  <paragraph num="A.">
    <text>Claim Hearings.</text>
    <paragraph num="(1)">
      <text>Parties.</text>
      <paragraph num="(a)">
        <text>The claimant who brought the claim, and the contractor alleged to be responsible for the monetary loss of the claimant, shall be parties in all claim hearings.</text>
      </paragraph>
      <paragraph num="(b)">
        <text>Assistant Attorneys General. Assistant attorneys general assigned to either represent the Fund on a claim, or present regulatory charges, shall participate as a party in the hearing and receive all appropriate notices.</text>
      </paragraph>
      <paragraph num="(c)">
        <text>The same assistant attorney general assigned to present the regulatory case may be assigned to represent the Fund.</text>
      </paragraph>
    </paragraph>
    <paragraph num="(2)">
      <text>Notice.</text>
      <paragraph num="(a)">
        <text>The Commission shall notify all parties to a claim hearing of the date, time, and place of the hearing.</text>
      </paragraph>
      <paragraph num="(b)">
        <text>This notice shall contain a statement of any regulatory charges brought against the contractor which will be heard at the claim hearing.</text>
      </paragraph>
      <paragraph num="(c)">
        <text>The notice shall be mailed so as to give at least 10 days notice of the claim hearing.</text>
      </paragraph>
    </paragraph>
    <paragraph num="(3)">
      <text>The burden of proof shall be on the claimant to establish the validity of the claim.</text>
    </paragraph>
    <paragraph num="(4)">
      <text>Conduct of the Hearing.</text>
      <paragraph num="(a)">
        <text>If a hearing does not involve regulatory charges, the order of presentation shall be as follows:</text>
        <paragraph num="(i)">
          <text>The claimant shall present the case for the claim;</text>
        </paragraph>
        <paragraph num="(ii)">
          <text>The contractor may submit any evidence against the claim;</text>
        </paragraph>
        <paragraph num="(iii)">
          <text>An assistant attorney general representing the Fund may submit evidence concerning the claim; and</text>
        </paragraph>
        <paragraph num="(iv)">
          <text>Any party in the hearing may cross-examine any witnesses and submit rebuttal evidence and closing arguments.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(b)">
        <text>If a hearing involves regulatory charges and a claim arising from the same event or transaction, the order of presentation shall be as follows:</text>
        <paragraph num="(i)">
          <text>The assistant attorney general representing the State shall present the case for the regulatory charges against the contractor;</text>
        </paragraph>
        <paragraph num="(ii)">
          <text>The claimant shall present the case for the claim;</text>
        </paragraph>
        <paragraph num="(iii)">
          <text>The contractor may submit evidence against the charges and the claim;</text>
        </paragraph>
        <paragraph num="(iv)">
          <text>An assistant attorney general representing the Fund may submit evidence concerning the claim; and</text>
        </paragraph>
        <paragraph num="(v)">
          <text>Any party in the hearing may cross-examine any witnesses and submit rebuttal evidence and closing arguments.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(c)">
        <text>When a hearing involves regulatory charges and a claim arising from the same event or transaction, all evidence submitted at the hearing concerning that event or transaction shall be considered in determining the validity of the charges and the claim.</text>
      </paragraph>
    </paragraph>
  </paragraph>
  <paragraph num="B.">
    <text>Measure of Awards from Guaranty Fund.</text>
    <paragraph num="(1)">
      <text>The Commission may not award from the Fund any amount for:</text>
      <paragraph num="(a)">
        <text>Consequential or punitive damages;</text>
      </paragraph>
      <paragraph num="(b)">
        <text>Personal injury;</text>
      </paragraph>
      <paragraph num="(c)">
        <text>Attorney's fees;</text>
      </paragraph>
      <paragraph num="(d)">
        <text>Court costs;</text>
      </paragraph>
      <paragraph num="(e)">
        <text>Interest;</text>
      </paragraph>
      <paragraph num="(f)">
        <text>Payments made to a person who does not hold a contractor license to correct or complete a deficient home improvement unless the work performed by the unlicensed person did not require a contractor license or was performed by a person who was not required to hold a contractor license under Business Regulation Article, §8-301(c)(4)-(6), Annotated Code of Maryland; or</text>
      </paragraph>
      <paragraph num="(g)">
        <text>Estimated costs to correct or complete a deficient home improvement based on the estimates of a person who does not hold a contractor license unless the estimated work did not require a contractor license or the unlicensed person was not required to hold a contractor license under Business Regulation Article, §8-301(c)(4)-(6), Annotated Code of Maryland.</text>
      </paragraph>
    </paragraph>
    <paragraph num="(2)">
