<?xml version='1.0' encoding='utf-8'?>
<subtitle article="gpu" title_number="7" subtitle_number="9" title_name="Gas, Electric, and Water Companies" subtitle_name="Electric Vehicle Charging Infrastructure">
  <section article="gpu" article_name="Public Utilities" number="7-901" title_number="7" title_name="Gas, Electric, and Water Companies" subtitle_number="9" subtitle_name="Electric Vehicle Charging Infrastructure">
    <level label="a">
      <text>In this subtitle the following words have the meanings indicated.</text>
    </level>
    <level label="b">
      <text>“EV charging network” means the total number of EV charging stations an electric company installs or maintains for public use.</text>
    </level>
    <level label="c">
      <text>“EV charging station” means a connected point in an electrical wiring installation:</text>
      <level label="1">
        <text>at which current is taken to charge a battery or any other energy storage device in an electric vehicle; and</text>
      </level>
      <level label="2">
        <text>capable of providing Level 2 charging.</text>
      </level>
    </level>
    <level label="d">
      <text>“EV Pilot Program” means the EV Pilot Program established by Public Service Commission Order No. 88997 and administered by the Commission.</text>
    </level>
    <level label="e">
      <text>“Level 2 charging” means the ability to charge a battery or other energy storage device in an electric vehicle in a manner that:</text>
      <level label="1">
        <text>is capable of using an alternating current electrical service with a minimum of 208 volts; and</text>
      </level>
      <level label="2">
        <text>meets applicable industry safety standards.</text>
      </level>
    </level>
    <level label="f">
      <text>“Underserved community” means any census tract in which, according to the most recent U.S. Census Bureau Survey:</text>
      <level label="1">
        <text>at least 25% of the residents qualify as low–income;</text>
      </level>
      <level label="2">
        <text>at least 50% of the residents identify as nonwhite; or</text>
      </level>
      <level label="3">
        <text>at least 15% of the residents have limited English proficiency.</text>
      </level>
    </level>
    <level label="g">
      <text>“Uptime” means the availability and consistency of an EV charging station in an EV charging network to successfully dispense electricity as designed, measured as a percentage of both hours and days of a calendar year.</text>
    </level>
  </section>
  <section article="gpu" article_name="Public Utilities" number="7-902" title_number="7" title_name="Gas, Electric, and Water Companies" subtitle_number="9" subtitle_name="Electric Vehicle Charging Infrastructure">
    <text>This subtitle applies to an electric company that: </text>
    <level label="1">
      <text>installs or maintains an EV charging station for public use; or</text>
    </level>
    <level label="2">
      <text>participates in the EV Pilot Program.</text>
    </level>
  </section>
  <section article="gpu" article_name="Public Utilities" number="7-903" title_number="7" title_name="Gas, Electric, and Water Companies" subtitle_number="9" subtitle_name="Electric Vehicle Charging Infrastructure">
    <level label="a">
      <text>Subject to subsection (b) of this section, the Commission shall, by order or regulation and subject to reasonable cost limitations balanced with the public interest:</text>
      <level label="1">
        <text>expand the EV Pilot Program to allow participating electric companies to install EV charging stations in new and existing multifamily dwellings in underserved communities; and</text>
      </level>
      <level label="2">
        <text>terminate the EV Pilot Program expansion required under item (1) of this section on December 31, 2025.</text>
      </level>
    </level>
    <level label="b">
      <text>The termination of the EV Pilot Program expansion required under subsection (a) of this section may not be construed to:</text>
      <level label="1">
        <text>terminate an electric company’s authority to operate EV charging stations under a program approved by the Commission on or before March 1, 2023;</text>
      </level>
      <level label="2">
        <text>limit an electric company’s efforts to operate and maintain EV charging stations installed under the EV Pilot Program; or</text>
      </level>
      <level label="3">
        <text>impact the cost recovery by an investor–owned electric company for the lifetime of an EV charging station installed under the EV Pilot Program.</text>
      </level>
    </level>
  </section>
  <section article="gpu" article_name="Public Utilities" number="7-904" title_number="7" title_name="Gas, Electric, and Water Companies" subtitle_number="9" subtitle_name="Electric Vehicle Charging Infrastructure">
    <level label="a">
