  <level label="a">
    <text>Subject to subsection (b) of this section, the Commission shall, by order or regulation and subject to reasonable cost limitations balanced with the public interest:</text>
    <level label="1">
      <text>expand the EV Pilot Program to allow participating electric companies to install EV charging stations in new and existing multifamily dwellings in underserved communities; and</text>
    </level>
    <level label="2">
      <text>terminate the EV Pilot Program expansion required under item (1) of this section on December 31, 2025.</text>
    </level>
  </level>
  <level label="b">
    <text>The termination of the EV Pilot Program expansion required under subsection (a) of this section may not be construed to:</text>
    <level label="1">
      <text>terminate an electric company’s authority to operate EV charging stations under a program approved by the Commission on or before March 1, 2023;</text>
    </level>
    <level label="2">
      <text>limit an electric company’s efforts to operate and maintain EV charging stations installed under the EV Pilot Program; or</text>
    </level>
    <level label="3">
      <text>impact the cost recovery by an investor–owned electric company for the lifetime of an EV charging station installed under the EV Pilot Program.</text>
    </level>
  </level>
</section>