  <paragraph num="A.">
    <text>The Contractor shall develop, maintain, and modify as required by the Administration and the Department a comprehensive quality assurance and maintenance plan for vehicle emissions inspection stations complying with the provisions of this chapter, and shall implement the quality assurance plan after approval of the plan by the Administration and the Department.</text>
  </paragraph>
  <paragraph num="B.">
    <text>The contractor shall include the following information in the quality assurance plan:</text>
    <paragraph num="(1)">
      <text>Test assurance procedures to be conducted by the contractor for each test;</text>
    </paragraph>
    <paragraph num="(2)">
      <text>Periodic quality assurance check procedures and precision check procedures to be conducted by the contractor on the test equipment;</text>
    </paragraph>
    <paragraph num="(3)">
      <text>For each test assurance procedure, periodic quality assurance check, and precision check conducted by the contractor, the:</text>
      <paragraph num="(a)">
        <text>Primary standard to which each instrument, device, or material used for a check is traceable,</text>
      </paragraph>
      <paragraph num="(b)">
        <text>Acceptable tolerance for each check,</text>
      </paragraph>
      <paragraph num="(c)">
        <text>Corrective action to be taken for a check result outside of the acceptable tolerance, and</text>
      </paragraph>
      <paragraph num="(d)">
        <text>Recheck procedure to follow corrective action;</text>
      </paragraph>
    </paragraph>
    <paragraph num="(4)">
      <text>Maintenance procedures to be conducted by the contractor on the test equipment, which follow the equipment manufacturers' specifications at a minimum; and</text>
    </paragraph>
    <paragraph num="(5)">
      <text>Record-keeping practices to be conducted by the contractor.</text>
    </paragraph>
  </paragraph>
  <paragraph num="C.">
    <text>If a test assurance procedure is failed, the contractor shall record the event and void the test.</text>
  </paragraph>
  <paragraph num="D.">
    <text>If a periodic quality assurance check or precision check is failed, the contractor shall record the event, automatically prevent official testing, and take immediate corrective action.</text>
  </paragraph>
  <paragraph num="E.">
    <text>Maintenance Log.</text>
    <paragraph num="(1)">
      <text>The contractor shall keep a maintenance log for each test system, in a form which has been approved by the Administration and the Department, and shall record each maintenance event in the log.</text>
    </paragraph>
    <paragraph num="(2)">
      <text>Failure of the contractor to properly maintain equipment or to properly keep a maintenance log may be cause for the Administration or the Department to suspend official testing until the contractor takes corrective action which has been approved by the Administration or the Department.</text>
    </paragraph>
    <paragraph num="(3)">
      <text>The contractor shall keep each maintenance log for the duration of the vehicle emissions inspection program unless otherwise directed by the Department.</text>
    </paragraph>
  </paragraph>
  <paragraph num="F.">
    <text>The contractor shall allow access to inspection equipment, personnel, and records for Administration or Department personnel to perform quality assurance audits. Failure of a quality assurance audit may be cause for the Administration or the Department to suspend official testing until the contractor takes corrective action which has been approved by the Administration or the Department.</text>
  </paragraph>