      <text>A unit may assert a contract claim against a contractor by sending written notice to the contractor and the procurement officer that states:</text>
      <level label="i">
        <text>the basis for the contract claim;</text>
      </level>
      <level label="ii">
        <text>to the extent known, the amount, or the performance or other action, requested by the unit in the contract claim; and</text>
      </level>
      <level label="iii">
        <text>the date by which the contractor is required to provide a written response to the contract claim.</text>
      </level>
    </level>
    <level label="2">
      <text>On receipt of a contract claim from a unit, a procurement officer:</text>
      <level label="i">
        <text>shall review the substance of the contract claim;</text>
      </level>
      <level label="ii">
        <text>may request additional information or substantiation through an appropriate procedure; and</text>
      </level>
      <level label="iii">
        <text>may discuss or, if appropriate, negotiate the contract claim with the unit or contractor.</text>
      </level>
    </level>
    <level label="3">
      <text>The procurement officer shall proceed under subsection (b) of this section if the contractor fails to respond, provides an inadequate response, or denies the contract claim or the relief sought by the unit in whole or in part.</text>
    </level>
  </level>
  <level label="b">
    <level label="1">
      <text>If the contractor and the unit do not resolve the contract claim, the procurement officer shall prepare a proposed decision on the contract claim, including:</text>
      <level label="i">
        <text>a description of the contract claim;</text>
      </level>
      <level label="ii">
        <text>references to pertinent contract provisions;</text>
      </level>
      <level label="iii">
        <text>a statement of factual areas of agreement or disagreement; and</text>
      </level>
      <level label="iv">
        <text>a statement in the proposed decision wholly or partly granting or denying the relief sought, with supporting rationale.</text>
      </level>
    </level>
    <level label="2">
      <text>Unless otherwise provided by regulation, the procurement officer shall submit the contract claim and proposed decision to:</text>
      <level label="i">
        <text>the head of the unit; and</text>
      </level>
      <level label="ii">
        <text>the head of the principal department or other equivalent unit of which the unit is a part.</text>
      </level>
    </level>
    <level label="3">
      <level label="i">
        <text>The reviewing authority shall approve, modify, or disapprove the proposed decision.</text>
      </level>
      <level label="ii">
        <text>In disapproving a proposed decision, the reviewing authority may remand the contract claim with instructions to the procurement officer.</text>
      </level>
      <level label="iii">
        <text>On remand, the procurement officer shall proceed as required under this subsection and in accordance with the instructions of the reviewing authority.</text>
      </level>
    </level>
    <level label="4">
      <text>The decision of the reviewing authority is the final action of the unit.</text>