  <paragraph num="A.">
    <text>Internal Inspection.</text>
    <paragraph num="(1)">
      <text>Unless an internal inspection is required by law or by an inspector at the inspector's discretion, a:</text>
      <paragraph num="(a)">
        <text>Hot water boiler requires only an external inspection for certificate purposes; and</text>
      </paragraph>
      <paragraph num="(b)">
        <text>Pressure vessel requires only an external inspection for certificate purposes.</text>
      </paragraph>
    </paragraph>
    <paragraph num="(2)">
      <text>At least 7 days before an internal inspection, the inspector shall notify the owner of the inspection date.</text>
    </paragraph>
  </paragraph>
  <paragraph num="B.">
    <text>The owner of a boiler shall prepare the boiler for internal inspection and hydrostatic test, if necessary, by:</text>
    <paragraph num="(1)">
      <text>Drawing off water and washing the boiler thoroughly;</text>
    </paragraph>
    <paragraph num="(2)">
      <text>Removing manhole and handhole plates, washout plugs, and inspection plugs in water column connections;</text>
    </paragraph>
    <paragraph num="(3)">
      <text>Cooling and thoroughly cleaning furnace and combustion chambers;</text>
    </paragraph>
    <paragraph num="(4)">
      <text>Removing all grates of internally fired boilers;</text>
    </paragraph>
    <paragraph num="(5)">
      <text>Removing the pressure gage for testing;</text>
    </paragraph>
    <paragraph num="(6)">
      <text>Disconnecting the pipe or valve at the most convenient point to prevent leakage of steam or hot water into the boiler;</text>
    </paragraph>
    <paragraph num="(7)">
      <text>Performing the following procedures before opening a manhole or handhole cover and entering any part of a steam-generating unit connected to a common header with other boilers:</text>
      <paragraph num="(a)">
        <text>Close, tag, and preferably padlock:</text>
        <paragraph num="(i)">
          <text>Non return and steam stop valves; and</text>
        </paragraph>
        <paragraph num="(ii)">
          <text>Feed and check valves;</text>
        </paragraph>
      </paragraph>
      <paragraph num="(b)">
        <text>Open drain valves or cocks between:</text>
        <paragraph num="(i)">
          <text>Non return and steam stop valves; and</text>
        </paragraph>
        <paragraph num="(ii)">
          <text>Feed and check valves; and</text>
        </paragraph>
      </paragraph>
      <paragraph num="(c)">
        <text>After draining the boiler:</text>
        <paragraph num="(i)">
          <text>Close and padlock the blowoff valves;</text>
        </paragraph>
        <paragraph num="(ii)">
          <text>Where practicable, disconnect blowoff lines at a point between pressure parts and valves; and</text>
        </paragraph>
        <paragraph num="(iii)">
          <text>Open all drains and vent lines.</text>
        </paragraph>
      </paragraph>
    </paragraph>
  </paragraph>
  <paragraph num="C.">
    <text>The owner of a pressure vessel shall prepare the pressure vessel for inspection to the extent required by the inspector, using the applicable procedures set out in §B of this regulation.</text>
  </paragraph>
  <paragraph num="D.">
    <text>Removal of Covering During Inspection.</text>
    <paragraph num="(1)">
      <text>At each annual inspection, brickwork shall be removed, as required by the inspector, to determine the condition of the boiler, headers, furnace, supports, or other parts.</text>
    </paragraph>
    <paragraph num="(2)">
      <text>Unless the information can be obtained by other means, if boiler or pressure vessel jacketing conceals the longitudinal seams of a shell, drum, or dome, sufficient jacketing, setting wall, or other casing or housing shall be removed to permit:</text>
      <paragraph num="(a)">
        <text>Reasonable inspection of the seams; and</text>
      </paragraph>
      <paragraph num="(b)">
        <text>Determination of:</text>
        <paragraph num="(i)">
          <text>The size and pitch of the rivets; and</text>
        </paragraph>
        <paragraph num="(ii)">
          <text>Other data necessary to ascertain the safety of the boiler or pressure vessel.</text>
        </paragraph>
      </paragraph>
    </paragraph>
    <paragraph num="(3)">
      <text>When an external inspection discloses evidence of a leak or crack:</text>
      <paragraph num="(a)">
        <text>Sufficient covering shall be removed from the boiler or pressure vessel to permit the inspector to make a safety determination; and</text>
      </paragraph>
      <paragraph num="(b)">
        <text>If the covering cannot be removed during the inspection, the inspector may order use of the boiler or pressure vessel discontinued until:</text>
        <paragraph num="(i)">
          <text>The covering can be removed; and</text>
        </paragraph>
        <paragraph num="(ii)">
          <text>Proper inspection can be made.</text>
        </paragraph>
      </paragraph>
    </paragraph>
  </paragraph>
  <paragraph num="E.">
    <text>Hydrostatic Pressure Test.</text>
    <paragraph num="(1)">
      <text>A hydrostatic pressure test of a boiler or pressure vessel may not exceed:</text>
      <paragraph num="(a)">
        <text>1-1/2 times the maximum allowable working pressure; or</text>
      </paragraph>
      <paragraph num="(b)">
        <text>The required test pressure by more than 2 percent.</text>
      </paragraph>
    </paragraph>
    <paragraph num="(2)">
      <text>During a hydrostatic test:</text>
      <paragraph num="(a)">
        <text>Each safety valve shall be removed; or</text>
      </paragraph>
      <paragraph num="(b)">
        <text>Each valve disk shall be held to its seat by a testing clamp, and not by tightening the compression screw on the spring.</text>
      </paragraph>
    </paragraph>
    <paragraph num="(3)">
      <text>Water used to apply a hydrostatic test shall have a:</text>
      <paragraph num="(a)">
        <text>Recommended minimum temperature of 70°F; and</text>
      </paragraph>
      <paragraph num="(b)">
        <text>Maximum temperature of 140°F.</text>
      </paragraph>
    </paragraph>
    <paragraph num="(4)">
      <text>When a hydrostatic test is applied to an existing installation to determine:</text>
      <paragraph num="(a)">
        <text>Tightness, test pressure shall equal the release pressure of the safety valve having the lowest release setting; and</text>
      </paragraph>
      <paragraph num="(b)">
        <text>Safety, test pressure shall equal 1-1/2 times the maximum allowable working pressure.</text>
      </paragraph>
    </paragraph>
  </paragraph>
  <paragraph num="F.">
    <text>If a boiler or pressure vessel is not properly prepared for internal inspection, or if the owner fails to comply with the requirements for a hydrostatic test as set out in this regulation:</text>
    <paragraph num="(1)">
      <text>The inspector may refuse to conduct the inspection or test; and</text>
    </paragraph>
    <paragraph num="(2)">
      <text>If the inspector refuses, the chief boiler inspector shall withhold the inspection certificate until the owner complies with the requirements.</text>
    </paragraph>
  </paragraph>
  <paragraph num="G.">
    <text>An inspector is authorized to:</text>
    <paragraph num="(1)">
      <text>Conduct inspections in accordance with Public Safety Article, §12-909, Annotated Code of Maryland; and</text>
    </paragraph>
    <paragraph num="(2)">
      <text>Review and verify records required by Public Safety Article, Title 12, Subtitle 9, Annotated Code of Maryland, and by Codes referenced in Regulation .01-1 of this chapter.</text>
    </paragraph>
  </paragraph>