      <level label="1">
        <text>Except as provided in paragraph (2) of this subsection, an electric company operating an EV charging network shall maintain uptime standards for each EV charging station in accordance with:</text>
        <level label="i">
          <text>federal National Electric Vehicle Infrastructure standards and requirements; or</text>
        </level>
        <level label="ii">
          <text>alternative uptime standards and requirements approved by the Commission.</text>
        </level>
      </level>
      <level label="2">
        <text>The uptime requirement under paragraph (1) of this subsection does not include any time in which an EV charging station is unavailable due to:</text>
        <level label="i">
          <text>force majeure, as determined by the Commission; or</text>
        </level>
        <level label="ii">
          <text>vandalism.</text>
        </level>
      </level>
    </level>
    <level label="b">
      <text>An electric company shall calculate EV charging station uptime on a quarterly basis for the immediately preceding 12 months.</text>
    </level>
    <level label="c">
      <level label="1">
        <text>An electric company that operates an EV charging station for public use shall be subject to the same reporting requirements as an electric company that receives federal funding related to electric vehicle charging infrastructure.</text>
      </level>
      <level label="2">
        <text>An electric company that operates an EV charging network or EV charging station shall submit the following EV charging station data to the Commission on a quarterly basis:</text>
        <level label="i">
          <text>the location of the EV charging station; and</text>
        </level>
        <level label="ii">
          <text>for each EV charging station:</text>
          <level label="1">
            <text>charging session start and end times;</text>
          </level>
          <level label="2">
            <text>the total amount of electricity, in kilowatt–hours, dispensed to an electric vehicle for each charging session;</text>
          </level>
          <level label="3">
            <text>the peak amount of electricity, in kilowatts, dispensed to an electric vehicle for each charging session;</text>
          </level>
          <level label="4">
            <text>uptime for each of the previous 3 months;</text>
          </level>
          <level label="5">
            <text>the cost of electricity needed to operate each EV charging station for each of the previous 3 months;</text>
          </level>
          <level label="6">
            <text>maintenance and repair costs for each of the previous 3 months;</text>
          </level>
          <level label="7">
            <text>the cost of acquiring real property for use as an EV charging station;</text>
          </level>
          <level label="8">
            <text>the cost of acquiring and installing electric vehicle charging equipment;</text>
          </level>
          <level label="9">
            <text>the cost of acquiring and installing distributed energy resources;</text>
          </level>
          <level label="10">
            <text>the cost to the electric company of connecting to the electric grid and any applicable connection upgrades;</text>
          </level>
          <level label="11">
            <text>the capacity, in kilowatts or kilowatt–hours as appropriate, of each type of distributed energy resource used by an EV charging station;</text>
          </level>
          <level label="12">
            <text>the number of EV charging stations that failed to meet the uptime requirements under subsection (a) of this section;</text>
          </level>
          <level label="13">
            <text>when applicable, the reason an EV charging station failed to meet the uptime requirements under subsection (a) of this section; and</text>
          </level>
          <level label="14">
            <text>when applicable, the date an EV charging station was repaired.</text>
          </level>
        </level>
      </level>
    </level>
  </section>
  <section article="gpu" article_name="Public Utilities" number="7-905" title_number="7" title_name="Gas, Electric, and Water Companies" subtitle_number="9" subtitle_name="Electric Vehicle Charging Infrastructure">
    <level label="a">
      <text>An electric company participating in the EV Pilot Program shall maintain an adequate number of staff to monitor, assess, and, when necessary, repair the EV charging stations operated by the electric company.</text>
    </level>
    <level label="b">
      <text>The Commission may, in accordance with § 13–201 of this article, impose a penalty on or take additional remedial action against an electric company that fails to satisfy the uptime requirements under § 7–904 of this subtitle.</text>
    </level>
  </section>