commission shall establish a method for calculating the value of any accrued net excess generation that a customer–generator elects to accrue for an indefinite period under subparagraph (i)2 of this paragraph.</text>
      </level>
    </level>
    <level label="6">
      <level label="i">
        <text>If an eligible customer–generator elects to accrue net excess generation under paragraph (5)(i)1 of this subsection, on or before 30 days after the billing cycle that is complete immediately prior to the end of April of each year, the electric company shall pay the eligible customer–generator for the dollar value of any accrued net excess generation remaining at the end of the previous 12–month period ending with the billing cycle that is complete immediately before the end of April.</text>
      </level>
      <level label="ii">
        <text>Within 15 days after the date an eligible customer–generator that elects to accrue net excess generation under paragraph (5)(i)1 of this subsection closes the eligible customer–generator’s account, the electric company shall pay the eligible customer–generator for the dollar value of any accrued net excess generation remaining at the time the eligible customer–generator closes the account.</text>
      </level>
    </level>
    <level label="7">
      <level label="i">
        <text>Notwithstanding paragraphs (5) and (6) of this subsection, an eligible customer–generator served by an electric cooperative that serves a population of less than 250,000 in its distribution territory may choose to be paid for the dollar value of net excess generation remaining at the end of each month instead of at the end of the accrual period specified under paragraph (5)(i)1 of this subsection.</text>
      </level>
      <level label="ii">
        <text>If an eligible customer–generator chooses to be paid for the dollar value of net excess generation remaining at the end of each month:</text>
        <level label="1">
          <text>the customer–generator may accrue net excess generation on a monthly basis;</text>
        </level>
        <level label="2">
          <text>the dollar value of the net excess generation shall be equal to the generation or commodity portion of the rate that the eligible customer–generator would have been charged by the electric company for the previous month; and</text>
        </level>
        <level label="3">
          <text>on or before 30 days after the end of each month, the electric cooperative shall pay the eligible customer–generator for the dollar value of net excess generation remaining at the end of the previous month.</text>
        </level>
      </level>
    </level>
  </level>
  <level label="g">
    <level label="1">
      <text>Except as provided in paragraphs (6), (7), and (8) of this subsection, the generating capacity of an electric generating system used by an eligible customer–generator for net metering may not exceed 2 megawatts.</text>
    </level>
    <level label="2">
      <text>An electric generating system used by an eligible customer–generator for net metering shall meet all applicable safety and performance standards established by the National Electrical Code, the Institute of Electrical and Electronics Engineers, and Underwriters Laboratories.</text>
    </level>
    <level label="3">
      <text>The Commission may adopt by regulation additional control and testing requirements for eligible customer–generators that the Commission determines are necessary to protect public safety and system reliability.</text>
    </level>
    <level label="4">
      <text>An electric company may not require an eligible customer–generator whose electric generating system meets the standards of paragraphs (2) and (3) of this subsection to:</text>
      <level label="i">
        <text>install additional controls;</text>
      </level>
      <level label="ii">
        <text>perform or pay for additional tests; or</text>
      </level>
      <level label="iii">
        <text>purchase additional liability insurance.</text>
      </level>
    </level>
    <level label="5">
      <text>An eligible customer–generator or the eligible customer–generator’s assignee shall own and have title to all renewable energy attributes or renewable energy credits associated with any electricity produced by its electric generating system.</text>
    </level>
    <level label="6">
      <text>The Commission may not prohibit the construction or operation of multiple net metered solar energy generating facilities located on separate contiguous lots that are owned by a local government solely because the capacity of the combined net metering systems exceeds the limit established under paragraph (1) of this subsection, if:</text>
      <level label="i">
        <text>the net metered solar energy generating facilities are intended to be used solely for the benefit of the local government;</text>
      </level>
      <level label="ii">
        <text>the total capacity of the net metered solar energy generating facilities on the contiguous lots does not exceed 5 megawatts;</text>
      </level>
      <level label="iii">
        <text>the contiguous lots were not subdivided for the purpose of circumventing the limit established under paragraph (1) of this subsection; and</text>
      </level>
      <level label="iv">
        <text>the utility serving the net metered solar energy generating facilities is not an electric cooperative or municipal electric utility.</text>
      </level>
    </level>
    <level label="7">
      <text>The generating capacity of a community solar energy generating system established under § 7–306.2 of this subtitle that is used for net metering may not exceed 5 megawatts.</text>
    </level>
    <level label="8">
      <text>The generating capacity of a net metered facility that is meter aggregated under § 7–306.3 of this subtitle may not exceed 5 megawatts.</text>
    </level>
  </level>
  <level label="h">
    <text>An eligible customer–generator participating in net energy metering may participate in the aggregation activities of a community choice aggregator under § 7–510.3 of this title.</text>
  </level>
  <level label="i">
    <text>Notwithstanding the generating capacity limits established in subsection (g) of this section, an eligible customer–generator participating in meter aggregation under § 7–306.2 or § 7–306.3 of this subtitle may receive excess generation from more than one generating system, including if the combined generating capacity of all net metered facilities that are meter aggregated exceeds 5 megawatts.</text>
  </level>
  <level label="j">
    <text>On or before November 1 of each year, the Commission shall report to the General Assembly, in accordance with § 2–1257 of the State Government Article, on the status of the net energy metering program under this section and § 7–306.4 of this subtitle, including:</text>
    <level label="1">
      <text>the amount of capacity of electric generating facilities owned and operated by eligible customer–generators in the State by type of energy resource;</text>
    </level>
    <level label="2">
      <text>based on the need to encourage a diversification of the State’s energy resource mix to ensure reliability, whether the rated generating capacity limit in subsection (d) of this section should be altered;</text>
    </level>
    <level label="3">
      <text>the status of the implementation and efficacy of the successor program developed and implemented under § 7–306.4 of this subtitle; and</text>
    </level>
    <level label="4">
      <text>other pertinent information.</text>
    </level>
  </level>
</section>