<?xml version='1.0' encoding='utf-8'?>
<subtitle article="gsf" title_number="2" subtitle_number="4" title_name="General Provisions" subtitle_name="Water and Sewerage Systems">
  <section article="gsf" article_name="State Finance and Procurement" number="2-401" title_number="2" title_name="General Provisions" subtitle_number="4" subtitle_name="Water and Sewerage Systems">
    <level label="a">
      <text>In this subtitle the following words have the meanings indicated.</text>
    </level>
    <level label="b">
      <text>“Annual operating costs” include the cost of:</text>
      <level label="1">
        <text>the production, treatment, pumping, storage, transmission, and distribution of water and the maintenance and repair of equipment associated with these functions;</text>
      </level>
      <level label="2">
        <text>the collection, pumping, transmission, and treatment of wastewater, and the maintenance and repair of equipment associated with these functions;</text>
      </level>
      <level label="3">
        <text>administrative overhead;</text>
      </level>
      <level label="4">
        <text>debt service;</text>
      </level>
      <level label="5">
        <text>depreciation; and</text>
      </level>
      <level label="6">
        <text>servicing customer accounts.</text>
      </level>
    </level>
    <level label="c">
      <text>“Lateral system construction costs” include:</text>
      <level label="1">
        <text>any cost necessary to plan, design, acquire, construct, inspect, test, and put into operation the lateral system to serve a State facility; and</text>
      </level>
      <level label="2">
        <text>any indirect cost incurred by the local jurisdiction that is necessary to construct water and sewer lines.</text>
      </level>
    </level>
  </section>
  <section article="gsf" article_name="State Finance and Procurement" number="2-402" title_number="2" title_name="General Provisions" subtitle_number="4" subtitle_name="Water and Sewerage Systems">
    <level label="a">
      <text>The State shall pay its share of:</text>
      <level label="1">
        <text>the annual operating costs of furnishing water and sewer service to any State facility; and</text>
      </level>
      <level label="2">
        <text>the lateral system construction costs associated with the installation of any water or sewer line that directly serves the State facility.</text>
      </level>
    </level>
    <level label="b">
      <text>The State shall pay the cost of expanding a water or sewage treatment facility if the expansion is necessitated by the use of the facility by the State. However, the amount the State pays may not exceed the cost of the capacity required by the State.</text>
    </level>
  </section>
  <section article="gsf" article_name="State Finance and Procurement" number="2-403" title_number="2" title_name="General Provisions" subtitle_number="4" subtitle_name="Water and Sewerage Systems">
    <text>The State shall pay any assessment, charge, or fee that is:</text>
    <level label="1">
      <text>levied by the local jurisdiction in which the State facility is located; and</text>
    </level>
    <level label="2">
      <text>designated as the State’s share of annual operating costs or lateral system construction costs.</text>
    </level>
  </section>
  <section article="gsf" article_name="State Finance and Procurement" number="2-404" title_number="2" title_name="General Provisions" subtitle_number="4" subtitle_name="Water and Sewerage Systems">
    <level label="a">
      <text>If the State has agreed to pay the costs set out in § 2-402 of this subtitle and any additional construction costs associated with the connection, the State may connect a State facility, regardless of its location, to a publicly owned utility system.</text>
    </level>
    <level label="b">
      <text>If an existing publicly owned utility system is inadequate to handle proposed State utility needs, the State shall pay all costs that are:</text>
      <level label="1">
        <text>associated with the expansion of the publicly owned utility system to meet the needs of the State; and</text>
      </level>
      <level label="2">
        <text>in excess of available federal funds.</text>
      </level>
    </level>
    <level label="c">
      <text>Before connecting to any publicly owned utility system, the State shall:</text>
      <level label="1">
        <text>coordinate with the owner of the publicly owned utility system; and</text>
      </level>
      <level label="2">
        <text>consider any existing master plan in establishing the fiscal obligation of the State under this section.</text>
      </level>
    </level>
    <level label="d">
      <level label="1">
        <text>After determining the need of the State for water or sewerage capacity, the State shall provide the information to the appropriate local jurisdictions.</text>
      </level>
      <level label="2">
        <text>The local jurisdictions shall include State facility needs in developing their master plans for water and sewerage systems.</text>
      </level>
    </level>
  </section>
</subtitle>