<regulation prefix="Regulation" num=".04" citation="COMAR 09.12.81.04" title_num="09" subtitle_num="12" chapter_num="81" heading="Final Acceptance Inspection.">
  <paragraph num="A.">
    <text>A final acceptance inspection by the Commissioner is required before the Commissioner may issue a certificate of registration and inspection on all new or modified elevator units.</text>
  </paragraph>
  <paragraph num="B.">
    <text>A contractor shall request a final acceptance inspection at least 30 days before the date the contractor requests for the final acceptance inspection to be conducted.</text>
  </paragraph>
  <paragraph num="C.">
    <text>A contractor may cancel a scheduled inspection under this regulation by written notice to the Commissioner at least 24 hours before the scheduled inspection.</text>
  </paragraph>
</regulation>