      <text>The Fund may only compensate claimants for actual losses they incurred as a result of misconduct by a licensed contractor.</text>
    </paragraph>
    <paragraph num="(3)">
      <text>Unless it determines that a particular claim requires a unique measurement, the Commission shall measure actual loss as follows:</text>
      <paragraph num="(a)">
        <text>If the contractor abandoned the contract without doing any work, the claimant's actual loss shall be the amount which the claimant paid to the contractor under the contract.</text>
      </paragraph>
      <paragraph num="(b)">
        <text>If the contractor did work according to the contract and the claimant is not soliciting another contractor to complete the contract, the claimant's actual loss shall be the amount which the claimant paid to the original contractor less the value of any materials and services provided by the contractor.</text>
      </paragraph>
      <paragraph num="(c)">
        <text>If the contractor did work according to the contract and the claimant has solicited or is soliciting another contractor to complete the contract or correct the contractor’s poor work, the claimant's actual loss shall be the amounts the claimant has paid to or on behalf of the contractor under the original contract, added to any reasonable amounts the claimant has paid or will be required to pay another contractor to repair poor work done by the original contractor under the original contract and complete the original contract, less the original contract price. If the Commission determines that the original contract price is too unrealistically low or high to provide a proper basis for measuring actual loss, the Commission may adjust its measurement accordingly.</text>
      </paragraph>
    </paragraph>
    <paragraph num="(4)">
      <text>The Commission may not award from the Fund an amount in excess of the amount paid by or on behalf of the claimant to or on behalf of the contractor against whom the claim is filed.</text>
    </paragraph>
  </paragraph>
  <paragraph num="C.">
    <text>Determinations.</text>
    <paragraph num="(1)">
      <text>Hearing Officers.</text>
      <paragraph num="(a)">
        <text>If the claim hearing is held before a hearing officer, the provisions of COMAR 09.01.03 shall be applicable.</text>
      </paragraph>
      <paragraph num="(b)">
        <text>A hearing board comprised of commissioners other than commissioners who initially reviewed the claim shall adopt, reject, or modify the hearing officer's recommendations pursuant to COMAR 09.01.03.</text>
      </paragraph>
    </paragraph>
    <paragraph num="(2)">
      <text>Unless the Commission or any of its members determines within 15 days of its issuance that a full hearing by the Commission is required, a hearing board's decision on a claim shall be a Final Order of the Commission which may be appealable by any aggrieved party to the circuit court where any party resides or has a principal place of business.</text>
    </paragraph>
    <paragraph num="(3)">
      <text>If the claim hearing is held before the full Commission, the Commission shall issue a decision on the claim which shall be a Final Order which may be appealed by an aggrieved party to the circuit court where any party resides or has a principal place of business.</text>
    </paragraph>
  </paragraph>
  <paragraph num="D.">
    <text>Payments.</text>
    <paragraph num="(1)">
      <text>Upon the issuance of a Final Order that a claim is valid, with all appeals to court exhausted, the Commission shall pay the claim from the Fund subject to the limitations in §§B(1) and D(2) of this regulation.</text>
    </paragraph>
    <paragraph num="(2)">
      <text>The Commission may not award from the Fund:</text>
      <paragraph num="(a)">
        <text>To any one claimant more than the amount authorized in Business Regulation Article, §8-405(e)(1), Annotated Code of Maryland, for acts or omissions of one contractor; or</text>
      </paragraph>
      <paragraph num="(b)">
        <text>More than the amount authorized in Business Regulation Article, §8-405(e)(2), Annotated Code of Maryland) to claimants on account of the conduct of any one licensee, unless, after the Commission has paid out that amount on account of the conduct of one licensed contractor, that contractor has repaid the full amount.</text>
      </paragraph>
    </paragraph>
    <paragraph num="(3)">
      <text>If the aggregate amount of the approved claims to be paid from the Fund involving one contractor exceeds the maximum payout amount authorized in Business Regulation Article, §8-405(e)(2), Annotated Code of Maryland, the Commission may either:</text>
      <paragraph num="(a)">
        <text>Pay the approved claims in the order filed until the maximum payout is reached; or</text>
      </paragraph>
      <paragraph num="(b)">
        <text>Prorate the approved claims by awarding each claimant the same percent of their approved claim which the maximum payout amount is of the total amount of the approved claims.</text>
      </paragraph>
    </paragraph>
    <paragraph num="(4)">
      <text>For purposes of this regulation, the term “approved claim” means the amount which the Commission has approved to be paid from the Fund which cannot exceed the amount authorized in Business Regulation Article, §8-405(e)(1), Annotated Code of Maryland.</text>