<section article="gsf" article_name="State Finance and Procurement" number="13-225" title_number="13" title_name="Source Selection -- State Procurement Contracts" subtitle_number="2" subtitle_name="Procedural Requirements">
  <level label="a">
    <level label="1">
      <text>In this section the following words have the meanings indicated.</text>
    </level>
    <level label="2">
      <text>“Payment security” has the meaning stated in § 17-101 of this article.</text>
    </level>
    <level label="3">
      <text>“Performance security” has the meaning stated in § 17-101 of this article.</text>
    </level>
  </level>
  <level label="b">
    <level label="1">
      <text>If a contractor has furnished 100% payment security and 100% performance security in accordance with Title 17, Subtitle 1 of this article under a State procurement contract for construction, the percentage specified in the contract for retainage may not exceed 5% of the total amount.</text>
    </level>
    <level label="2">
      <text>In addition to retainage, a primary procurement unit and the Maryland Transportation Authority may withhold from payments otherwise due a contractor any amount that the unit reasonably believes necessary to protect the State’s interest.</text>
    </level>
    <level label="3">
      <text>Retainage withheld by a primary procurement unit and the Maryland Transportation Authority may be deposited in an interest-bearing escrow account in accordance with § 15-108 of this article.</text>
    </level>
  </level>
  <level label="c">
    <level label="1">
      <text>A contractor may not retain a percentage of payments due a subcontractor that exceeds the percentage of payments retained by the primary procurement unit or the Maryland Transportation Authority.</text>
    </level>
    <level label="2">
      <text>Paragraph (1) of this subsection may not be construed to prohibit a contractor from withholding any amount in addition to retainage if the contractor determines that a subcontractor’s performance under the subcontract provides reasonable grounds for withholding the additional amount.</text>
    </level>
  </level>
  <level label="d">
    <level label="1">
      <text>A subcontractor may not retain a percentage of payments due a lower tier subcontractor that exceeds the percentage of payments retained from the subcontractor.</text>
    </level>
    <level label="2">
      <text>Paragraph (1) of this subsection may not be construed to prohibit a subcontractor from withholding any amount in addition to retainage if the subcontractor determines that a lower tier subcontractor’s performance under the subcontract provides reasonable grounds for withholding the additional amount.</text>
    </level>
  </level>
  <level label="e">
    <text>If retainage has been placed in escrow under § 15-108 of this article, each payment of retainage shall include a pro rata portion of interest earned.</text>
  </level>
  <level label="f">
    <text>This section may not be construed to limit the application of the provisions of Title 17, Subtitle 1 of this article.</text>
  </level>