<section article="gsf" article_name="State Finance and Procurement" number="13-215" title_number="13" title_name="Source Selection -- State Procurement Contracts" subtitle_number="2" subtitle_name="Procedural Requirements">
  <level label="a">
    <text>A unit may not enter into a cost-reimbursement contract unless the procurement officer determines that:</text>
    <level label="1">
      <text>a cost-reimbursement contract is likely to be less costly to the State than any other type of contract; or</text>
    </level>
    <level label="2">
      <text>except for leases of real property, the kind or quality of procurement that the unit requires could not be obtained practicably under any other type of contract.</text>
    </level>
  </level>
  <level label="b">
    <text>A unit may not enter into a procurement contract that is wholly or partly a cost-reimbursement contract unless the procurement officer determines that the accounting system of the contractor:</text>
    <level label="1">
      <text>will allow timely development of all necessary cost data in the form required by the specific type of procurement contract under consideration; and</text>
    </level>
    <level label="2">
      <text>is adequate to allocate costs in accordance with generally accepted accounting principles.</text>
    </level>
  </level>
  <level label="c">
    <text>A cost-reimbursement contract shall provide that costs, including costs for subcontractors, will be reimbursed only if the costs are allowable and allocable under:</text>
    <level label="1">
      <text>the procurement contract; or</text>
    </level>
    <level label="2">
      <text>the regulations of the Board on cost principles.</text>
    </level>
  </level>
  <level label="d">
    <text>A contractor under a cost-reimbursement contract shall give notice to and, as required under the contract, obtain approval from a procurement officer before the contractor enters into:</text>
    <level label="1">
      <text>a cost-reimbursement subcontract; or</text>
    </level>
    <level label="2">
      <text>any subcontract involving more than:</text>
      <level label="i">
        <text>$25,000; or</text>
      </level>
      <level label="ii">
        <text>5% of the estimated cost of the procurement contract.</text>
      </level>
    </level>
  </level>
</section>